Line 2: |
Line 2: |
| | number = ML15098A014 | | | number = ML15098A014 |
| | issue date = 04/07/2015 | | | issue date = 04/07/2015 |
| | title = 2015/04/07 NRR E-mail Capture - Diablo Canyon, Units 1 and 2 - National Fire Protection Association Standard 805 Radiation Release Additional Requests for Additional Information (TAC Nos. MF2333 and MF2334) | | | title = National Fire Protection Association Standard 805 Radiation Release Additional Requests for Additional Information (TAC Nos. MF2333 and MF2334) |
| | author name = Lingam S P | | | author name = Lingam S P |
| | author affiliation = NRC/NRR/DORL/LPLIV-1 | | | author affiliation = NRC/NRR/DORL/LPLIV-1 |
Revision as of 11:50, 7 February 2019
Letter Sequence RAI |
---|
|
|
MONTHYEARML13266A0642013-09-24024 September 2013 Supplemental Information Needed for Acceptance of Application to Adopt National Fire Protection Association NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: Acceptance Review ML13281A4952013-10-30030 October 2013 Acceptance of Application Following Supplement, Adopt National Fire Protection Association NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: Acceptance Review ML14162A4582014-06-12012 June 2014 Pacific Gas and Electric Company Diablo Canyon Power Plant Units 1 and 2, Regulatory Audit in Support of the License Amendment Request to Implement Risk-Informed, Performance-Based, Fire Protection Program as Allowed by Title 10 of the Code Project stage: Other ML14206A0082014-07-31031 July 2014 Request for Additional Information, Request to Adopt National Fire Protection Association NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: RAI RC-14-0144, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-04)2014-08-28028 August 2014 Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-04) Project stage: Other ML14268A4362014-09-23023 September 2014 NRR E-mail Capture - Request for Additional Information (RAI) - License Amendment Request (LAR) 13-03 to Adopt NFPA 805 Project stage: RAI DCL-14-098, Ninety-Day Response to NRC Request for Additional Information- National Fire Protection Association Standard 8052014-10-29029 October 2014 Ninety-Day Response to NRC Request for Additional Information- National Fire Protection Association Standard 805 Project stage: Response to RAI ML14330A6392014-11-26026 November 2014 One-Hundred-Twenty-Day Response to NRC Request for Additional Information - National Fire Protection Association Standard 805, Part 2 of 2 Project stage: Response to RAI DCL-14-123, Radiation Release Response to NRC Request for Additional Information- National Fire Protection Association Standard 8052014-12-31031 December 2014 Radiation Release Response to NRC Request for Additional Information- National Fire Protection Association Standard 805 Project stage: Response to RAI ML15035A1622015-02-0404 February 2015 NRR E-mail Capture - Diablo Canyon, Units 1 and 2 - Requests for Additional Information (Rais) for Fire Protection (NFPA-805) License Amendment Request (LAR) Project stage: RAI ML15104A6992015-04-0202 April 2015 NRR E-mail Capture - FW: Generic Audit Plan - See Attachment Project stage: Other ML15098A0142015-04-0707 April 2015 NRR E-mail Capture - Diablo Canyon, Units 1 and 2 - National Fire Protection Association Standard 805 Radiation Release Additional Requests for Additional Information Project stage: RAI ML15092A0792015-04-16016 April 2015 July 14-17, 2014 - Summary of Diablo Canyon, Units 1 and 2, Audit to Adopt National Fire Protection Association NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: Other DCL-15-061, Second Radiation Release Response to NRC Request for Additional Information - National Fire Protection Association Standard 8052015-05-0707 May 2015 Second Radiation Release Response to NRC Request for Additional Information - National Fire Protection Association Standard 805 Project stage: Response to RAI DCL-15-119, Response to NRC Request for Additional Information - National Fire Protection Association Standard 805, Enclosure, Attachment 12015-10-15015 October 2015 Response to NRC Request for Additional Information - National Fire Protection Association Standard 805, Enclosure, Attachment 1 Project stage: Response to RAI ML15300A0062015-10-15015 October 2015 Submittal of Response to NRC Request for Additional Information - National Fire Protection Association Standard 805 Project stage: Response to RAI ML15316A0092015-10-15015 October 2015 Response to NRC Request for Additional Information - National Fire Protection Association Standard 805, Enclosure, Attachment 3 Project stage: Response to RAI 2014-08-28
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24250A0542024-09-0606 September 2024 LRA - Requests for Additional Information - Set 1 - Email from Brian Harris to Adam Peck ML24250A0502024-09-0606 September 2024 NRR E-mail Capture - Acceptance Review Diablo Canyon Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies ML24235A2032024-08-22022 August 2024 OEDO-24-00083 - 10 CFR 2.206 - Diablo Canyon Units 1 and 2 Seismic - Final Determination e-mail - EPID L-2024-CRS-0000 ML24205A0622024-07-23023 July 2024 NRR E-mail Capture - Acceptance Review - Diablo Canyon Request for Approval to Extend the Alternative for Use of Full Structural Weld Overlay ML24187A1382024-07-0202 July 2024 License Renewal Environmental Review: Summary of June 27 Clarification Call Regarding Pg&Es Response to RCI AQN-3 ML24184C0422024-07-0202 July 2024 NRR E-mail Capture - Request for Additional Information Diablo Canyon 50.69 risk-informed Categorization ML24149A0832024-05-28028 May 2024 Acceptance Review: Diablo Canyon Request for Alternative Security Measures and Exemption for the Early Warning System ML24145A0612024-05-22022 May 2024 Written Limited Appearance Statement of Doris Nassiry ML24136A1622024-05-15015 May 2024 OEDO-24-00083 (E-Mail) 10 CFR 2.206 - Diablo Canyon Power Plant, Unit Nos. 1 and 2 Seismic - Initial Assessment ML24134A1872024-05-10010 May 2024 Written Limited Appearance Statement of Charlene M. Woodcock ML24134A1902024-05-10010 May 2024 Written Limited Appearance Statement of Shelley Hamilton ML24122C6702024-04-29029 April 2024 Request from NRC Review of a Draft EA for an Exemption for the Limerick Generating Station ML24095A3172024-04-0404 April 2024 NRR E-mail Capture - Acceptance Review Diablo Canyon Request to Revise Technical Specification 5.6.6 for Pressure and Temperature Limits Report ML24088A2382024-03-28028 March 2024 10 CFR 2.206 - Diablo Canyon Units 1 and 2 OEDO-24-00083 - Screen-in e-mail L-2024-CRS-0000 ML24058A1032024-03-0808 March 2024 OEDO-23-00350-NRR - Initial Assessment - 10 CFR 2.206 Petition from Mothers for Peace and Friends of the Earth Regarding Diablo Canyon ML24071A1762024-03-0707 March 2024 Email - (External Sender) NRC Proceeding on Diablo Canyon 50-275 and 50-323 LR-2 ML24067A0902024-03-0505 March 2024 Email to Diane Curran from the Office of the Secretary, Assistant for Rulemaking and Adjudications, Russell Chazell ML24067A0892024-03-0505 March 2024 Email Response from Diane Curran to Office of the Secretary, Assistant for Rulemaking and Adjudications, Russell Chazell ML24067A0882024-03-0404 March 2024 Email Hearing Request from San Luis Obispo Mothers for Peace, Friends of the Earth, and Environmental Working Group ML24060A0022024-02-28028 February 2024 (External Sender) Pre-Sub Mittal EWS Participants List E-mail ML24045A1972024-02-0606 February 2024 Tribal Consultation Request ML24033A3062024-02-0101 February 2024 Dcisc 2-1-2024 Email: Comments by Mr. Bruce Severance at This Mornings Public Meeting Re Scope of Review for DCPP License Extension ML23334A0912023-11-30030 November 2023 NRR E-mail Capture - Diablo Canyon 1 and 2 - Audit Questions for License Amendment Associated with TSTF-505, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML23335A1012023-11-0606 November 2023 OEDO-23-00350-NRR - Screen-in Email - 10 CFR 2.206 Petition from Mothers for Peace and Change.Org Regarding Diablo Canyon ML23306A0422023-11-0202 November 2023 NRR E-mail Capture - Acceptance Review Diablo Canyon Request to Adopt 10 CFR 50.69, risk-informed Categorization and Treatment of SSCs ML23230A0702023-08-18018 August 2023 NRR E-mail Capture - Acceptance Review - Diablo Canyon Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b ML23165A2702023-06-14014 June 2023 NRR E-mail Capture - Acceptance Review - Diablo Canyon Revision to the Unit 1 Reactor Vessel Material Surveillance Program Withdrawal Schedule ML23157A2392023-06-0505 June 2023 Limited Appearance Statement from Nina Babiarz in the Matter of the Diablo Canyon ISFSI License Renewal Application ML23096A1792023-04-0606 April 2023 NRR E-mail Capture - Request for Additional Information Diablo Canyon Exemption Request Regarding Senior Reactor Operator License Application ML23094A1032023-04-0404 April 2023 NRR E-mail Capture - Acceptance Review - Diablo Canyon Exemption Request Regarding Senior Reactor Operator License Application ML23076A0932023-03-16016 March 2023 16-2023 Email - Estimate of Spent Nuclear Fuel in Tons ML23067A0202023-03-0808 March 2023 NRR E-mail Capture - Diablo Canyon Nuclear Power Plant Evacuation Time Estimate Analysis Review ML23046A1042023-02-13013 February 2023 Transmittal Email, Diane Curran to Gibson, 2/13/23, Filing of Formal Opposition to PG&E Exemption Request ML23046A1132023-02-13013 February 2023 Transmittal Email, Paul Bessette to Gibson, 2/13/23, Filing of Formal Opposition to PG&E Exemption Request ML23052A2042023-01-10010 January 2023 E-mail from Paul Bessette Dated 01/10/2023 Regarding Diablo Canyon ML22326A1632022-11-21021 November 2022 Licensee Comment Email on Post-Shutdown Emergency Plan Amendment ML22266A0012022-09-22022 September 2022 (External Sender) E-Mail Diablo Canyon Power Plant, Unit Nos. 1 and 2 - Total Amount of Spent Nuclear Fuel Stored in Tons ML22241A1142022-08-29029 August 2022 NRR E-mail Capture - Acceptance Review - Diablo Canyon Application to Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions ML22194A8872022-07-11011 July 2022 September 2022 Emergency Preparedness Exercise Inspection - Request for Information Email ML22187A2652022-07-0606 July 2022 NRR E-mail Capture - Request for Additional Information: Diablo Canyon Exemption Request for Part 73 force-on-force Training Due to COVID-19 ML22105A0702022-04-15015 April 2022 NRR E-mail Capture - Acceptance Review - Diablo Canyon Request to Revise Technical Specifications to Adopt TSTF 577, Revised Frequencies for Steam Generator Tube Inspections ML22090A0832022-03-31031 March 2022 NRR E-mail Capture - Acceptance Review - Diablo Canyon Request for Approval of a Certified Fuel Handler Training and Retraining Program ML22089A1672022-03-29029 March 2022 Email - Acknowledgement of NRC Receipt of Diablo Canyon ISFSI Renewal Application ML22087A0412022-03-25025 March 2022 NRR E-mail Capture - Acceptance Review - Diablo Canyon Request for Approval of Alternative Security Measures for Early Warning System ML22061A2192022-03-0202 March 2022 NRR E-mail Capture - Request for Additional Information - Diablo Canyon Proposed Changes to Emergency Plan for post-shutdown and Permanently Defueled Condition ML21323A0652021-11-19019 November 2021 NRR E-mail Capture - Acceptance Review - Diablo Canyon Revision of Emergency Plan for post-shutdown Condition ML21264A6722021-09-21021 September 2021 NRR E-mail Capture - Revised Schedule: Diablo Canyon Request to Revise Technical Specification to Reflect the Permanent Cessation of Reactor Operation ML21215A3432021-08-0303 August 2021 NRR E-mail Capture - Request for Additional Information - Diablo Canyon Request to Revise Technical Specification 3.8.1, AC Sources - Operating to Support Diesel Fuel Oil Transfer System Component Planned Maintenance ML21188A0382021-07-0707 July 2021 (External_Sender) DCPP Draft Emergency LAR - Asw ML21189A0662021-07-0707 July 2021 NRR E-mail Capture - Additional Draft Request for Additional Information - Diablo Canyon Emergency Amendment Request to Revise Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System 2024-09-06
[Table view] |
Text
1 NRR-PMDAPEm Resource From: Lingam, Siva Sent: Tuesday, April 07, 2015 3:08 PM To: mjrm@pge.com Cc: Markley, Michael; Shoop, Undine; Pedersen, Roger; Miller, Barry
Subject:
Diablo Canyon, Units 1 and 2 - National Fire Protection Association Standard 805 Radiation Release Additional Requests for Additional Information (TAC Nos. MF2333 and MF2334)By letter dated December 31, 2014 (Agencywide Documents Access and Management System Accession No. ML14365A377), Pacific Gas and Electric Company (the licensee) responded to the Nuclear Regulatory Commission's (NRC's) request for additi onal information (RAI) related to the review of the radioactive release portion of the subject license amendment request (LAR).
The NRC staff noted that the response indicated that the licensee "-has chosen an alternative approach to ensure that 10 CFR 20 [Title 10 of the Code of Federal Regulations (10 CFR), Part 20] limits are met..." The licensee further described that to support this alternative approach, two calculations are being developed to supersede existing calculations referenced in the LAR, but these calculations were not yet completed and/or approved. As a result, the NRC staff has the following official additional RAIs that need your responses by May 8, 2015:
Radiation Release RAI 09 Will each zone/area/building of interest have its own administrative activity limit, based on a zone specific calculation?
Radiation Release RAI 10 The response states that the Administrative Limit will ensure that "releases do not exceed 10 CFR Part 20 limits." Is this statement referring to the dose limit for a member of the public? If so, is the calculated dose to a real individual or a maximum exposed individual consistent with the Offsite Dose Calculation Manual? Is the Administrative Limit set bases on meeting the concentration limits in Appendix B to 10 CFR Part 20?
Radiation Release RAI 11 Describe the methodology used for each calculation to establish the maximum curie Administrative Limit, including all of the input assumptions and parameters used in these calculations.
Radiation Release RAI 12 What fraction of the contaminated oil stored in the Fire Zone is assumed to be consumed in the fire? If less than 1.0 provide basis for the assumption. What fraction of the activity in the contaminated oil is assumed to be released as an airborne effluent? - as a liquid effluent?
Radiation Release RAI 13 Are operator actions credited in the calculations for reducing the amount of effluent released? If so, specify the
operator actions and describe the assumed impact on the resulting dose.
Siva P. Lingam U.S. Nuclear Regulatory Commission Project Manager (NRR/DORL/LPL4-1)
Cooper Nuclear Station Diablo Canyon Nuclear Power Plant Location: O8-D5; Mail Stop: O8-B3 Telephone: 301-415-1564; Fax: 301-415-1222 E-mail address: siva.lingam@nrc.gov
Hearing Identifier: NRR_PMDA Email Number: 1977 Mail Envelope Properties (Siva.Lingam@nrc.gov20150407150800)
Subject:
Diablo Canyon, Units 1 and 2 - National Fire Protection Association Standard 805 Radiation Release Additional Requests for Additional Information (TAC Nos. MF2333 and MF2334) Sent Date: 4/7/2015 3:08:27 PM Received Date: 4/7/2015 3:08:00 PM From: Lingam, Siva Created By: Siva.Lingam@nrc.gov Recipients: "Markley, Michael" <Michael.Markley@nrc.gov> Tracking Status: None "Shoop, Undine" <Undine.Shoop@nrc.gov> Tracking Status: None "Pedersen, Roger" <Roger.Pedersen@nrc.gov> Tracking Status: None "Miller, Barry" <Barry.Miller@nrc.gov> Tracking Status: None "mjrm@pge.com" <mjrm@pge.com> Tracking Status: None Post Office: Files Size Date & Time MESSAGE 2640 4/7/2015 3:08:00 PM
Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: Recipients Received: