| number = ML15016A433
| number = ML15016A433
| issue date = 01/16/2015
| issue date = 01/16/2015
| title = Arkansas Nuclear One, Unit 1 - Commitment Change Notification for NRC Order EA-12-049
| title = Commitment Change Notification for NRC Order EA-12-049
| author name = Browning J G
| author name = Browning J
| author affiliation = Entergy Operations, Inc
| author affiliation = Entergy Operations, Inc
| addressee name =  
| addressee name =  
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:1CAN011504  
{{#Wiki_filter:Entergy Operations, Inc.
 
1448 S.R. 333 Russellville, AR 72802 Tel 479-858-3110 Jeremy G. Browning Site Vice President Arkansas Nuclear One 1CAN011504 January 16, 2015 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
January 16, 2015  
 
U.S. Nuclear Regulatory Commission  
 
Attn: Document Control Desk  
 
Washington, DC 20555-0001  


==SUBJECT:==
==SUBJECT:==
Commitment Change Notification for NRC Order EA-12-049 Arkansas Nuclear One - Unit 1  
Commitment Change Notification for NRC Order EA-12-049 Arkansas Nuclear One - Unit 1 Docket No. 50-313 License No. DPR-51
 
Docket No. 50-313  
 
License No. DPR-51  


==REFERENCES:==
==REFERENCES:==
: 1. NRC Letter to Entergy, Arkansas Nuclear One, Unit 1 - Relaxation of the Schedule Requirements for Order EA-12-049 "Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for  
: 1. NRC Letter to Entergy, Arkansas Nuclear One, Unit 1 - Relaxation of the Schedule Requirements for Order EA-12-049 Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (BDBEEs) (TAC No. MF0942),
 
dated May 20, 2014 (1CNA051402) (ML14114A697)
Beyond-Design-Basis External Events (BDBEEs)" (TAC No. MF0942), dated May 20, 2014 (1CNA051402) (ML14114A697)  
: 2. Entergy letter to NRC, Request for Implementation Date Relief in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for BDBEEs (NRC Order EA-12-049), dated April 7, 2014 (1CAN041401) (ML14098A114)
: 2. Entergy letter to NRC, Request for Implementation Date Relief in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for BDBEEs (NRC  
 
Order EA-12-049), dated April 7, 2014 (1CAN041401) (ML14098A114)  


==Dear Sir or Madam:==
==Dear Sir or Madam:==


On March 12, 2012, the NRC issued order EA-12-049 to Entergy Operations, Inc. (Entergy).
On March 12, 2012, the NRC issued order EA-12-049 to Entergy Operations, Inc. (Entergy).
The order was immediately effective and directed Entergy to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a BDBEE.
In response to order EA-12-049 Entergy requested a relaxation of the order due date for Arkansas Nuclear One, Unit 1 (ANO-1) as documented in Reference 2, and it was subsequently granted by the NRC as documented in Reference 1. As part of the request, (Reference 2)
Entergy made two specific commitments and is withdrawing these commitments as discussed with the NRC Staff on January 14, 2015, and justified in the attachment to this letter.
There are no new regulatory commitments in this letter. If you have any questions regarding this request, please contact Stephenie Pyle at 479.858.4704.
I declare under penalty of perjury that the foregoing is true and correct; executed on January 16 2015.


The order was immediately effective and directed Entergy to develop, implement, and maintain
1CAN011504 Page 2 of 2 Sincerely, ORIGINAL SIGNED BY JEREMY G. BROWNING JGB/nbm
 
guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool
 
cooling capabilities in the event of a BDBEE.
 
In response to order EA-12-049 Entergy requested a relaxation of the order due date for
 
Arkansas Nuclear One, Unit 1 (ANO-1) as documented in Reference 2, and it was subsequently
 
granted by the NRC as documented in Reference 1. As part of the request, (Reference 2)
 
Entergy made two specific commitments and is withdrawing these commitments as discussed
 
with the NRC Staff on January 14, 2015, and justified in the attachment to this letter.
 
There are no new regulatory commitments in this letter. If you have any questions regarding
 
this request, please contact Stephenie Pyle at 479.858.4704.
 
I declare under penalty of perjury that the foregoing is true and correct; executed on
 
January 16 2015.
 
Entergy Operations, Inc.
1448 S.R. 333 Russellville, AR  72802
 
Tel  479-858-3110 Jeremy G. Browning Site Vice President A rkansas Nuclear One
 
1CAN011504 Page 2 of 2  
 
Sincerely, ORIGINAL SIGNED BY JEREMY G. BROWNING  
 
JGB/nbm  


==Attachment:==
==Attachment:==
ANO-1 Commitment Change Justification  
ANO-1 Commitment Change Justification cc:   Mr. Marc L. Dapas Regional Administrator U. S. Nuclear Regulatory Commission, Region IV 1600 East Lamar Boulevard Arlington, TX 76011-4511 NRC Senior Resident Inspector Arkansas Nuclear One P.O. Box 310 London, AR 72847 U. S. Nuclear Regulatory Commission Attn: Mr. Peter Bamford MS O-8B3 One White Flint North 11555 Rockville Pike Rockville, MD 20852
 
cc: Mr. Marc L. Dapas Regional Administrator  
 
U. S. Nuclear Regulatory Commission, Region IV  
 
1600 East Lamar Boulevard Arlington, TX 76011-4511  
 
NRC Senior Resident Inspector  
 
Arkansas Nuclear One  
 
P.O. Box 310  
 
London, AR 72847  
 
U. S. Nuclear Regulatory Commission  
 
Attn: Mr. Peter Bamford  
 
MS O-8B3 One White Flint North  
 
11555 Rockville Pike  
 
Rockville, MD 20852
 
Attachment to 1CAN011504 Arkansas Nuclear One, Unit 1 (ANO-1) Commitment Change Justification Attachment to 1CAN011504


Page 1 of 2
Attachment to 1CAN011504 Arkansas Nuclear One, Unit 1 (ANO-1) Commitment Change Justification


ANO-1 Commitment Change Justification  
Attachment to 1CAN011504 Page 1 of 2 ANO-1 Commitment Change Justification


==Background:==
==Background:==


In a letter to the NRC (Reference 2) Entergy Operations, Inc. (Entergy) made two specific  
In a letter to the NRC (Reference 2) Entergy Operations, Inc. (Entergy) made two specific commitments as part of the request for NRC order EA-12-049 Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Event (BDBEEs), schedule relaxation. The two commitments were:
 
: 1. As an interim measure, instructions will be in place by startup from the ANO-1 refueling outage 1R25 for connecting a portable diesel generator to the 2B5 load center should the ANO-2 2B6 load center not be capable of being powered for some unforeseen reason during an extended loss of alternating current power.
commitments as part of the request for NRC order EA-12-049 "Issuance of Order to Modify  
: 2. The 2B5 load center modification will be the only aspect of the ANO-1 Diverse and Flexible Coping Strategies (FLEX) that will not be in full compliance with NRC Order EA-12-049 by the ordered schedule date of February 2015. Additionally, the other aspects of compliance with NRC Order EA-12-049 will be complete by 1R25 (e.g., FLEX Support Guidelines, training, equipment staged, and modifications installed).
 
Both these commitments were scheduled Prior to ANO-1 Startup from 1R25 (February 2015).
Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis  
 
External Event (BDBEEs)," schedule relaxation. The two commitments were:  
: 1. As an interim measure, instructions will be in place by startup from the ANO-1 refueling outage 1R25 for connecting a portable diesel generator to the 2B5 load center should  
 
the ANO-2 2B6 load center not be capable of being powered for some unforeseen  
 
reason during an extended loss of alternating current power.  
: 2. The 2B5 load center modification will be the only aspect of the ANO-1 Diverse and Flexible Coping Strategies (FLEX) that will not be in full compliance with NRC Order  
 
EA-12-049 by the ordered schedule date of February 2015. Additionally, the other aspects of compliance with NRC Order EA-12-049 will be complete by 1R25 (e.g., FLEX  
 
Support Guidelines, training, equipment staged, and modifications installed).  
 
Both these commitments were scheduled "Prior to ANO-1 Startup from 1R25 (February 2015)."
 
Commitment Change:
Commitment Change:
Entergy has determined that ANO-1 implementation of the NRC order EA-12-049 prior to  
Entergy has determined that ANO-1 implementation of the NRC order EA-12-049 prior to implementation at ANO-2 is a less optimal action than a coordinated ANO-1 and ANO-2 implementation. As a result, the two commitments discussed above are withdrawn. The basis for this change is discussed below.
 
Basis:
implementation at ANO-2 is a less optimal action than a coordinated ANO-1 and ANO-2  
NRC Order EA-12-049 requires the development, implementation, and maintenance of guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a BDBEE. Section II of this order dictates the need to have guidance and strategies available to prevent fuel damage in the reactor and spent fuel pit should the loss of power, motive force, and normal access to the ultimate heat sink affect all units at a site simultaneously.
 
ANO is a two-unit site with significant physical and procedural interdependencies. The two units share certain common structures, systems, components (such as water tanks, electrical cross connections, and station blackout diesel generator), and common operational staff resources for BDBEEs.
implementation. As a result, the two commitments discussed above are withdrawn. The basis  
Compliance with the ANO-1 commitments to the NRC requires full implementation for ANO-1 with the exception of the 2B5 load center modification. This results in an approximate six-month interim period that the two units would not be consistently configured for responding to a BDBEE at the site. A specific example is the ANO qualified condensate storage tank (QCST).
 
The QCST is a seismically qualified tank common to both units which contains a protected
for this change is discussed below.  
 
Basis: NRC Order EA-12-049 requires the development, implementation, and maintenance of  
 
guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool  
 
cooling capabilities in the event of a BDBEE. Section II of this order dictates the need to have  
 
guidance and strategies available to prevent fuel damage in the reactor and spent fuel pit  
 
should the loss of power, motive force, and normal access to the ultimate heat sink affect all  
 
units at a site simultaneously.  
 
ANO is a two-unit site with significant physical and procedural interdependencies. The two units  
 
share certain common structures, systems, com ponents (such as water tanks, electrical cross connections, and station blackout diesel generator), and common operational staff resources for  
 
BDBEEs.  
 
Compliance with the ANO-1 commitments to the NRC requires full implementation for ANO-1  
 
with the exception of the 2B5 load center modifi cation. This results in an approximate six-month interim period that the two units would not be consistently configured for responding to a  
 
BDBEE at the site. A specific example is the ANO qualified condensate storage tank (QCST).
 
The QCST is a seismically qualified tank common to both units which contains a protected Attachment to 1CAN011504
 
Page 2 of 2
 
water volume sufficient for both units to utilize until time is available to transfer to alternate water sources under current licensing basis conditions. Entergy is working to qualify the QCST in order to credit a larger volume of water for both units to meet FLEX needs. Currently, with ANO-1 in a FLEX condition and ANO-2 complying with the current license basis procedures, the
 
sharing of the volume of water available in the QCST would challenge operators to make
 
alternate line-ups in the time required. A similar issue also exists for the ANO-1 borated water
 
storage tank and the ANO-2 refueling water tank qualification for crediting the availability of the
 
volume of water.
 
While most of the physical modifications are unit-specific, due to the interdependency of needed
 
systems and structures, the interim period would require special procedures and training that
 
would create operational challenges on both units with respect to BDBEE mitigation philosophy. 
 
Additionally the creation of a six-month interi m mixed implementation would create training, procedural, and regulatory issues while attempting to establish different requirements on the
 
same piece of equipment. An example of this is the commitment for an interim action to
 
connect a portable diesel generator to the 2B5 load center.
 
The elimination of the two ANO-1 stated commitments would allow both ANO-1 and ANO-2 to
 
be in compliance with the NRC Order EA-12-049 requirements at the same time. The
 
justification for this commitment withdrawal is based on implementation of a more consistent
 
and overall site response to a BDBEE. The ANO-1 full order compliance date is startup from
 
the 2R24 (October 2015).
 
== Conclusion:==
 
As described above, compliance with the previous commitments results in undue burden to the
 
operators by creating two separate operating environments, ANO-1 implementing FLEX while ANO-2 is using normal emergency operating procedures. Entergy has determined that


withdrawal of the commitments is a better approach by allowing implementation of a more  
Attachment to 1CAN011504 Page 2 of 2 water volume sufficient for both units to utilize until time is available to transfer to alternate water sources under current licensing basis conditions. Entergy is working to qualify the QCST in order to credit a larger volume of water for both units to meet FLEX needs. Currently, with ANO-1 in a FLEX condition and ANO-2 complying with the current license basis procedures, the sharing of the volume of water available in the QCST would challenge operators to make alternate line-ups in the time required. A similar issue also exists for the ANO-1 borated water storage tank and the ANO-2 refueling water tank qualification for crediting the availability of the volume of water.
While most of the physical modifications are unit-specific, due to the interdependency of needed systems and structures, the interim period would require special procedures and training that would create operational challenges on both units with respect to BDBEE mitigation philosophy.
Additionally the creation of a six-month interim mixed implementation would create training, procedural, and regulatory issues while attempting to establish different requirements on the same piece of equipment. An example of this is the commitment for an interim action to connect a portable diesel generator to the 2B5 load center.
The elimination of the two ANO-1 stated commitments would allow both ANO-1 and ANO-2 to be in compliance with the NRC Order EA-12-049 requirements at the same time. The justification for this commitment withdrawal is based on implementation of a more consistent and overall site response to a BDBEE. The ANO-1 full order compliance date is startup from the 2R24 (October 2015).


consistent and overall site response to a BDBEE. Accordingly, Entergy is withdrawing the
==
Conclusion:==


commitments to the NRC identified above.
As described above, compliance with the previous commitments results in undue burden to the operators by creating two separate operating environments, ANO-1 implementing FLEX while ANO-2 is using normal emergency operating procedures. Entergy has determined that withdrawal of the commitments is a better approach by allowing implementation of a more consistent and overall site response to a BDBEE. Accordingly, Entergy is withdrawing the commitments to the NRC identified above.


==References:==
==References:==
: 1. NRC Letter to Entergy, Arkansas Nuclear One, Unit 1 - Relaxation of the Schedule Requirements for Order EA-12-049 "Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for BDBEEs" (TAC No. MF0942), dated May 20, 2014 (1CNA051402) (ML14114A697)  
: 1. NRC Letter to Entergy, Arkansas Nuclear One, Unit 1 - Relaxation of the Schedule Requirements for Order EA-12-049 Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for BDBEEs (TAC No. MF0942), dated May 20, 2014 (1CNA051402) (ML14114A697)
: 2. Entergy letter to NRC, Request for Implementation Date Relief in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for BDBEEs (NRC Order EA-12-049), dated April 7, 2014 (1CAN041401) (ML14098A114)}}
: 2. Entergy letter to NRC, Request for Implementation Date Relief in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for BDBEEs (NRC Order EA-12-049), dated April 7, 2014 (1CAN041401) (ML14098A114)}}

Latest revision as of 16:55, 31 October 2019

Commitment Change Notification for NRC Order EA-12-049
ML15016A433
Person / Time
Site: Arkansas Nuclear Entergy icon.png
Issue date: 01/16/2015
From: Jeremy G. Browning
Entergy Operations
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
EA-12-049
Download: ML15016A433 (5)


Text

Entergy Operations, Inc.

1448 S.R. 333 Russellville, AR 72802 Tel 479-858-3110 Jeremy G. Browning Site Vice President Arkansas Nuclear One 1CAN011504 January 16, 2015 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001

SUBJECT:

Commitment Change Notification for NRC Order EA-12-049 Arkansas Nuclear One - Unit 1 Docket No. 50-313 License No. DPR-51

REFERENCES:

1. NRC Letter to Entergy, Arkansas Nuclear One, Unit 1 - Relaxation of the Schedule Requirements for Order EA-12-049 Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (BDBEEs) (TAC No. MF0942),

dated May 20, 2014 (1CNA051402) (ML14114A697)

2. Entergy letter to NRC, Request for Implementation Date Relief in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for BDBEEs (NRC Order EA-12-049), dated April 7, 2014 (1CAN041401) (ML14098A114)

Dear Sir or Madam:

On March 12, 2012, the NRC issued order EA-12-049 to Entergy Operations, Inc. (Entergy).

The order was immediately effective and directed Entergy to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a BDBEE.

In response to order EA-12-049 Entergy requested a relaxation of the order due date for Arkansas Nuclear One, Unit 1 (ANO-1) as documented in Reference 2, and it was subsequently granted by the NRC as documented in Reference 1. As part of the request, (Reference 2)

Entergy made two specific commitments and is withdrawing these commitments as discussed with the NRC Staff on January 14, 2015, and justified in the attachment to this letter.

There are no new regulatory commitments in this letter. If you have any questions regarding this request, please contact Stephenie Pyle at 479.858.4704.

I declare under penalty of perjury that the foregoing is true and correct; executed on January 16 2015.

1CAN011504 Page 2 of 2 Sincerely, ORIGINAL SIGNED BY JEREMY G. BROWNING JGB/nbm

Attachment:

ANO-1 Commitment Change Justification cc: Mr. Marc L. Dapas Regional Administrator U. S. Nuclear Regulatory Commission, Region IV 1600 East Lamar Boulevard Arlington, TX 76011-4511 NRC Senior Resident Inspector Arkansas Nuclear One P.O. Box 310 London, AR 72847 U. S. Nuclear Regulatory Commission Attn: Mr. Peter Bamford MS O-8B3 One White Flint North 11555 Rockville Pike Rockville, MD 20852

Attachment to 1CAN011504 Arkansas Nuclear One, Unit 1 (ANO-1) Commitment Change Justification

Attachment to 1CAN011504 Page 1 of 2 ANO-1 Commitment Change Justification

Background:

In a letter to the NRC (Reference 2) Entergy Operations, Inc. (Entergy) made two specific commitments as part of the request for NRC order EA-12-049 Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Event (BDBEEs), schedule relaxation. The two commitments were:

1. As an interim measure, instructions will be in place by startup from the ANO-1 refueling outage 1R25 for connecting a portable diesel generator to the 2B5 load center should the ANO-2 2B6 load center not be capable of being powered for some unforeseen reason during an extended loss of alternating current power.
2. The 2B5 load center modification will be the only aspect of the ANO-1 Diverse and Flexible Coping Strategies (FLEX) that will not be in full compliance with NRC Order EA-12-049 by the ordered schedule date of February 2015. Additionally, the other aspects of compliance with NRC Order EA-12-049 will be complete by 1R25 (e.g., FLEX Support Guidelines, training, equipment staged, and modifications installed).

Both these commitments were scheduled Prior to ANO-1 Startup from 1R25 (February 2015).

Commitment Change:

Entergy has determined that ANO-1 implementation of the NRC order EA-12-049 prior to implementation at ANO-2 is a less optimal action than a coordinated ANO-1 and ANO-2 implementation. As a result, the two commitments discussed above are withdrawn. The basis for this change is discussed below.

Basis:

NRC Order EA-12-049 requires the development, implementation, and maintenance of guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a BDBEE.Section II of this order dictates the need to have guidance and strategies available to prevent fuel damage in the reactor and spent fuel pit should the loss of power, motive force, and normal access to the ultimate heat sink affect all units at a site simultaneously.

ANO is a two-unit site with significant physical and procedural interdependencies. The two units share certain common structures, systems, components (such as water tanks, electrical cross connections, and station blackout diesel generator), and common operational staff resources for BDBEEs.

Compliance with the ANO-1 commitments to the NRC requires full implementation for ANO-1 with the exception of the 2B5 load center modification. This results in an approximate six-month interim period that the two units would not be consistently configured for responding to a BDBEE at the site. A specific example is the ANO qualified condensate storage tank (QCST).

The QCST is a seismically qualified tank common to both units which contains a protected

Attachment to 1CAN011504 Page 2 of 2 water volume sufficient for both units to utilize until time is available to transfer to alternate water sources under current licensing basis conditions. Entergy is working to qualify the QCST in order to credit a larger volume of water for both units to meet FLEX needs. Currently, with ANO-1 in a FLEX condition and ANO-2 complying with the current license basis procedures, the sharing of the volume of water available in the QCST would challenge operators to make alternate line-ups in the time required. A similar issue also exists for the ANO-1 borated water storage tank and the ANO-2 refueling water tank qualification for crediting the availability of the volume of water.

While most of the physical modifications are unit-specific, due to the interdependency of needed systems and structures, the interim period would require special procedures and training that would create operational challenges on both units with respect to BDBEE mitigation philosophy.

Additionally the creation of a six-month interim mixed implementation would create training, procedural, and regulatory issues while attempting to establish different requirements on the same piece of equipment. An example of this is the commitment for an interim action to connect a portable diesel generator to the 2B5 load center.

The elimination of the two ANO-1 stated commitments would allow both ANO-1 and ANO-2 to be in compliance with the NRC Order EA-12-049 requirements at the same time. The justification for this commitment withdrawal is based on implementation of a more consistent and overall site response to a BDBEE. The ANO-1 full order compliance date is startup from the 2R24 (October 2015).

==

Conclusion:==

As described above, compliance with the previous commitments results in undue burden to the operators by creating two separate operating environments, ANO-1 implementing FLEX while ANO-2 is using normal emergency operating procedures. Entergy has determined that withdrawal of the commitments is a better approach by allowing implementation of a more consistent and overall site response to a BDBEE. Accordingly, Entergy is withdrawing the commitments to the NRC identified above.

References:

1. NRC Letter to Entergy, Arkansas Nuclear One, Unit 1 - Relaxation of the Schedule Requirements for Order EA-12-049 Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for BDBEEs (TAC No. MF0942), dated May 20, 2014 (1CNA051402) (ML14114A697)
2. Entergy letter to NRC, Request for Implementation Date Relief in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for BDBEEs (NRC Order EA-12-049), dated April 7, 2014 (1CAN041401) (ML14098A114)