| {{#Wiki_filter:From: Eric Frank <eric.frank@dteenergy.com> | | {{#Wiki_filter:From: Eric Frank <eric.frank@dteenergy.com> |
| Sent: Thursday, May 11, 2023 9:22 AM To: Surinder Arora | | Sent: Thursday, May 11, 2023 9:22 AM To: Surinder Arora |
|
| |
|
| ==Subject:== | | ==Subject:== |
| [External_Sender] Fermi 2 LAR (EDG Crankcase Trip) Month Review | | [External_Sender] Fermi 2 LAR (EDG Crankcase Trip) Month Review |
| : Surinder, As discussed on the phone, this email is to document acknowledgment of your proposal to perform an expedited review in 6-months for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 (ML23128A017) submitted to you on 5/8/23. We accept that this is beyond the original LAR-submitted request to perform the review in 90 days. | | : Surinder, |
| | |
| | As discussed on the phone, this email is to document acknowledgment of your proposal to perform an expedited review in 6-months for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 (ML23128A017) submitted to you on 5/8/23. We accept that this is beyond the original LAR-submitted request to perform the review in 90 days. |
| | |
| We understand that this expedited schedule is dependent on Fermi 2s ability to promptly respond to any Requests for Additional Information (RAI) and that significant delays in RAI response could impact the 6-month review target. | | We understand that this expedited schedule is dependent on Fermi 2s ability to promptly respond to any Requests for Additional Information (RAI) and that significant delays in RAI response could impact the 6-month review target. |
| : Regards, Eric W. Frank DTE Fermi 2 Power Plant l Manager - Licensing | | : Regards, |
| | |
| | Eric W. Frank DTE Fermi 2 Power Plant l Manager - Licensing |
| [o] 734.586.4772 | | [o] 734.586.4772 |
| [m] 419.340.1351 eric.frank@dteenergy.com My working day may not be your working day. Please do not feel obliged to reply to this email outside of your normal working hours. | | [m] 419.340.1351 eric.frank@dteenergy.com |
| | |
| | My working day may not be your working day. Please do not feel obliged to reply to this email outside of your normal working hours. |
| | |
| | Hearing Identifier: NRR_DRMA Email Number: 2093 |
|
| |
|
| Hearing Identifier: NRR_DRMA Email Number: 2093 Mail Envelope Properties (CH3PR15MB5772A586CCE8C2522E29B31681749)
| | Mail Envelope Properties (CH3PR15MB5772A586CCE8C2522E29B31681749) |
|
| |
|
| ==Subject:== | | ==Subject:== |
| [External_Sender] Fermi 2 LAR (EDG Crankcase Trip) Month Review Sent Date: 5/11/2023 9:21:37 AM Received Date: 5/11/2023 9:22:12 AM From: Eric Frank Created By: eric.frank@dteenergy.com Recipients: | | [External_Sender] Fermi 2 LAR (EDG Crankcase Trip) Month Review Sent Date: 5/11/2023 9:21:37 AM Received Date: 5/11/2023 9:22:12 AM From: Eric Frank |
| | |
| | Created By: eric.frank@dteenergy.com |
| | |
| | Recipients: |
| "Surinder Arora" <Surinder.Arora@nrc.gov> | | "Surinder Arora" <Surinder.Arora@nrc.gov> |
| Tracking Status: None Post Office: CH3PR15MB5772.namprd15.prod.outlook.com Files Size Date & Time MESSAGE 997 5/11/2023 9:22:12 AM Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:}} | | Tracking Status: None |
| | |
| | Post Office: CH3PR15MB5772.namprd15.prod.outlook.com |
| | |
| | Files Size Date & Time MESSAGE 997 5/11/2023 9:22:12 AM |
| | |
| | Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:}} |
Letter Sequence Other |
---|
EPID:L-2023-LLA-0069, License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 (Approved, Closed) |
|
MONTHYEARNRC-23-0002, License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122023-05-0505 May 2023 License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 Project stage: Request ML23131A1912023-05-11011 May 2023 NRR E-mail Capture - (External_Sender) Fermi 2 LAR (EDG Crankcase Trip) - 6-Month Review Project stage: Other ML23163A1742023-06-12012 June 2023 NRR E-mail Capture - Fermi 2 - Acceptance of Requested Licensing Action Regarding Amendment to Revise SR 3.8.1.2 in TS 3.8.1, AC Sources - Operating Project stage: Acceptance Review ML23250A2732023-09-0707 September 2023 NRR E-mail Capture - Fermi 2 - Request for Additional Information for License Amendment Request to Revise TS 3.8.1, AC Sources - Operating, Surveillance Requirement 3.8.1.12 Project stage: RAI ML23276A0052023-10-0202 October 2023 NRR E-mail Capture - (External_Sender) Fermi EDG Crankcase Trip LAR RAI Response Project stage: Other NRC-23-0062, Response to Request for Additional Information for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122023-10-12012 October 2023 Response to Request for Additional Information for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 Project stage: Response to RAI NRC-24-0002, Clarification for Request for Additional Information Responses for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122024-01-12012 January 2024 Clarification for Request for Additional Information Responses for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 Project stage: Request ML24052A2772024-04-30030 April 2024 Issuance of Amendment No. 229 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 Project stage: Approval 2023-05-05
[Table View] |
Similar Documents at Fermi |
---|
Category:E-Mail
MONTHYEARML24213A3222024-07-30030 July 2024 NRR E-mail Capture - Fermi 2 Audit Questions from the Audit Team Supporting Review of the LAR to Adopt TSTF-505 ML24102A2462024-04-11011 April 2024 NRR E-mail Capture - Fermi 2 Acceptance of Requested Licensing Action Re Amendment to Adopt TSTF-505, TSTF-439, and TSTF-591 ML24080A3912024-03-20020 March 2024 NRR E-mail Capture - Fermi 2 - Request for Additional Information for License Amendment Request Regarding Risk-Informed ECCS Strainer Performance Evaluation (Final) (L-2023-LLA-0092) ML24080A3902024-03-19019 March 2024 NRR E-mail Capture - (External_Sender) Fermi 2 - Request for Additional Information for License Amendment Request Regarding Risk-Informed ECCS Strainer Performance Evaluation (DRAFT)(L-2023-LLA-0092) ML23340A1322023-12-0606 December 2023 NRR E-mail Capture - (External_Sender) Fermi 2 Audit Clarifications - EPID L-2023-LLA-0092 ML24044A1492023-12-0404 December 2023 NRR E-mail Capture - Follow Up of Our Phone Call - Fermi 2 Exemption Request ML24011A2072023-11-17017 November 2023 Approval to Conduct NRC Appendix C Inspection Procedure 93100 at Fermi-2 ML23277A1332023-10-0303 October 2023 NRR E-mail Capture - ECCS Strainer Risk Informed Licensing Amendment - Audit Questions ML23276A0052023-10-0202 October 2023 NRR E-mail Capture - (External_Sender) Fermi EDG Crankcase Trip LAR RAI Response ML23250A2732023-09-0707 September 2023 NRR E-mail Capture - Fermi 2 - Request for Additional Information for License Amendment Request to Revise TS 3.8.1, AC Sources - Operating, Surveillance Requirement 3.8.1.12 ML23244A0022023-08-30030 August 2023 NRR E-mail Capture - Fermi 2 - Acceptance of Relief Request RR-A25 for Extended License Period ML23241B0162023-08-24024 August 2023 Exigent License Amendment Request for Additional Information RAI-12 (EPID L-2023-LLA-0112) (Email) ML23235A1822023-08-23023 August 2023 Exigent LAR Request for Additional Information NRC-23-0055, NRR E-mail Capture - (External Sender) Fermi 2 Power Plant, Emergency Application to Revise Technical Specifications to Adopt TSTF 568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 - Updated Clean Sheet for NRC-23-00552023-08-16016 August 2023 NRR E-mail Capture - (External_Sender) Fermi 2 Power Plant, Emergency Application to Revise Technical Specifications to Adopt TSTF 568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 - Updated Clean Sheet for NRC-23-0055 NRC-23-0028, NRR E-mail Capture - (External Sender) Fermi Relief Request RR-A25 (NRC-23-0028)2023-08-0707 August 2023 NRR E-mail Capture - (External_Sender) Fermi Relief Request RR-A25 (NRC-23-0028) ML23199A2472023-07-14014 July 2023 – Acceptance Review License Amendment Pertaining to ECCS Strainer Performance Evaluation ML23163A1742023-06-12012 June 2023 NRR E-mail Capture - Fermi 2 - Acceptance of Requested Licensing Action Regarding Amendment to Revise SR 3.8.1.2 in TS 3.8.1, AC Sources - Operating NRC-23-0037, 56542-EN 56542 - Fermi2023-05-26026 May 2023 56542-EN 56542 - Fermi ML23146A0622023-05-25025 May 2023 Acceptance of Requested Licensing Action Regarding Amendment to Correct Non-Conservative TS 3.4.5, RCS Pressure Isolation Valve (PIV) Leakage ML23131A1912023-05-11011 May 2023 NRR E-mail Capture - (External_Sender) Fermi 2 LAR (EDG Crankcase Trip) - 6-Month Review ML23115A1452023-04-25025 April 2023 NRR E-mail Capture - Fermi 2 - Request for Additional Information for Changes to TS 3.8.1, AC Sources - Operating ML23076A0222023-03-14014 March 2023 Email SUNSI Action Related to Fermi Unit 1 Safety Hazards Summary Report (ML23066A135) ML23010A0962023-01-10010 January 2023 NRR E-mail Capture - Fermi 2 - Acceptance Review of the Requested Licensing Action Re License Amendment Request to Revise TS 3.8.1 ML22241A0622022-08-29029 August 2022 NRR E-mail Capture - Fermi 2: Acceptance Review of LAR Regarding Adoption of TSTF-582 ML22027A3612022-01-26026 January 2022 U1: CY2022 Inspection Plan, Docket No. 05000016, License No. DPR-9 ML21350A0482021-11-18018 November 2021 NRR E-mail Capture - (External_Sender) Request for Comments on the Proposed Issuance of Amendment to Technical Specifications for Fermi Nuclear Power Plant, Unit 2 ML21266A4342021-09-20020 September 2021 Acceptance of DTE Request for Exemption from 10 CFR 72.44(d)(3) for Fermi 2 ML21214A1492021-08-0202 August 2021 License Amendment Request: Request for Additional Information ML21209A0132021-07-27027 July 2021 NRR E-mail Capture - Petition Review Board Initial Assessment of 2.206 Petition Regarding Fermi Unit 2 - Follow-Up to July 12, 2021 Email ML21194A0282021-07-12012 July 2021 NRR E-mail Capture - Petition Review Board Initial Assessment of 2.206 Petition Regarding Fermi Unit 2 - Continuance on Fall 2020 Emails ML21126A0532021-05-0404 May 2021 NRR E-mail Capture - Fermi 2 - Request for Additional Information for Revised Relief Request RR A-39 ML21116A2572021-04-21021 April 2021 NRR E-mail Capture - Fermi 2 - Acceptance Review Licensing Amendment Request to Revise Technical Specifications ML21089A3962021-03-30030 March 2021 NRR E-mail Capture - (External_Sender) Request for Comments on the Proposed Issuance of Amendment to Technical Specifications for Fermi Nuclear Power Plant, Unit 2 ML21084A1322021-03-19019 March 2021 NRR E-mail Capture - (External_Sender) Request for Comments on the Proposed Issuance of Amendment to Technical Specifications for Fermi Nuclear Power Plant, Unit 2 ML21026A1372021-01-25025 January 2021 NRR E-mail Capture - Acceptance Review: Fermi 2 Revised Relief Request RR-A39 ML20329A3802020-11-23023 November 2020 NRR E-mail Capture - Fermi 2 (COVID-19) Part 73 Exemption Request ML20275A2962020-09-30030 September 2020 NRR E-mail Capture - (External_Sender) Action - Request for Comments on the Proposed Issuance of Amendment to Technical Specifications for Fermi 2 Nuclear Power Plant ML20289A1032020-09-29029 September 2020 NRR E-mail Capture - Petition Review Board Initial Assessment of 2.206 Petition Regarding Fermi Unit 2 ML20289A1052020-09-24024 September 2020 NRR E-mail Capture - Status Update on 2.206 Petition Regarding Fermi Unit 2 ML20261H9282020-08-14014 August 2020 NRR E-mail Capture - (External_Sender) Action - Request for Comments on the Proposed Issuance of Amendments to Technical Specifications for Fermi 2 Nuclear Power Plant ML20239A9682020-08-12012 August 2020 NRR E-mail Capture - Fermi 2 LAR: RAI for Revision to Technical Specifications to Change the Surveillance Intervals to Accommodate a 24-Month Fuel Cycle ML20195A2762020-07-0909 July 2020 NRR E-mail Capture - Your Request for Extension of Part 26 Exemption Date - Documentation of Our Discussion on July 8, 2020 ML20181A4102020-06-29029 June 2020 NRR E-mail Capture - Acceptance Review: Fermi 2 Licensing Amendment Request to Adopt TSTF-563 ML20239A7962020-06-26026 June 2020 NRR E-mail Capture - Screening Result of 2.206 Petition Regarding Fermi Unit 2 ML20149K4242020-05-19019 May 2020 NRR E-mail Capture - Acceptance Review: Fermi 2 Relief Request RR-A42 ML20073E4222020-03-12012 March 2020 NRR E-mail Capture - Fermi 2: Relief Request VRR-004, Minor Clarifications to Ensure Consistency with the Specific Language in the ASME Code ML20029F0232020-01-29029 January 2020 NRR E-mail Capture - Acceptance Review: Fermi 2 Relief Requests (Proposed Alternatives), VRR-010 and VRR-011 for the Fourth 10-year IST Program ML20017A1782020-01-17017 January 2020 Relief Request #1 for Four RHR Valves (E1150F006A/B/C/D) ML20015A3012020-01-14014 January 2020 E-mail Fermi 1: CY2020 Master Inspection Plan ML20008D5752020-01-0808 January 2020 NRR E-mail Capture - Acceptance Review: Fermi 2 - LAR to Revise Technical Specification for Secondary Containment Surveillance Requirements 2024-07-30
[Table view] |
Text
From: Eric Frank <eric.frank@dteenergy.com>
Sent: Thursday, May 11, 2023 9:22 AM To: Surinder Arora
Subject:
[External_Sender] Fermi 2 LAR (EDG Crankcase Trip) Month Review
- Surinder,
As discussed on the phone, this email is to document acknowledgment of your proposal to perform an expedited review in 6-months for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 (ML23128A017) submitted to you on 5/8/23. We accept that this is beyond the original LAR-submitted request to perform the review in 90 days.
We understand that this expedited schedule is dependent on Fermi 2s ability to promptly respond to any Requests for Additional Information (RAI) and that significant delays in RAI response could impact the 6-month review target.
- Regards,
Eric W. Frank DTE Fermi 2 Power Plant l Manager - Licensing
[o] 734.586.4772
[m] 419.340.1351 eric.frank@dteenergy.com
My working day may not be your working day. Please do not feel obliged to reply to this email outside of your normal working hours.
Hearing Identifier: NRR_DRMA Email Number: 2093
Mail Envelope Properties (CH3PR15MB5772A586CCE8C2522E29B31681749)
Subject:
[External_Sender] Fermi 2 LAR (EDG Crankcase Trip) Month Review Sent Date: 5/11/2023 9:21:37 AM Received Date: 5/11/2023 9:22:12 AM From: Eric Frank
Created By: eric.frank@dteenergy.com
Recipients:
"Surinder Arora" <Surinder.Arora@nrc.gov>
Tracking Status: None
Post Office: CH3PR15MB5772.namprd15.prod.outlook.com
Files Size Date & Time MESSAGE 997 5/11/2023 9:22:12 AM
Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: