ML20225A068

From kanterella
Jump to navigation Jump to search
301 Exam Corporate Notification Letter
ML20225A068
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 08/11/2020
From: Gerald Mccoy
NRC/RGN-II/DRS/PSB1
To: Burchfield J
Duke Energy Carolinas
References
Download: ML20225A068 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 August 11, 2020 J. Ed Burchfield, Jr.

Site Vice President, Oconee Nuclear Station Duke Energy Carolinas, LLC 7800 Rochester Highway Seneca, SC 29672-0752

SUBJECT:

OCONEE NUCLEAR STATION - NOTIFICATION OF LICENSED OPERATOR INITIAL EXAMINATION 05000269/2021301, 05000270/2021301 AND 05000287/2021301

Dear Mr. Burchfield:

During a telephone conversation on August 10, 2020, between Mr. M. Adair, Oconee Training Instructor, and Mr. M. Bates, Senior Operations Engineer, arrangements were made for the administration of licensing examinations at the Oconee Nuclear Station. The on-site preparatory week is scheduled for the week of April 26, 2021. The operating test is scheduled to be administered during the week of June 7, 2021. The written examination is scheduled to be administered the week of June 14, 2021.

As agreed during the telephone conversation, the U.S. Nuclear Regulatory Commission (NRC) will prepare both the operating test outlines and the written examination based on the guidelines in Revision 11 of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors." To meet the above schedule, your staff previously furnished the supporting reference materials identified in Attachment 3 to ES-201.

Your staff will be given the opportunity to review the operating test outlines beginning on October 30, 2020 and to review the written examination beginning on January 8, 2021. Your staff has also agreed to make copies of all examination materials that are necessary for administering the examination.

We request that any personal, proprietary, sensitive unclassified, or safeguards information in your response be contained in a separate enclosure and appropriately marked. Any delay in receiving the required examination and reference materials, or the submittal of inadequate or incomplete materials, may cause the examinations to be rescheduled.

In order to conduct the requested written examinations and operating tests, it will be necessary for your staff to provide adequate space and accommodations in accordance with ES-402, and to make the simulation facility available on the dates noted above. In accordance with ES-302, your staff should retain the original simulator performance data (e.g., system pressures, temperatures, and levels) generated during the dynamic operating tests until the NRC takes licensing action on all the applications and any adjudicatory actions on any hearing demands are complete.

E. Burchfield 2 Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in effect while the written examinations and operating tests are being administered.

To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator waiver and/or excusal requests (Office of Management and Budget (OMB) approval number 3150-0090) at least 60 days before the first examination date (if possible). Contact Mr. Bates to determine the method for submission of the waiver or excusal requests. Preliminary reactor operator and senior reactor operator license applications (OMB approval number 3150-0090) and medical certifications (OMB approval number 3150-0024) should be submitted at least 30 days before the first examination date. If the applications are not received at least 30 days before the examination date, a postponement may be necessary.

Final signed applications certifying that all training has been completed and requesting any waivers or excusals, as applicable, should be submitted at least 14 days before the first examination date.

Although the guidelines for receiving waiver or excusal requests call for at least 30 days before the first examination date (preliminary) and 14 days before the first examination date (final), the requests should be submitted as early as possible in the process (see the 60-day guideline above). Resolutions resulting from verbal inquiries by the licensee to the NRC are not binding.

Submittals addressing waivers or excusals, or both, should be in writing (i.e., using NRC Form 398, Personal Qualifications StatementLicensee, or as directed by Mr. Bates when contacting him to determine the method for submission). The NRC will document its final decision on whether to grant a waiver or excusal on the final (not preliminary) NRC Form 398 submitted for the applicant. The NRC will not provide its decision until the final application is submitted to the agency.

This letter contains information collection requirements that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number 3150-0018.

The burden to the public for these mandatory information collections is estimated to average 400 hours0.00463 days <br />0.111 hours <br />6.613757e-4 weeks <br />1.522e-4 months <br /> per examination, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the information collections. You may submit comments on any aspect of the information collections, including suggestions for reducing the burden, to FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by electronic mail to infocollects.resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, DC 20503.

The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information, unless the document requesting or requiring the collection displays a currently valid OMB control number.

In accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding, of the agencys Rules of Practice, a copy of this letter and its enclosures will be available electronically for public inspection through the Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm.adams.html.

E. Burchfield 3 Thank you for your cooperation in this matter. Mr. Adair has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRC's examination procedures and guidelines, please contact Mr. Bates at (404) 997-4612, (E-mail:

Mark.Bates@nrc.gov), or me at (404) 997-4551, (E-mail: Gerald.McCoy@nrc.gov).

Sincerely,

/RA/

Gerald J. McCoy, Chief Operations Branch 1 Division of Reactor Safety Docket Nos.: 50-269, 50-270 and 50-287 License Nos.: DPR-38, DPR-47 and DPR-55 cc: Distribution via Listserv

ML20225A068 SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII/ DRS/ RII/DRS/OB1 NAME OB2G \OLE M.BATES G. McCOY DATE 8/ 11 /2020 8/ 11 /2020 E-MAIL COPY? YES NO YES NO