ML19225D315: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:Code of Federal Regulations}}
{{#Wiki_filter:NRR-DRMAPEm Resource From:                              Wentzel, Michael Sent:                              Tuesday, August 13, 2019 3:39 PM To:                                Godes, Wyatt Cc:                                Mack, Jarrett; Catron, Steve; Frehafer, Ken
 
==Subject:==
St. Lucie Plant, Unit No. 2, Request for Additional Information Regarding License Amendment Request to Relocate the MOV Thermal Overload Bypass Devices (L-2019-LLA-0106)
 
==Dear Mr. Godes:==
 
By application dated May 20, 2019 (Agencywide Documents Access and Management System Accession No.
ML19140A100), Florida Power & Light Company (FPL, the licensee) submitted a license amendment request (LAR) for St. Lucie Plant, Unit No. 2 (St. Lucie 2). The proposed amendments would modify Technical Specification (TS) to relocate the requirements pertaining to the Motor Operated Valve (MOV) Thermal Overload Protection Bypass Devices to licensee control, whereby future changes will be subject to regulatory controls of Section 50.59 of Title 10 of the Code of Federal Regulations (10 CFR).
The NRCs Electrical Engineering Operating Reactors Branch (EEOB) staff is reviewing the application and has identified areas where it needs additional information to support its review. The NRC staffs request for additional information (RAI) is provided below. As discussed with the licensees staff on call on August 13, 2019, the NRC staff requests your response to the RAI within 30 days of the date of this email.
If you have any questions, please contact me at (301) 415-6459 or michael.wentzel@nrc.gov.
Sincerely, Michael Wentzel, Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation REQUEST FOR ADDITIONAL INFORMATION LICENSE AMENDMENT REQUEST REGARDING MOTOR-OPERATED VALVE THERMAL OVERLOAD PROTECTION BYPASS DEVICES ST. LUCIE PLANT, UNIT NO. 2 EPID L-2019-LLA-0106 FLORIDA POWER & LIGHT COMPANY DOCKET NO. 50-389 Requirements:
1
 
The regulatory requirements related to limiting conditions for operation are contained in the regulations at 10 CFR 50.36, "Technical specifications." Section 50.36 (c)(2)(ii) of 10 CFR requires TSs to have a technical specification limiting condition for operation for each item meeting one or more of the following criteria:
(A) Criterion 1: Installed instrumentation that is used to detect, and indicate in the control room, a significant abnormal degradation of the reactor coolant pressure boundary.
(B) Criterion 2: A process variable, design feature, or operating restriction that is an initial condition of a design basis accident or transient analysis that either assumes the failure of or presents a challenge to the integrity of a fission product barrier.
(C) Criterion 3: A structure, system, or component that is part of the primary success path and which functions or actuates to mitigate a design basis accident or transient that either assumes the failure of or presents a challenge to the integrity of a fission product barrier.
(D) Criterion 4: A structure, system, or component which operating experience or probabilistic risk assessment has shown to be significant to public health and safety.
RAI-EEOB-1 The license amendment request dated May 20, 2019, states, in part, that the proposed change deletes TS 3/4.8.4 and Table 3.8-1 in their entirety and relocates the MOV thermal overload protection bypass devices requirements to the stations Preventive Maintenance Program. However, the license amendment request does not contain a description of the Preventive Maintenance Program, nor does the program appear to be described in the Updated Final Safety Analysis Report. Further, it is not apparent why future changes to the relocated requirements would be subject to the controls of 10 CFR 50.59. Therefore:
: a. Provide a description of the St. Lucie Preventive Maintenance Program. Further, describe how future changes made to the relocated requirements would be subject to the controls of 10 CFR 50.59.
RAI-EEOB-2 The license amendment request dated May 20, 2019, states in Section 3.0 under Criterion 3 that the valves are not subject to repetitive cycling or prolonged periods of continuous operation that produce the elevated motor temperatures thermal overload protection is designed to prohibit.
: a. Provide the basis for this statement.
RAI-EEOB-3 The license amendment request dated May 20, 2019, states in Section 3.0 under Criterion 4 that MOV thermal overload protection and the need to bypass the protection during accident conditions are not SSCs that industry OE [operating experience] or the St. Lucie Unit 2 PRA [probabilistic risk assessment] have shown to be significant to public health and safety. Later in that section the LAR states, Moreover, MOV thermal overload protection is neither credited in the PRA nor is it subject to Maintenance Rule unavailability monitoring pursuant 10 CFR 50.65.
: a. Clarify what is meant by the statement that MOV thermal overload protection and/or their bypass devices are not specifically credited in the PRA for St. Lucie 2.
: b. Explain why MOV thermal overload protection is not subject to Maintenance Rule monitoring.
2
 
Hearing Identifier:      NRR_DRMA Email Number:            170 Mail Envelope Properties      (BL0PR0901MB3250349C9383C2E03518ED7FE7D20)
 
==Subject:==
St. Lucie Plant, Unit No. 2, Request for Additional Information Regarding License Amendment Request to Relocate the MOV Thermal Overload Bypass Devices (L-2019-LLA-0106)
Sent Date:              8/13/2019 3:39:02 PM Received Date:          8/13/2019 3:39:02 PM From:                    Wentzel, Michael Created By:              Michael.Wentzel@nrc.gov Recipients:
"Mack, Jarrett" <Jarrett.Mack@fpl.com>
Tracking Status: None "Catron, Steve" <Steve.Catron@fpl.com>
Tracking Status: None "Frehafer, Ken" <Ken.Frehafer@fpl.com>
Tracking Status: None "Godes, Wyatt" <Wyatt.Godes@fpl.com>
Tracking Status: None Post Office:            BL0PR0901MB3250.namprd09.prod.outlook.com Files                            Size                      Date & Time MESSAGE                          4843                      8/13/2019 3:39:02 PM Options Priority:                        Standard Return Notification:            No Reply Requested:                No Sensitivity:                    Normal Expiration Date:
Recipients Received:}}

Revision as of 23:22, 7 October 2019

Request for Additional Information Regarding License Amendment Request to Relocate the MOV Thermal Overload Bypass Devices (L-2019-LLA-0106)
ML19225D315
Person / Time
Site: Saint Lucie NextEra Energy icon.png
Issue date: 08/13/2019
From: Michael Wentzel
Plant Licensing Branch II
To: Godes W
Florida Power & Light Co
References
L-2019-LLA-0106
Download: ML19225D315 (3)


Text

NRR-DRMAPEm Resource From: Wentzel, Michael Sent: Tuesday, August 13, 2019 3:39 PM To: Godes, Wyatt Cc: Mack, Jarrett; Catron, Steve; Frehafer, Ken

Subject:

St. Lucie Plant, Unit No. 2, Request for Additional Information Regarding License Amendment Request to Relocate the MOV Thermal Overload Bypass Devices (L-2019-LLA-0106)

Dear Mr. Godes:

By application dated May 20, 2019 (Agencywide Documents Access and Management System Accession No.

ML19140A100), Florida Power & Light Company (FPL, the licensee) submitted a license amendment request (LAR) for St. Lucie Plant, Unit No. 2 (St. Lucie 2). The proposed amendments would modify Technical Specification (TS) to relocate the requirements pertaining to the Motor Operated Valve (MOV) Thermal Overload Protection Bypass Devices to licensee control, whereby future changes will be subject to regulatory controls of Section 50.59 of Title 10 of the Code of Federal Regulations (10 CFR).

The NRCs Electrical Engineering Operating Reactors Branch (EEOB) staff is reviewing the application and has identified areas where it needs additional information to support its review. The NRC staffs request for additional information (RAI) is provided below. As discussed with the licensees staff on call on August 13, 2019, the NRC staff requests your response to the RAI within 30 days of the date of this email.

If you have any questions, please contact me at (301) 415-6459 or michael.wentzel@nrc.gov.

Sincerely, Michael Wentzel, Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation REQUEST FOR ADDITIONAL INFORMATION LICENSE AMENDMENT REQUEST REGARDING MOTOR-OPERATED VALVE THERMAL OVERLOAD PROTECTION BYPASS DEVICES ST. LUCIE PLANT, UNIT NO. 2 EPID L-2019-LLA-0106 FLORIDA POWER & LIGHT COMPANY DOCKET NO. 50-389 Requirements:

1

The regulatory requirements related to limiting conditions for operation are contained in the regulations at 10 CFR 50.36, "Technical specifications." Section 50.36 (c)(2)(ii) of 10 CFR requires TSs to have a technical specification limiting condition for operation for each item meeting one or more of the following criteria:

(A) Criterion 1: Installed instrumentation that is used to detect, and indicate in the control room, a significant abnormal degradation of the reactor coolant pressure boundary.

(B) Criterion 2: A process variable, design feature, or operating restriction that is an initial condition of a design basis accident or transient analysis that either assumes the failure of or presents a challenge to the integrity of a fission product barrier.

(C) Criterion 3: A structure, system, or component that is part of the primary success path and which functions or actuates to mitigate a design basis accident or transient that either assumes the failure of or presents a challenge to the integrity of a fission product barrier.

(D) Criterion 4: A structure, system, or component which operating experience or probabilistic risk assessment has shown to be significant to public health and safety.

RAI-EEOB-1 The license amendment request dated May 20, 2019, states, in part, that the proposed change deletes TS 3/4.8.4 and Table 3.8-1 in their entirety and relocates the MOV thermal overload protection bypass devices requirements to the stations Preventive Maintenance Program. However, the license amendment request does not contain a description of the Preventive Maintenance Program, nor does the program appear to be described in the Updated Final Safety Analysis Report. Further, it is not apparent why future changes to the relocated requirements would be subject to the controls of 10 CFR 50.59. Therefore:

a. Provide a description of the St. Lucie Preventive Maintenance Program. Further, describe how future changes made to the relocated requirements would be subject to the controls of 10 CFR 50.59.

RAI-EEOB-2 The license amendment request dated May 20, 2019, states in Section 3.0 under Criterion 3 that the valves are not subject to repetitive cycling or prolonged periods of continuous operation that produce the elevated motor temperatures thermal overload protection is designed to prohibit.

a. Provide the basis for this statement.

RAI-EEOB-3 The license amendment request dated May 20, 2019, states in Section 3.0 under Criterion 4 that MOV thermal overload protection and the need to bypass the protection during accident conditions are not SSCs that industry OE [operating experience] or the St. Lucie Unit 2 PRA [probabilistic risk assessment] have shown to be significant to public health and safety. Later in that section the LAR states, Moreover, MOV thermal overload protection is neither credited in the PRA nor is it subject to Maintenance Rule unavailability monitoring pursuant 10 CFR 50.65.

a. Clarify what is meant by the statement that MOV thermal overload protection and/or their bypass devices are not specifically credited in the PRA for St. Lucie 2.
b. Explain why MOV thermal overload protection is not subject to Maintenance Rule monitoring.

2

Hearing Identifier: NRR_DRMA Email Number: 170 Mail Envelope Properties (BL0PR0901MB3250349C9383C2E03518ED7FE7D20)

Subject:

St. Lucie Plant, Unit No. 2, Request for Additional Information Regarding License Amendment Request to Relocate the MOV Thermal Overload Bypass Devices (L-2019-LLA-0106)

Sent Date: 8/13/2019 3:39:02 PM Received Date: 8/13/2019 3:39:02 PM From: Wentzel, Michael Created By: Michael.Wentzel@nrc.gov Recipients:

"Mack, Jarrett" <Jarrett.Mack@fpl.com>

Tracking Status: None "Catron, Steve" <Steve.Catron@fpl.com>

Tracking Status: None "Frehafer, Ken" <Ken.Frehafer@fpl.com>

Tracking Status: None "Godes, Wyatt" <Wyatt.Godes@fpl.com>

Tracking Status: None Post Office: BL0PR0901MB3250.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 4843 8/13/2019 3:39:02 PM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: