UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 September 3, 2013 Mr. Richard L. Anderson Vice President NextEra Energy Duane Arnold, LLC 3277 DAEC Road Palo, IA 52324-9785
SUBJECT:
MID-CYCLE ASSESSMENT LETTER FOR DUANE ARNOLD ENERGY CENTER (REPORT 05000331/2013006)
Dear Mr. Anderson:
On August 14, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of Duane Arnold Energy Center. The NRC reviewed quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2012 through June 30, 2013. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined that performance at Duane Arnold Energy Center was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The enclosed inspection plan lists the inspections scheduled through December 31, 2014, including inspection procedure (IP) 60855.1, Operation of an Independent Spent Fuel Storage Installation (ISFSI) at Operating Plants and IP 71003, Post-Approval Site Inspection for License Renewal. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at (630) 829-9703 with any questions you have regarding this letter.
Sincerely,
/RA/
Christine A. Lipa, Chief Branch 1 Division of Reactor Projects Docket No. 50-331 License No. DPR-49
Enclosure:
Duane Arnold Energy Center Inspection/Activity Plan cc w/encl: Distribution via ListServTM
Please contact me at (630) 829-9703 with any questions you have regarding this letter.
Sincerely,
/RA/
Christine A. Lipa, Chief Branch 1 Division of Reactor Projects Docket No. 50-331 License No. DPR-49
Enclosure:
Duane Arnold Energy Center Inspection/Activity Plan cc w/encl: Distribution via ListServTM DISTIRUBTION:
See next page DOCUMENT NAME: Duane Arnold Energy Center MOC Letter Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII-DRP E RIII-DRP RIII RIII NAME CLipa:rj/mvt DATE 09/03/13 OFFICIAL RECORD COPY
Letter to R. Anderson from C. Lipa dated September 3, 2013
SUBJECT:
MID-CYCLE ASSESSMENT LETTER FOR DUANE ARNOLD ENERGY CENTER (REPORT 05000331/2013006)
DISTRIBUTION:
Vivian Campbell RidsNrrDorlLpl3-1 Resource RidsNrrPMDuaneArnold Resource RidsNrrDirsIrib Resource Cynthia Pederson Anne Boland Steven Orth Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPassessment.Resource@nrc.gov
Page 1 of 1 08/26/2013 06:56:06 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Duane Arnold Inspection / Activity Plan 09/01/2013 - 12/31/2014 BI MODS
- TRIENNIAL PERM MODS/50.59 3
1 IP Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications 7111117T 09/02/2013 09/20/2013 BI RP
- RADIATION PROTECTION BASELINE INSPECTION 1
1 IP Radiation Monitoring Instrumentation 71124.05 09/09/2013 09/13/2013 ISFSI
- ISFSI INSPECTION - SCHEDULE DEPENDENT 2
1 IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.1 10/01/2013 10/31/2013 BI RP
- RADIATION PROTECTION BASELINE INSPECTION 1
1 IP Radiological Hazard Assessment and Exposure Controls 71124.01 09/23/2013 09/27/2013 1
IP Reactor Coolant System Activity 71151-BI01 09/23/2013 09/27/2013 1
IP Occupational Exposure Control Effectiveness 71151-OR01 09/23/2013 09/27/2013 1
IP RETS/ODCM Radiological Effluent 71151-PR01 09/23/2013 09/27/2013 RENEWAL
- LR 71003 - PHASE 2 (DATE INFLEXIBLE) 6 1
IP Post-Approval Site Inspection for License Renewal 71003 11/04/2013 11/22/2013 BI EPX
- EP EXERCISE INSPECTION / PI VERIFICATION 2
1 IP Performance Indicator Verification 71151 04/07/2014 04/11/2014 BI RP
- RADIATION PROTECTION BASELINE INSPECTION 1
1 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124.08 02/03/2014 02/07/2014 BI ENG
- COMPONENT DESIGN BASIS INSPECTION 6
1 IP Component Design Bases Inspection 7111121 05/19/2014 06/20/2014 BI RP
- RADIATION PROTECTION BASELINE INSPECTION 1
1 IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 06/09/2014 06/13/2014 BI RP
- RADIATION PROTECTION BASELINE INSPECTION 1
1 IP Radiological Environmental Monitoring Program 71124.07 09/22/2014 09/26/2014 BI OLRQ
- BIENNIAL REQUAL PROGRAM INSPECTION 2
1 IP Licensed Operator Requalification Program 7111111B 09/15/2014 09/19/2014 BI RP
- RADIATION PROTECTION BASELINE INSPECTION 1
1 IP Radiological Hazard Assessment and Exposure Controls 71124.01 11/03/2014 11/07/2014 1
IP Reactor Coolant System Activity 71151-BI01 11/03/2014 11/07/2014 1
IP Occupational Exposure Control Effectiveness 71151-OR01 11/03/2014 11/07/2014 1
IP RETS/ODCM Radiological Effluent 71151-PR01 11/03/2014 11/07/2014 BI ISI
- INSERVICE INSPECTION 1
1 IP Inservice Inspection Activities - BWR 7111108G 10/23/2014 11/22/2014 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.