Other: 0CAN011601, Notification of Full Compliance with NRC Order EA-12-049 Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Bdbees), 0CAN021302, Units 1 and 2 - Overall Integrated Plan in Response to March 12, 2012, Commission Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), 0CAN021405, Second Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order EA-12-049), 0CAN021502, Fourth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Bdbees), 0CAN021503, Fourth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool (SFP) Instrumentation (Order Number EA-12-051), 0CAN081402, Third Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Bdbees), ML13063A015, ML13241A414, ML13241A415, ML14045A156, ML14140A514, ML15016A433, ML15054A320, ML15236A340
|
MONTHYEAR0CAN021302, Units 1 and 2 - Overall Integrated Plan in Response to March 12, 2012, Commission Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2013-02-28028 February 2013 Units 1 and 2 - Overall Integrated Plan in Response to March 12, 2012, Commission Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML13063A0152013-02-28028 February 2013 Overall Integrated Plan in Response to March 12, 2012, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051) Project stage: Other ML13127A2352013-05-0707 May 2013 Request for Additional Information Email Overall Integrated Plan in Response to the Commission Order Modifying Licenses Project stage: RAI ML13156A3132013-06-26026 June 2013 Request for Additional Information, Overall Integrated Plan in Response to 3/12/12 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order EA-12-051) Project stage: RAI 0CAN071301, Response to Request for Additional Information for Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation2013-07-25025 July 2013 Response to Request for Additional Information for Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation Project stage: Response to RAI ML13241A4142013-08-28028 August 2013 First Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML13241A4152013-08-28028 August 2013 First Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML13281A5022013-10-29029 October 2013 Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation Project stage: RAI ML14045A1562014-02-20020 February 2014 Mega-Tech Services, LLC Technical Evaluation Report Regarding the Overall Integrated Plan for Arkansas Nuclear One, Units 1 and 2, TAC Nos.: MF0942 and MF0943 Project stage: Other ML14007A4592014-02-25025 February 2014 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) Project stage: Acceptance Review 0CAN021405, Second Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order EA-12-049)2014-02-27027 February 2014 Second Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order EA-12-049) Project stage: Other 1CAN041401, Request for Implementation Date Relief in Response to March 12, 2012,Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Bdbees)2014-04-0808 April 2014 Request for Implementation Date Relief in Response to March 12, 2012,Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Bdbees) Project stage: Request ML14114A6972014-05-20020 May 2014 Relaxation of the Schedule Requirements for Order EA-12-049 Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events Project stage: Approval ML14140A5142014-05-28028 May 2014 Update Regarding Audit Activities Associated with Order EA-12-049 (Mitigation Strategies) Project stage: Other 0CAN081402, Third Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Bdbees)2014-08-28028 August 2014 Third Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Bdbees) Project stage: Other ML15016A4332015-01-16016 January 2015 Commitment Change Notification for NRC Order EA-12-049 Project stage: Other 0CAN021503, Fourth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool (SFP) Instrumentation (Order Number EA-12-051)2015-02-24024 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool (SFP) Instrumentation (Order Number EA-12-051) Project stage: Other 0CAN021502, Fourth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Bdbees)2015-02-24024 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Bdbees) Project stage: Other ML15054A3202015-03-0909 March 2015 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other ML15236A3402015-09-0101 September 2015 Report for the Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other 0CAN011601, Notification of Full Compliance with NRC Order EA-12-049 Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Bdbees)2016-01-12012 January 2016 Notification of Full Compliance with NRC Order EA-12-049 Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Bdbees) Project stage: Other 2014-02-27
[Table View] |
|
---|
Category:Letter
MONTHYEARML23326A0392024-01-24024 January 2024 Issuance of Amendment No. 281 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24017A1582024-01-17017 January 2024 Submittal of Emergency Plan Revision 50 IR 05000313/20234202024-01-10010 January 2024 Security Baseline Inspection Report 05000313/2023420 and 05000368/2023420 IR 05000313/20234022024-01-0202 January 2024 Security Baseline Inspection Report 05000313/2023402 and 05000368/2023402 ML23354A0022023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology Slides and Affidavit for Pre-Submittal Meeting ML23352A0292023-12-13013 December 2023 Entergy - 2024 Nuclear Energy Liability Evidence of Financial Protection ML23340A1592023-12-13013 December 2023 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment IR 05000313/20234052023-12-12012 December 2023 Security Baseline Inspection Report 05000313/2023405 and 05000368/2023405 ML23341A0832023-12-11011 December 2023 Material Control and Accounting Program Inspection Report 05000313/368/2023404- Cover Letter ML23305A0922023-12-0707 December 2023 Summary of Regulatory Audit Regarding License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b ML23333A1362023-11-29029 November 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23275A2072023-11-28028 November 2023 Issuance of Amendment No. 280 Removal of Technical Specification Condition Allowing Two Reactor Coolant Pump Operation ML23325A1412023-11-21021 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000313/20230032023-11-21021 November 2023 Revised - ANO Revised Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/ 2023001 ML23243B0452023-11-13013 November 2023 Request for Withholding Information from Public Disclosure ML23313A0962023-11-13013 November 2023 Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/2023001 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000313/20230112023-10-10010 October 2023 Commercial Grade Dedication Inspection Report 05000313/2023011 and 05000368/2023011 IR 05000313/20230052023-08-21021 August 2023 Updated Inspection Plan for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2023005 and 05000368/2023005) - Mid Cycle IR 05000313/20243012023-08-14014 August 2023 Notification of NRC Initial Operator Licensing Examination 05000313/2024301 IR 05000313/20230022023-08-11011 August 2023 Integrated Inspection Report 05000313/2023002 and 05000368/2023002 and Notice of Violation ML23209A6022023-08-0909 August 2023 Regulatory Audit Plan in Support of License Amendment Request to Revise Technical Specifications to Adopt Risk- Informed Completion Times IR 05000416/20230022023-08-0808 August 2023 Integrated Inspection Report 05000416/2023002 and Independent Spent Fuel Storage Installation Inspection Report 07200050/2023001 ML23208A2132023-08-0303 August 2023 Regulatory Audit Summary Concerning Review of License Amendment Request to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation ML23208A2112023-07-27027 July 2023 Entergy Operations Inc., Application to Revise Technical Specifications to Adopt TSTF-205, Revision of Channel Calibration, Channel Functional Test, and Related Definitions ML23188A1732023-07-12012 July 2023 Request for Withholding Information from Public Disclosure ML23142A2022023-06-29029 June 2023 Issuance of Amendment Nos. 279 and 332 Emergency Plan Staffing Requirements IR 05000313/20234032023-06-28028 June 2023 Security Baseline Inspection Report 05000313/2023403 and 05000368/2023403 ML23178A0892023-06-26026 June 2023 August 2023 Emergency Preparedness Program Inspection-Request for Information ML23166B0902023-06-21021 June 2023 Request for Relief ANO1 ISI 036 Regarding Volumetric Examination Requirements ML23180A1082023-06-20020 June 2023 ANO Unit 1 SAR Amendment 31, TRM, TS Bases, 10 CFR 50.59 Report, and Commitment Change Summary Report IR 05000313/20234012023-06-13013 June 2023 Cyber Security Inspection Report 05000313/2023401 and 05000368/2023401 ML23130A2972023-05-17017 May 2023 Notification of Inspection (NRC Inspection Report 05000313/2023003) and Request for Information ML23121A3012023-05-10010 May 2023 Regulatory Audit Plan in Support of License Amendment Request to Revise Technical Specifications to Adopt Risk - Informed Completion Times ML23114A3572023-05-10010 May 2023 Regulatory Audit Summary Concerning Review of Request for Alternative ANO-CISI-002 Regarding Containment Inservice Inspection Frequency ML23130A2732023-05-10010 May 2023 and Waterford 3 Steam Electric Station - Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000313/20230012023-05-0909 May 2023 Integrated Inspection Report 05000313/2023001 and 05000368/2023001 ML23118A3202023-05-0808 May 2023 Notification of Biennial Problem Identification and Resolution Inspection and Request for Information (05000313;05000368/2023010) IR 05000368/20233012023-05-0101 May 2023 NRC Examination Report 05000368/2023301 ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment ML23108A1362023-04-24024 April 2023 Approval of Request for Half-Nozzle Repair of Reactor Vessel Closure Head Penetration No. 46 ML23110A1122023-04-20020 April 2023 Annual Report for Entergy Quality Assurance Program Manual Changes Under 10 CFR 50.54(a)(3), 10 CFR 71.106, and 10 CFR 72.140(d). Notification of Application of Approved Appendix B to 10 CFR 72 Subpart G 2024-01-24
[Table view] |
Text
Entergy Operations, Inc.
1448 S.R. 333 Russellville, AR 72802 Tel 479-858-3110 Jeremy G. Browning Vice President, Operations Arkansas Nuclear One 0CAN081303 August 28, 2013 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike Rockville, MD 20852
SUBJECT:
First Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)
Arkansas Nuclear One - Units 1 and 2 Docket Nos. 50-313 and 50-368 License Nos. DPR-51 and NPF-6
REFERENCES:
- 1. NRC Order Number EA-12-051, Order to Modify Licenses with Regard to Reliable Spent Fuel Pool (SFP) Instrumentation, dated March 12, 2012 (0CNA031207) (ML12054A679)
- 2. NRC Interim Staff Guidance JLD-ISG-2012-03, Compliance with Order EA-12-051, Reliable SFP Instrumentation, Revision 0, dated August 29, 2012 (ML12221A339)
- 3. Nuclear Energy Institute (NEI) 12-02, Industry Guidance for Compliance with NRC Order EA-12-051, To Modify Licenses with Regard to Reliable SFP Instrumentation, Revision 1, dated August 2012 (ML12240A307)
- 4. Entergy letter to NRC, Initial Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Reliable SFP Instrumentation (Order Number EA-12-051), dated October 26, 2012 (0CAN101204)
(ML12305A274)
- 5. Entergy letter to NRC, Overall Integrated Plan (OIP) in Response to March 12, 2012, Commission Order Modifying License with Regard to Reliable SFP Instrumentation (Order Number EA-12-051), dated February 28, 2013 (0CAN021303)
(ML13063A015)
0CAN081303 Page 2 of 3
Dear Sir or Madam:
On March 12, 2012, the NRC issued an order (Reference 1) to Entergy Operations, Inc.
(Entergy). Reference 1 was immediately effective and directs Entergy to install reliable SFP level instrumentation. Specific requirements are outlined in Attachment 2 of Reference 1.
Reference 1 required submission of an initial status report 60 days following issuance of the final interim staff guidance (Reference 2) and an OIP pursuant to Section IV, Condition C. Reference 2 endorses industry guidance document NEI 12-02, Revision 1 (Reference 3). Reference 4 provided the initial status report regarding SFP instrumentation, and Reference 5 provided the OIP.
Reference 1 requires submission of a status report at six-month intervals following submittal of the OIP. Reference 3 provides direction regarding the content of the status reports. The purpose of this letter is to provide the first six-month status report pursuant to Section IV, Condition C.2, of Reference 1, that delineates progress made in implementing the requirements of Reference 1. The attached report provides an update of milestone accomplishments since the last status report, including any changes to the compliance method, schedule, or need for relief and the basis, if any.
This letter contains no new regulatory commitments. Should you have any questions regarding this submittal, please contact Stephenie Pyle at 479.858.4704.
I declare under penalty of perjury that the foregoing is true and correct; executed on August 28, 2013.
Sincerely, Original signed by Jeremy G. Browning JGB/nbm
Attachment:
Arkansas Nuclear One Units 1 and 2 First Six Month Status Report for the Implementation of Order EA-12-051, Order to Modify Licenses with Regard to Reliable SFP Instrumentation
0CAN081303 Page 3 of 3 cc: Mr. Steven A. Reynolds Regional Administrator U. S. Nuclear Regulatory Commission, Region IV 1600 East Lamar Boulevard Arlington, TX 76011-4511 U. S. Nuclear Regulatory Commission Attn: Director, Office of Nuclear Reactor Regulation One White Flint North 11555 Rockville Pike Rockville, MD 20852 NRC Senior Resident Inspector Arkansas Nuclear One P.O. Box 310 London, AR 72847 U. S. Nuclear Regulatory Commission Attn: Mr. Kaly Kalyanam One White Flint North MS O-8 B1 11555 Rockville Pike Rockville, MD 20852 U. S. Nuclear Regulatory Commission Attn: Jessica A. Kratchman One White Flint North MS 9-D2 11555 Rockville Pike Rockville, MD 20852
Attachment to 0CAN081303 Arkansas Nuclear One (ANO) Units 1 and 2 (ANO-1 and ANO-2) First Six Month Status Report for the Implementation of Order EA-12-051, Order to Modify Licenses with Regard to Reliable Spent Fuel Pool (SFP) Instrumentation
Attachment to 0CAN081302 Page 1 of 3 ANO-1 and ANO-2 First Six Month Status Report for the Implementation of Order EA-12-051, Order to Modify Licenses with Regard to Reliable SFP Instrumentation Introduction Entergy Operations, Inc. developed an overall integrated plan (OIP) provided via Reference 1 for ANO-1 and ANO-2, documenting the requirements to install reliable spent fuel pool instrumentation (SFPI), in response to Reference 2. This attachment provides an update of milestone accomplishments since submittal of the OIP, including any changes to the compliance method, schedule, or need for relief/relaxation and the basis, if any.
Milestone Accomplishments The following milestone(s) have been completed since the development of the OIP (Reference 1) and are current as of July 31, 2013.
- Although not part of the original milestone schedule, NRC requests for additional information (RAIs) were received June 26, 2013 (Reference 3) and responded to on July 25, 2013 (Reference 4). The responses to the RAIs were added to the milestone schedule. The addition of this milestone and target completion date does not impact the Order implementation date.
Milestone Schedule Status The following provides an update to the milestone schedule to support the OIP. This section provides the activity status of each item, and the expected completion date noting any change. The dates are planning dates subject to change as design and implementation details are developed.
Revised Target Completion Activity Target Milestone Date Status Completion Date ANO-1 Reliable SFPI October 2013 In Progress Design Modification Package Developed/Issued ANO-1 Reliable SFPI 1R25 Fall 2014 Pending 1R25 Early Installed Refueling Outage 2015 Refueling Outage (see Note)
ANO-2 Reliable SFPI July 2014 Pending Design Modification Package Developed/Issued ANO-2 Reliable SFPI 2R24 Fall 2015 Pending Installed Refueling Outage NRC RAIs (Received Submitted Not Applicable July 25, 2013 June 26, 2013)
Attachment to 0CAN081302 Page 2 of 3 Note: The ANO-1 Refueling Outage 1R25 (second refueling outage after submittal of the OIP) original schedule date of Fall 2014 has slipped to early 2015 due to the 1R24 (Spring 2013) stator drop event recovery and outage extension.
Changes to Compliance Method There are no significant changes to the compliance method as documented in the OIP (Reference 1). OIP changes and/or updates based on current design and implementation plans are considered minor in nature and are summarized as follows:
- Reference OIP Section 2 (Schedule). ANO-1 compliance / implementation /
target completion date has slipped as noted in the above Milestone Schedule Status. This is a change of the physical date only while maintaining the required implementation association with the second refueling outage after submittal of the OIP.
- Reference OIP Section 6 (Instrument Channel Design Criteria), Section 7 (Arrangement), and Attachments 1 and 2 (SFPI Simplified Approximate Locations and Cable Routing). These sections state that in the SFP area, cables shall be routed in rigid metal conduit. As already identified in the RAI response (Reference 4), this is updated to protective metal raceway to open up the generic use of raceway (versus conduit) to allow use of wire/tube tracks with convenient removable covers to better facilitate installation.
Need for Relief/Relaxation and Basis for the Relief/Relaxation ANO expects to comply with the order implementation date and no relief/relaxation is required at this time.
Open Items from OIP and Draft Safety Evaluation None Potential Draft Safety Evaluation (SE) Impacts The NRC has not issued a draft SE for either unit; therefore, there are no potential impacts to the draft SE identified at this time.
Attachment to 0CAN081302 Page 3 of 3 References
- 1. OIP in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051),
dated February 28, 2013 (0CAN021303) (ML13063A015)
- 2. NRC Order Number EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, dated March 12, 2012 (0CNA031207)
(ML12054A679)
- 3. RAI for the OIP in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable SFP Instrumentation (Order Number EA-12-051), dated June 26, 2013, (0CNA061308) (ML13156A313)
- 4. Response to RAI for the OIP in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable SFP Instrumentation, dated July 25, 2013 (0CAN071301) (ML13207A269)