{{#Wiki_filter:Question:
(1 point) 1ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following plant conditions: Unit 1 has just reached 100% power following a refueling outage  Unit 2 is at 100% power with 93 EFPD Which ONE of the following will result in the highest amount of Emergency Feedwater flow required to stabilize RCS temperature 5 minutes following the trip?
A. Both Main Feedwater PumpsONLY trip on Unit 1 B. Both Main Feedwater Pumps ONLY trip on Unit 2 C. Loss of Offsite Power on Unit 1 D. Loss of Offsite Power on Unit 2 Page 1 of 100 Question:
(1 point) 2ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor power = 100%  1RC-66 (PORV) is leaking past its seat  Pressurizer temperature = 648 0F  Quench tank pressure = 5 psig  Reactor Building pressure = 0 psig Which ONE of the following describes the expected tailpipe temperature (°F) downstream of 1RC-66?
A. 212 B. 228  C. 272  D. 648  Page 2 of 100 Question:
(1 point) 3ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor tripped from 100% power due to SBLOCA  1A HPI Pump failed  Subcooling Margin = 0°F stable Which ONE of the following is the reason the EOP directs increasing SG levels to the Loss of Subcooling Margin Setpoint level?
A. Establish a large secondary side inventory in support of a rapid RCS cooldown.
B. Establish a large secondary side inventory to ensure that a loss of coupling will NOT occur if a momentary loss of EFDW occurs.
C. Ensure a secondary water level higher than the primary water level inside the SG tubes to establish boiler condenser mode heat transfe r  D. Ensure a secondary side levelsufficient to minimize the consequences of a total loss of feedwater during boiler condenser mode heat transfer Page 3 of 100 Question:
(1 point) 4ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor power = 50% stable  1B2 RCP is OFF Which ONE of the following would require immediate entry into AP/1/A/1700/016 (Abnormal Reactor Coolant Pump Operation)?
A. OAC point O1A0061 (RCP 1A1 MTR INPUT POWER) in HI alarm B. OAC point O1A1579 (RCP 1A2 MTR LOWER AIR TEMP) in HI alarm C. 1SA-15/A5 (RC PUMP MOTOR 1B1 OIL POT LOW LEVEL) in alarm D. 1SA-6/D5 (PUMP 1B2 CAVITY PRESS HI/LOW
) in alarm Page 4 of 100 Question:
(1 point) 5ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions:  Reactor power = 100%
Current conditions:
LPI Flow Train A = 1800 gpm stable  LPI Flow Train B = 1780 gpm stable  Rule 2 (Loss of SCM) in progress. IMAs complete
: 1) The SRO will direct actions from the __ (1) __ tab of the EOP.
: 2) In accordance with Rule 2, performance of Rule 3 (Loss of Main or Emergency FDW) __ (2) __ required.
Which ONE of the following completes the statements above?
A. 1. LOSCM 2. is  B. 1. LOSCM 2. is NOT C. 1. ICC 2. is  D. 1. ICC 2. is NOT Page 5 of 100 Question:
(1 point) 6ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions:  Normal LPI decay heat removal in service Current conditions:  Loss of offsite power occurs  Power restored via CT-4  1A and 1B LPI Pumps NOT available Which ONE of the following describes the requirements to start the 1C LPI Pump?
Manual reset of Load Shed is __(1)___ and starting of 1C LPI Pump is allowed after a MINIMUM of ___(2)__ seconds.
A. 1. NOT required 2. 5    B. 1. required 2. 5    C. 1. NOT required 2. 30    D. 1. required 2. 30    Page 6 of 100 Question:
(1 point) 7ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor trip has just occurred  Total RCP seal injection flow = 0 gpm  Running Component Cooling pump tripped  Standby CC pump did not start Which ONE of the following describes the procedure whose performance is directed by the EOP and why?
Initiate-
A. AP/20 (Loss of CC) to restore Component Cooling B. AP/20 (Loss of CC) to ensure letdown is isolated C. AP/25 (SSF EOP) to align an alternate letdown flowpath D. AP/25 (SSF EOP) to align an alternate source of seal in jection  Page 7 of 100 Question:
(1 point) 8ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions:  Reactor power = 90%  1B Main Feedwater pump trips Current conditions:  Reactor power = 70% decreasing  RCS pressure = 2165 psig slowly decreasing  Pressurizer level = 228 inches slowly decreasing  Pressurizer temperature = 640°F slowly decreasing  Pressurizer heater bank 1 (Group A and K) is ON  Pressurizer heater banks 2, 3, and 4 are in AUTO and are OFF The pressurizer is ___(1)____ AND the pressurizer heater bank 2 ___(2)____.
Which ONE of the following completes the statement above?
A. 1. subcooled 2. will ener gize at 2145 psi g  B. 1. subcooled 2. should be ener gized  C. 1. saturated 2. will ener gize at 2145 psi g  D. 1. saturated 2. should be energized Page 8 of 100 Question:
(1 point) 9ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 2 conditions: Loss of all sources of Feedwater has occurred  RCS Pressure = 2250 psig increasing  Pressurizer level = 294 inches increasing  ALL SCM's = 24°F slowly decreasing What is the:
: 1)  lowest RCS pressure (psig) that will require Rule 4 (Initiation of HPI Forced Cooling) to be performed?
: 2)  PRIMARY reason for reducing the number of operating RCP's in accordance with Rule 4?  A. 1. 2300 2. Reduce the heat input to the RCS B. 1. 2300 2. Provide the ability to recover from HPI forced cooling and re-establish a Pressurizer bubble.
C. 1. 2255 2. Reduce the heat input to the RCS D. 1. 2255 2. Provide the ability to recover from HPI forced cooling and re-establish a Pressurizer bubble.
Page 9 of 100 Question:
(1 point) 10ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 3 conditions: Reactor power = 100%
Which ONE of the following will result in a Tech Spec LCO being NOT met?
A. 3A SGTL rate = 160 gpd B. 3B Core Flood Tank level = 12.69 feet C. 3B Core Flood Tank pressure = 622 psig D. 4 gpm RCS leak identified as being through valve stem packing of 3HP-1 Page 10 of 100 Question:
(1 point) 11ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: ALL sources of feedwater have been lost  Rule 4 (Initiation of HPI Forced Cooling) is complete with outstanding IAAT's  1A HPI pump has failed  HPI flow parameters are as indicated below In accordance with Rule 4, __(1)__ RCP('s) is/are operating and HPI flow __(2)__ required to be throttled.
Which ONE of the following completes the statement above?
A. 1. 1 2. is  B. 1. 1 2. is NOT C. 1. 2 2. is  D. 1. 2 2. is NOT Page 11 of 100 Question:
(1 point) 12ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 Conditions:Initial conditions:  Reactor Power = 100%  ACB-4 closed Current conditions:  Reactor trip  CT-1 Locks out  KHU-2 Emergency Lockout occurs Assuming no additional failures, which ONE of the following describes the first method used to restore power to Unit 1 MFB's?
A. Automatically through ACB-3 B. Automaticall y through SL1 and SL2 C. Manually through ACB-3 in accordance with Enclosure 5.38 (Restoration of Power) of the EOP D. Manually through SL1 and SL2 in accordance with Enclosure 5.38 (Restoration of Power) of the EOP Page 12 of 100 Question:
(1 point) 13ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Unit shutdown in progress  Reactor power = 38% slowly decreasing  LOOP (Switchyard Isolation) occurs
: 1)  Based on the conditions above, the status of the Main Turbine will be __(1)__ 5 minutes following the LOOP?
: 2)  ANYTIME the Main Turbine is tripped, ICS uses __(2)__  to control the Turbine Bypass Valves?
Which ONE of the following completes the statements above?
A. 1. tripped 2. Turbine Header Pressure B. 1. tripped 2. Steam Generator Outlet Pressure C. 1. NOT tripped 2. Turbine Header Pressure D. 1. NOT tripped 2. Steam Generator Outlet Pressure Page 13 of 100 Question:
(1 point) 14ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions  Reactor Power = 100%  SASS in Manual while SPOC repairs Pressurizer Level 3 level transmitter  1HP-120 in AUTO selected to Pressurizer Level 1 Current conditions:  Vital Power to ICCM Train A fails Which ONE of the following describes Pressurizer level control with 1HP-120?
A. Selecting Pressurizer Level 2and depressing the AUTO pushbutton on 1HP-120 are required to restore automatic controlat setpoint B. Selectin g Pressurizer Le vel 2ONLY will restore automatic control at setpoint C. Manual control using 1HP-120 Bailey controller is all that is available D. Additional actions are NOT required since Automatic controlat setoint is retained Page 14 of 100 Question:
(1 point) 15ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions:  Reactor power = 100%  Instrument Air pressure = 85 psig decreasing  AP/22 (Loss of Instrument Air) has been initiated Which ONE of the following 
: 1)  is the higher Instrument Air pressure (psig) that would require an immediate manual Reactor trip in accordance with AP/22?
: 2)  states the reason AP/22 directs tripping the Main FDW pumps immediately after tripping the Reactor as described above?
A. 1. 70 2. Controllin g FDW valves fail "as is" B. 1. 65 2. Controllin g FDW valves fail "as is" C. 1. 70 2. Controllin g FDW valves fail closed D. 1. 65 2. Controllin g FDW valves fail closed Page 15 of 100 Question:
(1 point) 16ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions:  AP/34 (Degraded Grid) in progress  Generator output = 850 MWe and 450 MVARs  Generator Hydrogen Pressure = 60 psig  Generator Output Voltage = 18.2 KV
: 1)  The Generator output __ (1) __ within the limits of the Generator Capability Curve.
: 2)  If the generator exceeds the Underfrequency Maximum Allowable Time given in AP/34 (Degraded Grid) the Main Turbine __ (2) __ automatically trip.
Which ONE of the following completes the statements above?
REFERENCE PROVIDED A. 1. is NOT 2. will B. 1. is NOT 2. will NOT C. 1. is 2. will D. 1. is 2. will NOT Page 16 of 100 Question:
(1 point) 17ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 3 conditions: A brief loss of power has occurred  Unit auxiliaries are being supplied from the switchyard via CT-3  Subsequent Actions tab in progress
: 1)  Subsequent Actions directs restarting __(1)__.
: 2)  The __(2)__ RCP will provide the best Pressurizer Spray.
Which ONE of the following completes the statements above?
A. 1. one RCP ONLY 2. 3A1  B. 1. one RCP ONLY 2. 3B1  C. 1. one RCP per loop 2. 3A1  D. 1. one RCP per loop 2. 3B1  Page 17 of 100 Question:
(1 point) 18ILT44 ONS SRO NRC Examination Oconee Nuclear Station In accordance with the EOP, which ONE of the following describes the instruments that are used when initially stabilizing RCS temperature following a Main Steam Line Break and states one of the reasons why they are used?
A. Tcolds are used since Tech Specs specifies that Tcold is RCS temperature B. Tcolds are used since they are the coldest temperature and therefore most indicative of PTS issues C. CETC's are used since the resultant RCS cooldown may result in Tcold being off scale low D. CETC's are used since they are qualified instruments and are therefore more reliable in the hostile containment environment Page 18 of 100 Question:
(1 point) 19ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions:  Time = 1200  Reactor power = 100%  1A steam generator tube leak = 2.1 gpd stable  RCS activity = 0.25 Ci/ml DEI increasing Current conditions:  Time = 1400  NO change in 1A SG tube leak rate  RCS activity = 0.65 Ci/ml DEI increasing Which ONE of the following describes the response of the radiation monitors between 1200 and 1400?
A. 1RIA-59 (N-16 monitor) and 1RIA-40 (CSAE Off-gas) increased.
B. 1RIA-16 (Main Steam Line Monitor
) and 1RIA-40 increased.
C. 1RIA-59 increased while1RIA-40 remained constant.
D. 1RIA-16 increased while 1RI A-40 remained constant.
Page 19 of 100 Question:
(1 point) 20ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 2 condition:Initial conditions:  Time = 0900  Reactor Startup in progress  NI 1 & 2 = 370 cps      NI 3 & 4 = 0 cps (out of service)  ALL WR NI's = ~ 2.7 E-4%
Current conditions:  Time = 0901  NI 1 & 2 are inoperable Which ONE of the following describes:
: 1)  immediate actions required by Tech Spec 3.3.9 (Source Range Neutron Flux)?
: 2)  the reason for the actions described above?
A. 1. Insert Control Rods to Group 1 at 50% withdrawn2. Prevents power increases when the primary power indication for the operator is not available.
B. 1. Insert Control Rods to Group 1 at 50% withdrawn2. 2 dpm Startup Rate Control Rod Out Inhibit is no lon ger available C. 1. Fully insert all Control Rods2. Prevents power increases when the primary power indication for the operator is not available.
D. 1. Fully insert all Control Rods2. 2 dpm Startup Rate Control Rod Out Inhibit is no longer available Page 20 of 100 Question:
(1 point) 21ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor power = 92% decreasing  Unit shutdown in progress per the SGTR tab
: 1)  In accordance with the SGTR tab and Enclosure 5.5 (Pzr and LDST Level Control), RCS makeup and letdown will be adjusted to maintain Pressurizer level betw een __ (1) __ inches.
: 2)  The reason for this Pzr level band is to provide adequate inventory to __ (2) __.
Which ONE of the following completes the statements above?
A. 1. 140
- 180 2. ensure Pzr heaters will remain covered if a subsequent reactor trip occurs B. 1. 140
- 180 2. accommodate system shrinkage during shutdown/cooldown from 18% power  C. 1. 220
- 260 2. ensure Pzr heaters will remain covered if a subsequent reactor trip occurs D. 1. 220 - 260 2. accommodate system shrinkage during shutdown/cooldown from 18% power  Page 21 of 100 Question:
(1 point) 22ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor power = 100%
Which ONE of the following will result in an AUTOMATIC trip of the Main Turbine?
A. Bearing Oil Pressure = 5.5 psig B. Main Turbine speed = 1955 RPM C. EHC Hydraulic Oil pressure = 1210 psig D. EITHER Steam Generator Level = 93% OR Page 22 of 100 Question:
(1 point) 23ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions:  Reactor power = 100%  1A GWD tank release in progress  1RIA-38 OOS Current conditions:  Maintenance activities in the area result in an inadvertent loss of power to RM-80 skid of 1RIA-37  1SA8/B9 RM PROCESS MONITOR RADIATION HIGH in alarm  1SA8/B10 RM PROCESS MONITOR FAULT in alarm
: 1)  1GWD-4 (A GWD TANK DISCHARGE) should __(1)__.
: 2)  The required Completion Time in SLC 16.11.3 (Radioactive Effluent Monitoring Instrumentation) for suspending the release by this pathway if not already isolated and both 1RIA-37 and 1RIA-38 become inoperable is __(2)__.
Which ONE of the following completes the statements above?
A. 1. remain open 2. immediatel y  B. 1. automatically close 2. immediatel y  C. 1. remain open 2. 1 hour D. 1. automatically close 2. 1 hou r  Page 23 of 100 Question:
(1 point) 24ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor power = 2%  1SA2/B11 (ICS AUTO POWER FAILURE) actuated  1SA2/B13 (ICS HAND POWER FAILURE) actuated Which ONE of the following describes: 
: 1)  the level at which SGs will be maintained?
: 2)  how decay heat removal from the core is controlled?
A. 1. 25 inches SUR 2. ADVs B. 1. 30 inches XSUR 2. ADVs C. 1. 25 inches SU R 2. TBVs D. 1. 30 inches XSUR 2. TBVs Page 24 of 100 Question:
(1 point) 25ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions:  Switchyard isolation occurs Current conditions:  Shutdown of KHU's is desired Which ONE of the following states:
: 1)  if a Load Shed has occurred?
: 2)  the procedure that will be used to perform a remote shutdown of the KHU's?
A. 1. Yes 2. OP/0/A/2000/041 (Keowee Modes of Operations
)  B. 1. No 2. OP/0/A/2000/041 (Keowee Modes of Operations
)  C. 1. Yes 2. OP/0/A/1106/019 (Keowee Hydro AtOconee
)  D. 1. No 2. OP/0/A/1106/019 (Keowee Hydro AtOconee
)  Page 25 of 100 Question:
(1 point) 26ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: ES 1-8 have actuated  LOCA CD tab in progress  RCS pressure = 423 psig slowly decreasing  1A LPI Pump operating in the Piggyback alignment Which ONE of the following describes the:
: 1)  operational limitations on the operating LPI pump?
: 2)  pump(s) being protected by the above limitation?
A. 1. Maximized to < 3100 gpm 2. LPI  B. 1. Maximized to < 3100 gpm2. HPI  C. 1. Maximized to < 2900 gpm2. LPI  D. 1. Maximized to < 2900 gpm2. HPI  Page 26 of 100 Question:
(1 point) 27ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor trip from 100% due to a SBLOCA  Reactor building pressure has peaked at 1.7 psig  Subcooled margins are stable as indicated below Which ONE of the following describes how Feedwater will be used to mitigate this event?  Steam Generator levels will be controlled at ________?
A. 240 inches using Emergency Feedwate r  B. 240 inches using Main Feedwater C. Loss of Subcooling Margin setpointusing Emergency Feedwate r  D. Loss of Subcoolin g Margin setpointusin g Main Feedwate r  Page 27 of 100 Question:
(1 point) 28ILT44 ONS SRO NRC Examination Oconee Nuclear Station Which ONE of the following describes:
: 1)  the design purpose of extending RCP coast down time with the flywheel?
: 2)  an expected core delta T (&deg;F) 30 minutes following a lockout of 1TA and 1TB?
A. 1. Helps prevent the core from reaching DNBR limits2. 35  B. 1. Helps prevent the core from reaching DNBR limits 2. 47  C. 1. Reduces the likelihood of a Reactor trip following a RCP trip at power 2. 35  D. 1. Reduces the likelihood of a Reactor trip following a RCP trip at powe r 2. 47  Page 28 of 100 Question:
(1 point) 29ILT44 ONS SRO NRC Examination Oconee Nuclear Station
: 1)  The Letdown Storage Tank contains approximately __(1)__ gallons of water per inch of level.
: 2)  The HIGHER Letdown Storage Tank level that will automatically open 1HP-24 and 1HP-25 is __(2)__ inches.
Which ONE of the following completes the statements above?
A. 1. 24 2. 38  B. 1. 24 2. 54  C. 1. 31 2. 38  D. 1. 31 2. 54  Page 29 of 100 Question:
(1 point) 30ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 2 conditions: RCS Cooldown in progress  2B LPI cooler isolated due to cooler leak Which ONE of the following states the: 
: 1)  LPI Decay Heat Removal mode that will be used for the INITIAL transition to LPI cooling?
: 2)  HIGHER RCS pressure (psig) that will allow aligning LPI in the Normal Decay Heat Removal alignment?
A. 1. Switchover 2. 220 B. 1. High Pressure 2. 220  C. 1. Switchover 2. 115  D. 1. High Pressure 2. 115  Page 30 of 100 Question:
(1 point) 31ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Rule 3 initiated  Loss of Heat Transfer tab in progress  Efforts underway to re-establish Steam Generator cooling  1SA-18/D1 (RC SYSTEM APPROACHING SATURATED CONDTIONS) in alarm  1SA-2/D3 (RC PRESS HIGH/LOW) in alarm  Pressurizer level = 380" slowly increasing  RCS pressure = 2240 psig slowly increasing  SCM = 0&deg;F Which ONE of the following states which additional EOP Rules (if any) should be initiated?
A. NO additional rules required B. Rule 2 (Loss of SCM) ONLY C. Rule 4 (Initiation of HPI Forced Cooling) ONLY D. Rule 2 AND Rule 4 Page 31 of 100 Question:
(1 point) 32ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 2 condition:Initial conditions:  Unit startup in progress  RCS temperature = 310&deg;F slowly increasing  Maintenance in progress in the area of 2DIB panelboard Current conditions:  2DIB breaker #24 (2RC-66 Pilot Valve DC solenoid power supply) is inadvertently opened Which ONE of the following describes:
: 1)  a Tech Spec Limiting Condition of Operation that is NOT met?
: 2)  the position of 2RC-66?
A. 1. 3.4.9 (Pressurizer) 2. Open B. 1. 3.4.9 (Pressurizer) 2. Closed C. 1. 3.4.12 (LTOP) 2. Open D. 1. 3.4.12 (LTOP) 2. Closed Page 32 of 100 Question:
(1 point) 33ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:
Initial conditions  Loss of all Feedwater  HPI forced cooling initiated  Quench Tank pressure = 40 psig increasing  RCS activity indicates no fuel failures present Current conditions  Quench Tank pressure = 3 psig stable Which ONE of the following describes the:
: 1)  reactor building RIA's response to the above conditions?
: 2)  valve(s) that will automatically close anytime 1RIA-49 reaches its HIGH alarm setpoint?
A. 1. increases 2. 1LWD-1 AND 1LWD-2 B. 1. remains constant 2. 1LWD-1 AND 1LWD-2 C. 1. increases 2. 1LWD-2 ONLY D. 1. remains constant 2. 1LWD-2 ONLY Page 33 of 100 Question:
(1 point) 34ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: 1SA-08/B-9 (PROCESS MONITOR RADIATION HIGH)  1RIA-50 in HIGH alarm  CC Surge Tank level increasing
: 1)  The CC Surge tank  __(1)__.
: 2)  If the RCS leakage threatens to overflow the associated waste tank, AP/1/A/1700/002 (Excessive RCS Leakage) will direct __(2)__.
Which ONE of the following completes the statements above?
A. 1. will overflow to the LAWT 2. trippin g the Reactor B. 1. will overflow to the LAWT2. initiatin g a shutdown usin g AP/1/A/1700/029 (Rapid Unit Shutdown
)  C. 1. will overflow to a floor drain which drains to the MWHUT2. trippin g the Reactor D. 1. will overflow to a floor drain which drains to the MWHUT 2. initiatin g a shutdown usin g AP/1/A/1700/029 (Rapid Unit Shutdown
)  Page 34 of 100 Question:
(1 point) 35ILT44 ONS SRO NRC Examination Oconee Nuclear Station Which ONE of the following states the automatic OPEN setpoints (psig) for 1RC-1 (Pzr Spray) and 1RC-66 (PORV) in Mode 1?
1RC-1    1RC-66 A. 2205  2450 B. 2205  2500 C. 2255  2450 D. 2255  2500
Page 35 of 100 Question:
(1 point) 36ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor power = 100%  1D RPS channel in Manual Bypass  1A RPS Thot RTD fails low Which ONE of the following: 
: 1) describes ALL 1A RPS functions affected by the failure?
: 2) states if OP/1/A/1105/014 (Control Room Instrumentation Operation And Information) requires tripping the 1A RPS channel?
A. 1. RCS High Outlet Temperature ONLY2. yes  B. 1. RCS High Outlet Temperature ONLY 2. no  C. 1. RCS High Outlet Temperature and RCS Variable Low Pressure 2. yes  D. 1. RCS High Outlet Temperature and RCS Variable Low Pressure  2. no  Page 36 of 100 Question:
(1 point) 37ILT44 ONS SRO NRC Examination Oconee Nuclear Station Which ONE of the following describes how RCS Pressure signals are used to provide control signals to the Integrated Control System?
A. Median Selected from one wide range pressure and two channels of RPS narrow range pressure (A and B)
B. Median Selected from three channels of RPS narrow range pressure (A, B, and E)  C. 2nd Max Selected from RPS narrow range pressures (A, B, C, & D)
D. 2nd Min Selected from RPS narrow ran ge pressures (A, B, C, & D
)  Page 37 of 100 Question:
(1 point) 38ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 2 conditions:Initial conditions:  Reactor power = 100%
Current conditions:  MSLB occurs  RCS pressure = 1580 psig slowly increasing  RB peak pressure = 2.8 psig Which ONE of the following describes a valve that has received a signal to CLOSE?
A. 2CC-7 B. 2HP-24 C. 2LWD-2 D. 2LPSW-1062 Page 38 of 100 Question:
(1 point) 39ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following plant conditions:Time = 1200  Unit 1 Reactor power = 100%  Unit 2 Reactor power = 100%  ACB-4 closed Time = 1201  LOCA occurs on Unit 1 Switchyard Isolation occurs Which ONE of the following states the source of power being used to energize 1DIA at Time = 1202?
A. Control Batteries B. KHU-1 C. KHU-2 D. CT-5 Page 39 of 100 Question:
(1 point) 40ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 2 conditions:Time = 1200  Reactor in MODE 5  LPI aligned to normal Decay Heat Removal mode  2RIA-35 (Combined LPSW effluent leaving the Reactor Building and the Auxiliary Building) is isolated for repair Time = 1300  Large LPI Cooler leak in 2A LPI Cooler occurs Time = 1500  Actions to isolate the 2A LPI Cooler are initiated  RCS temperature slowly increasing
: 1)  At Time = 1330 there __(1)__ an RIA alarm indicating the LPI Cooler leak?
: 2)  Entry into MODE 4 will occur when RCS temperature exceeds __(2)__&deg;F?
Which ONE of the following completes the statements above? 
A. 1. is 2. 200  B. 1. is 2. 250  C. 1. is NOT 2. 200  D. 1. is NOT 2. 250  Page 40 of 100 Question:
(1 point) 41ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor is in MODE 5  RB Purge in progress  Unit 1 vent activity increasing  1RIA-45 HIGH alarm fails to actuate at setpoint
: 1)  Automatic termination of RB Purge operation due to increasing activity __(2)__ available?
: 2)  Purge operation __(1)__ be allowed if the unit were in MODE 4.
Which ONE of the following completes the statements above?
A. 1. is 2. would B. 1. is  2. would NOT C. 1. is NOT 2. would D. 1. is NOT 2. would NOT Page 41 of 100 Question:
(1 point) 42ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: 1A LPSW Pump trips  Standby LPSW pump fails to start Which ONE of the following will begin to increase in temperature?
ASSUME NO MANUAL ACTIONS ARE TAKEN A. Letdown B. Spent Fuel Pool C. Main Feedwater Pump oil temperature D. Primary Instrument Air Compresso rdischarge air temperature Page 42 of 100 Question:
(1 point) 43ILT44 ONS SRO NRC Examination Oconee Nuclear Station Which ONE of the following is the power supply for the Unit 2 Auxiliary Instrument Air System compressor?
A. 2XD  B. 2XF  C. 2XP  D. 2XS1  Page 43 of 100 Question:
(1 point) 44ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions:  Reactor Power = 100%  1A MSLB inside containment
Current conditions:  Core SCM = 18&deg;F stable  RB Pressure = 17 psig slowly decreasing Which ONE of the following sets of actions is required by Enclosure 5.1 (ES Actuation)
A. Take ES Channel 1 to manual AND open 1HP-20 B. Take ES Channel 1 to manual AND open 1HP-3 C. Override Odd Voters AND open 1HP-20 D. Override Odd Voters AND open 1HP-3 Page 44 of 100 Question:
(1 point) 45ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions:  Reactor Power = 100%
Which ONE of the following:
: 1)  describes the LOWER SG Operating Range level (%) that will result in an automatic trip of both Main Feedwater pumps?
: 2)  states if SG Operating Range level indications are temperature compensated?
A. 1. 87 2. No  B. 1. 87 2. Yes  C. 1. 97 2. No  D. 1. 97 2. Yes  Page 45 of 100 Question:
(1 point) 46ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor power = 50% slowly decreasing  OAC Unavailable  Computer Reactor Calculation Package NOT running Which ONE of the following:
: 1)  is the HIGHER power level (% Power) at which Tech Spec limits on Reactor Power Imbalance do NOT apply?
: 2)  describes how OP/1/A/1105/014 (Control Room Instrumentation Operation And Information) directs the operator to determine if Imbalance limits specified in the COLR have been exceeded?
A. 1. 35 2. by use of CR gages for Power Range NI's  B. 1. 35 2. by performin g PT/1/A/1103/019 (Backup Incore Detector S ystem)  C. 1. 15 2. by use of CR gages for Power Range NI's  D. 1. 15 2. by performin g PT/1/A/1103/019 (Backup Incore Detector S ystem)  Page 46 of 100 Question:
(1 point) 47ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions:  Mode 6  REFUELING is in progress  All four SR NIs in service  SR 1NI-1 and SR 1NI-3 are the designated NIs for Fuel Handling Current conditions:  Power supply to SR 1NI-1 fails (0 vdc)
Which ONE of the following describes the impact on refueling activities in accordance with OP/1/A/1502/007 (Operations Defueling/Refueling Responsibilities)?
A. Allowed to continue because two other SR NIs remain in service B. Allowed to continue because SR NI-3 is still in service C. Required to be stopped until another SR NI is designated because other NIs are procedurall y allowed to be desi gnated  D. Required to be stopped and cannot be resumed until SR 1NI-1 is returned to service because other NIs are NOT procedurally allowed to be designated Page 47 of 100 Question:
(1 point) 48ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Time = 1200  Reactor Power = 40% stable following an instrument failure  Turbine Header Pressure = 860 psig stable  Feedwater, Reactor, and Main Turbine in Manual Time = 1300  ICS in Automatic  Turbine Header Pressure = 860 psig stable Time = 1301  Reactor Trips prior to any additional Turbine Header Pressure setpoint adjustments Which ONE of the following is the pressure (psig) where the Turbine Bypass Valves will automatically control Steam Generator pressure?
A. 885    B. 910  C. 985  D. 1010  Page 48 of 100 Question:
(1 point) 49ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Time = 1200:00  Reactor power = 80% stable  1A and 1B CBP operating Time = 1201:00  1A CBP trips  Feedwater Pump suction pressure = 225 psig slowly decreasing Time = 1203:00  Feedwater Pump suction pressure = 220 slowly increasing Which ONE of the following describes the:
: 1) runback rate (%/min) inserted at Time = 1201:00 to ICS?
: 2) procedure that will be directed by the CRS at Time = 1203:00?
A. 1. 15 2. AP/1/A/1700/001 (Unit Runback
)  B. 1. 15 2. EOP  C. 1. 20 2. AP/1/A/1700/001 (Unit Runback
)  D. 1. 20 2. EOP  Page 49 of 100 Question:
(1 point) 50ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor power = 100%  Primary to Secondary leakage of 10 gpd has just been detected  AP/1/A/1700/031 (Primary to Secondary Leakage) has been initiated
: 1)  In accordance with AP/31, opening the Turbine Building Sump (TSP) pump breakers prior to being ready to hang White Tags on the TBS pump breakers __(1)__ allowed.
: 2)  A sustained loss of power to 1RIA-54 will trip BOTH Turbine Building Sump Pumps __(2)__.
Which ONE of the following completes the statements above?
A. 1. is NOT 2. after a 2 minute time r  B. 1. is NOT 2. immediatel y  C. 1. is 2. after a 2 minute time r  D. 1. is 2. immediatel y  Page 50 of 100 Question:
(1 point) 51ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions:  Time = 1200  1A GWD tank pressure = 68 psig stable Current conditions:  Time = 1205  1A GWD tank pressure = 18 psig rapidly decreasing  Various Aux Building RIA's in alarm  1RIA-1 (Control Room Monitor) in HIGH alarm  1RIA-39 (CNTL RM Gas) in HIGH alarm  AP/1/A/1700/018 (Abnormal Release of Radioactivity) in progress  A and B Outside Air Booster Fans have been started Which ONE of the following:
: 1)  states if 1RIA-1 has a local alarm (do not count associated statalarm(s))?
: 2)  describes the areas being provided outside air via the Outside Air Booster Fans?
A. 1. Yes 2. Control Room ONLY B. 1. No 2. Control Room ONLY C. 1. Yes 2. Control Room, Cable Rooms, and the Equipment Rooms D. 1. No 2. Control Room, Cable Rooms, and the Equipment Rooms Page 51 of 100 Question:
(1 point) 52ILT44 ONS SRO NRC Examination Oconee Nuclear Station 1RIA-59 setpoints are set by __(1)__ and the MINIMUM power level at which 1RI A-59is used to determine SGTL rate is __(2)__ (% power) in accordance with the EOP.
Which ONE of the following completes the statement above?
A. 1. I&E 2. 20  B. 1. I&E 2. 40  C. 1. ROs 2. 20  D. 1. ROs 2. 40  Page 52 of 100 Question:
(1 point) 53ILT44 ONS SRO NRC Examination Oconee Nuclear Station Which ONE of the following states all of the switchgear that can supply power to the B LPSW pump?
A. 1TD ONLY B. 2TC ONLY C. 1TC or 2TD D. 1TD or 2TD Page 53 of 100 Question:
(1 point) 54ILT44 ONS SRO NRC Examination Oconee Nuclear Station Based on the graph above, which ONE of the following describes the EARLIEST time at which SA-141 (SA to IA Controller) will automatically open?
A. 1207  B. 1210  C. 1212  D. 1215  Page 54 of 100 Question:
(1 point) 55ILT44 ONS SRO NRC Examination Oconee Nuclear Station Which ONE of the following describes what should be used in the case of a large Hydrogen leak to maintain Hydrogen concentration below the lower flammability limit in accordance with OP/1/A/1106/017 (Hydrogen System)?
A. CO2  B. Water C. Halon D. Foam fire retardant Page 55 of 100 Question:
(1 point) 56ILT44 ONS SRO NRC Examination Oconee Nuclear Station Which ONE of the following is the LOWER limit on RCS activity that would require entry into AP/21 (RCS Activity)?
A. Xe-133 = 0.25 &#xb5;Ci/gm  B. Xe-133 = 1.0
&#xb5;Ci/gm  C. DEI = 0.25 &#xb5;Ci/gm  D. DEI = 1.0 &#xb5;Ci/gm  Page 56 of 100 Question:
(1 point) 57ILT44 ONS SRO NRC Examination Oconee Nuclear Station Which ONE of the following activities complies withguidance contained in SOMP 1-2 (Reactivity Management)? A. Manual rod withdrawal during a Feedwater transient to stop a temperature decrease caused by an instrument failure B. Manually increasing Feedwater flow to stop an RCS pressure increase caused by an RCS temperature increase C. Manually raising one Loop FDW demand while lowering the other Loop FDW demand to control Tcold following an RCP trip D. Manually increasing turbine demand to adjust RCS temperature Page 57 of 100 Question:
(1 point) 58ILT44 ONS SRO NRC Examination Oconee Nuclear Station Which ONE of the following tags would be used ONLY for configuration control of 1HP-409 in accordance with NSD-500 (Red Tags/Configuration Control Tags)?
A. White Tag B. MORT Ta g  C. OORT Tag D. CORT Tag Page 58 of 100 Question:
(1 point) 59ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 condition:  Reactor in MODE 1 Which ONE of the following is the MINIMUM Pressurizer level (inches) that would require declaring Tech Spec 3.4.9 (Pressurizer) LCO NOT met in accordance with PT/1/A/0600/001 (Periodic Instrument Surveillance)?
A. 240  B. 260  C. 285  D. 340  Page 59 of 100 Question:
(1 point) 60ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor trip due to loss of both Main FDW pumps  Instrument Air pressure = 0 psig  Auxiliary Instrument Air pressure= 0 psig Which ONE of the following describes the status of 1FDW-315 and 1FDW-316?
A. Available for Manual operation ONLYonce the air supply was lost B. Will be available for Automatic operation for a MINIMUM of 30 minutes from the loss of air supply C. Will be available for Automatic operation for a MINIMUM of 1  hou r from the loss of air suppl y  D. Will be available for Automatic operation for a MINIMUM of 2  hours from the loss of air supply Page 60 of 100 Question:
(1 point) 61ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 2 conditions:Initial conditions:  Time = 1200  RCS temperature = 92&deg;F stable  RB Purge in progress  2RIA-45 HIGH alarm setpoint = 1520 cpm  2RIA-45 = 1342 cpm stable Current conditions:  Time = 1205  2RIA-45 = 1520 cpm increasing Which ONE of the following describes:
: 1)  ALL valves that will CLOSE?
: 2)  2RIA-46 reading (cpm) at time = 1200?
A. 1. 2P R-1 through 2P R-6 2. Zero B. 1. 2P R-1 through 2P R-6 2. 1342 C. 1. 2PR-2 through 2PR-5 ONLY 2. Zero D. 1. 2P R-2 through 2P R-5 ONLY2. 1342 Page 61 of 100 Question:
(1 point) 62ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following plant conditions:  Venting the 1C LPI Pump in progress using the following RWP information:
o Dose Alarm : 25 mrem o Dose Rate Alarm: 200 mrem/hr o Dose Alarm: Stop work - Exit Area - Notify RP o Unanticipated Dose Rate Alarm: Stop Work - Exit Area - Notify RP Which ONE of the following states the MAXIMUM time work can continue before complying with the RWP will require exiting the area?
SEE PLAN VIEW PROVIDED Do NOT consider dose received while traveling to or from the job.
A. 15 minutes B. 30 minutes C. 2 hours D. 4 hours Page 62 of 100 Question:
(1 point) 63ILT44 ONS SRO NRC Examination Oconee Nuclear Station Of the two tabs below, the __(1)__ tab of the EOP has a higher priority because __(2)__.
Which ONE of the following completes the statement above?
A. 1. LOSCM 2. prompt actions are required to ensure core coolin g is maintained B. 1. LOSCM 2. actions to initiate HPI injection are required prior to the RCS void fraction reaching 70%.
C. 1. SGTR 2. a Reactor trip with a SGTR results in a direct release path for radionuclides to the environment D. 1. SGTR 2. actions to depressurize RCS to minimize SCM during a SGTR is a Time Critical Action that ma y not otherwise be met Page 63 of 100 Question:
(1 point) 64ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor Power = 70%
Which ONE of the following would require entry into the EOP?
A. Condenser vacuum = 22.3" hg B. 1RIA-59 = 31.4 gpm  C. 1B Main FDW pump trips D. 1A1 RCP trips Page 64 of 100 Question:
(1 point) 65ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions:  Reactor power = 100%  1KVIA Panelboard de-energized Current conditions:  MSLB inside the Reactor Building occurs  Lowest RCS pressure = 1137 psig  Reactor Building Pressure peaked at 32 psig Which ONE of the following describes ALL ES Actuation Logic Channels that have actuated?
A. 1, 3, 5, 7 B. 2, 4, 6, 8 C. 1, 5, 7 ONLY D. 2, 6, 8 ONLY Page 65 of 100 Question:
(1 point) 66ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions:  Time = 1200  Reactor Power = 100%  1A MSLB inside the Reactor Building Current conditions:  Time = 1201  Reactor Building Pressure = 3 psig increasing Which ONE of the following describes the operation of 1LPSW-18?
A. It is NORMALLY fully open however it will receive a signal to open from ES-5 at 1201  B. It is NORMALLY throttled and will go fully open when it receives a signal to open from ES-5 at 1201 C. It is NORMALLY fully open however it will receive a signal to open from ES-5 at 1204  D. It is NORMALLY throttled and will go fully open when it receives a signal to open from ES-5 at 1204 Page 66 of 100 Question:
(1 point) 67ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions:  Reactor power = 50%
Current conditions:  LBLOCA occurs  1TD de-energized  1B RBCU switch in OFF Which ONE of the following describes the status of the below listed Reactor Building Cooling Units five (5) minutes after ES actuates?
ASSUME NO OPERATOR ACTIONS 1B RBCU 1C RBCU  A. LOW  LOW B. LOW  OFF C. OFF  LOW D. OFF OFF Page 67 of 100 Question:
(1 point) 68ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following plant conditions: SBLOCA has occurred on Unit 1  Reactor Building Pressure = 11.2 psig slowly decreasing  Unit 2 Reactor Power = 100%
Which ONE of the following describes the actions directed (if any) by Enclosure 5.1 (ES Actuation) to ensure the required LPSW flow exists in the 1A LPI cooler?
A. Place 1LPSW-251 in "Failed Open" ONLY B. Place 1LPSW-251 in "Failed Open" AND fully open 1LPSW-4 C. Place 1LPSW-251 in "Failed Open" AND Throttle LPSW flow to approximately 3000 gpm using 1LPSW-4 D. Place 1LPSW-251 in "Failed Open" AND Throttle LPSW flow to approximately 5200 gpm using 1LPSW-4 Page 68 of 100 Question:
(1 point) 69ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions:  Reactor power = 100%  Loss of offsite power occurs Current conditions:  Main Feeder Buses remain de-energized
: 1) The position of 1MS-112 (SSRH Control) is __(1)__.
: 2) 1MS-77 (MS to MSRH) __(2)__ be operated from the control room switch.
Which ONE of the following completes the statements above?
A. 1. open 2. can  B. 1. closed 2. can  C. 1. open 2. can NO T  D. 1. closed 2. can NO T  Page 69 of 100 Question:
(1 point) 70ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:  Reactor Power = 50%  1A Turbine Bypass Valve fails OPEN Which ONE of the following describes the plant response?
ASSUME NO OPERATOR ACTIONS Reactor power will...
A. Increase then return to pre-transient level.
B. Increase and stabilize at a higher power level.
C. Decrease then return to pre-transient level.
D. Decrease and stabilize at a lower power level.
Page 70 of 100 Question:
(1 point) 71ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:  Reactor Power = 80% stable  ICS in Manual  1B Main Feedwater Pump trips Which ONE of the following is the MAXIMUM power level allowed in accordance with AP/1 (Plant Runback).
A. 74%  B. 65%  C. 60%  D. 55%  Page 71 of 100 Question:
(1 point) 72ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 3 conditions: Initial conditions:  Reactor tripped from 35% power due to 3TA lockout  3A Main FDW pump operating  3FDW-35 & 3FDW-44 (3A and 3B Startup FDW Control) in MANUAL  3A and 3B SG levels = 38" SU and stable Current conditions:  3FDW-35 & 44 are placed in Automatic Which ONE of the following describes the response of 3FDW-35 & 44?
A. Travel open to increase SG levels to 240" XSUR.
B. Travel open to increase SG levels to 50% on Operating level.
C. Travel closed to decrease SG level to 30" on XSUR.
D. Travel closed to decrease SG level to 25" on SU level.
Page 72 of 100 Question:
(1 point) 73ILT44 ONS SRO NRC Examination Oconee Nuclear Station Which ONE of the following describes the:
: 1)  primary concern at ONS regarding Main Feedwater backleakage into the EFDW discharge piping?
: 2)  method used to determine if Main Feedwater backleakage into the EFDW discharge piping is occurring?
A. 1. Vapor binding of the EFDWpumps2. locall y monitorin g EFDW pump dischar ge piping for increasin g temperature B. 1. Vapor binding of the EFDWpumps2. Monitorin g EFDW temperature OAC points fo rincreasin g temperature C. 1. Overpressurizing the EFDW system piping 2. locall y monitorin g EFDW pump dischar ge piping for increasin g temperature D. 1. Overpressurizing the EFDW system piping 2. Monitoring EFDW temperature OAC points for increasing temperature Page 73 of 100 Question:
(1 point) 74ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following plant conditions: No Keowee Units are operating  ACB-3 closed
: 1)  KHU 1X switchgear is being powered from __ (1) __.
: 2)  Keowee control power will be available for a MINIMUM of approximately __ (2) __ hour(s) following a loss of ALL AC power.
Which ONE of the following completes the statements above?
A. 1. 1TC 2. one  B. 1. 1TC 2. four  C. 1. the 230 KV switchyard 2. one  D. 1. the 230 KV switch yard  2. four Page 74 of 100 Question:
(1 point) 75ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following plant conditions: 3CA Battery Charger fails - output voltage = 0 VDC  3CA Battery voltage = 120 VDC  3DCB Bus voltage = 123 VDC  Unit 1 DCA/DCB Bus voltage = 125 VDC  Unit 2 DCA/DCB Bus voltage = 127 VDC Which ONE of the following will automatically supply power to 3DIA panelboard?
A. 3CA Battery B. Unit 1 DC Bus C. 3DCB Bus D. Unit 2 DC Bus Page 75 of 100 Question:
(1 point) 76ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions:  Reactor power = 100%  Quench Tank temperature, level, and pressure are slowly increasing  1RC-66 tailpipe temperature slowly increasing Current conditions:  1RC-4 has been closed to verify the leak source Which ONE of the following states:
: 1)  if ALL equipment credited in the UFSAR to prevent the RCS from exceeding the Tech Spec Safety Limit on RCS pressure is still available?
: 2)  the LOWER Quench Tank pressure that will result in blowing the Quench Tank rupture disc?
A. 1. No 2. 45 psi g  B. 1. No 2. 55 psi g  C. 1. Yes 2. 45 psi g  D. 1. Yes 2. 55 psig Page 76 of 100 Question:
(1 point) 77ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Time = 1200  RCS temperature = 274&deg;F stable  1/0 Pump Ops in progress  1A1 RCP operating  1A2 RCP NOT available  1B1 RCP available  1B2 RCP NOT available  LPSW to the 1A1 RCP ONLY is lost Time = 1202  1A1 RCP secured
: 1)  In accordance with AP/16, the 1A1 RCP must be tripped as soon as its stator temperature reaches __(1)__ degrees F.
: 2)  At Time = 1205, Tech Spec 3.4.5 (RCS Loops - MODE 3) Condition(s) __(2)__ apply. Which ONE of the following completes the statements above?
REFERENCE PROVIDED A. 1. 260 2. A  B. 1. 260 2. A and C C. 1. 295 2. A  D. 1. 295 2. A and C Page 77 of 100 Question:
(1 point) 78ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor in MODE 5  LPI aligned to normal DHR mode  Low Range Cooldown Pressure = 5 psig Which ONE of the following:
: 1)  are the MINIMUM conditions that would indicate a TOTAL loss of LPI flow?
: 2)  actions are taken to control RCS pressure in accordance with AP/26 (Loss of Decay Heat Removal) once a total loss of LPI flow has occurred?
NOTE: 1SA-3/C8 = LP Injection Loop A Flow High/Low 1SA-3/C9 = LP Injection Loop B Flow High/Low A. 1. 1SA-3/C8 ONLY with Train A LPI flow = 0 gpm 2. Initiate Enclosure 5.18 (SSF Operation For Loss of DHR Events
)  B. 1. 1S A-3/C8 ONLY with Train A LPI flow = 0 gpm2. Cycle 1RC-66 C. 1. 1S A-3/C8 AND 1SA-3/C9 actuated with Train A AND Train B LPI flow = 0 gpm 2. Initiate Enclosure 5.18 (SSF Operation For Loss of DHR Events
)  D. 1. 1SA-3/C8 AND 1SA-3/C9 actuated with Train A AND Train B LPI flow = 0 gpm 2. Cycle 1RC-66 Page 78 of 100 Question:
(1 point) 79ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions:  Reactor power = 100%  BOTH channels of AMSAC disabled Current conditions:  Both Main Feedwater Pumps Tripped  Reactor power = 60% and slowly decreasing
: 1)  1A MDEFWP, 1B MDEFWP AND the TDEFWP __(1)__ automatically start.
: 2)  In accordance with B&W analysis, a MINIMUM of __ (2)__ gallons per minute of Emergency Feedwater flow is required to limit the RCS pressure increase to below the design standard for this event.
Which ONE of the following completes the statements above?
A. 1. will 2. 750  B. 1. will NOT 2. 750  C. 1. will 2. 375  D. 1. will NOT 2. 375  Page 79 of 100 Question:
(1 point) 80ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Time = 1200:  Reactor power = 100%  1SA6/B2 INVERTER 1DID SYSTEM TROUBLE actuated Time = 1205  NEO reports:
o 1SA13/A8 INVERTER 1DID INPUT VOLTAGE LOW actuated o Inverter 1DID output voltage low
: 1)  The status of 1KVID at Time = 1205 is __(1)__.
: 2)  The MINIMUM action(s) required to restore the 1DID inverter to OPERABLE in accordance with Tech Spec 3.8.6 (Vital Inverters-Operating) is/are to restore DC input voltage __(2)__.
Which ONE of the following completes the statements above?
A. 1. NOT energized 2. ONLY  B. 1. NOT energized 2. AND re-connect to 1KVID C. 1. Energized 2. ONLY  D. 1. Energized 2. AND re-connect to 1KVID Page 80 of 100 Question:
(1 point) 81ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Time = 1200  Reactor power = 100%  1RIA-60 = 35 gpm stable
Time = 1215  Main Turbine manually tripped due to  high bearing vibration Time = 1245  Steam Line Break in 1A Steam Generator
: 1)  The __(1)__ tab will be used to stabilize the plant following the reactor trip.
: 2)  The __(2)__ tab will direct the unit cooldown to LPI.
Which ONE of the following completes the statements above?
A. 1. Subsequent Actions 2. SGTR  B. 1. SGT R 2. SGTR  C. 1. Subsequent Actions 2. Forced Cooldown D. 1. SGT R 2. Forced Cooldown Page 81 of 100 Question:
(1 point) 82ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Time = 1200  Reactor Power = 100%  Control Rod Group 5 Rod 4 ONLY has partially inserted and indicates 90% withdrawn Time = 1330  Reactor Power = 55% stable Time = 1400  Control Rod Group 3 Rod 1 has dropped and indicates 0% withdrawn At Time = 1330 Control Rod Group 5 Rod 4 is considered __(1)__ in accordance with Tech Spec 3.1.4 (Control rod Group Alignment Limits),.
At Time = 1400 the CRS will direct the RO's to __(2)__.
Which ONE of the following completes the statements above?
A. 1. misaligned ONLY 2. notif y SPOC to reduce RPS trip setpoints B. 1. misaligned ONLY 2. trip the Reactor C. 1. Inoperable 2. notif y SPOC to reduce RPS trip setpoints D. 1. Inoperable 2. trip the Reactor Page 82 of 100 Question:
(1 point) 83ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions  Reactor Power = 100%  A Fire has been identified in the Reactor Building  AP/43 (Fire Brigade Response Procedure) is in progress  AP/50 (Challenging Plant Fire) has been initiated
Current conditions:  Reactor in MODE 3  Steam Generator level indications in the control room are erratic and suspected to be inaccurate due to the fire
Which ONE of the following:
: 1)  states the definition of a "Challenging Fire" in accordance with AP/43?
: 2)  should be used to validate the Steam Generator level indication in accordance with AP/50?  A. 1. A fire that is burning cables (bundles/ trays which have the potential to affect additional equipment) 2. SSF Steam Generator level B. 1. A fire that is burning cables (bundles/ trays which have the potential to affect additional equipment) 2. Aux Shutdown Panel Steam Generator level C. 1. A fire in the plant that is NOT extinguished within 15 minutes of Control Room notification 2. SSF Steam Generator level D. 1. A fire in the plant that is NOT extinguished within 15 minutes of Control Room notification 2. Aux Shutdown Panel Steam Generato rlevel  Page 83 of 100 Question:
(1 point) 84ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial Conditions:  Reactor Power = 50% stable  Toxic gas is entering the Control room Current Conditions:  The Reactor has been manually tripped  KHU's have been Emergency Started  1HP-24 has been opened Which ONE of the following describes the: 
: 1)  initial actions directed to control Pressurizer level in accordance with AP/8?
: 2)  Pressurizer level instrumentation available at the alternate location INITIALLY used in accordance with AP/8 (Loss of Control Room)?
A. 1. At ASDP, take control of the 1B HPI pump and 1HP-120 to control level 2. Temperature compensated Pzr level B. 1. At SSF, start the SSF-RCMUP and adjust RC makeup and letdown to control level 2. Temperature compensated Pzr level C. 1. At ASDP, take control of the 1B HPI pump and 1HP-120 to control level 2. Uncompensated Pzr level D. 1. At SSF, start the SSF-RCMUP and adjust RC makeup and letdown to control level 2. Uncompensated Pzr level Page 84 of 100 Question:
(1 point) 85ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions:  Time = 1200  Reactor power = 80% stable  1B2 RCP breaker fails causing the 1B2 RCP to trip Current conditions:  Time = 1300  Control Rod #2 in Group 4 drops into core Which ONE of the following states the:
: 1)  abnormal procedure entered at Time = 1200?
: 2)  procedure that will be used to reach the final power level required by the dropped rod?  A. 1. AP/1 (Unit Runbac k) 2. AP/1 (Unit Runback)
B. 1. AP/1 (Unit Runbac k) 2. OP/1/A/1102/004 (Operation at Power
)  C. 1. AP/16 (Abnormal RCP Operations)2. AP/1 (Unit Runbac k)  D. 1. AP/16 (Abnormal RCP Operations) 2. OP/1/A/1102/004 (Operation at Power
)  Page 85 of 100 Question:
(1 point) 86ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Time = 1200:  Reactor Power = 100%  1A HPI Pump operating  1B HPI Pump in AUTO Time = 1202:  A seal supply filter problem results in total Reactor Coolant Pump seal injection flow decreasing to 25 gpm
: 1)  At time 1202 the 1B HPI pump is __(1)__.
: 2)  The low seal injection flow Auto Start of the 1B HPI pump __(2)__ required to be operable for the 1B HPI pump to be Operable in accordance with Tech Spec 3.5.2 (HPI). Which ONE of the following completes the statements above?
Assume NO operator actions A. 1. running 2. is  B. 1. running 2. is NOT C. 1. NOT running2. is  D. 1. NOT running 2. is NOT Page 86 of 100 Question:
(1 point) 87ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Time = 1215  Unit shutdown in progress  1A1 RCP in operation  Tcold = 220&deg;F slowly decreasing  RCS Pressure 325 psig slowly decreasing  LPI Cooler outlet temperature = 110&deg;F stable Time = 1230  Tcold = 200&deg;F slowly decreasing  RCS Pressure 275 psig slowly stable  LPI Cooler outlet temperature = 110&deg;F stable  1A LPI Pump is started Time = 1240  Tcold = 197&deg;F stable  1A1 RCP secured Time = 1245  LPI Cooler outlet temperature = 180&deg;F stable
: 1)  The RCS cooldown rate  __(1)__ violate the maximum cooldown rate allowed per Tech Specs?
: 2)  When the 1A LPI pump is started at Time = 1230, the temperature transient that results from the difference in LPI Cooler Outlet temperature and Tcold __(2)__ outside the bounds of the Reactor Vessel stress analysis?
Which ONE of the following completes the statements above?
A. 1. does 2. is  B. 1. does 2. is NOT C. 1. does NOT 2. is  D. 1. does NOT 2. is NOT Page 87 of 100 Question:
(1 point) 88ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial Conditions  Reactor power = 100%  BOTH Main FDW pumps trip Current Conditions  Reactor power = 28% decreasing  RULE 1 (ATWS/UNPP) is complete  1RC-66 is failed open  Pressurizer level = 400" stable
: 1)  The UNPP tab __(1)__ direct closing 1RC-4.
: 2)  The HIGHEST RCS pressure that will allow a retransfer to Subsequent Actions is less than __(2)__ psig.
Which ONE of the following completes the statements above?
A. 1. will 2. 2450  B. 1. will NOT 2. 2450  C. 1. will 2. 2300  D. 1. will NOT 2. 2300  Page 88 of 100 Question:
(1 point) 89ILT44 ONS SRO NRC Examination Oconee Nuclear Station Unit 1 initial conditions:  RCS temperature = 310&deg;F stable  1A2 and 1B2 RCPs operating  Unit Auxiliaries powered from CT-1 Current conditions:  RC Makeup Flow = 150 gpm  PCB-17 AND PCB-18 trip OPEN Which ONE of the following describes the: 
: 1)  status of Reactor Coolant Pumps
: 2)  MAXIMUM cooldown rate allowed in accordance with the EOP once cooldown to LPI has commenced?
A. 1. Off 2. 50&deg;F pe r hour  B. 1. Off 2. 50&deg;F per 1/2 hou r  C. 1. On 2. 50&deg;F per hou r  D. 1. On 2. 50&deg;F per 1/2 hour Page 89 of 100 Question:
(1 point) 90ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Time = 1200  Reactor power = 100%  BOTH AFIS channels in OFF Time = 1205  Large MSLB inside the RB occurs  ES Channels 1-8 have actuated Time = 1207  Component status as pictured below
: 1)  Reactor Building Cooling Units __(1)__ operating as designed.
: 2)  Systems and/or equipment required to ensure Reactor Building Pressure is maintained below the design pressure of the Reactor Building __(2)__ available.
Which ONE of the following completes the statements above?
ASSUME NO OPERATOR ACTIONS A. 1. are 2. is    B. 1. are NOT 2. is    C. 1. are 2. is NOT D. 1. are NO T 2. is NOT Page 90 of 100 Question:
(1 point) 91ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 3 plant conditions:Time = 1200  Reactor in MODE 1  RBNS level 20 inches increasing  LPSW leak into RB  Begin pumping RBNS using 1A and 1B RBNS Pumps Time = 1205  RBNS level as indicated below Time = 1230  RBNS level indication unchanged from Time = 1205 Which ONE of the following states: 
: 1)  if Condition A of Tech Spec 3.4.15 must be entered?
: 2)  which RIA can be used to satisfy the requirements of TS 3.4.15 LCO?
REFERENCE PROVIDED A. 1. Yes 2. 1RIA-47  B. 1. Yes 2. 1RIA-49 C. 1. No 2. 1RIA-47  D. 1. No 2. 1RIA-49 Page 91 of 100 Question:
(1 point) 92ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Time = 1200  Reactor power = 100%  Relative Position Indication (RPI) inoperable for ALL Control Rods Time = 1230  Absolute Position Indication (API) inoperable for Group 1 Rod 7 Control Rod
Current Conditions:  Tech Spec 3.1.4 Required Action A.2.1.1 (SDM Verification) has just been completed and shutdown margin requirements of the COLR have been determined to be NOT met
Which ONE of the following:
: 1)  is the LATEST time that Group 1 Rod 7 Control Rod must be declared inoperable in accordance with Tech Specs?
: 2)  should be used to restore shutdown margin requirements in accordance with Tech Spec bases?
REFERENCE ATTACHED A. 1. 1230 2. OP/1/A/1103/004A Enclosure 4.1 (RCS Boration from CBAST With CBAST Pump) ONLY  B. 1. 1230 2. OP/1/A/1103/004A Enclosure 4.1 (RCS Boration from CBAST With CBAST Pump) OR OP/1/A/1103/004 Enclosure 4.4 (RCS Makeup From 1A BHUT C. 1. 1330 2. OP/1/A/1103/004A Enclosure 4.1 (RCS Boration from CBAST With CBAST Pump) ONLY D. 1. 1330 2. OP/1/A/1103/004A Enclosure 4.1 (RCS Boration from CBAST With CBAST Pump) OR OP/1/A/1103/004 Enclosure 4.4 (RCS Makeup From 1A BHUT Page 92 of 100 Question:
(1 point) 93ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Time = 0900  Reactor trip due a sheared RCP shaft on 1A1 RCP  Control Room has indications that the 1A1 RCP seals have failed.
Time = 0904  ES 1 & 2 actuate on low RCS Pressure. The 1A HPI pump fails to Auto start and cannot be started manually.
Time = 0910  RCS saturated and stable at 1000 psig. Rule 2 is complete Time = 0919  1RIA-57 reads 350 R/HR and stable. RB Pressure = 2.6 psig slowly increasing Time = 0920  RB Pressure = 0.2 psig decreasing Which ONE of the following states the:
: 1)  position of 1HP-410?
: 2)  Emergency Classification in accordance with RP/0/A/1000/001 (Emergency Classification)?
REFERENCE PROVIDED DO NOT USE EMERGENCY COORDINATOR JUDGEMENT WHEN DETERMINING CLASSIFICATION A. 1. Open 2. General Emer gency  B. 1. Open 2. Site Area Emer gency  C. 1. Closed 2. General Emer gency  D. 1. Closed 2. Site Area Emer gency  Page 93 of 100 Question:
(1 point) 94ILT44 ONS SRO NRC Examination Oconee Nuclear Station In accordance with AD-OP-ALL-1000 (Conduct of Operations), 
: 1)  The CRS __(1)__  allowed to correct archived log entries when the original watchstander will not be available in the near future.
: 2)  the MINIMUM level of management with overall responsibility for the approval of the quality of Unit Log entries is the __(2)__.
Which ONE of the following completes the statements above A. 1. is 2. SM  B. 1. is 2. CRS  C. 1. is NOT 2. SM  D. 1. is NOT 2. CRS  Page 94 of 100 Question:
(1 point) 95ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor power = 100%  Main T/G Journal Bearing #7 vibration as described below:
Which ONE of the following describes:
: 1)  The EARLIEST time that the Main Turbine must be manually tripped in accordance with Limits and Precautions of OP/1/A/1106/001 (Turbine Generator)?
: 2)  The procedure that would be used to take the Main Turbine off line without tripping the Reactor?
A. 1. 1216 2. AP/29 (Rapid Unit Shutdown)
B. 1. 1216 2. OP/1/A/1106/001 (Turbine Generator)
C. 1. 1224 2. AP/29 (Rapid Unit Shutdown)
D. 1. 1224 2. OP/1/A/1106/001 (Turbine Generator)
Page 95 of 100 Question:
(1 point) 96ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 2 conditions: Reactor in MODE 5  Maintenance is required on 2FDW-105 (2A SG SAMPLE)  Multiple electrical valve manipulations of 2FDW-105 are required as part of the repairs  A check valve needs to be used as one of the isolation boundary valves Which ONE of the following describes the requirements in accordance with NSD 500 (Red Tags/Configuration Control Tags) for:
: 1)  the lowest level of Operations Management approval required for the tagout?
: 2)  who must approve the use of wax string to attach a Red Tag to its associated component?
A. 1. ANY Licensed SRO 2. Shift Mana ger  B. 1. Any Operations Manager2. Shift Mana ger  C. 1. ANY Licensed SRO 2. Operational Control Group superviso r  D. 1. Any Operations Manager2. Operational Control Group superviso r  Page 96 of 100 Question:
(1 point) 97ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor = Mode 3  "B" shift is performing a plant startup following a refueling outage in progress  PT/0/A/0711/001 (Zero Power Physics Testing) is to be performed
Which ONE of the following is the LOWEST level of management that meets the expectations provided in NSD 213 (Risk Management Process) regarding who can provide the 91-01 IPTE briefing associated with ZPPT?
A. "B" shift Shift Technical Advisor B. Reactor Engineering Supervisor C. "B" shift Shift Manager (Operations Shift Manager)
D. Operations Manager (Superintendant of Operations)
Page 97 of 100 Question:
(1 point) 98ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions:  Mode 6  Defueling in progress  1RIA-3 (Fuel Transfer Canal Monitor) = 4 mr/hr stable  Main Fuel Bridge Area Monitor = 6 mr/hr stable Current conditions:  1RIA-3 local reading = 0 mr/hr  1RIA-3 View Node indication is magenta The Refueling SRO will determine that Fuel Handling activities in the Reactor Building may ______ in accordance with OP/1/A/1502/007 (Operations Defueling/Refueling Responsibilities)?
Which ONE of the following completes the statement above?
A. NOT continue until a portable area monitor with local alarm capability is in place. B. continue because onl y the Main Fuel Brid ge Area Monitor is required.
C. NOT continue until continuous RP coverage is present on the Main Fuel Bridge. D. continue provided the audiblealarm associatedwith 1RI A-49 (RB Normal Gas) is operable.
Page 98 of 100 Question:
(1 point) 99ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor trip has occurred  Main Turbine status as indicated below SRO directs performance of Immediate Manual Actions
: 1)  The Reactor Operator performing IMA's __(1)__ expected to depress the "Turbine Trip" pushbutton.
: 2)  IF the Main Turbine is not tripped during performance of IMA's, the basis behind requiring the EHC pumps being secured is to prevent __(2)__.
Which ONE of the following completes the statements above?
A. 1. is 2. water from reachin g the Main Turbine durin g a SG overfeed B. 1. is 2. excessive RCS cooldown C. 1. is NOT 2. water from reachin g the Main Turbine durin g a SG overfeed D. 1. is NOT 2. excessive RCS cooldown Page 99 of 100 Question:
(1 point) 100ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor Power = 100%  Operating CC pump trips and standby fails to Auto start  CC Surge tank level = 28" stable  Letdown Temperature = 138&deg;F increasing  The following alarms have actuated and associated actions are being performed:
o 1SA-9/B-1 (CC CRD Return Flow Low).
o 1SA-2/C-1 (HP Letdown Temperature High) o 1SA-9/C-1 (CC Component Cooling Return Flow Low)
Which ONE of the following states:
: 1)  The SETPOINT (degrees F) at which 1SA-2/C1 actuated?
: 2)  The Procedure that will be entered FIRST if actions directed in the associated Alarm Response guides fail to restore normal system parameters?
A. 1. 130 2. AP/20 (Loss of Component Coolin g)  B. 1. 130 2. AP/32 (Loss of Letdown)
C. 1. 135 2. AP/20 (Loss of Component Coolin g)  D. 1. 135 2. AP/32 (Loss of Letdown
)  Page 100 of 100 Examination KEY for:ILT44 ONS SRO NRC ExaminQuestionNumberAnswer1B2B3C4C5B6A7D8B9A10A11A12C13D14C15B16C17D18D19B20C21D22A23B24B25DPrinted 12/17/2013 8:20:05 AMPage 1 of 4 Examination KEY for:ILT44 ONS SRO NRC ExaminQuestionNumberAnswer26A27C28A29C30D31D32D33C34A35A36C37B38C39C40A41B42A43C44A45D46A47C48C49D50DPrinted 12/17/2013 8:20:06 AMPage 2 of 4 Examination KEY for:ILT44 ONS SRO NRC ExaminQuestionNumberAnswer51B52B53D54D55B56C57C58A59B60D61C62A63A64B65B66B67B68B69D70A71B72D73A74A75BPrinted 12/17/2013 8:20:06 AMPage 3 of 4 Examination KEY for:ILT44 ONS SRO NRC ExaminQuestionNumberAnswer76D77C78D79A80B81B82D83A84A85A86D87B88D89A90C91A92A93C94B95C96B97D98A99B100APrinted 12/17/2013 8:20:06 AMPage 4 of 4}}

Revision as of 08:48, 3 July 2018

Oconee 2013-302 Initial Exam Final SRO Written Exam
ML13364A337
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 12/30/2013
From:
NRC/RGN-III
To:
References
Download: ML13364A337 (104)


Text

Question:

(1 point) 1ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following plant conditions: Unit 1 has just reached 100% power following a refueling outage Unit 2 is at 100% power with 93 EFPD Which ONE of the following will result in the highest amount of Emergency Feedwater flow required to stabilize RCS temperature 5 minutes following the trip?

A. Both Main Feedwater PumpsONLY trip on Unit 1 B. Both Main Feedwater Pumps ONLY trip on Unit 2 C. Loss of Offsite Power on Unit 1 D. Loss of Offsite Power on Unit 2 Page 1 of 100 Question:

(1 point) 2ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor power = 100% 1RC-66 (PORV) is leaking past its seat Pressurizer temperature = 648 0F Quench tank pressure = 5 psig Reactor Building pressure = 0 psig Which ONE of the following describes the expected tailpipe temperature (°F) downstream of 1RC-66?

A. 212 B. 228 C. 272 D. 648 Page 2 of 100 Question:

(1 point) 3ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor tripped from 100% power due to SBLOCA 1A HPI Pump failed Subcooling Margin = 0°F stable Which ONE of the following is the reason the EOP directs increasing SG levels to the Loss of Subcooling Margin Setpoint level?

A. Establish a large secondary side inventory in support of a rapid RCS cooldown.

B. Establish a large secondary side inventory to ensure that a loss of coupling will NOT occur if a momentary loss of EFDW occurs.

C. Ensure a secondary water level higher than the primary water level inside the SG tubes to establish boiler condenser mode heat transfe r D. Ensure a secondary side levelsufficient to minimize the consequences of a total loss of feedwater during boiler condenser mode heat transfer Page 3 of 100 Question:

(1 point) 4ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor power = 50% stable 1B2 RCP is OFF Which ONE of the following would require immediate entry into AP/1/A/1700/016 (Abnormal Reactor Coolant Pump Operation)?

A. OAC point O1A0061 (RCP 1A1 MTR INPUT POWER) in HI alarm B. OAC point O1A1579 (RCP 1A2 MTR LOWER AIR TEMP) in HI alarm C. 1SA-15/A5 (RC PUMP MOTOR 1B1 OIL POT LOW LEVEL) in alarm D. 1SA-6/D5 (PUMP 1B2 CAVITY PRESS HI/LOW

) in alarm Page 4 of 100 Question:

(1 point) 5ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions: Reactor power = 100%

Current conditions:

LPI Flow Train A = 1800 gpm stable LPI Flow Train B = 1780 gpm stable Rule 2 (Loss of SCM) in progress. IMAs complete

1) The SRO will direct actions from the __ (1) __ tab of the EOP.
2) In accordance with Rule 2, performance of Rule 3 (Loss of Main or Emergency FDW) __ (2) __ required.

Which ONE of the following completes the statements above?

A. 1. LOSCM 2. is B. 1. LOSCM 2. is NOT C. 1. ICC 2. is D. 1. ICC 2. is NOT Page 5 of 100 Question:

(1 point) 6ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions: Normal LPI decay heat removal in service Current conditions: Loss of offsite power occurs Power restored via CT-4 1A and 1B LPI Pumps NOT available Which ONE of the following describes the requirements to start the 1C LPI Pump?

Manual reset of Load Shed is __(1)___ and starting of 1C LPI Pump is allowed after a MINIMUM of ___(2)__ seconds.

A. 1. NOT required 2. 5 B. 1. required 2. 5 C. 1. NOT required 2. 30 D. 1. required 2. 30 Page 6 of 100 Question:

(1 point) 7ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor trip has just occurred Total RCP seal injection flow = 0 gpm Running Component Cooling pump tripped Standby CC pump did not start Which ONE of the following describes the procedure whose performance is directed by the EOP and why?

Initiate-

A. AP/20 (Loss of CC) to restore Component Cooling B. AP/20 (Loss of CC) to ensure letdown is isolated C. AP/25 (SSF EOP) to align an alternate letdown flowpath D. AP/25 (SSF EOP) to align an alternate source of seal in jection Page 7 of 100 Question:

(1 point) 8ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions: Reactor power = 90% 1B Main Feedwater pump trips Current conditions: Reactor power = 70% decreasing RCS pressure = 2165 psig slowly decreasing Pressurizer level = 228 inches slowly decreasing Pressurizer temperature = 640°F slowly decreasing Pressurizer heater bank 1 (Group A and K) is ON Pressurizer heater banks 2, 3, and 4 are in AUTO and are OFF The pressurizer is ___(1)____ AND the pressurizer heater bank 2 ___(2)____.

Which ONE of the following completes the statement above?

A. 1. subcooled 2. will ener gize at 2145 psi g B. 1. subcooled 2. should be ener gized C. 1. saturated 2. will ener gize at 2145 psi g D. 1. saturated 2. should be energized Page 8 of 100 Question:

(1 point) 9ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 2 conditions: Loss of all sources of Feedwater has occurred RCS Pressure = 2250 psig increasing Pressurizer level = 294 inches increasing ALL SCM's = 24°F slowly decreasing What is the:

1) lowest RCS pressure (psig) that will require Rule 4 (Initiation of HPI Forced Cooling) to be performed?
2) PRIMARY reason for reducing the number of operating RCP's in accordance with Rule 4? A. 1. 2300 2. Reduce the heat input to the RCS B. 1. 2300 2. Provide the ability to recover from HPI forced cooling and re-establish a Pressurizer bubble.

C. 1. 2255 2. Reduce the heat input to the RCS D. 1. 2255 2. Provide the ability to recover from HPI forced cooling and re-establish a Pressurizer bubble.

Page 9 of 100 Question:

(1 point) 10ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 3 conditions: Reactor power = 100%

Which ONE of the following will result in a Tech Spec LCO being NOT met?

A. 3A SGTL rate = 160 gpd B. 3B Core Flood Tank level = 12.69 feet C. 3B Core Flood Tank pressure = 622 psig D. 4 gpm RCS leak identified as being through valve stem packing of 3HP-1 Page 10 of 100 Question:

(1 point) 11ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: ALL sources of feedwater have been lost Rule 4 (Initiation of HPI Forced Cooling) is complete with outstanding IAAT's 1A HPI pump has failed HPI flow parameters are as indicated below In accordance with Rule 4, __(1)__ RCP('s) is/are operating and HPI flow __(2)__ required to be throttled.

Which ONE of the following completes the statement above?

A. 1. 1 2. is B. 1. 1 2. is NOT C. 1. 2 2. is D. 1. 2 2. is NOT Page 11 of 100 Question:

(1 point) 12ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 Conditions:Initial conditions: Reactor Power = 100% ACB-4 closed Current conditions: Reactor trip CT-1 Locks out KHU-2 Emergency Lockout occurs Assuming no additional failures, which ONE of the following describes the first method used to restore power to Unit 1 MFB's?

A. Automatically through ACB-3 B. Automaticall y through SL1 and SL2 C. Manually through ACB-3 in accordance with Enclosure 5.38 (Restoration of Power) of the EOP D. Manually through SL1 and SL2 in accordance with Enclosure 5.38 (Restoration of Power) of the EOP Page 12 of 100 Question:

(1 point) 13ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Unit shutdown in progress Reactor power = 38% slowly decreasing LOOP (Switchyard Isolation) occurs

1) Based on the conditions above, the status of the Main Turbine will be __(1)__ 5 minutes following the LOOP?
2) ANYTIME the Main Turbine is tripped, ICS uses __(2)__ to control the Turbine Bypass Valves?

Which ONE of the following completes the statements above?

A. 1. tripped 2. Turbine Header Pressure B. 1. tripped 2. Steam Generator Outlet Pressure C. 1. NOT tripped 2. Turbine Header Pressure D. 1. NOT tripped 2. Steam Generator Outlet Pressure Page 13 of 100 Question:

(1 point) 14ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions Reactor Power = 100% SASS in Manual while SPOC repairs Pressurizer Level 3 level transmitter 1HP-120 in AUTO selected to Pressurizer Level 1 Current conditions: Vital Power to ICCM Train A fails Which ONE of the following describes Pressurizer level control with 1HP-120?

A. Selecting Pressurizer Level 2and depressing the AUTO pushbutton on 1HP-120 are required to restore automatic controlat setpoint B. Selectin g Pressurizer Le vel 2ONLY will restore automatic control at setpoint C. Manual control using 1HP-120 Bailey controller is all that is available D. Additional actions are NOT required since Automatic controlat setoint is retained Page 14 of 100 Question:

(1 point) 15ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions: Reactor power = 100% Instrument Air pressure = 85 psig decreasing AP/22 (Loss of Instrument Air) has been initiated Which ONE of the following

1) is the higher Instrument Air pressure (psig) that would require an immediate manual Reactor trip in accordance with AP/22?
2) states the reason AP/22 directs tripping the Main FDW pumps immediately after tripping the Reactor as described above?

A. 1. 70 2. Controllin g FDW valves fail "as is" B. 1. 65 2. Controllin g FDW valves fail "as is" C. 1. 70 2. Controllin g FDW valves fail closed D. 1. 65 2. Controllin g FDW valves fail closed Page 15 of 100 Question:

(1 point) 16ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions: AP/34 (Degraded Grid) in progress Generator output = 850 MWe and 450 MVARs Generator Hydrogen Pressure = 60 psig Generator Output Voltage = 18.2 KV

1) The Generator output __ (1) __ within the limits of the Generator Capability Curve.
2) If the generator exceeds the Underfrequency Maximum Allowable Time given in AP/34 (Degraded Grid) the Main Turbine __ (2) __ automatically trip.

Which ONE of the following completes the statements above?

REFERENCE PROVIDED A. 1. is NOT 2. will B. 1. is NOT 2. will NOT C. 1. is 2. will D. 1. is 2. will NOT Page 16 of 100 Question:

(1 point) 17ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 3 conditions: A brief loss of power has occurred Unit auxiliaries are being supplied from the switchyard via CT-3 Subsequent Actions tab in progress

1) Subsequent Actions directs restarting __(1)__.
2) The __(2)__ RCP will provide the best Pressurizer Spray.

Which ONE of the following completes the statements above?

A. 1. one RCP ONLY 2. 3A1 B. 1. one RCP ONLY 2. 3B1 C. 1. one RCP per loop 2. 3A1 D. 1. one RCP per loop 2. 3B1 Page 17 of 100 Question:

(1 point) 18ILT44 ONS SRO NRC Examination Oconee Nuclear Station In accordance with the EOP, which ONE of the following describes the instruments that are used when initially stabilizing RCS temperature following a Main Steam Line Break and states one of the reasons why they are used?

A. Tcolds are used since Tech Specs specifies that Tcold is RCS temperature B. Tcolds are used since they are the coldest temperature and therefore most indicative of PTS issues C. CETC's are used since the resultant RCS cooldown may result in Tcold being off scale low D. CETC's are used since they are qualified instruments and are therefore more reliable in the hostile containment environment Page 18 of 100 Question:

(1 point) 19ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions: Time = 1200 Reactor power = 100% 1A steam generator tube leak = 2.1 gpd stable RCS activity = 0.25 Ci/ml DEI increasing Current conditions: Time = 1400 NO change in 1A SG tube leak rate RCS activity = 0.65 Ci/ml DEI increasing Which ONE of the following describes the response of the radiation monitors between 1200 and 1400?

A. 1RIA-59 (N-16 monitor) and 1RIA-40 (CSAE Off-gas) increased.

B. 1RIA-16 (Main Steam Line Monitor

) and 1RIA-40 increased.

C. 1RIA-59 increased while1RIA-40 remained constant.

D. 1RIA-16 increased while 1RI A-40 remained constant.

Page 19 of 100 Question:

(1 point) 20ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 2 condition:Initial conditions: Time = 0900 Reactor Startup in progress NI 1 & 2 = 370 cps NI 3 & 4 = 0 cps (out of service) ALL WR NI's = ~ 2.7 E-4%

Current conditions: Time = 0901 NI 1 & 2 are inoperable Which ONE of the following describes:

1) immediate actions required by Tech Spec 3.3.9 (Source Range Neutron Flux)?
2) the reason for the actions described above?

A. 1. Insert Control Rods to Group 1 at 50% withdrawn2. Prevents power increases when the primary power indication for the operator is not available.

B. 1. Insert Control Rods to Group 1 at 50% withdrawn2. 2 dpm Startup Rate Control Rod Out Inhibit is no lon ger available C. 1. Fully insert all Control Rods2. Prevents power increases when the primary power indication for the operator is not available.

D. 1. Fully insert all Control Rods2. 2 dpm Startup Rate Control Rod Out Inhibit is no longer available Page 20 of 100 Question:

(1 point) 21ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor power = 92% decreasing Unit shutdown in progress per the SGTR tab

1) In accordance with the SGTR tab and Enclosure 5.5 (Pzr and LDST Level Control), RCS makeup and letdown will be adjusted to maintain Pressurizer level betw een __ (1) __ inches.
2) The reason for this Pzr level band is to provide adequate inventory to __ (2) __.

Which ONE of the following completes the statements above?

A. 1. 140

- 180 2. ensure Pzr heaters will remain covered if a subsequent reactor trip occurs B. 1. 140

- 180 2. accommodate system shrinkage during shutdown/cooldown from 18% power C. 1. 220

- 260 2. ensure Pzr heaters will remain covered if a subsequent reactor trip occurs D. 1. 220 - 260 2. accommodate system shrinkage during shutdown/cooldown from 18% power Page 21 of 100 Question:

(1 point) 22ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor power = 100%

Which ONE of the following will result in an AUTOMATIC trip of the Main Turbine?

A. Bearing Oil Pressure = 5.5 psig B. Main Turbine speed = 1955 RPM C. EHC Hydraulic Oil pressure = 1210 psig D. EITHER Steam Generator Level = 93% OR Page 22 of 100 Question:

(1 point) 23ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions: Reactor power = 100% 1A GWD tank release in progress 1RIA-38 OOS Current conditions: Maintenance activities in the area result in an inadvertent loss of power to RM-80 skid of 1RIA-37 1SA8/B9 RM PROCESS MONITOR RADIATION HIGH in alarm 1SA8/B10 RM PROCESS MONITOR FAULT in alarm

1) 1GWD-4 (A GWD TANK DISCHARGE) should __(1)__.
2) The required Completion Time in SLC 16.11.3 (Radioactive Effluent Monitoring Instrumentation) for suspending the release by this pathway if not already isolated and both 1RIA-37 and 1RIA-38 become inoperable is __(2)__.

Which ONE of the following completes the statements above?

A. 1. remain open 2. immediatel y B. 1. automatically close 2. immediatel y C. 1. remain open 2. 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> D. 1. automatically close 2. 1 hou r Page 23 of 100 Question:

(1 point) 24ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor power = 2% 1SA2/B11 (ICS AUTO POWER FAILURE) actuated 1SA2/B13 (ICS HAND POWER FAILURE) actuated Which ONE of the following describes:

1) the level at which SGs will be maintained?
2) how decay heat removal from the core is controlled?

A. 1. 25 inches SUR 2. ADVs B. 1. 30 inches XSUR 2. ADVs C. 1. 25 inches SU R 2. TBVs D. 1. 30 inches XSUR 2. TBVs Page 24 of 100 Question:

(1 point) 25ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions: Switchyard isolation occurs Current conditions: Shutdown of KHU's is desired Which ONE of the following states:

1) if a Load Shed has occurred?
2) the procedure that will be used to perform a remote shutdown of the KHU's?

A. 1. Yes 2. OP/0/A/2000/041 (Keowee Modes of Operations

) B. 1. No 2. OP/0/A/2000/041 (Keowee Modes of Operations

) C. 1. Yes 2. OP/0/A/1106/019 (Keowee Hydro AtOconee

) D. 1. No 2. OP/0/A/1106/019 (Keowee Hydro AtOconee

) Page 25 of 100 Question:

(1 point) 26ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: ES 1-8 have actuated LOCA CD tab in progress RCS pressure = 423 psig slowly decreasing 1A LPI Pump operating in the Piggyback alignment Which ONE of the following describes the:

1) operational limitations on the operating LPI pump?
2) pump(s) being protected by the above limitation?

A. 1. Maximized to < 3100 gpm 2. LPI B. 1. Maximized to < 3100 gpm2. HPI C. 1. Maximized to < 2900 gpm2. LPI D. 1. Maximized to < 2900 gpm2. HPI Page 26 of 100 Question:

(1 point) 27ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor trip from 100% due to a SBLOCA Reactor building pressure has peaked at 1.7 psig Subcooled margins are stable as indicated below Which ONE of the following describes how Feedwater will be used to mitigate this event? Steam Generator levels will be controlled at ________?

A. 240 inches using Emergency Feedwate r B. 240 inches using Main Feedwater C. Loss of Subcooling Margin setpointusing Emergency Feedwate r D. Loss of Subcoolin g Margin setpointusin g Main Feedwate r Page 27 of 100 Question:

(1 point) 28ILT44 ONS SRO NRC Examination Oconee Nuclear Station Which ONE of the following describes:

1) the design purpose of extending RCP coast down time with the flywheel?
2) an expected core delta T (°F) 30 minutes following a lockout of 1TA and 1TB?

A. 1. Helps prevent the core from reaching DNBR limits2. 35 B. 1. Helps prevent the core from reaching DNBR limits 2. 47 C. 1. Reduces the likelihood of a Reactor trip following a RCP trip at power 2. 35 D. 1. Reduces the likelihood of a Reactor trip following a RCP trip at powe r 2. 47 Page 28 of 100 Question:

(1 point) 29ILT44 ONS SRO NRC Examination Oconee Nuclear Station

1) The Letdown Storage Tank contains approximately __(1)__ gallons of water per inch of level.
2) The HIGHER Letdown Storage Tank level that will automatically open 1HP-24 and 1HP-25 is __(2)__ inches.

Which ONE of the following completes the statements above?

A. 1. 24 2. 38 B. 1. 24 2. 54 C. 1. 31 2. 38 D. 1. 31 2. 54 Page 29 of 100 Question:

(1 point) 30ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 2 conditions: RCS Cooldown in progress 2B LPI cooler isolated due to cooler leak Which ONE of the following states the:

1) LPI Decay Heat Removal mode that will be used for the INITIAL transition to LPI cooling?
2) HIGHER RCS pressure (psig) that will allow aligning LPI in the Normal Decay Heat Removal alignment?

A. 1. Switchover 2. 220 B. 1. High Pressure 2. 220 C. 1. Switchover 2. 115 D. 1. High Pressure 2. 115 Page 30 of 100 Question:

(1 point) 31ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Rule 3 initiated Loss of Heat Transfer tab in progress Efforts underway to re-establish Steam Generator cooling 1SA-18/D1 (RC SYSTEM APPROACHING SATURATED CONDTIONS) in alarm 1SA-2/D3 (RC PRESS HIGH/LOW) in alarm Pressurizer level = 380" slowly increasing RCS pressure = 2240 psig slowly increasing SCM = 0°F Which ONE of the following states which additional EOP Rules (if any) should be initiated?

A. NO additional rules required B. Rule 2 (Loss of SCM) ONLY C. Rule 4 (Initiation of HPI Forced Cooling) ONLY D. Rule 2 AND Rule 4 Page 31 of 100 Question:

(1 point) 32ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 2 condition:Initial conditions: Unit startup in progress RCS temperature = 310°F slowly increasing Maintenance in progress in the area of 2DIB panelboard Current conditions: 2DIB breaker #24 (2RC-66 Pilot Valve DC solenoid power supply) is inadvertently opened Which ONE of the following describes:

1) a Tech Spec Limiting Condition of Operation that is NOT met?
2) the position of 2RC-66?

A. 1. 3.4.9 (Pressurizer) 2. Open B. 1. 3.4.9 (Pressurizer) 2. Closed C. 1. 3.4.12 (LTOP) 2. Open D. 1. 3.4.12 (LTOP) 2. Closed Page 32 of 100 Question:

(1 point) 33ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:

Initial conditions Loss of all Feedwater HPI forced cooling initiated Quench Tank pressure = 40 psig increasing RCS activity indicates no fuel failures present Current conditions Quench Tank pressure = 3 psig stable Which ONE of the following describes the:

1) reactor building RIA's response to the above conditions?
2) valve(s) that will automatically close anytime 1RIA-49 reaches its HIGH alarm setpoint?

A. 1. increases 2. 1LWD-1 AND 1LWD-2 B. 1. remains constant 2. 1LWD-1 AND 1LWD-2 C. 1. increases 2. 1LWD-2 ONLY D. 1. remains constant 2. 1LWD-2 ONLY Page 33 of 100 Question:

(1 point) 34ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: 1SA-08/B-9 (PROCESS MONITOR RADIATION HIGH) 1RIA-50 in HIGH alarm CC Surge Tank level increasing

1) The CC Surge tank __(1)__.
2) If the RCS leakage threatens to overflow the associated waste tank, AP/1/A/1700/002 (Excessive RCS Leakage) will direct __(2)__.

Which ONE of the following completes the statements above?

A. 1. will overflow to the LAWT 2. trippin g the Reactor B. 1. will overflow to the LAWT2. initiatin g a shutdown usin g AP/1/A/1700/029 (Rapid Unit Shutdown

) C. 1. will overflow to a floor drain which drains to the MWHUT2. trippin g the Reactor D. 1. will overflow to a floor drain which drains to the MWHUT 2. initiatin g a shutdown usin g AP/1/A/1700/029 (Rapid Unit Shutdown

) Page 34 of 100 Question:

(1 point) 35ILT44 ONS SRO NRC Examination Oconee Nuclear Station Which ONE of the following states the automatic OPEN setpoints (psig) for 1RC-1 (Pzr Spray) and 1RC-66 (PORV) in Mode 1?

1RC-1 1RC-66 A. 2205 2450 B. 2205 2500 C. 2255 2450 D. 2255 2500

Page 35 of 100 Question:

(1 point) 36ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor power = 100% 1D RPS channel in Manual Bypass 1A RPS Thot RTD fails low Which ONE of the following:

1) describes ALL 1A RPS functions affected by the failure?
2) states if OP/1/A/1105/014 (Control Room Instrumentation Operation And Information) requires tripping the 1A RPS channel?

A. 1. RCS High Outlet Temperature ONLY2. yes B. 1. RCS High Outlet Temperature ONLY 2. no C. 1. RCS High Outlet Temperature and RCS Variable Low Pressure 2. yes D. 1. RCS High Outlet Temperature and RCS Variable Low Pressure 2. no Page 36 of 100 Question:

(1 point) 37ILT44 ONS SRO NRC Examination Oconee Nuclear Station Which ONE of the following describes how RCS Pressure signals are used to provide control signals to the Integrated Control System?

A. Median Selected from one wide range pressure and two channels of RPS narrow range pressure (A and B)

B. Median Selected from three channels of RPS narrow range pressure (A, B, and E) C. 2nd Max Selected from RPS narrow range pressures (A, B, C, & D)

D. 2nd Min Selected from RPS narrow ran ge pressures (A, B, C, & D

) Page 37 of 100 Question:

(1 point) 38ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 2 conditions:Initial conditions: Reactor power = 100%

Current conditions: MSLB occurs RCS pressure = 1580 psig slowly increasing RB peak pressure = 2.8 psig Which ONE of the following describes a valve that has received a signal to CLOSE?

A. 2CC-7 B. 2HP-24 C. 2LWD-2 D. 2LPSW-1062 Page 38 of 100 Question:

(1 point) 39ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following plant conditions:Time = 1200 Unit 1 Reactor power = 100% Unit 2 Reactor power = 100% ACB-4 closed Time = 1201 LOCA occurs on Unit 1 Switchyard Isolation occurs Which ONE of the following states the source of power being used to energize 1DIA at Time = 1202?

A. Control Batteries B. KHU-1 C. KHU-2 D. CT-5 Page 39 of 100 Question:

(1 point) 40ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 2 conditions:Time = 1200 Reactor in MODE 5 LPI aligned to normal Decay Heat Removal mode 2RIA-35 (Combined LPSW effluent leaving the Reactor Building and the Auxiliary Building) is isolated for repair Time = 1300 Large LPI Cooler leak in 2A LPI Cooler occurs Time = 1500 Actions to isolate the 2A LPI Cooler are initiated RCS temperature slowly increasing

1) At Time = 1330 there __(1)__ an RIA alarm indicating the LPI Cooler leak?
2) Entry into MODE 4 will occur when RCS temperature exceeds __(2)__°F?

Which ONE of the following completes the statements above?

A. 1. is 2. 200 B. 1. is 2. 250 C. 1. is NOT 2. 200 D. 1. is NOT 2. 250 Page 40 of 100 Question:

(1 point) 41ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor is in MODE 5 RB Purge in progress Unit 1 vent activity increasing 1RIA-45 HIGH alarm fails to actuate at setpoint

1) Automatic termination of RB Purge operation due to increasing activity __(2)__ available?
2) Purge operation __(1)__ be allowed if the unit were in MODE 4.

Which ONE of the following completes the statements above?

A. 1. is 2. would B. 1. is 2. would NOT C. 1. is NOT 2. would D. 1. is NOT 2. would NOT Page 41 of 100 Question:

(1 point) 42ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: 1A LPSW Pump trips Standby LPSW pump fails to start Which ONE of the following will begin to increase in temperature?

ASSUME NO MANUAL ACTIONS ARE TAKEN A. Letdown B. Spent Fuel Pool C. Main Feedwater Pump oil temperature D. Primary Instrument Air Compresso rdischarge air temperature Page 42 of 100 Question:

(1 point) 43ILT44 ONS SRO NRC Examination Oconee Nuclear Station Which ONE of the following is the power supply for the Unit 2 Auxiliary Instrument Air System compressor?

A. 2XD B. 2XF C. 2XP D. 2XS1 Page 43 of 100 Question:

(1 point) 44ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions: Reactor Power = 100% 1A MSLB inside containment

Current conditions: Core SCM = 18°F stable RB Pressure = 17 psig slowly decreasing Which ONE of the following sets of actions is required by Enclosure 5.1 (ES Actuation)

A. Take ES Channel 1 to manual AND open 1HP-20 B. Take ES Channel 1 to manual AND open 1HP-3 C. Override Odd Voters AND open 1HP-20 D. Override Odd Voters AND open 1HP-3 Page 44 of 100 Question:

(1 point) 45ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions: Reactor Power = 100%

Which ONE of the following:

1) describes the LOWER SG Operating Range level (%) that will result in an automatic trip of both Main Feedwater pumps?
2) states if SG Operating Range level indications are temperature compensated?

A. 1. 87 2. No B. 1. 87 2. Yes C. 1. 97 2. No D. 1. 97 2. Yes Page 45 of 100 Question:

(1 point) 46ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor power = 50% slowly decreasing OAC Unavailable Computer Reactor Calculation Package NOT running Which ONE of the following:

1) is the HIGHER power level (% Power) at which Tech Spec limits on Reactor Power Imbalance do NOT apply?
2) describes how OP/1/A/1105/014 (Control Room Instrumentation Operation And Information) directs the operator to determine if Imbalance limits specified in the COLR have been exceeded?

A. 1. 35 2. by use of CR gages for Power Range NI's B. 1. 35 2. by performin g PT/1/A/1103/019 (Backup Incore Detector S ystem) C. 1. 15 2. by use of CR gages for Power Range NI's D. 1. 15 2. by performin g PT/1/A/1103/019 (Backup Incore Detector S ystem) Page 46 of 100 Question:

(1 point) 47ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions: Mode 6 REFUELING is in progress All four SR NIs in service SR 1NI-1 and SR 1NI-3 are the designated NIs for Fuel Handling Current conditions: Power supply to SR 1NI-1 fails (0 vdc)

Which ONE of the following describes the impact on refueling activities in accordance with OP/1/A/1502/007 (Operations Defueling/Refueling Responsibilities)?

A. Allowed to continue because two other SR NIs remain in service B. Allowed to continue because SR NI-3 is still in service C. Required to be stopped until another SR NI is designated because other NIs are procedurall y allowed to be desi gnated D. Required to be stopped and cannot be resumed until SR 1NI-1 is returned to service because other NIs are NOT procedurally allowed to be designated Page 47 of 100 Question:

(1 point) 48ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Time = 1200 Reactor Power = 40% stable following an instrument failure Turbine Header Pressure = 860 psig stable Feedwater, Reactor, and Main Turbine in Manual Time = 1300 ICS in Automatic Turbine Header Pressure = 860 psig stable Time = 1301 Reactor Trips prior to any additional Turbine Header Pressure setpoint adjustments Which ONE of the following is the pressure (psig) where the Turbine Bypass Valves will automatically control Steam Generator pressure?

A. 885 B. 910 C. 985 D. 1010 Page 48 of 100 Question:

(1 point) 49ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Time = 1200:00 Reactor power = 80% stable 1A and 1B CBP operating Time = 1201:00 1A CBP trips Feedwater Pump suction pressure = 225 psig slowly decreasing Time = 1203:00 Feedwater Pump suction pressure = 220 slowly increasing Which ONE of the following describes the:

1) runback rate (%/min) inserted at Time = 1201:00 to ICS?
2) procedure that will be directed by the CRS at Time = 1203:00?

A. 1. 15 2. AP/1/A/1700/001 (Unit Runback

) B. 1. 15 2. EOP C. 1. 20 2. AP/1/A/1700/001 (Unit Runback

) D. 1. 20 2. EOP Page 49 of 100 Question:

(1 point) 50ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor power = 100% Primary to Secondary leakage of 10 gpd has just been detected AP/1/A/1700/031 (Primary to Secondary Leakage) has been initiated

1) In accordance with AP/31, opening the Turbine Building Sump (TSP) pump breakers prior to being ready to hang White Tags on the TBS pump breakers __(1)__ allowed.
2) A sustained loss of power to 1RIA-54 will trip BOTH Turbine Building Sump Pumps __(2)__.

Which ONE of the following completes the statements above?

A. 1. is NOT 2. after a 2 minute time r B. 1. is NOT 2. immediatel y C. 1. is 2. after a 2 minute time r D. 1. is 2. immediatel y Page 50 of 100 Question:

(1 point) 51ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions: Time = 1200 1A GWD tank pressure = 68 psig stable Current conditions: Time = 1205 1A GWD tank pressure = 18 psig rapidly decreasing Various Aux Building RIA's in alarm 1RIA-1 (Control Room Monitor) in HIGH alarm 1RIA-39 (CNTL RM Gas) in HIGH alarm AP/1/A/1700/018 (Abnormal Release of Radioactivity) in progress A and B Outside Air Booster Fans have been started Which ONE of the following:

1) states if 1RIA-1 has a local alarm (do not count associated statalarm(s))?
2) describes the areas being provided outside air via the Outside Air Booster Fans?

A. 1. Yes 2. Control Room ONLY B. 1. No 2. Control Room ONLY C. 1. Yes 2. Control Room, Cable Rooms, and the Equipment Rooms D. 1. No 2. Control Room, Cable Rooms, and the Equipment Rooms Page 51 of 100 Question:

(1 point) 52ILT44 ONS SRO NRC Examination Oconee Nuclear Station 1RIA-59 setpoints are set by __(1)__ and the MINIMUM power level at which 1RI A-59is used to determine SGTL rate is __(2)__ (% power) in accordance with the EOP.

Which ONE of the following completes the statement above?

A. 1. I&E 2. 20 B. 1. I&E 2. 40 C. 1. ROs 2. 20 D. 1. ROs 2. 40 Page 52 of 100 Question:

(1 point) 53ILT44 ONS SRO NRC Examination Oconee Nuclear Station Which ONE of the following states all of the switchgear that can supply power to the B LPSW pump?

A. 1TD ONLY B. 2TC ONLY C. 1TC or 2TD D. 1TD or 2TD Page 53 of 100 Question:

(1 point) 54ILT44 ONS SRO NRC Examination Oconee Nuclear Station Based on the graph above, which ONE of the following describes the EARLIEST time at which SA-141 (SA to IA Controller) will automatically open?

A. 1207 B. 1210 C. 1212 D. 1215 Page 54 of 100 Question:

(1 point) 55ILT44 ONS SRO NRC Examination Oconee Nuclear Station Which ONE of the following describes what should be used in the case of a large Hydrogen leak to maintain Hydrogen concentration below the lower flammability limit in accordance with OP/1/A/1106/017 (Hydrogen System)?

A. CO2 B. Water C. Halon D. Foam fire retardant Page 55 of 100 Question:

(1 point) 56ILT44 ONS SRO NRC Examination Oconee Nuclear Station Which ONE of the following is the LOWER limit on RCS activity that would require entry into AP/21 (RCS Activity)?

A. Xe-133 = 0.25 µCi/gm B. Xe-133 = 1.0

µCi/gm C. DEI = 0.25 µCi/gm D. DEI = 1.0 µCi/gm Page 56 of 100 Question:

(1 point) 57ILT44 ONS SRO NRC Examination Oconee Nuclear Station Which ONE of the following activities complies withguidance contained in SOMP 1-2 (Reactivity Management)? A. Manual rod withdrawal during a Feedwater transient to stop a temperature decrease caused by an instrument failure B. Manually increasing Feedwater flow to stop an RCS pressure increase caused by an RCS temperature increase C. Manually raising one Loop FDW demand while lowering the other Loop FDW demand to control Tcold following an RCP trip D. Manually increasing turbine demand to adjust RCS temperature Page 57 of 100 Question:

(1 point) 58ILT44 ONS SRO NRC Examination Oconee Nuclear Station Which ONE of the following tags would be used ONLY for configuration control of 1HP-409 in accordance with NSD-500 (Red Tags/Configuration Control Tags)?

A. White Tag B. MORT Ta g C. OORT Tag D. CORT Tag Page 58 of 100 Question:

(1 point) 59ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 condition: Reactor in MODE 1 Which ONE of the following is the MINIMUM Pressurizer level (inches) that would require declaring Tech Spec 3.4.9 (Pressurizer) LCO NOT met in accordance with PT/1/A/0600/001 (Periodic Instrument Surveillance)?

A. 240 B. 260 C. 285 D. 340 Page 59 of 100 Question:

(1 point) 60ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor trip due to loss of both Main FDW pumps Instrument Air pressure = 0 psig Auxiliary Instrument Air pressure= 0 psig Which ONE of the following describes the status of 1FDW-315 and 1FDW-316?

A. Available for Manual operation ONLYonce the air supply was lost B. Will be available for Automatic operation for a MINIMUM of 30 minutes from the loss of air supply C. Will be available for Automatic operation for a MINIMUM of 1 hou r from the loss of air suppl y D. Will be available for Automatic operation for a MINIMUM of 2 hours from the loss of air supply Page 60 of 100 Question:

(1 point) 61ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 2 conditions:Initial conditions: Time = 1200 RCS temperature = 92°F stable RB Purge in progress 2RIA-45 HIGH alarm setpoint = 1520 cpm 2RIA-45 = 1342 cpm stable Current conditions: Time = 1205 2RIA-45 = 1520 cpm increasing Which ONE of the following describes:

1) ALL valves that will CLOSE?
2) 2RIA-46 reading (cpm) at time = 1200?

A. 1. 2P R-1 through 2P R-6 2. Zero B. 1. 2P R-1 through 2P R-6 2. 1342 C. 1. 2PR-2 through 2PR-5 ONLY 2. Zero D. 1. 2P R-2 through 2P R-5 ONLY2. 1342 Page 61 of 100 Question:

(1 point) 62ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following plant conditions: Venting the 1C LPI Pump in progress using the following RWP information:

o Dose Alarm : 25 mrem o Dose Rate Alarm: 200 mrem/hr o Dose Alarm: Stop work - Exit Area - Notify RP o Unanticipated Dose Rate Alarm: Stop Work - Exit Area - Notify RP Which ONE of the following states the MAXIMUM time work can continue before complying with the RWP will require exiting the area?

SEE PLAN VIEW PROVIDED Do NOT consider dose received while traveling to or from the job.

A. 15 minutes B. 30 minutes C. 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> D. 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> Page 62 of 100 Question:

(1 point) 63ILT44 ONS SRO NRC Examination Oconee Nuclear Station Of the two tabs below, the __(1)__ tab of the EOP has a higher priority because __(2)__.

Which ONE of the following completes the statement above?

A. 1. LOSCM 2. prompt actions are required to ensure core coolin g is maintained B. 1. LOSCM 2. actions to initiate HPI injection are required prior to the RCS void fraction reaching 70%.

C. 1. SGTR 2. a Reactor trip with a SGTR results in a direct release path for radionuclides to the environment D. 1. SGTR 2. actions to depressurize RCS to minimize SCM during a SGTR is a Time Critical Action that ma y not otherwise be met Page 63 of 100 Question:

(1 point) 64ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor Power = 70%

Which ONE of the following would require entry into the EOP?

A. Condenser vacuum = 22.3" hg B. 1RIA-59 = 31.4 gpm C. 1B Main FDW pump trips D. 1A1 RCP trips Page 64 of 100 Question:

(1 point) 65ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions: Reactor power = 100% 1KVIA Panelboard de-energized Current conditions: MSLB inside the Reactor Building occurs Lowest RCS pressure = 1137 psig Reactor Building Pressure peaked at 32 psig Which ONE of the following describes ALL ES Actuation Logic Channels that have actuated?

A. 1, 3, 5, 7 B. 2, 4, 6, 8 C. 1, 5, 7 ONLY D. 2, 6, 8 ONLY Page 65 of 100 Question:

(1 point) 66ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions: Time = 1200 Reactor Power = 100% 1A MSLB inside the Reactor Building Current conditions: Time = 1201 Reactor Building Pressure = 3 psig increasing Which ONE of the following describes the operation of 1LPSW-18?

A. It is NORMALLY fully open however it will receive a signal to open from ES-5 at 1201 B. It is NORMALLY throttled and will go fully open when it receives a signal to open from ES-5 at 1201 C. It is NORMALLY fully open however it will receive a signal to open from ES-5 at 1204 D. It is NORMALLY throttled and will go fully open when it receives a signal to open from ES-5 at 1204 Page 66 of 100 Question:

(1 point) 67ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions: Reactor power = 50%

Current conditions: LBLOCA occurs 1TD de-energized 1B RBCU switch in OFF Which ONE of the following describes the status of the below listed Reactor Building Cooling Units five (5) minutes after ES actuates?

ASSUME NO OPERATOR ACTIONS 1B RBCU 1C RBCU A. LOW LOW B. LOW OFF C. OFF LOW D. OFF OFF Page 67 of 100 Question:

(1 point) 68ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following plant conditions: SBLOCA has occurred on Unit 1 Reactor Building Pressure = 11.2 psig slowly decreasing Unit 2 Reactor Power = 100%

Which ONE of the following describes the actions directed (if any) by Enclosure 5.1 (ES Actuation) to ensure the required LPSW flow exists in the 1A LPI cooler?

A. Place 1LPSW-251 in "Failed Open" ONLY B. Place 1LPSW-251 in "Failed Open" AND fully open 1LPSW-4 C. Place 1LPSW-251 in "Failed Open" AND Throttle LPSW flow to approximately 3000 gpm using 1LPSW-4 D. Place 1LPSW-251 in "Failed Open" AND Throttle LPSW flow to approximately 5200 gpm using 1LPSW-4 Page 68 of 100 Question:

(1 point) 69ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions: Reactor power = 100% Loss of offsite power occurs Current conditions: Main Feeder Buses remain de-energized

1) The position of 1MS-112 (SSRH Control) is __(1)__.
2) 1MS-77 (MS to MSRH) __(2)__ be operated from the control room switch.

Which ONE of the following completes the statements above?

A. 1. open 2. can B. 1. closed 2. can C. 1. open 2. can NO T D. 1. closed 2. can NO T Page 69 of 100 Question:

(1 point) 70ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor Power = 50% 1A Turbine Bypass Valve fails OPEN Which ONE of the following describes the plant response?

ASSUME NO OPERATOR ACTIONS Reactor power will...

A. Increase then return to pre-transient level.

B. Increase and stabilize at a higher power level.

C. Decrease then return to pre-transient level.

D. Decrease and stabilize at a lower power level.

Page 70 of 100 Question:

(1 point) 71ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor Power = 80% stable ICS in Manual 1B Main Feedwater Pump trips Which ONE of the following is the MAXIMUM power level allowed in accordance with AP/1 (Plant Runback).

A. 74% B. 65% C. 60% D. 55% Page 71 of 100 Question:

(1 point) 72ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 3 conditions: Initial conditions: Reactor tripped from 35% power due to 3TA lockout 3A Main FDW pump operating 3FDW-35 & 3FDW-44 (3A and 3B Startup FDW Control) in MANUAL 3A and 3B SG levels = 38" SU and stable Current conditions: 3FDW-35 & 44 are placed in Automatic Which ONE of the following describes the response of 3FDW-35 & 44?

A. Travel open to increase SG levels to 240" XSUR.

B. Travel open to increase SG levels to 50% on Operating level.

C. Travel closed to decrease SG level to 30" on XSUR.

D. Travel closed to decrease SG level to 25" on SU level.

Page 72 of 100 Question:

(1 point) 73ILT44 ONS SRO NRC Examination Oconee Nuclear Station Which ONE of the following describes the:

1) primary concern at ONS regarding Main Feedwater backleakage into the EFDW discharge piping?
2) method used to determine if Main Feedwater backleakage into the EFDW discharge piping is occurring?

A. 1. Vapor binding of the EFDWpumps2. locall y monitorin g EFDW pump dischar ge piping for increasin g temperature B. 1. Vapor binding of the EFDWpumps2. Monitorin g EFDW temperature OAC points fo rincreasin g temperature C. 1. Overpressurizing the EFDW system piping 2. locall y monitorin g EFDW pump dischar ge piping for increasin g temperature D. 1. Overpressurizing the EFDW system piping 2. Monitoring EFDW temperature OAC points for increasing temperature Page 73 of 100 Question:

(1 point) 74ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following plant conditions: No Keowee Units are operating ACB-3 closed

1) KHU 1X switchgear is being powered from __ (1) __.
2) Keowee control power will be available for a MINIMUM of approximately __ (2) __ hour(s) following a loss of ALL AC power.

Which ONE of the following completes the statements above?

A. 1. 1TC 2. one B. 1. 1TC 2. four C. 1. the 230 KV switchyard 2. one D. 1. the 230 KV switch yard 2. four Page 74 of 100 Question:

(1 point) 75ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following plant conditions: 3CA Battery Charger fails - output voltage = 0 VDC 3CA Battery voltage = 120 VDC 3DCB Bus voltage = 123 VDC Unit 1 DCA/DCB Bus voltage = 125 VDC Unit 2 DCA/DCB Bus voltage = 127 VDC Which ONE of the following will automatically supply power to 3DIA panelboard?

A. 3CA Battery B. Unit 1 DC Bus C. 3DCB Bus D. Unit 2 DC Bus Page 75 of 100 Question:

(1 point) 76ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions: Reactor power = 100% Quench Tank temperature, level, and pressure are slowly increasing 1RC-66 tailpipe temperature slowly increasing Current conditions: 1RC-4 has been closed to verify the leak source Which ONE of the following states:

1) if ALL equipment credited in the UFSAR to prevent the RCS from exceeding the Tech Spec Safety Limit on RCS pressure is still available?
2) the LOWER Quench Tank pressure that will result in blowing the Quench Tank rupture disc?

A. 1. No 2. 45 psi g B. 1. No 2. 55 psi g C. 1. Yes 2. 45 psi g D. 1. Yes 2. 55 psig Page 76 of 100 Question:

(1 point) 77ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Time = 1200 RCS temperature = 274°F stable 1/0 Pump Ops in progress 1A1 RCP operating 1A2 RCP NOT available 1B1 RCP available 1B2 RCP NOT available LPSW to the 1A1 RCP ONLY is lost Time = 1202 1A1 RCP secured

1) In accordance with AP/16, the 1A1 RCP must be tripped as soon as its stator temperature reaches __(1)__ degrees F.
2) At Time = 1205, Tech Spec 3.4.5 (RCS Loops - MODE 3) Condition(s) __(2)__ apply. Which ONE of the following completes the statements above?

REFERENCE PROVIDED A. 1. 260 2. A B. 1. 260 2. A and C C. 1. 295 2. A D. 1. 295 2. A and C Page 77 of 100 Question:

(1 point) 78ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor in MODE 5 LPI aligned to normal DHR mode Low Range Cooldown Pressure = 5 psig Which ONE of the following:

1) are the MINIMUM conditions that would indicate a TOTAL loss of LPI flow?
2) actions are taken to control RCS pressure in accordance with AP/26 (Loss of Decay Heat Removal) once a total loss of LPI flow has occurred?

NOTE: 1SA-3/C8 = LP Injection Loop A Flow High/Low 1SA-3/C9 = LP Injection Loop B Flow High/Low A. 1. 1SA-3/C8 ONLY with Train A LPI flow = 0 gpm 2. Initiate Enclosure 5.18 (SSF Operation For Loss of DHR Events

) B. 1. 1S A-3/C8 ONLY with Train A LPI flow = 0 gpm2. Cycle 1RC-66 C. 1. 1S A-3/C8 AND 1SA-3/C9 actuated with Train A AND Train B LPI flow = 0 gpm 2. Initiate Enclosure 5.18 (SSF Operation For Loss of DHR Events

) D. 1. 1SA-3/C8 AND 1SA-3/C9 actuated with Train A AND Train B LPI flow = 0 gpm 2. Cycle 1RC-66 Page 78 of 100 Question:

(1 point) 79ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions: Reactor power = 100% BOTH channels of AMSAC disabled Current conditions: Both Main Feedwater Pumps Tripped Reactor power = 60% and slowly decreasing

1) 1A MDEFWP, 1B MDEFWP AND the TDEFWP __(1)__ automatically start.
2) In accordance with B&W analysis, a MINIMUM of __ (2)__ gallons per minute of Emergency Feedwater flow is required to limit the RCS pressure increase to below the design standard for this event.

Which ONE of the following completes the statements above?

A. 1. will 2. 750 B. 1. will NOT 2. 750 C. 1. will 2. 375 D. 1. will NOT 2. 375 Page 79 of 100 Question:

(1 point) 80ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Time = 1200: Reactor power = 100% 1SA6/B2 INVERTER 1DID SYSTEM TROUBLE actuated Time = 1205 NEO reports:

o 1SA13/A8 INVERTER 1DID INPUT VOLTAGE LOW actuated o Inverter 1DID output voltage low

1) The status of 1KVID at Time = 1205 is __(1)__.
2) The MINIMUM action(s) required to restore the 1DID inverter to OPERABLE in accordance with Tech Spec 3.8.6 (Vital Inverters-Operating) is/are to restore DC input voltage __(2)__.

Which ONE of the following completes the statements above?

A. 1. NOT energized 2. ONLY B. 1. NOT energized 2. AND re-connect to 1KVID C. 1. Energized 2. ONLY D. 1. Energized 2. AND re-connect to 1KVID Page 80 of 100 Question:

(1 point) 81ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Time = 1200 Reactor power = 100% 1RIA-60 = 35 gpm stable

Time = 1215 Main Turbine manually tripped due to high bearing vibration Time = 1245 Steam Line Break in 1A Steam Generator

1) The __(1)__ tab will be used to stabilize the plant following the reactor trip.
2) The __(2)__ tab will direct the unit cooldown to LPI.

Which ONE of the following completes the statements above?

A. 1. Subsequent Actions 2. SGTR B. 1. SGT R 2. SGTR C. 1. Subsequent Actions 2. Forced Cooldown D. 1. SGT R 2. Forced Cooldown Page 81 of 100 Question:

(1 point) 82ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Time = 1200 Reactor Power = 100% Control Rod Group 5 Rod 4 ONLY has partially inserted and indicates 90% withdrawn Time = 1330 Reactor Power = 55% stable Time = 1400 Control Rod Group 3 Rod 1 has dropped and indicates 0% withdrawn At Time = 1330 Control Rod Group 5 Rod 4 is considered __(1)__ in accordance with Tech Spec 3.1.4 (Control rod Group Alignment Limits),.

At Time = 1400 the CRS will direct the RO's to __(2)__.

Which ONE of the following completes the statements above?

A. 1. misaligned ONLY 2. notif y SPOC to reduce RPS trip setpoints B. 1. misaligned ONLY 2. trip the Reactor C. 1. Inoperable 2. notif y SPOC to reduce RPS trip setpoints D. 1. Inoperable 2. trip the Reactor Page 82 of 100 Question:

(1 point) 83ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions Reactor Power = 100% A Fire has been identified in the Reactor Building AP/43 (Fire Brigade Response Procedure) is in progress AP/50 (Challenging Plant Fire) has been initiated

Current conditions: Reactor in MODE 3 Steam Generator level indications in the control room are erratic and suspected to be inaccurate due to the fire

Which ONE of the following:

1) states the definition of a "Challenging Fire" in accordance with AP/43?
2) should be used to validate the Steam Generator level indication in accordance with AP/50? A. 1. A fire that is burning cables (bundles/ trays which have the potential to affect additional equipment) 2. SSF Steam Generator level B. 1. A fire that is burning cables (bundles/ trays which have the potential to affect additional equipment) 2. Aux Shutdown Panel Steam Generator level C. 1. A fire in the plant that is NOT extinguished within 15 minutes of Control Room notification 2. SSF Steam Generator level D. 1. A fire in the plant that is NOT extinguished within 15 minutes of Control Room notification 2. Aux Shutdown Panel Steam Generato rlevel Page 83 of 100 Question:

(1 point) 84ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial Conditions: Reactor Power = 50% stable Toxic gas is entering the Control room Current Conditions: The Reactor has been manually tripped KHU's have been Emergency Started 1HP-24 has been opened Which ONE of the following describes the:

1) initial actions directed to control Pressurizer level in accordance with AP/8?
2) Pressurizer level instrumentation available at the alternate location INITIALLY used in accordance with AP/8 (Loss of Control Room)?

A. 1. At ASDP, take control of the 1B HPI pump and 1HP-120 to control level 2. Temperature compensated Pzr level B. 1. At SSF, start the SSF-RCMUP and adjust RC makeup and letdown to control level 2. Temperature compensated Pzr level C. 1. At ASDP, take control of the 1B HPI pump and 1HP-120 to control level 2. Uncompensated Pzr level D. 1. At SSF, start the SSF-RCMUP and adjust RC makeup and letdown to control level 2. Uncompensated Pzr level Page 84 of 100 Question:

(1 point) 85ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions: Time = 1200 Reactor power = 80% stable 1B2 RCP breaker fails causing the 1B2 RCP to trip Current conditions: Time = 1300 Control Rod #2 in Group 4 drops into core Which ONE of the following states the:

1) abnormal procedure entered at Time = 1200?
2) procedure that will be used to reach the final power level required by the dropped rod? A. 1. AP/1 (Unit Runbac k) 2. AP/1 (Unit Runback)

B. 1. AP/1 (Unit Runbac k) 2. OP/1/A/1102/004 (Operation at Power

) C. 1. AP/16 (Abnormal RCP Operations)2. AP/1 (Unit Runbac k) D. 1. AP/16 (Abnormal RCP Operations) 2. OP/1/A/1102/004 (Operation at Power

) Page 85 of 100 Question:

(1 point) 86ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Time = 1200: Reactor Power = 100% 1A HPI Pump operating 1B HPI Pump in AUTO Time = 1202: A seal supply filter problem results in total Reactor Coolant Pump seal injection flow decreasing to 25 gpm

1) At time 1202 the 1B HPI pump is __(1)__.
2) The low seal injection flow Auto Start of the 1B HPI pump __(2)__ required to be operable for the 1B HPI pump to be Operable in accordance with Tech Spec 3.5.2 (HPI). Which ONE of the following completes the statements above?

Assume NO operator actions A. 1. running 2. is B. 1. running 2. is NOT C. 1. NOT running2. is D. 1. NOT running 2. is NOT Page 86 of 100 Question:

(1 point) 87ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Time = 1215 Unit shutdown in progress 1A1 RCP in operation Tcold = 220°F slowly decreasing RCS Pressure 325 psig slowly decreasing LPI Cooler outlet temperature = 110°F stable Time = 1230 Tcold = 200°F slowly decreasing RCS Pressure 275 psig slowly stable LPI Cooler outlet temperature = 110°F stable 1A LPI Pump is started Time = 1240 Tcold = 197°F stable 1A1 RCP secured Time = 1245 LPI Cooler outlet temperature = 180°F stable

1) The RCS cooldown rate __(1)__ violate the maximum cooldown rate allowed per Tech Specs?
2) When the 1A LPI pump is started at Time = 1230, the temperature transient that results from the difference in LPI Cooler Outlet temperature and Tcold __(2)__ outside the bounds of the Reactor Vessel stress analysis?

Which ONE of the following completes the statements above?

A. 1. does 2. is B. 1. does 2. is NOT C. 1. does NOT 2. is D. 1. does NOT 2. is NOT Page 87 of 100 Question:

(1 point) 88ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial Conditions Reactor power = 100% BOTH Main FDW pumps trip Current Conditions Reactor power = 28% decreasing RULE 1 (ATWS/UNPP) is complete 1RC-66 is failed open Pressurizer level = 400" stable

1) The UNPP tab __(1)__ direct closing 1RC-4.
2) The HIGHEST RCS pressure that will allow a retransfer to Subsequent Actions is less than __(2)__ psig.

Which ONE of the following completes the statements above?

A. 1. will 2. 2450 B. 1. will NOT 2. 2450 C. 1. will 2. 2300 D. 1. will NOT 2. 2300 Page 88 of 100 Question:

(1 point) 89ILT44 ONS SRO NRC Examination Oconee Nuclear Station Unit 1 initial conditions: RCS temperature = 310°F stable 1A2 and 1B2 RCPs operating Unit Auxiliaries powered from CT-1 Current conditions: RC Makeup Flow = 150 gpm PCB-17 AND PCB-18 trip OPEN Which ONE of the following describes the:

1) status of Reactor Coolant Pumps
2) MAXIMUM cooldown rate allowed in accordance with the EOP once cooldown to LPI has commenced?

A. 1. Off 2. 50°F pe r hour B. 1. Off 2. 50°F per 1/2 hou r C. 1. On 2. 50°F per hou r D. 1. On 2. 50°F per 1/2 hour Page 89 of 100 Question:

(1 point) 90ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Time = 1200 Reactor power = 100% BOTH AFIS channels in OFF Time = 1205 Large MSLB inside the RB occurs ES Channels 1-8 have actuated Time = 1207 Component status as pictured below

1) Reactor Building Cooling Units __(1)__ operating as designed.
2) Systems and/or equipment required to ensure Reactor Building Pressure is maintained below the design pressure of the Reactor Building __(2)__ available.

Which ONE of the following completes the statements above?

ASSUME NO OPERATOR ACTIONS A. 1. are 2. is B. 1. are NOT 2. is C. 1. are 2. is NOT D. 1. are NO T 2. is NOT Page 90 of 100 Question:

(1 point) 91ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 3 plant conditions:Time = 1200 Reactor in MODE 1 RBNS level 20 inches increasing LPSW leak into RB Begin pumping RBNS using 1A and 1B RBNS Pumps Time = 1205 RBNS level as indicated below Time = 1230 RBNS level indication unchanged from Time = 1205 Which ONE of the following states:

1) if Condition A of Tech Spec 3.4.15 must be entered?
2) which RIA can be used to satisfy the requirements of TS 3.4.15 LCO?

REFERENCE PROVIDED A. 1. Yes 2. 1RIA-47 B. 1. Yes 2. 1RIA-49 C. 1. No 2. 1RIA-47 D. 1. No 2. 1RIA-49 Page 91 of 100 Question:

(1 point) 92ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Time = 1200 Reactor power = 100% Relative Position Indication (RPI) inoperable for ALL Control Rods Time = 1230 Absolute Position Indication (API) inoperable for Group 1 Rod 7 Control Rod

Current Conditions: Tech Spec 3.1.4 Required Action A.2.1.1 (SDM Verification) has just been completed and shutdown margin requirements of the COLR have been determined to be NOT met

Which ONE of the following:

1) is the LATEST time that Group 1 Rod 7 Control Rod must be declared inoperable in accordance with Tech Specs?
2) should be used to restore shutdown margin requirements in accordance with Tech Spec bases?

REFERENCE ATTACHED A. 1. 1230 2. OP/1/A/1103/004A Enclosure 4.1 (RCS Boration from CBAST With CBAST Pump) ONLY B. 1. 1230 2. OP/1/A/1103/004A Enclosure 4.1 (RCS Boration from CBAST With CBAST Pump) OR OP/1/A/1103/004 Enclosure 4.4 (RCS Makeup From 1A BHUT C. 1. 1330 2. OP/1/A/1103/004A Enclosure 4.1 (RCS Boration from CBAST With CBAST Pump) ONLY D. 1. 1330 2. OP/1/A/1103/004A Enclosure 4.1 (RCS Boration from CBAST With CBAST Pump) OR OP/1/A/1103/004 Enclosure 4.4 (RCS Makeup From 1A BHUT Page 92 of 100 Question:

(1 point) 93ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Time = 0900 Reactor trip due a sheared RCP shaft on 1A1 RCP Control Room has indications that the 1A1 RCP seals have failed.

Time = 0904 ES 1 & 2 actuate on low RCS Pressure. The 1A HPI pump fails to Auto start and cannot be started manually.

Time = 0910 RCS saturated and stable at 1000 psig. Rule 2 is complete Time = 0919 1RIA-57 reads 350 R/HR and stable. RB Pressure = 2.6 psig slowly increasing Time = 0920 RB Pressure = 0.2 psig decreasing Which ONE of the following states the:

1) position of 1HP-410?
2) Emergency Classification in accordance with RP/0/A/1000/001 (Emergency Classification)?

REFERENCE PROVIDED DO NOT USE EMERGENCY COORDINATOR JUDGEMENT WHEN DETERMINING CLASSIFICATION A. 1. Open 2. General Emer gency B. 1. Open 2. Site Area Emer gency C. 1. Closed 2. General Emer gency D. 1. Closed 2. Site Area Emer gency Page 93 of 100 Question:

(1 point) 94ILT44 ONS SRO NRC Examination Oconee Nuclear Station In accordance with AD-OP-ALL-1000 (Conduct of Operations),

1) The CRS __(1)__ allowed to correct archived log entries when the original watchstander will not be available in the near future.
2) the MINIMUM level of management with overall responsibility for the approval of the quality of Unit Log entries is the __(2)__.

Which ONE of the following completes the statements above A. 1. is 2. SM B. 1. is 2. CRS C. 1. is NOT 2. SM D. 1. is NOT 2. CRS Page 94 of 100 Question:

(1 point) 95ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor power = 100% Main T/G Journal Bearing #7 vibration as described below:

Which ONE of the following describes:

1) The EARLIEST time that the Main Turbine must be manually tripped in accordance with Limits and Precautions of OP/1/A/1106/001 (Turbine Generator)?
2) The procedure that would be used to take the Main Turbine off line without tripping the Reactor?

A. 1. 1216 2. AP/29 (Rapid Unit Shutdown)

B. 1. 1216 2. OP/1/A/1106/001 (Turbine Generator)

C. 1. 1224 2. AP/29 (Rapid Unit Shutdown)

D. 1. 1224 2. OP/1/A/1106/001 (Turbine Generator)

Page 95 of 100 Question:

(1 point) 96ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 2 conditions: Reactor in MODE 5 Maintenance is required on 2FDW-105 (2A SG SAMPLE) Multiple electrical valve manipulations of 2FDW-105 are required as part of the repairs A check valve needs to be used as one of the isolation boundary valves Which ONE of the following describes the requirements in accordance with NSD 500 (Red Tags/Configuration Control Tags) for:

1) the lowest level of Operations Management approval required for the tagout?
2) who must approve the use of wax string to attach a Red Tag to its associated component?

A. 1. ANY Licensed SRO 2. Shift Mana ger B. 1. Any Operations Manager2. Shift Mana ger C. 1. ANY Licensed SRO 2. Operational Control Group superviso r D. 1. Any Operations Manager2. Operational Control Group superviso r Page 96 of 100 Question:

(1 point) 97ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor = Mode 3 "B" shift is performing a plant startup following a refueling outage in progress PT/0/A/0711/001 (Zero Power Physics Testing) is to be performed

Which ONE of the following is the LOWEST level of management that meets the expectations provided in NSD 213 (Risk Management Process) regarding who can provide the 91-01 IPTE briefing associated with ZPPT?

A. "B" shift Shift Technical Advisor B. Reactor Engineering Supervisor C. "B" shift Shift Manager (Operations Shift Manager)

D. Operations Manager (Superintendant of Operations)

Page 97 of 100 Question:

(1 point) 98ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions:Initial conditions: Mode 6 Defueling in progress 1RIA-3 (Fuel Transfer Canal Monitor) = 4 mr/hr stable Main Fuel Bridge Area Monitor = 6 mr/hr stable Current conditions: 1RIA-3 local reading = 0 mr/hr 1RIA-3 View Node indication is magenta The Refueling SRO will determine that Fuel Handling activities in the Reactor Building may ______ in accordance with OP/1/A/1502/007 (Operations Defueling/Refueling Responsibilities)?

Which ONE of the following completes the statement above?

A. NOT continue until a portable area monitor with local alarm capability is in place. B. continue because onl y the Main Fuel Brid ge Area Monitor is required.

C. NOT continue until continuous RP coverage is present on the Main Fuel Bridge. D. continue provided the audiblealarm associatedwith 1RI A-49 (RB Normal Gas) is operable.

Page 98 of 100 Question:

(1 point) 99ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor trip has occurred Main Turbine status as indicated below SRO directs performance of Immediate Manual Actions

1) The Reactor Operator performing IMA's __(1)__ expected to depress the "Turbine Trip" pushbutton.
2) IF the Main Turbine is not tripped during performance of IMA's, the basis behind requiring the EHC pumps being secured is to prevent __(2)__.

Which ONE of the following completes the statements above?

A. 1. is 2. water from reachin g the Main Turbine durin g a SG overfeed B. 1. is 2. excessive RCS cooldown C. 1. is NOT 2. water from reachin g the Main Turbine durin g a SG overfeed D. 1. is NOT 2. excessive RCS cooldown Page 99 of 100 Question:

(1 point) 100ILT44 ONS SRO NRC Examination Oconee Nuclear Station Given the following Unit 1 conditions: Reactor Power = 100% Operating CC pump trips and standby fails to Auto start CC Surge tank level = 28" stable Letdown Temperature = 138°F increasing The following alarms have actuated and associated actions are being performed:

o 1SA-9/B-1 (CC CRD Return Flow Low).

o 1SA-2/C-1 (HP Letdown Temperature High) o 1SA-9/C-1 (CC Component Cooling Return Flow Low)

Which ONE of the following states:

1) The SETPOINT (degrees F) at which 1SA-2/C1 actuated?
2) The Procedure that will be entered FIRST if actions directed in the associated Alarm Response guides fail to restore normal system parameters?

A. 1. 130 2. AP/20 (Loss of Component Coolin g) B. 1. 130 2. AP/32 (Loss of Letdown)

C. 1. 135 2. AP/20 (Loss of Component Coolin g) D. 1. 135 2. AP/32 (Loss of Letdown

) Page 100 of 100 Examination KEY for:ILT44 ONS SRO NRC ExaminQuestionNumberAnswer1B2B3C4C5B6A7D8B9A10A11A12C13D14C15B16C17D18D19B20C21D22A23B24B25DPrinted 12/17/2013 8:20:05 AMPage 1 of 4 Examination KEY for:ILT44 ONS SRO NRC ExaminQuestionNumberAnswer26A27C28A29C30D31D32D33C34A35A36C37B38C39C40A41B42A43C44A45D46A47C48C49D50DPrinted 12/17/2013 8:20:06 AMPage 2 of 4 Examination KEY for:ILT44 ONS SRO NRC ExaminQuestionNumberAnswer51B52B53D54D55B56C57C58A59B60D61C62A63A64B65B66B67B68B69D70A71B72D73A74A75BPrinted 12/17/2013 8:20:06 AMPage 3 of 4 Examination KEY for:ILT44 ONS SRO NRC ExaminQuestionNumberAnswer76D77C78D79A80B81B82D83A84A85A86D87B88D89A90C91A92A93C94B95C96B97D98A99B100APrinted 12/17/2013 8:20:06 AMPage 4 of 4