MONTHYEARML24282A6722024-10-0808 October 2024 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - Transition to 24-Month Fuel Cycles (L-2023-LLA-0161) ML24261B8062024-09-17017 September 2024 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - Transition to 24-Month Fuel Cycles (L-2023-LLA-0161) ML24250A0852024-09-0606 September 2024 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - Transition to 24-Month Fuel Cycles (L-2023-LLA-0161) ML24250A0242024-09-0606 September 2024 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - Transition to 24-Month Fuel Cycles (L-2023-LLA-0161) ML24248A0822024-09-0303 September 2024 NRR E-mail Capture - Acceptance Review for Turkey Point Alternative Request VR-02 for Certain Motor-Operated Isolation Valves (L-2024-LLR-0059) ML24234A0842024-08-21021 August 2024 Notification of Inspection and Request for Information ML24234A0142024-08-20020 August 2024 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - Spent Fuel Storage License Amendment Request (LAR) (L-2023-LLA-0142) ML24170A9352024-06-18018 June 2024 NRR E-mail Capture - Supplement to Audit Plan - Turkey Point - 18 to 24 Month Fuel Cycle LAR (L-2023-LLA-0161) ML24149A3532024-05-24024 May 2024 Change in Estimated Review Schedule for Nextera Common Emergency Plan Amendment ML24130A0112024-05-0808 May 2024 NRR E-mail Capture - Acceptance Review - Turkey Point 3 and 4 - Sixth 10-Year Inservice Testing Interval Proposed Alternative PR-02 (L-2024-LLR-0029) ML24122C6922024-05-0101 May 2024 NextEra Fleet EP Amendment - Demonstration Drill ML24113A0372024-04-22022 April 2024 NRR E-mail Capture - Acceptance Review - Turkey Point 3 and 4 and St. Lucie 2 - Request to Use Later Code of ASME (L-2024-LLR-0024) ML24107A9062024-04-11011 April 2024 Fws to NRC, Response to Notification of Final EIS for Turkey Point SLR ML24102A2772024-04-11011 April 2024 NRR E-mail Capture - Audit Plan - Turkey Point - Spent Fuel Pool Criticality License Amendment Request (LAR) (L-2023-LLA-0142) ML24102A1692024-04-11011 April 2024 NRR E-mail Capture - Audit Plan - Turkey Point - 18 to 24 Month Fuel Cycle License Amendment Request (LAR) (L-2023-LLA-0161) ML24101A0592024-04-11011 April 2024 NRC to Fws, Notification of Nrc’S Issuance of the Final EIS for Turkey Point Subsequent License Renewal ML24101A0602024-04-11011 April 2024 NRC to NMFS, Notification of Nrc’S Issuance of the Final EIS for Turkey Point Subsequent License Renewal ML24024A0182024-01-24024 January 2024 LTR-23-0216-1 - (E-Mail) Turkey Point Nuclear Plant, Units 3 and 4 - 10 CFR 2.206 Petition -Turkey Point and PWR RPV Embrittlement E-Mail Closure Letter to Petitioner, January 23, 2024 ML24023A0622024-01-10010 January 2024 10 CFR 2.206 Petition - LTR-23-0216-1 - Turkey Point and PWR RPV Embrittlement - E-mail Final Determination Status to Petitioner - 1-10-2024 - L-2023-CRS-0005 IR 05000250/20240102024-01-0505 January 2024 Focused Engineering Inspection 05000250/2024010 and 05000251/2024010 ML23347A0772023-12-13013 December 2023 NRR E-mail Capture - Acceptance Review - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - LAR to Transition to 24-Month Fuel Cycles (L-2023-LLA-00161) ML23341A0602023-12-0707 December 2023 NRR E-mail Capture - Acceptance Review - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Exemption Request for Use of Axiom Fuel Cladding (L-2023-LLE-0036) ML23317A3752023-11-0808 November 2023 NRR E-mail Capture - Acceptance Review - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - LAR to Update SFP Criticality Analysis (L-2023-LLA-0142) ML23307A2382023-11-0303 November 2023 10 CFR 2.206 Petition - LTR-23-0216-1 - Initial Assessment; Turkey Point Subsequent License Renewal with Petitioner 11/3/2023 - L-2023-CRS-0005 ML23333A0092023-10-27027 October 2023 Attachment a - NRC Extension of Comment Period-1 ML23265A2692023-09-15015 September 2023 Turkey Point,_Rp Document Request 2023-004 ML23226A0752023-08-14014 August 2023 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - RCP LAR (L-2022-LLA-0128) ML23173A1522023-06-22022 June 2023 Request for Additional Information NextEra Fleet Emergency Plan Amendment Request ML23171B0532023-06-20020 June 2023 NRR E-mail Capture - Change in Estimated Review Schedule for Turkey Point Improved Standard Technical Specifications (ITS) LAR (L-2022-LLI-0002) ML23198A0592023-05-22022 May 2023 FPL to Fws, Notification of Doa Crocodile in CCS on 5/22/23 ML23138A0212023-05-17017 May 2023 Telephone Record, Call with Florida Power and Light Regarding Decommissioning Funding Plan Update Dated March 30, 2021 ML23129A8322023-05-0505 May 2023 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - RCP LAR (L-2022-LLA-0128) ML23109A1862023-04-19019 April 2023 And Turkey Point – Acceptance of Requested Licensing Action Proposed Alternative to Asme Section XI Authorizing Implementation of Asme Code Case N-752-1 ML23117A2712023-04-11011 April 2023 NRR E-mail Capture - (External_Sender) Updated Data for Doa Turkey Point American Crocodile at 4/10/2023 ML23067A2812023-03-0808 March 2023 NRR E-mail Capture - (External_Sender) Non-causal American Croc Doa Turkey Point ML23038A1892023-02-0303 February 2023 RP RFI April 2023 ML23006A0262023-01-0505 January 2023 NRR E-mail Capture - Audit Plan - Turkey Point Fire Protection Changes to Support RCP Seal Replacement LAR ML22311A4752022-11-0707 November 2022 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - ITS ML22293B6562022-10-18018 October 2022 Request for 45 Day Extension of Comment Period of Turkey Point Subsequent License Renewal Scoping Process, Docket Id NRC-2022-0172 by Natural Resources Defense Council, Miami Waterkeeper and Counsel for Friends of the Earth ML22265A1522022-09-21021 September 2022 NRR E-mail Capture - Acceptance Review - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - LAR to Revise Fire Protection Program (L-2022-LLA-0128) ML22258A1862022-09-15015 September 2022 NRR E-mail Capture - Turkey Point Unit Nos. 3 and 4 - Supplemental Information Needed for Acceptance of Requested Licensing Action License Amendment Requests to Replace Instrumentation with Digital Systems ML22181A0562022-06-30030 June 2022 NRR E-mail Capture - Request for Additional Information - Turkey Point U3 Sgtir (L-2022-LRO-0070) ML22178A1032022-06-25025 June 2022 NRR E-mail Capture - (External_Sender) Turkey Point Doa American Crocodile 6/25/22 ML22147A0672022-05-19019 May 2022 NRR E-mail Capture - (External_Sender) Turkey Point Doa Crocodile 05/19/2022 ML22095A0162022-04-0505 April 2022 NRR E-mail Capture - Verbal Authorization of Turkey Point Nuclear Plant Unit 3 - Icw Relief Request No. 10-II ML22081A0292022-03-21021 March 2022 NRR E-mail Capture - Turkey Point Nuclear Generating Unit No. 3 - Request for Additional Information - Icw Alternative ML22018A0272022-01-18018 January 2022 2022 All RFI Responses - Exercise and Program Inspections - Revl ML21302A0052021-12-23023 December 2021 Email to Nextera/Fpl Re Discussion of Availability of Human Factor Validation Information to Support the Planned Turkey Point Digital I&C License Amendment Request ML21307A2882021-11-18018 November 2021 NRC to Fws, Request to Reinitiate Endangered Species Act Section 7 Consultation for Continued Operation of Turkey Point ML21298A0572021-10-25025 October 2021 NRR E-mail Capture - Final: Tpn Request for Additional Information - Round 2 Concerning Relief Request 10 - Extension EPID: L-2021-LLR-0077 2024-09-06
[Table view] |
Text
From: Michael Mahoney Sent: Tuesday, June 20, 2023 12:12 PM To: Davis, J.Michael
Subject:
CHANGE IN ESTIMATED REVIEW SCHEDULE FOR TURKEY POINT ITS LAR (L-2022-LLI-0002)
Mr. Davis, By letter dated September 22, 2021 (ML21265A370), Florida Power and Light Company (FPL, the licensee) submitted a license amendment request for the Turkey Point Nuclear Generating Units 3 and 4. By letters dated January 19, 2022 (ML22019A067), March 30, 2022 (ML22089A195), December 1, 2022 (ML22336A051), April 4, 2023 (ML23095A006) and May 24, 2023 (ML23144A114), FPL provided supplements to this submittal. The proposed license amendment request would revise Technical Specifications to Improved Standard Technical Specifications (ITS), consistent with NUREG-1431, Standard Technical Specifications Westinghouse Plants, Revision 5. On February 2, 2022 (ML22019A129), the NRC staff notified you that your request had been accepted for review, and the NRC staff estimated it would complete the review by November 30, 2022, and require 4,300 hours0.00347 days <br />0.0833 hours <br />4.960317e-4 weeks <br />1.1415e-4 months <br />.
In May 2022 NRC staff posted questions in the ITS Question-and-Answer portal (questions MEH003 and MEH006) related to FPLs planned relocation of certain TS setpoints to the Technical Requirements Manual (TRM). To resolve the issue, the NRC staff discussed with you or FPL during numerous public meetings from May 2022 to February 2023, and sent Requests for Additional Information (RAIs) on November 7, 2022 (ML22311A475) to which FPL responded on December 2, 2022 (ML22336A051). In its April 4, 2023, supplement (ML23095A006), FPL revised its request to remove the proposed relocation of the TS setpoints to the TRM, which maintains the setpoints in the TS. By letter dated May 24, 2023, FPL provided Revision 3 to the requested LAR, which principally provided additional responses to NRCs RAIs related to ITS Section 3.3, Instrumentation and ITS Section 3.6, Electrical Power Systems. During routine interactions by phone on May 26, 2023, the assigned project manager informed you of a delay in the schedule to complete the subject license amendment request due to the significant additional time needed to resolve the TS Setpoint issue and the additional time needed for the NRC to complete its review of FPLs responses to RAIs and Revisions 2 and 3 of the LAR provided in FPLs April 4, 2023 and May 24, 2023 supplements. The purpose of this email is to officially inform you that the NRC staff now expects to complete its review by July 28, 2023.
This estimate could change due to several factors such as requests for additional information and an unanticipated addition of scope to the review.
If there are emergent complexities or challenges in our review that would result in a change to the estimated completion date or significant changes in the estimated hours, the reasons for the change, and a revised estimate will be communicated during routine interactions with the assigned project manager. The change in the estimated completion date was discussed with and approved by the Deputy Director for the Division of Operating Reactor Licensing.
If you have any questions, please contact me.
Thanks Mike Mahoney Project Manager, LPL2-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Desk: (301)-415-3867 Mobile: (301)-250-0450 Email: Michael.Mahoney@nrc.gov
Hearing Identifier: NRR_DRMA Email Number: 2134
Mail Envelope Properties (SA1PR09MB948675A91FD757E66EAA023FE5479)
Subject:
CHANGE IN ESTIMATED REVIEW SCHEDULE FOR TURKEY POINT ITS LAR (L-2022-LLI-0002)
Sent Date: 6/20/2023 12:12:14 PM Received Date: 6/20/2023 12:12:15 PM From: Michael Mahoney
Created By: Michael.Mahoney@nrc.gov
Recipients:
"Davis, J.Michael" <J.Michael.Davis@nexteraenergy.com>
Tracking Status: None
Post Office: SA1PR09MB9486.namprd09.prod.outlook.com
Files Size Date & Time MESSAGE 3214 6/20/2023 12:12:15 PM
Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: