ML073540392: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 3: Line 3:
| issue date = 12/19/2007
| issue date = 12/19/2007
| title = Change to Inspection Plan 1/1/08 - 12/31/08
| title = Change to Inspection Plan 1/1/08 - 12/31/08
| author name = Riemer K R
| author name = Riemer K
| author affiliation = NRC/RGN-III/DRP/B2
| author affiliation = NRC/RGN-III/DRP/B2
| addressee name = Anderson R L
| addressee name = Anderson R
| addressee affiliation = Florida Power & Light Co
| addressee affiliation = Florida Power & Light Co
| docket = 05000331, 07200032
| docket = 05000331, 07200032

Revision as of 17:21, 12 July 2019

Change to Inspection Plan 1/1/08 - 12/31/08
ML073540392
Person / Time
Site: Duane Arnold  NextEra Energy icon.png
Issue date: 12/19/2007
From: Kenneth Riemer
NRC/RGN-III/DRP/B2
To: Richard Anderson
Florida Power & Light Co
References
Download: ML073540392 (5)


Text

December 19, 2007

Mr. Richard L. Anderson

Vice-President Duane Arnold Energy Center 3277 DAEC Road Palo, IA 52324-9785

SUBJECT:

CHANGE TO THE INSPECTION PLAN - DUANE ARNOLD ENERGY CENTER

Dear Mr. Anderson:

As part of a periodic self-assessment, the Nuclear Regulatory Commission (NRC) thoroughly reviewed its inspection procedures to ensure the continued effective application of inspection resources. The main objective of the review was to determine the appropriate inspection scope for the majority of the inspection procedures in the reactor oversight process (ROP). The result of this effort (designated ROP realignment) created changes to both inspection scope and/or inspection frequency for selected inspection procedures in the ROP. The purpose of this letter is to update the schedule of future inspection activities at your facility that was provided with the mid-cycle assessment letter in August 2007. Please note that there were no changes made to inspection procedures in the security, emergency preparedness, and health physics areas. The enclosed inspection plan details the inspections (less those related to security) scheduled for calendar year 2008. The inspection plan is provided to resolve any scheduling and/or personnel availability issues well in advance of the inspectors' arrival onsite. Routine resident inspections are not listed due to their continuous nature. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 630-829-9628 with any questions you may have regarding this letter or the inspection plan.

Sincerely, /RA by Nick Shah Acting for/

Kenneth Riemer, Chief Projects Branch 2 Division of Reactor Projects Docket No. 50-331;72-032 License No. DPR-49

Enclosure:

As Stated

cc w/encl: J. Stall, Senior Vice President, Nuclear and Chief Nuclear Officer R. Helfrich, Senior Attorney

M. Ross, Managing Attorney W. Webster, Vice President, Nuclear Operations M. Warner, Vice President, Nuclear Operations Support R. Kundalkar, Vice President, Nuclear Engineering J. Bjorseth, Site Director

D. Curtland, Plant Manager

S. Catron, Manager, Regulatory Affairs Chief Radiological Emergency Preparedness Section, Dept. Of Homeland Security M. Rasmusson, State Liaison Officer

Please contact me at 630-829-9628 with any questions you may have regarding this letter or the inspection plan.

Sincerely, /RA by Nick Shah Acting for/

Kenneth Riemer, Chief Projects Branch 2 Division of Reactor Projects Docket No. 50-331;72-032 License No. DPR-49

Enclosure:

As Stated

cc w/encl: J. Stall, Senior Vice President, Nuclear and Chief Nuclear Officer R. Helfrich, Senior Attorney

M. Ross, Managing Attorney W. Webster, Vice President, Nuclear Operations M. Warner, Vice President, Nuclear Operations Support R. Kundalkar, Vice President, Nuclear Engineering J. Bjorseth, Site Director

D. Curtland, Plant Manager

S. Catron, Manager, Regulatory Affairs Chief Radiological Emergency Preparedness Section, Dept. Of Homeland Security M. Rasmusson, State Liaison Officer

DOCUMENT NAME:G:\BRANCH TSS\ALL MOC\MIDCYCLE 2006 TO 2007\ROP REALIGNMENT LETTER\DUANE ARNOLD.DOC G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII E RIII RIII RIII NAME NShah, Acting for KRiemer:cms DATE 12/19/07 OFFICIAL RECORD COPY Letter to R. Anderson from K. Riemer dated December 19, 2007

SUBJECT:

CHANGE TO THE INSPECTION PLAN - DUANE ARNOLD ENERGY CENTER DISTRIBUTION:

TEB DWS RidsNrrDirsIrib

MAS KGO JKH3 SRI Duane Arnold CAA1 DRPIII DRSIII PLB1 TXN Duane Arnold Inspection / Activity Plan 01/01/2008

-12/31/2008 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 1 12/19/2007 Report 22 6 BI ENG-COMPONENT DESIGN BASES INSPECTION Baseline Inspections 02/11/2008 03/14/2008 1 7111121 IP Component Design Bases Inspection 1 BI RP-RADIATION PROTECTION BASELINE INSPECTION Baseline Inspections 02/04/2008 02/08/2008 1 7112101 IP A ccess Control to Radiologically Significant Areas 1 BI RP-RADIATION PROTECTION BASELINE INSPECTION Baseline Inspections 03/31/2008 04/04/2008 1 7112201 IP Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems Baseline Inspections 03/31/2008 04/04/2008 1 71151-PR01 IP RETS/ODCM Radiological Effluent 1 BI RP-RADIATION PROTECTION BASELINE INSPECTION Baseline Inspections 08/04/2008 08/08/2008 1 7112103 IP Radiation Monitoring Instrumentation and Protective Equipment Baseline Inspections 08/04/2008 08/08/2008 1 71151-BI01 IP Reactor Coolant System Activity Baseline Inspections 08/04/2008 08/08/2008 1 71151-OR01 IP Occupational Exposure Control Effectiveness 2 BI OL-BIENNIAL REQUAL. PROGRAM INSPECTION Baseline Inspections 10/06/2008 10/10/2008 1 7111111B IP Licensed Operator Requalification Program 3 BI EP-EP EXERCISE INSPECTION / PI VERIFICATION EP Baseline Inspecti o 10/20/2008 10/24/2008 1 7111401 IP Exercise Evaluation Baseline Inspections 10/20/2008 10/24/2008 1 71151-EP01 IP Drill/Exercise Performance Baseline Inspections 10/20/2008 10/24/2008 1 71151-EP02 IP ERO Drill Participation Baseline Inspections 10/20/2008 10/24/2008 1 71151-EP03 IP A lert & Notification System 1 BI RP-RADIATION PROTECTION BASELINE INSPECTION Baseline Inspections 10/20/2008 10/24/2008 1 7112102 IP A LARA Planning and Controls This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.