| | number = ML13338A696 | | | number = ML13338A696 |
| | issue date = 12/04/2013 | | | issue date = 12/04/2013 |
| | title = 2013/12/04 NRR E-mail Capture - Request for Additional Information (RAI) for Turkey Point Unit 3 Relief Request #13 (TAC MF2996) | | | title = Request for Additional Information (RAI) for Turkey Point Unit 3 Relief Request #13 |
| | author name = Klett A | | | author name = Klett A |
| | author affiliation = NRC/NRR/DORL/LPLII-2 | | | author affiliation = NRC/NRR/DORL/LPLII-2 |
Letter Sequence RAI |
---|
|
|
MONTHYEARML13325A9492013-11-18018 November 2013 NRR E-mail Capture - Acceptance Review for Turkey Point 3 Relief Request #13 Project stage: Acceptance Review ML13338A6962013-12-0404 December 2013 NRR E-mail Capture - Request for Additional Information (RAI) for Turkey Point Unit 3 Relief Request #13 Project stage: RAI 2013-11-18
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24024A0182024-01-24024 January 2024 LTR-23-0216-1 - (E-Mail) Turkey Point Nuclear Plant, Units 3 and 4 - 10 CFR 2.206 Petition -Turkey Point and PWR RPV Embrittlement E-Mail Closure Letter to Petitioner, January 23, 2024 ML24023A0622024-01-10010 January 2024 10 CFR 2.206 Petition - LTR-23-0216-1 - Turkey Point and PWR RPV Embrittlement - E-mail Final Determination Status to Petitioner - 1-10-2024 - L-2023-CRS-0005 IR 05000250/20240102024-01-0505 January 2024 Focused Engineering Inspection 05000250/2024010 and 05000251/2024010 ML23347A0772023-12-13013 December 2023 NRR E-mail Capture - Acceptance Review - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - LAR to Transition to 24-Month Fuel Cycles (L-2023-LLA-00161) ML23341A0602023-12-0707 December 2023 NRR E-mail Capture - Acceptance Review - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Exemption Request for Use of Axiom Fuel Cladding (L-2023-LLE-0036) ML23317A3752023-11-0808 November 2023 NRR E-mail Capture - Acceptance Review - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - LAR to Update SFP Criticality Analysis (L-2023-LLA-0142) ML23307A2382023-11-0303 November 2023 10 CFR 2.206 Petition - LTR-23-0216-1 - Initial Assessment; Turkey Point Subsequent License Renewal with Petitioner 11/3/2023 - L-2023-CRS-0005 ML23333A0092023-10-27027 October 2023 Attachment a - NRC Extension of Comment Period-1 ML23265A2692023-09-15015 September 2023 Turkey Point,_Rp Document Request 2023-004 ML23226A0752023-08-14014 August 2023 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - RCP LAR (L-2022-LLA-0128) ML23173A1522023-06-22022 June 2023 Request for Additional Information NextEra Fleet Emergency Plan Amendment Request ML23171B0532023-06-20020 June 2023 NRR E-mail Capture - Change in Estimated Review Schedule for Turkey Point Improved Standard Technical Specifications (ITS) LAR (L-2022-LLI-0002) ML23198A0592023-05-22022 May 2023 FPL to Fws, Notification of Doa Crocodile in CCS on 5/22/23 ML23138A0212023-05-17017 May 2023 Telephone Record, Call with Florida Power and Light Regarding Decommissioning Funding Plan Update Dated March 30, 2021 ML23129A8322023-05-0505 May 2023 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - RCP LAR (L-2022-LLA-0128) ML23109A1862023-04-19019 April 2023 and Turkey Point Acceptance of Requested Licensing Action Proposed Alternative to Asme Section XI Authorizing Implementation of Asme Code Case N-752-1 ML23117A2712023-04-11011 April 2023 NRR E-mail Capture - (External_Sender) Updated Data for Doa Turkey Point American Crocodile at 4/10/2023 ML23067A2812023-03-0808 March 2023 NRR E-mail Capture - (External_Sender) Non-causal American Croc Doa Turkey Point ML23038A1892023-02-0303 February 2023 RP RFI April 2023 ML23006A0262023-01-0505 January 2023 NRR E-mail Capture - Audit Plan - Turkey Point Fire Protection Changes to Support RCP Seal Replacement LAR ML22311A4752022-11-0707 November 2022 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - ITS ML22293B6562022-10-18018 October 2022 Request for 45 Day Extension of Comment Period of Turkey Point Subsequent License Renewal Scoping Process, Docket Id NRC-2022-0172 by Natural Resources Defense Council, Miami Waterkeeper and Counsel for Friends of the Earth ML22265A1522022-09-21021 September 2022 NRR E-mail Capture - Acceptance Review - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - LAR to Revise Fire Protection Program (L-2022-LLA-0128) ML22258A1862022-09-15015 September 2022 NRR E-mail Capture - Turkey Point Unit Nos. 3 and 4 - Supplemental Information Needed for Acceptance of Requested Licensing Action License Amendment Requests to Replace Instrumentation with Digital Systems ML22181A0562022-06-30030 June 2022 NRR E-mail Capture - Request for Additional Information - Turkey Point U3 Sgtir (L-2022-LRO-0070) ML22178A1032022-06-25025 June 2022 NRR E-mail Capture - (External_Sender) Turkey Point Doa American Crocodile 6/25/22 ML22147A0672022-05-19019 May 2022 NRR E-mail Capture - (External_Sender) Turkey Point Doa Crocodile 05/19/2022 ML22095A0162022-04-0505 April 2022 NRR E-mail Capture - Verbal Authorization of Turkey Point Nuclear Plant Unit 3 - Icw Relief Request No. 10-II ML22081A0292022-03-21021 March 2022 NRR E-mail Capture - Turkey Point Nuclear Generating Unit No. 3 - Request for Additional Information - Icw Alternative ML22018A0272022-01-18018 January 2022 2022 All RFI Responses - Exercise and Program Inspections - Revl ML21302A0052021-12-23023 December 2021 Email to Nextera/Fpl Re Discussion of Availability of Human Factor Validation Information to Support the Planned Turkey Point Digital I&C License Amendment Request ML21307A2882021-11-18018 November 2021 NRC to Fws, Request to Reinitiate Endangered Species Act Section 7 Consultation for Continued Operation of Turkey Point ML21298A0572021-10-25025 October 2021 NRR E-mail Capture - Final: Tpn Request for Additional Information - Round 2 Concerning Relief Request 10 - Extension EPID: L-2021-LLR-0077 ML21291A1272021-10-14014 October 2021 NRR E-mail Capture - Request for Additional Information - Fifth Ten-Year Inservice Inspection Interval Relief Request No.10 - Extension (L-2021-LLR-0077) ML21270A1652021-09-27027 September 2021 NRR E-mail Capture - Turkey Point Request for Additional Information Concerning Full Spectrum LOCA Methodology - EPID L-2021-LLA-0070 ML21266A2602021-09-22022 September 2021 NRR E-mail Capture - (External_Sender) Partial Sea Turtle Carcass at Turkey Point ML21252A2142021-09-0101 September 2021 NRR E-mail Capture - Final: Turkey Point Units 3 and 4 - Request for Additional Information Concerning Relief Requests 8 and 9 ML21207A1212021-06-30030 June 2021 Fws to NRC, Biological Opinion Notifications to Fws Law Enforcement ML21158A2332021-06-0707 June 2021 NRR E-mail Capture - Acceptance Review: Turkey Point Units 3 and 4 Fifth Ten-Year ISI Extension of ISI RPV Welds from 10 to 20 Years (L-2021-LLR-0038) ML21154A0872021-06-0202 June 2021 NRR E-mail Capture - 06/02/2021 Print a Logbook Entry: Turkey Point Endangered Species Report Regarding Injured American Crocodiles ML21154A0862021-05-25025 May 2021 NRR E-mail Capture - Acceptance Review: Turkey Point - Update Listing of Approved LOCA Methodologies to Adopt Full Spectrum LOCA Methodology ML21140A0672021-05-13013 May 2021 NRR E-mail Capture - (External_Sender) Regarding Doa American Crocodile Report 5-13-21 ML21131A1362021-05-0404 May 2021 NRR E-mail Capture - (External_Sender) 5/4/2021 Report Regarding Doa American Crocodile ML21097A1832021-03-30030 March 2021 NRR E-mail Capture - Endangered Species Death Report from Turkey Point Regarding Incident on 03/30/2021 ML21084A1312021-03-18018 March 2021 NRR E-mail Capture - (External_Sender) Deceased American Crocodile Found Outside FPL Property Line ML21056A0002021-02-24024 February 2021 NRR E-mail Capture - Endangered Species - 2/24/2021 Logbook Entry Regarding an American Crocodile ML21029A0172021-01-25025 January 2021 NRR E-mail Capture - 1/25/2021 Logbook Entry Regarding an American Crocodile Reported in the Owner Controlled Area ML21025A4152021-01-25025 January 2021 NRR E-mail Capture - 10 CFR 2.206 Petition Dated January 10, 2021 - Open Phase Condition Implementation ML20346A1022020-12-0808 December 2020 NRR E-mail Capture - Response: September 17, 2020 Submittal to the Nuclear Regulatory Commission ML20218A5502020-08-0505 August 2020 Florida Power & Light Letter L-2020-127: FPL QAPD for 10 CFR 52 Licenses FPL-2 Revision Summary 2024-01-05
[Table view] |
Text
1 NRR-PMDAPEm Resource From: Klett, Audrey Sent: Wednesday, December 04, 2013 8:13 AM To: Tomonto, Bob (Bob.Tomonto@fpl.com); 'Hanek , Olga' (Olga.Hanek@fpl.com); 'Mihalakea, Stavroula' (Stavroula.Mihalakea@fpl.com)
Subject:
Request for Additional Information (RAI) for Turkey Point Unit 3 Relief Request #13 (TAC MF2996)Bob, Olga, Stavy, Background By application dated October 23, 2013 (Agencywide Documents Access and Management System Accession No. ML13318A010), Florida Power & Light Company (the licensee) requested relief from the American Society of Mechanical Engineers Boiler and Pressure Vessel Code for the alternate repair of degraded valve, 3-844A, in the common containment spray pump suction supply header. To complete its review, the Nuclear
Regulatory Commission (NRC) staff requests the follo wing additional information be provided by January 10, 2014. Request for Additional Information
- 1. The licensee's application dated October 23, 2013, contains a commitment, which states:
The projected final flaw size at time of repair is projected to be the present 5/16 inch [length] x 1/16 inch [width] measured. If the monthly measurement increases from the present by 1/16 inch in either direction (allowing 1/16 inch for measurement uncertainty), then the growth rate will be re-examined to verify the structural analysis conclusions and predicted growth rate.
(a) Page 4 of the application states that daily walkdowns will be performed to observe significant leakage. Provide the leak rate (in gallons per minute) that the licensee would consider significant. If the leakage does increase to the specified significant leak rate during service in the ensuing months, discuss the corrective actions.
(b) Clarify whether the licensee considers a length of 1/16 inches or 1/8 inches (1/16 inch + 1/16 inch for the measurement uncertainty) as the monthly measurement increase.
(c) If the monthly measurement indicates that the flaw grows more than the aforementioned length criterion, discuss whether any remedial actions will be taken, such as increasing the inspection frequency. If remedial actions will not be taken in this scenario, please justify why not.
(d) Discuss whether the physical location of the subject valve is conducive for the plant personnel to perform visual inspections during the daily walkdowns, measure the leakage, and to perform monthly measurements.
(e) Discuss whether the flaw on the valve is covered with insulation during normal operation. If yes, discuss whether the insulation will be removed for visual inspection during walkdowns.
- 2. Page 3 of the application states that the flaw size of 5/16 inches long and 1/16 inches wide was obtained based on the direct measurement at the outside surface of the bonnet. The length of the flaw at the inside surface of the bonnet may be longer than 5/16 inches. Discuss whether ultrasonic testing was conducted to measure the flaw size at the inside surface of the bonnet or bonnet thickness at the flaw location.
- 23. Page 4 of the application states that the subject valve will be repaired or replaced when the flaw length exceeds "the allowable and critical flaw size" of 5.63 inches and 23.4 inches in the circumferential and axial directions, respectively. Page 5 of the application refers the above sizes as "allowable critical size."
(a) Please clarify the "allowable and critical flaw size" and "allowable critical size" terminology. Please clarify whether the allowable flaw size is the same as the critical flaw size and whether the valve could fail catastrophically (or if it could become unstable and propagate uncontrollably) if the existing flaw reaches the critical flaw size. Explain whether the licensee will establish an allowable flaw size that is less than the critical flaw size to prevent such a catastrophic event so that actions can be taken before the flaw reaches its critical size.
(b) Justify why the allowable flaw size is the same as the critical flaw size.
(c) Discuss whether a crack growth rate criterion or a leak rate criterion should also be required to compliment the flaw size criterion as a defense-in-depth measure.
- 4. The corrosion report in the submittal concluded that the crack growth from corrosion for the subject valve is insignificant. The NRC staff notes that if a flaw can grow through the wall of the bonnet, then the crack growth rate must not be insignificant. Discuss why the flaw has been able to grow through the wall of the bonnet if the flaw growth from corrosion is insignificant.
- 5. Attachment 2 of the application contains a structural analysis performed by Structural Integrity Associates, Inc.. Page 4 of that analysis states that it used the following maximum operating conditions: a temperature of 205 degrees Fahrenheit (F) and a pressure of 180 pounds per square inch gauge (psig).
The structural report's piping isometrics drawing, 5613-P-599-3, indicated that the design temperature and pressure are 300 degrees F and 200 psig, respectively. Discuss why the design conditions were not used in the structural calculation.
Audrey Klett Project Manager NRR/DORL/LPLII-2
301-415-0489
Hearing Identifier: NRR_PMDA Email Number: 943 Mail Envelope Properties (Audrey.Klett@nrc.gov20131204081200)
Subject:
Request for Additional Information (RAI) for Turkey Point Unit 3 Relief Request #13 (TAC MF2996) Sent Date: 12/4/2013 8:12:51 AM Received Date: 12/4/2013 8:12:00 AM From: Klett, Audrey Created By: Audrey.Klett@nrc.gov Recipients: "Tomonto, Bob (Bob.Tomonto@fpl.com)" <Bob.Tomonto@fpl.com> Tracking Status: None
"'Hanek, Olga' (Olga.Hanek@fpl.com)" <Olga.Hanek@fpl.com> Tracking Status: None "'Mihalakea, Stavroula' (Stavroula.Mihalakea@fpl.com)" <Stavroula.Mihalakea@fpl.com> Tracking Status: None Post Office: Files Size Date & Time MESSAGE 5019 12/4/2013 8:12:00 AM
Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: Recipients Received: