MONTHYEARML0917402832009-07-10010 July 2009 University of Missouri at Columbia - Request for Additional Information License Renewal Project stage: RAI ML0936200822009-12-30030 December 2009 University of Missouri at Columbia, RAI, License Renewal References Project stage: RAI ML0936200962009-12-30030 December 2009 University of Missouri at Columbia, RAI, Environmental Report Project stage: RAI ML1003300732010-01-29029 January 2010 Written Communication as Specified by 10 CFR 50.4(b)(1) Regarding the Response to the University of Missouri at Columbia - Request for Additional Information License Renewal Environmental Report, Dated December 30, 2009 Project stage: Request ML1010407262010-04-20020 April 2010 University of Missouri at Columbia, Request for Additional Information Regarding License Renewal, National Historic Preservation Act Project stage: RAI ML1011602442010-05-0606 May 2010 University of Missouri at Columbia - Request for Additional Information License Renewal, Safety Analysis Report, Complex Questions Project stage: RAI ML1011602662010-06-0101 June 2010 University of Missouri at Columbia - Request for Additional Information License Renewal, Safety Analysis Report, 45-Day Response Questions Project stage: RAI ML12354A2372010-07-16016 July 2010 University of Missouri, Columbia - *Redacted* Response to NRC Request for Additional Information Dated June 1, 2010 Project stage: Response to RAI ML1020900052010-08-0404 August 2010 University of Missouri- Request for Additional Time to Respond to NRC Request for Additional Information Regarding License Renewal Project stage: RAI ML1200503152010-08-31031 August 2010 University of Missouri - Columbia - *Redacted* Licensee Response to NRC Request for Additional Information - Chapter 10 Relating to Amendment Information Only Project stage: Response to RAI ML1025005322010-09-0303 September 2010 University of Missouri, Columbia, Response to Request for Additional Information Regarding License Renewal Request Project stage: Response to RAI ML1025700552010-09-27027 September 2010 University of Missouri - Request for Additional Time to Respond to NRC Request for Additional Information Regarding License Renewal Project stage: RAI ML12355A0192010-09-30030 September 2010 University of Missouri, Columbia - *Redacted* Response to NRC Request for Additional Information Dated June 1, 2010 Project stage: Response to RAI ML1028001182010-10-13013 October 2010 University of Missouri - Request for Additional Time to Respond to NRC Request for Additional Information Regarding License Renewal Project stage: RAI ML1030600202010-10-29029 October 2010 University of Missouri-Columbia Research Reactor - Amended Facility License Project stage: Other ML12355A0232010-10-29029 October 2010 University of Missouri, Columbia - (Redacted) Response to NRC Request for Additional Information 45-Day Response Questions Project stage: Response to RAI ML1030600172010-10-29029 October 2010 University of Missouri-Columbia Research Reactor - Amended Facility License R-103 Project stage: Request ML1034403972010-12-13013 December 2010 University of Missouri - Request for Additional Time to Respond to NRC Request for Additional Information Regarding License Renewal Project stage: RAI ML1102403272011-01-14014 January 2011 University of Missouri - Request for Additional Time to Respond to NRC Request for Additional Information Regarding License Renewal Project stage: Request ML1102700732011-02-0101 February 2011 University of Missouri - Request for Additional Time to Respond to NRC Request for Additional Information Regarding License Renewal (Tac No. MD3034) Project stage: RAI ML1107402492011-03-11011 March 2011 University of Missouri-Columbia Research Reactor Response to Request for Additional Information Regarding Renewal Request for Amendment Facility Operating License R-103 Project stage: Response to RAI ML1118110712011-07-0505 July 2011 University of Missouri - Request for Additional Time to Respond to NRC Request for Additional Information Regarding License Renewal (TAC No. M3034) Project stage: RAI ML11255A0032011-09-0808 September 2011 Univ of Missouri - Columbia Research Reactors Responses to NRC Request for Additional Information Regarding a Renewal Request for Amended Facility Operating License R-103 Project stage: Response to RAI ML12010A1862012-01-0606 January 2012 University of Missouri - Columbia Research Reactor, Written Communication as Specified by 10 CFR 50.4(b)(1) Regarding Responses to the University of Missouri at Columbia - Request for Additional Information License Renewal, Safety Analysis Project stage: Request ML1202400382012-01-23023 January 2012 University of Missouri, Columbia - E-mail from L. Foyto, Associate Director, to G. Wertz, NRC Project Manager Extension Request for the Remaining 45-Day and 120-Day Responses Project stage: Request ML1202600142012-01-26026 January 2012 University of Missouri - Approval of Request for Additional Time to Respond to NRC Request for Additional Information License Renewal Project stage: RAI ML12346A0042012-06-28028 June 2012 University of Missouri, Columbia - *Redacted* Licensee Response to NRC Request for Additional Information Dated May 6, 2010 (Complex Questions) and June 1, 2012 (45-Day Response Questions) License Renewal Project stage: Response to RAI ML12355A0632012-12-20020 December 2012 University of Missouri, Columbia - Request for a Copy of the Physical Security Plan and Operator Requalification Program, License Renewal (Tac No. ME1580) Project stage: Other ML13031A1572013-02-11011 February 2013 University of Missouri, Columbia - Request for Additional Information Updated Financial Information for License Renewal Project stage: RAI ML13079A2162013-02-28028 February 2013 Letter from Kelly Mescher the Court in Sherman V. the Curators of the University of Missouri Project stage: Other ML13079A2152013-03-0505 March 2013 Statement of Intent Project stage: Other ML13079A2172013-03-12012 March 2013 Letter from Ralph A. Butler Enclosed with University of Missouri-Columbia Research Reactors Responses to the U.S. Nuclear Regulatory Commissions (NRC) Request for Additional Information, Dated February 11, 2013, Regarding Our Renewal Reques Project stage: Request ML13079A2142013-03-12012 March 2013 Written Communication as Specified by 10 CFR 50.4(b)(1) Regarding the Response to the University of Missouri at Columbia - Request for Additional Information Updated Financial Information for License Renewal (TAC No. ME1580), Dated 02/11/20 Project stage: Request ML13079A2182013-03-12012 March 2013 University of Missouri System 2012 Financial Report Project stage: Other ML13098A0512013-04-0909 April 2013 University of Missouri, Columbia - NRC Staff Review of the Operator Requalification Program License Renewal (Tac No. ME1580) Project stage: Approval ML13099A1142013-05-0606 May 2013 University of Missouri, Columbia - Letter to Licensee Determination of Acceptability for Docketing the Application for License Renewal Project stage: Other ML13099A1402013-05-14014 May 2013 FRN: General Notice: University of Missouri, Columbia - Notice of Acceptability for Docketing and Hearing Opportunity License Renewal (Tac No. ME1580) Project stage: Other ML14324A7072014-12-0303 December 2014 Request for Additional Information Regarding the MURR License Renewal Review (Updated Info 11/19/2014) Project stage: RAI ML15034A4742015-01-28028 January 2015 Written Communication as Specified by 10 CFR 50.4(b)(1) Regarding the Response to the University of Missouri at Columbia - Request for Additional Information Regarding the Renewal of Facility Operating License No. R-103 for the University O Project stage: Request ML15034A4732015-01-28028 January 2015 University of Missouri-Columbia Research Reactor Response to NRC Request for Additional Information Re License Renewal Application Project stage: Response to RAI ML15049A0392015-02-12012 February 2015 University of Missouri-Columbia - Response to Request for Additional Information Regarding the Renewal of Facility Operating License No. R- 103 Dated December.3, 2014 Project stage: Response to RAI ML15051A0042015-02-20020 February 2015 University of Missouri at Columbia, Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML15098A6482015-04-17017 April 2015 University of Missouri at Columbia - Request for Additional Information Regarding the Renewal of Facility Operating License No. R-103 for the University of Missouri at Columbia Research Reactor Project stage: RAI ML15183A4612015-05-11011 May 2015 Federal Funding for the Conversion of the University of Missouri-Columbia Research Reactor from Highly-Enriched Uranium Fuel to Low-Enriched Uranium Fuel Project stage: Request ML15162A0982015-06-18018 June 2015 University of Missouri at Columbia - RAI Regarding the Renewal of Facility Operating License No. R-103 for the University of Missouri at Columbia Research Reactor Project stage: RAI ML15154B8122015-07-21021 July 2015 University of Missouri at Columbia Acknowledgement of the Imposition of an Administrative Limit for the Quantity of Iodine Processed in the Iodine Processing Laboratory Hot Cells for Facility Operating License No. R 103 Project stage: Other ML15216A1222015-07-31031 July 2015 University of Missouri-Columbia - Response to Request for Additional Information Regarding Renewal Request for Amended Facility Operating License Project stage: Response to RAI ML15224B3092015-09-14014 September 2015 University of Missouri at Columbia - Request for Additional Information Regarding, Physical Security Plan Review for Renewal of Facility Operating License No. R-103 for the University of Missouri at Columbia Research Reactor Project stage: RAI ML15260A4392015-09-15015 September 2015 University of Missouri-Columbia - Request for a Copy of the Emergency Plan in Support of the Renewal of Amended Facility License No. R-103 Project stage: Request ML15275A3132015-10-0101 October 2015 University of Missouri-Columbia - Transmittal of Responses to NRC Request for Additional Information, Dated April 17, 2015, Regarding Renewal Request for Amended Facility Operating License Project stage: Response to RAI 2012-01-26
[Table View] |
Text
July 10, 2009 Mr. Ralph Butler, Director Research Reactor Center University of Missouri-Columbia Research Park Columbia, MO 65211
SUBJECT:
UNIVERSITY OF MISSOURI AT COLUMBIA C REQUEST FOR ADDITIONAL INFORMATION RE: LICENSE RENEWAL (TAC NO. ME1580)
Dear Mr. Butler:
We are continuing our review of your renewal request for Amended Facility Operating License No. R-103 for the University of Missouri - Columbia Research Reactor which you submitted on August 31, 2006, as supplemented. During our review of your renewal request, questions have arisen for which we require additional information and clarification. Please provide responses to the enclosed request for additional information within 60 days of the date of this letter. In accordance with Title 10 of the Code of Federal Regulations, your response must be executed in a signed original under oath or affirmation. Following receipt of the additional information, we will continue our evaluation of your renewal request. If you have any questions regarding this review, please contact me at (301) 415-1127.
Sincerely,
/RA/
Alexander Adams, Jr., Senior Project Manager Research and Test Reactors Branch A Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Docket No. 50-186
Enclosure:
As stated cc see next page
ML091740283 OFFICE PRTA:PM PRTA:LA PFPB:SC PRTA:SC NAME AAdams GLappert gkl MDusaniwski for RCarlson KBrock DATE 6/30/09 6/25/09 7/1/09 7/10/09
OFFICE OF NUCLEAR REACTOR REGULATION REQUEST FOR ADDITIONAL INFORMATION REGARDING FINANCIAL QUALIFICATIONS FOR THE RENEWED LICENSE FOR THE UNIVERSITY OF MISSOURI-COLUMBIA RESEARCH REACTOR LICENSE NO. R-103; DOCKET NO. 50-186 As required by Title 10 of the Code of Federal Regulations (10 CFR) Section 50.33(f)(2),
[a]pplicants to renew or extend the term of an operating license for a nonpower reactor shall include the financial information that is required in an application for an initial license. To comply with this requirement, please provide the following updated and supplemental information to the August 31, 2006, University of Missouri-Columbia (MU, the applicant) application (the application) for a renewed facility operating license for the University of Missouri-Columbia Research Reactor (MURR).
- 1.
The U.S. Nuclear Regulatory Commission (NRC) staff will analyze the financial statements for the current year, which are required by 10 CFR 50.71(b), to determine if the applicant is financially qualified to operate the MURR. Since MUs financial statements included with the application are out of date, please provide a copy of the latest financial statements for the NRC staffs review.
- 2.
Pursuant to 10 CFR 50.33(f)(2), [t]he applicant shall submit estimates for total annual operating costs for each of the first five years of operations of the facility. Since the information included in the application is now out of date, please provide the following additional information:
(a)
Projected operating costs of the MURR for each of the years FY11 thru FY15 (the first five year period after the projected license renewal).
(b)
MUs source(s) of funding to cover the operating costs for the above fiscal years.
- 3.
The application references a decommissioning cost estimate for the MURR that was developed using NUREG/CR-1756, Technology, Safety and Costs of Decommissioning Reference Research and Test Reactors. The application states that the decommissioning cost estimate was $40 million in 2005 dollars, including safe storage (SAFSTOR) costs, and a 25 percent contingency factor. The NRC staff needs the following additional information to complete its review of the MURR decommissioning cost estimate:
(a)
A current decommissioning cost estimate in 2010 dollars for the MURR to meet the NRCs radiological release criteria for decommissioning the facility for unrestricted use, pursuant to 10 CFR 50.75(d)(2). Accordingly, describe the basis for how the cost estimate was developed (if NUREG/CR-1756 is still the basis for the decommissioning cost estimate, please so state).
(b)
A summary of total decommissioning costs by labor, waste disposal, other items (such as energy, equipment, and supplies) in current dollars, and a 25 percent contingency factor.
(c)
Provide a more detailed breakout of the total and annual MURR SAFSTOR costs shown in Table 17-1 "Annual Cost During SAFSTOR" to current dollars as well as the supporting bases for the costs associated with the SAFSTOR option. Also, please provide a numerical example showing how the SAFSTOR costs will be escalated each year.
(d)
Provide a numerical example showing how the 2010 cost estimate will be updated periodically in the future.
- 4.
The application indicates that MU plans to use a statement of intent (SOI) as the method to provide decommissioning funding assurance, as provided for by 10 CFR 50.75(e)(1)(iv). Where the applicant intends to use a SOI, the NRC staff must find that the applicant is a Federal, State, or local government licensee. To make this finding, the applicant must state that it is a State government organization and that the decommissioning funding obligations of the applicant are backed by the State government, and also provide corroborating documentation. Further, the applicant must provide documentation verifying that the signator of the SOI is authorized to execute said document that binds the University. This document may be a governing body resolution, management directives, or other form that provides an equivalent level of assurance. As the application does not include all of the above information, please submit the following:
(a)
An updated SOI which includes the current (2010 dollars) cost estimate for decommissioning, a statement that funds for decommissioning will be obtained when necessary, and the signators oath or affirmation attesting to the information.
(b)
Documentation that corroborates the statement in the application that MU is a State agency and a State of Missouri government licensee under 10 CFR 50.75(e)(2)(iv).
(c)
A statement as to whether the decommissioning funding obligations for the MURR are backed by the State of Missouri government. The application must also present documentation that corroborates this statement. For example, the documentation may be a copy of or complete citation to a state statute that expressly provides that the obligations, or at least the decommissioning funding obligations, of the applicant are backed or supported by the full faith and credit of the State of Missouri, or an opinion of the applicants General Counsel with citations to statutes, regulations, and/or case law that the obligations, or at least those with respect to the decommissioning funding of the applicant are obligations backed or supported by the full faith and credit of the State of Missouri.
(d)
Documentation verifying that the signator of the SOI is authorized to execute such a document that binds the applicant financially. For example, provide a copy of MUs governing board or equivalent resolution that shows that the signator of the
SOI has been authorized by MU to bind MU financially, at least with respect to funding the decommissioning of the MURR, or provide a copy of an official MU delegation of authority showing that the signator of the SOI is authorized to bind MU financially, at least with respect to funding the decommissioning of the MURR.
University of Missouri-Columbia Docket No. 50-186 cc:
University of Missouri Associate Director Research Reactor Facility Columbia, MO 65201 Homeland Security Coordinator Missouri Office of Homeland Security P.O. Box 749 Jefferson City, MO 65102 Planner, Dept of Health and Senior Services Section for Environmental Public Health 930 Wildwood Drive, P.O. Box 570 Jefferson City, MO 65102-0570 Deputy Director for Policy Department of Natural Resources 1101 Riverside Drive Fourth Floor East Jefferson City, MO 65101 A-95 Coordinator Division of Planning Office of Administration P.O. Box 809, State Capitol Building Jefferson City, MO 65101 Test, Research, and Training Reactor Newsletter University of Florida 202 Nuclear Sciences Center Gainesville, FL 32611