ML072700716: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
 
(2 intermediate revisions by the same user not shown)
Line 2: Line 2:
| number = ML072700716
| number = ML072700716
| issue date = 09/27/2007
| issue date = 09/27/2007
| title = Calvert Cliffs, Technical Specification Pages Re Unavailability of Barriers Using Consolidated Line Item Improvement Process
| title = Technical Specification Pages Re Unavailability of Barriers Using Consolidated Line Item Improvement Process
| author name = Pickett D V
| author name = Pickett D
| author affiliation = NRC/NRR/ADRO/DORL/LPLI-1
| author affiliation = NRC/NRR/ADRO/DORL/LPLI-1
| addressee name = Spina J A
| addressee name = Spina J
| addressee affiliation = Calvert Cliffs Nuclear Power Plant, Inc
| addressee affiliation = Calvert Cliffs Nuclear Power Plant, Inc
| docket = 05000317, 05000318
| docket = 05000317, 05000318
| license number = DPR-053, DPR-069
| license number = DPR-053, DPR-069
| contact person = Pickett D V, NRR/DORL, 415-1364
| contact person = Pickett D, NRR/DORL, 415-1364
| case reference number = TAC MD5437, TAC MD5438
| case reference number = TAC MD5437, TAC MD5438
| document type = Technical Specification, Amendment
| document type = Technical Specification, Amendment
| page count = 6
| page count = 6
| project = TAC:MD5437, TAC:MD5438
| project = TAC:MD5437, TAC:MD5438
| stage = Other
| stage = Acceptance Review
}}
}}


=Text=
=Text=
{{#Wiki_filter:-3-rules, regulations, and orders of the Commission, now or hereafter applicable; and is subject to the additional conditions specified and incorporated below: (1) Maximum Power Level The licensee is authorized to operate the facility at steady-state reactor core power levels not in excess of 2700 megawatts-thermal in accordance with the conditions specified herein.(2) Technical Specifications The Technical Specifications contained in Appendices A and B, as revised through Amendment No. 282, are hereby incorporated into this license. The licensee shall operate the facility in accordance with the Technical Specifications.(a) For Surveillance Requirements (SRs) that are new, in Amendment 227 to Facility Operating License No. DPR-53, the first performance is due at the end of the first surveillance interval that begins at implementation of Amendment 227. For SRs that existed prior to Amendment 227, including SRs with modified acceptance criteria and SRs whose frequency of performance is being extended, the first performance is due at the end of the first surveillance interval that begins on the date the Surveillance was last performed prior to implementation of Amendment 227.(3) Additional Conditions The Additional Conditions contained in Appendix C as revised through Amendment No. 267 are hereby incorporated into this license. Calvert Cliffs Nuclear Power Plant, Inc. shall operate the facility in accordance with the Additional Conditions.
{{#Wiki_filter: rules, regulations, and orders of the Commission, now or hereafter applicable; and is subject to the additional conditions specified and incorporated below:
(4) Secondary Water Chemistry Monitoring Program The Calvert .Cliffs Nuclear Power Plant, Inc., shall implement a secondary water chemistry monitoring program to inhibit steam generator tube degradation.
(1)     Maximum Power Level The licensee is authorized to operate the facility at steady-state reactor core power levels not in excess of 2700 megawatts-thermal in accordance with the conditions specified herein.
This program shall include: a. Identification of a sampling schedule for the critical parameters and control points for these parameters;
(2)     Technical Specifications The Technical Specifications contained in Appendices A and B, as revised through Amendment No. 282, are hereby incorporated into this license. The licensee shall operate the facility in accordance with the Technical Specifications.
: b. Identification of the procedures used to quantify parameters that are critical to control points;Amendment No. 282 C. This license is deemed to contain and is subject to the conditions set forth in 10 CFR ChapterI .and is subject to all applicable provisions of the Act, ,and the rules, regulations, and orders of the Commission, now and hereafter applicable; and is subject to the additional conditions specified and incorporated below: (1) Maximum Power Level The licensee is authorized to operate the facility at reactor steady-state core power levels not in excess of 2700 megawatts-thermal in accordance with the conditions specified herein.(2) Technical Specifications The Technical Specifications contained in Appendices A and B, as revised through Amendment No. 259, are hereby incorporated into this license.The licensee shall operate the facility in accordnace with the Technical Specifications.(a) For Surveillance Requirements (SRs) that are new, in Amendment 201 to Facility Operating License No. DPR-69, the first performance is due at the end of the first surveillance interval that begins at implementation of Amendment 201. For SRs that existed prior to Amendment 201, including SRs with modified acceptance criteria and SRs whose frequency of performance is being extended, the first performance is due at the end of the first surveillance interval that begins on the date the Surveillance was last performed prior to implementation of Amendment 201.(3) Less Than Four Pump Operation The licensee shall not operate the reactor at power levels in excess of five (5) percent of rated thermal power with less than four (4) reactor coolant pumps in operation.
(a)     For Surveillance Requirements (SRs) that are new, in Amendment 227 to Facility Operating License No. DPR-53, the first performance is due at the end of the first surveillance interval that begins at implementation of Amendment 227. For SRs that existed prior to Amendment 227, including SRs with modified acceptance criteria and SRs whose frequency of performance is being extended, the first performance is due at the end of the first surveillance interval that begins on the date the Surveillance was last performed prior to implementation of Amendment 227.
This condition shall remain in effect until the licensee has submitted safety analyses for less than four pump operation, and approval for such operation has been granted by the Commission by amendment of this license.(4) Environmental Monitoring Program If harmful effects or evidence of irreversible damage are detected by the biological monitoring program, hydrological monitoring program, and the radiological monitoring program specified in the Appendix B Technical Specifications, the licensee will provide to the staff a detailed analysis of the problem and a program of remedial action to be taken to eliminate or significantly reduce the detrimental effects or damage.Amendment No. 259 LCO Applicability 3.0 3.0 LIMITING CONDITION FOR OPERATION (LCO) APPLICABILITY not required to be entered. Only the support system LCO ACTIONS are required to be entered. This is an exception to LCO 3.0.2 for the supported system. In this event, additional evaluations and limitations may be required in accordance with Specification 5.5.15, "Safety Function Determination Program (SFDP)." If a loss of safety function is determined to exist by this program, the appropriate Conditions and Required Actions of the LCO in which the loss of safety function exists are required to be entered.When a support system's Required Action directs a supported system to be declared inoperable or directs entry into Conditions and Required Actions for a supported system, the applicable Conditions and Required Actions shall be entered in accordance with LCO 3.0.2.LCO 3.0.7 Special test exception (STE) LCOs in each applicable LCO section allow specified Technical Specification (TS)requirements to be changed to permit performance of special tests and operations.
(3)     Additional Conditions The Additional Conditions contained in Appendix C as revised through Amendment No. 267 are hereby incorporated into this license. Calvert Cliffs Nuclear Power Plant, Inc. shall operate the facility in accordance with the Additional Conditions.
Unless otherwise specified, all other TS requirements remain unchanged.
(4)     Secondary Water Chemistry Monitoring Program The Calvert .Cliffs Nuclear Power Plant, Inc., shall implement a secondary water chemistry monitoring program to inhibit steam generator tube degradation. This program shall include:
Compliance with STE LCOs is optional.
: a.       Identification of a sampling schedule for the critical parameters and control points for these parameters;
When an STE LCO is desired to be met but is not met, the ACTIONS of the STE LCO shall be met. When an STE LCO is not desired to be met, entry into a MODE or other specified condition in the Applicability shall only be made in accordance with the other applicable Specifications.
: b.       Identification of the procedures used to quantify parameters that are critical to control points; Amendment No. 282
LCO 3.0.8 [Reserved]
 
LCO 3.0.9 When one or more required barriers are unable to perform their related support function(s), any supported system LCO(s) are not required to be declared not met solely for this reason for up to 30 days provided that at least one train or subsystem of the supported system is OPERABLE and supported by barriers capable of providing their related support function(s), and risk is assessed and managed. This specification may be concurrently applied to more than one CALVERT CLIFFS -UNIT 1 CALVERT CLIFFS -UNIT 2 3.0-3 Amendment No. 282 Amendment No. 259 LCO Applicability 3.0 3.0 LIMITING CONDITION FOR OPERATION (LCO) APPLICABILITY train or subsystem of a multiple train or subsystem supported system provided at least one train or subsystem of the supported system is OPERABLE and the barriers supporting each of these trains or subsystems provide their related support function(s) for different categories of initiating events.If the required OPERABLE train or subsystem becomes inoperable while.this specification is in use, it must be restored to OPERABLE status within 24 hours or the provisions of this specification cannot be applied to the trains or subsystems supported by the barriers that cannot perform their related support function(s).
C. This license is deemed to contain and is subject to the conditions set forth in 10 CFR ChapterI .andis subject to all applicable provisions of the Act, ,andthe rules, regulations, and orders of the Commission, now and hereafter applicable; and is subject to the additional conditions specified and incorporated below:
At the end of the specified period, the required barriers must be able to perform their related support function(s) or the supported system LCO(s) shall be declared not met.CALVERT CLIFFS -UNIT 1 CALVERT CLIFFS -UNIT 2 3.0-4 Amendment No. 282 Amendment No. 259 SR Applicability 3.0 3.0 SURVEILLANCE REQUIREMENT (SR) APPLICABILITY SR 3.0.1 SRs shall be met during the MODES or other specified conditions in the Applicability for individual LCOs, unless otherwise stated in the SR. Failure to meet a Surveillance, whether such failure is experienced during the performance of the Surveillance or between performances of the Surveillance, shall be failure to meet the LCO. Failure to perform a Surveillance within the specified Frequency shall be failure to meet the LCO, except as provided in SR 3.0.3.Surveillances do not have to be performed on inoperable equipment or variables outside specified limits.SR 3.0.2 The specified Frequency for each SR is met if the Surveillance is performed within 1.25 times the interval specified in the Frequency, as measured from the previous performance, or as measured from the time a specified condition of the Frequency is met.For Frequencies specified as "once," the above interval extension does not apply.If a Completion Time requires periodic performance on a"once per .." basis, the above Frequency extension applies to each performance after the initial performance.
(1)     Maximum Power Level The licensee is authorized to operate the facility at reactor steady-state core power levels not in excess of 2700 megawatts-thermal in accordance with the conditions specified herein.
(2)     Technical Specifications The Technical Specifications contained in Appendices A and B, as revised through Amendment No. 259, are hereby incorporated into this license.
The licensee shall operate the facility in accordnace with the Technical Specifications.
(a)     For Surveillance Requirements (SRs) that are new, in Amendment 201 to Facility Operating License No. DPR-69, the first performance is due at the end of the first surveillance interval that begins at implementation of Amendment 201. For SRs that existed prior to Amendment 201, including SRs with modified acceptance criteria and SRs whose frequency of performance is being extended, the first performance is due at the end of the first surveillance interval that begins on the date the Surveillance was last performed prior to implementation of Amendment 201.
(3)     Less Than Four Pump Operation The licensee shall not operate the reactor at power levels in excess of five (5) percent of rated thermal power with less than four (4) reactor coolant pumps in operation. This condition shall remain in effect until the licensee has submitted safety analyses for less than four pump operation, and approval for such operation has been granted by the Commission by amendment of this license.
(4)     Environmental Monitoring Program If harmful effects or evidence of irreversible damage are detected by the biological monitoring program, hydrological monitoring program, and the radiological monitoring program specified in the Appendix B Technical Specifications, the licensee will provide to the staff a detailed analysis of the problem and a program of remedial action to be taken to eliminate or significantly reduce the detrimental effects or damage.
Amendment No. 259
 
LCO Applicability 3.0 3.0 LIMITING CONDITION FOR OPERATION (LCO)   APPLICABILITY not required to be entered. Only the support system LCO ACTIONS are required to be entered. This is an exception to LCO 3.0.2 for the supported system. In this event, additional evaluations and limitations may be required in accordance with Specification 5.5.15, "Safety Function Determination Program (SFDP)."   If a loss of safety function is determined to exist by this program, the appropriate Conditions and Required Actions of the LCO in which the loss of safety function exists are required to be entered.
When a support system's Required Action directs a supported system to be declared inoperable or directs entry into Conditions and Required Actions for a supported system, the applicable Conditions and Required Actions shall be entered in accordance with LCO 3.0.2.
LCO 3.0.7         Special test exception (STE) LCOs in each applicable LCO section allow specified Technical Specification (TS) requirements to be changed to permit performance of special tests and operations. Unless otherwise specified, all other TS requirements remain unchanged. Compliance with STE LCOs is optional. When an STE LCO is desired to be met but is not met, the ACTIONS of the STE LCO shall be met. When an STE LCO is not desired to be met, entry into a MODE or other specified condition in the Applicability shall only be made in accordance with the other applicable Specifications.
LCO 3.0.8         [Reserved]
LCO 3.0.9         When one or more required barriers are unable to perform their related support function(s), any supported system LCO(s) are not required to be declared not met solely for this reason for up to 30 days provided that at least one train or subsystem of the supported system is OPERABLE and supported by barriers capable of providing their related support function(s), and risk is assessed and managed. This specification may be concurrently applied to more than one CALVERT CLIFFS - UNIT 1             3.0-3                     Amendment No. 282 CALVERT CLIFFS - UNIT 2                                        Amendment No. 259
 
LCO Applicability 3.0 3.0 LIMITING CONDITION FOR OPERATION (LCO) APPLICABILITY train or subsystem of a multiple train or subsystem supported system provided at least one train or subsystem of the supported system is OPERABLE and the barriers supporting each of these trains or subsystems provide their related support function(s) for different categories of initiating events.
If the required OPERABLE train or subsystem becomes inoperable while.this specification is in use, it must be restored to OPERABLE status within [[estimated NRC review hours::24 hours]] or the provisions of this specification cannot be applied to the trains or subsystems supported by the barriers that cannot perform their related support function(s).
At the end of the specified period, the required barriers must be able to perform their related support function(s) or the supported system LCO(s) shall be declared not met.
CALVERT CLIFFS - UNIT 1             3.0-4                   Amendment No. 282 CALVERT CLIFFS - UNIT 2                                      Amendment No. 259
 
SR Applicability 3.0 3.0 SURVEILLANCE REQUIREMENT (SR)   APPLICABILITY SR 3.0.1           SRs shall be met during the MODES or other specified conditions in the Applicability for individual LCOs, unless otherwise stated in the SR. Failure to meet a Surveillance, whether such failure is experienced during the performance of the Surveillance or between performances of the Surveillance, shall be failure to meet the LCO. Failure to perform a Surveillance within the specified Frequency shall be failure to meet the LCO, except as provided in SR 3.0.3.
Surveillances do not have to be performed on inoperable equipment or variables outside specified limits.
SR 3.0.2           The specified   Frequency for each SR is met if the Surveillance is performed within 1.25 times the interval specified in the Frequency, as measured from the previous performance, or as measured from the time a specified condition of the Frequency is met.
For Frequencies specified as "once," the above interval extension does not apply.
If a Completion Time requires periodic performance on a "once per . ." basis, the above Frequency extension applies to each performance after the initial performance.
Exceptions to this Specification are stated in the individual Specifications.
Exceptions to this Specification are stated in the individual Specifications.
SR 3.0.3 If it is discovered that a Surveillance was not performed within its specified Frequency, then compliance with the requirement to declare the LCO not met may be delayed, from the time of discovery up to 24 hours, or up to the limit of the specified Frequency, whichever is greater. This delay period is permitted to allow performance of the Surveillance.
SR 3.0.3           If it is discovered that a Surveillance was not performed within its specified Frequency, then compliance with the requirement to declare the LCO not met may be delayed, from the time of discovery up to [[estimated NRC review hours::24 hours]], or up to the limit of the specified Frequency, whichever is greater. This delay period is permitted to allow performance of the Surveillance. A risk evaluation shall be performed for any Surveillance delayed greater than [[estimated NRC review hours::24 hours]] and the risk impact shall be managed.
A risk evaluation shall be performed for any Surveillance delayed greater than 24 hours and the risk impact shall be managed.CALVERT CLIFFS -UNIT 1 3.0-5 Amendment No. 282 CALVERT CLIFFS -UNIT 2 Amendment No. 259 SR Applicability 3.0 3.0 SURVEILLANCE REQUIREMENT (SR) APPLICABILITY If the Surveillance is not performed within the delay period, the LCO must immediately be declared not met, and the applicable Condition(s) must be entered.When the Surveillance is performed within the delay period and the Surveillance is not met, the LCO must immediately be declared not met, and the applicable Condition(s) must be entered.SR 3.0.4 Entry into a MODE or other specified condition in the Applicability of an LCO shall only be made when the LCO's Surveillances have been met within their specified Frequency, except as provided by SR 3.0.3. When an LCO is not met due to Surveillances not having been met, entry into a MODE or other specified condition in the Applicability shall only be made in accordance with LCO 3.0.4.This provision shall not prevent entry into MODES or other specified conditions in the Applicability that are required to comply with ACTIONS or that are part of the shutdown of the unit.CALVERT CLIFFS -UNIT I CALVERT CLIFFS -UNIT 2 3.0-6 Amendment No.Amendment No.282 259}}
CALVERT CLIFFS - UNIT 1               3.0-5                   Amendment No. 282 CALVERT CLIFFS - UNIT 2                                         Amendment No. 259
 
SR Applicability 3.0 3.0 SURVEILLANCE REQUIREMENT (SR) APPLICABILITY If the Surveillance is not performed within the delay period, the LCO must immediately be declared not met, and the applicable Condition(s) must be entered.
When the Surveillance is performed within the delay period and the Surveillance is not met, the LCO must immediately be declared not met, and the applicable Condition(s) must be entered.
SR 3.0.4         Entry into a MODE or other specified condition in the Applicability of an LCO shall only be made when the LCO's Surveillances have been met within their specified Frequency, except as provided by SR 3.0.3. When an LCO is not met due to Surveillances not having been met, entry into a MODE or other specified condition in the Applicability shall only be made in accordance with LCO 3.0.4.
This provision shall not prevent entry into MODES or other specified conditions in the Applicability that are required to comply with ACTIONS or that are part of the shutdown of the unit.
CALVERT CLIFFS - UNIT I             3.0-6                   Amendment No. 282 CALVERT CLIFFS - UNIT 2                                      Amendment No. 259}}

Latest revision as of 02:18, 23 November 2019

Technical Specification Pages Re Unavailability of Barriers Using Consolidated Line Item Improvement Process
ML072700716
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 09/27/2007
From: Pickett D
NRC/NRR/ADRO/DORL/LPLI-1
To: Spina J
Calvert Cliffs
Pickett D, NRR/DORL, 415-1364
References
TAC MD5437, TAC MD5438
Download: ML072700716 (6)


Text

rules, regulations, and orders of the Commission, now or hereafter applicable; and is subject to the additional conditions specified and incorporated below:

(1) Maximum Power Level The licensee is authorized to operate the facility at steady-state reactor core power levels not in excess of 2700 megawatts-thermal in accordance with the conditions specified herein.

(2) Technical Specifications The Technical Specifications contained in Appendices A and B, as revised through Amendment No. 282, are hereby incorporated into this license. The licensee shall operate the facility in accordance with the Technical Specifications.

(a) For Surveillance Requirements (SRs) that are new, in Amendment 227 to Facility Operating License No. DPR-53, the first performance is due at the end of the first surveillance interval that begins at implementation of Amendment 227. For SRs that existed prior to Amendment 227, including SRs with modified acceptance criteria and SRs whose frequency of performance is being extended, the first performance is due at the end of the first surveillance interval that begins on the date the Surveillance was last performed prior to implementation of Amendment 227.

(3) Additional Conditions The Additional Conditions contained in Appendix C as revised through Amendment No. 267 are hereby incorporated into this license. Calvert Cliffs Nuclear Power Plant, Inc. shall operate the facility in accordance with the Additional Conditions.

(4) Secondary Water Chemistry Monitoring Program The Calvert .Cliffs Nuclear Power Plant, Inc., shall implement a secondary water chemistry monitoring program to inhibit steam generator tube degradation. This program shall include:

a. Identification of a sampling schedule for the critical parameters and control points for these parameters;
b. Identification of the procedures used to quantify parameters that are critical to control points; Amendment No. 282

C. This license is deemed to contain and is subject to the conditions set forth in 10 CFR ChapterI .andis subject to all applicable provisions of the Act, ,andthe rules, regulations, and orders of the Commission, now and hereafter applicable; and is subject to the additional conditions specified and incorporated below:

(1) Maximum Power Level The licensee is authorized to operate the facility at reactor steady-state core power levels not in excess of 2700 megawatts-thermal in accordance with the conditions specified herein.

(2) Technical Specifications The Technical Specifications contained in Appendices A and B, as revised through Amendment No. 259, are hereby incorporated into this license.

The licensee shall operate the facility in accordnace with the Technical Specifications.

(a) For Surveillance Requirements (SRs) that are new, in Amendment 201 to Facility Operating License No. DPR-69, the first performance is due at the end of the first surveillance interval that begins at implementation of Amendment 201. For SRs that existed prior to Amendment 201, including SRs with modified acceptance criteria and SRs whose frequency of performance is being extended, the first performance is due at the end of the first surveillance interval that begins on the date the Surveillance was last performed prior to implementation of Amendment 201.

(3) Less Than Four Pump Operation The licensee shall not operate the reactor at power levels in excess of five (5) percent of rated thermal power with less than four (4) reactor coolant pumps in operation. This condition shall remain in effect until the licensee has submitted safety analyses for less than four pump operation, and approval for such operation has been granted by the Commission by amendment of this license.

(4) Environmental Monitoring Program If harmful effects or evidence of irreversible damage are detected by the biological monitoring program, hydrological monitoring program, and the radiological monitoring program specified in the Appendix B Technical Specifications, the licensee will provide to the staff a detailed analysis of the problem and a program of remedial action to be taken to eliminate or significantly reduce the detrimental effects or damage.

Amendment No. 259

LCO Applicability 3.0 3.0 LIMITING CONDITION FOR OPERATION (LCO) APPLICABILITY not required to be entered. Only the support system LCO ACTIONS are required to be entered. This is an exception to LCO 3.0.2 for the supported system. In this event, additional evaluations and limitations may be required in accordance with Specification 5.5.15, "Safety Function Determination Program (SFDP)." If a loss of safety function is determined to exist by this program, the appropriate Conditions and Required Actions of the LCO in which the loss of safety function exists are required to be entered.

When a support system's Required Action directs a supported system to be declared inoperable or directs entry into Conditions and Required Actions for a supported system, the applicable Conditions and Required Actions shall be entered in accordance with LCO 3.0.2.

LCO 3.0.7 Special test exception (STE) LCOs in each applicable LCO section allow specified Technical Specification (TS) requirements to be changed to permit performance of special tests and operations. Unless otherwise specified, all other TS requirements remain unchanged. Compliance with STE LCOs is optional. When an STE LCO is desired to be met but is not met, the ACTIONS of the STE LCO shall be met. When an STE LCO is not desired to be met, entry into a MODE or other specified condition in the Applicability shall only be made in accordance with the other applicable Specifications.

LCO 3.0.8 [Reserved]

LCO 3.0.9 When one or more required barriers are unable to perform their related support function(s), any supported system LCO(s) are not required to be declared not met solely for this reason for up to 30 days provided that at least one train or subsystem of the supported system is OPERABLE and supported by barriers capable of providing their related support function(s), and risk is assessed and managed. This specification may be concurrently applied to more than one CALVERT CLIFFS - UNIT 1 3.0-3 Amendment No. 282 CALVERT CLIFFS - UNIT 2 Amendment No. 259

LCO Applicability 3.0 3.0 LIMITING CONDITION FOR OPERATION (LCO) APPLICABILITY train or subsystem of a multiple train or subsystem supported system provided at least one train or subsystem of the supported system is OPERABLE and the barriers supporting each of these trains or subsystems provide their related support function(s) for different categories of initiating events.

If the required OPERABLE train or subsystem becomes inoperable while.this specification is in use, it must be restored to OPERABLE status within 24 hours1 days <br />0.143 weeks <br />0.0329 months <br /> or the provisions of this specification cannot be applied to the trains or subsystems supported by the barriers that cannot perform their related support function(s).

At the end of the specified period, the required barriers must be able to perform their related support function(s) or the supported system LCO(s) shall be declared not met.

CALVERT CLIFFS - UNIT 1 3.0-4 Amendment No. 282 CALVERT CLIFFS - UNIT 2 Amendment No. 259

SR Applicability 3.0 3.0 SURVEILLANCE REQUIREMENT (SR) APPLICABILITY SR 3.0.1 SRs shall be met during the MODES or other specified conditions in the Applicability for individual LCOs, unless otherwise stated in the SR. Failure to meet a Surveillance, whether such failure is experienced during the performance of the Surveillance or between performances of the Surveillance, shall be failure to meet the LCO. Failure to perform a Surveillance within the specified Frequency shall be failure to meet the LCO, except as provided in SR 3.0.3.

Surveillances do not have to be performed on inoperable equipment or variables outside specified limits.

SR 3.0.2 The specified Frequency for each SR is met if the Surveillance is performed within 1.25 times the interval specified in the Frequency, as measured from the previous performance, or as measured from the time a specified condition of the Frequency is met.

For Frequencies specified as "once," the above interval extension does not apply.

If a Completion Time requires periodic performance on a "once per . ." basis, the above Frequency extension applies to each performance after the initial performance.

Exceptions to this Specification are stated in the individual Specifications.

SR 3.0.3 If it is discovered that a Surveillance was not performed within its specified Frequency, then compliance with the requirement to declare the LCO not met may be delayed, from the time of discovery up to 24 hours1 days <br />0.143 weeks <br />0.0329 months <br />, or up to the limit of the specified Frequency, whichever is greater. This delay period is permitted to allow performance of the Surveillance. A risk evaluation shall be performed for any Surveillance delayed greater than 24 hours1 days <br />0.143 weeks <br />0.0329 months <br /> and the risk impact shall be managed.

CALVERT CLIFFS - UNIT 1 3.0-5 Amendment No. 282 CALVERT CLIFFS - UNIT 2 Amendment No. 259

SR Applicability 3.0 3.0 SURVEILLANCE REQUIREMENT (SR) APPLICABILITY If the Surveillance is not performed within the delay period, the LCO must immediately be declared not met, and the applicable Condition(s) must be entered.

When the Surveillance is performed within the delay period and the Surveillance is not met, the LCO must immediately be declared not met, and the applicable Condition(s) must be entered.

SR 3.0.4 Entry into a MODE or other specified condition in the Applicability of an LCO shall only be made when the LCO's Surveillances have been met within their specified Frequency, except as provided by SR 3.0.3. When an LCO is not met due to Surveillances not having been met, entry into a MODE or other specified condition in the Applicability shall only be made in accordance with LCO 3.0.4.

This provision shall not prevent entry into MODES or other specified conditions in the Applicability that are required to comply with ACTIONS or that are part of the shutdown of the unit.

CALVERT CLIFFS - UNIT I 3.0-6 Amendment No. 282 CALVERT CLIFFS - UNIT 2 Amendment No. 259