ML20245A360: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot change)
(StriderTol Bot change)
 
Line 15: Line 15:
| page count = 2
| page count = 2
| project = TAC:52665
| project = TAC:52665
| stage = Other
| stage = Approval
}}
}}



Latest revision as of 23:56, 23 May 2023

Requests Clarification of Paragraph 7.6 of ANSI N45.4 as to Who Makes Determination of Acceptability of Shorter than 24 H Integrated Leak Rate Test.W/O Encl
ML20245A360
Person / Time
Site: Oconee Duke Energy icon.png
Issue date: 07/11/1986
From: Gibson A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Holahan G
Office of Nuclear Reactor Regulation
Shared Package
ML20244D710 List:
References
TAC-52665, NUDOCS 8703200193
Download: ML20245A360 (2)


Text

{{#Wiki_filter:. - _- - __ _ _ _ _

  ~
              '                                                                            4

{

  '                                                  am,119 86 Gary Holahan, Director, Operating Reactor Assessment Staff NRR MEM3RANDUM FOR:

Albert F. Gibson, Director, Division of Reactor Safety FROM:

SUBJECT:

REQUEST FOR CLARIFICATION OF PIRIOD OF TEST WHE AN INTEGRATED LEAK RATE TEST (ILRT) - OCONEE UNIT 1 An' inspection o'f an integrated leak rate test (1LRT) at Oconee Unit I was recent-(See ly conducted and an issue was identified regarding the period of test. Appen enclosed Inspection Report 50-269/86-13). ANSI N45.4-1972 as the acceptable test method. (10 CFR 50. Appendix J. III.A.3.(a)) During the ILRT at Oconee 1, problems were experienced such that the period of test was' approximately 9 hours. collected was in error or not a Region 11 determined that this resulted in a failed test since the period of tes was less than 24 hours and the data would not pass the calculation The method of BN-TOP-1, which is accepted by the NRC as a shorter than 24 hour test. licensee stated that paragraph 7.6 of ANSI N45.4 allows him to detemine if a shorter period of test is acceptable and, therefore, if the test is successful or not. Paragraph 7.6 of ANSI N45.4 states that the leakage rate test period for any method shall be at least 24 hours. It also states that... "If it can be demonstrated to the satisfaction of those responsible f shorter test period, the agreed upon shorter period may be used." Region 11 believes that a deviationin from this caseatheclearly st f

approval of the regulatory body that established the rule
While w NRC.

containment structure, he is responsible for assuring that the containment structure is acceptable relative to design specifications, standards and func-I tional performance testing which have been reviewed and fcend acceptable to NRC. Consequently, we believe that the reference to "... those responsible...* in paragraph 7.6 of ANSI N45.4 requires that the NRC must review This and accept alteration of the 24 hour test requirement before it is implemented. There are situation appears analogous to changing a Technical Specification. methods for altering a specification, but any change cust be reviewed and accepted by the NRC prior to implementation. The issue is identified as an unresolved item in the enclosed inspection re We request clarification of paragraph 7.6 of ANSI N45.4 as to who makes the ' determination of acceptability of a shorter.than 24 hour test period. 57012 cot 4 @ I gjj A . g

2 3 gg Gary Holahan If you require additional details or discussion on this matter please contact H. Whitener (FTS 242-5593) or F. Jape (FTS 242-4182). . h' ScA nh W . % $ (.%- Albertf.Gibson

Enclosure:

HRC Inspection Report No. 50-269/86-13 cc w/ enc 1: H. Pastis, NRR J. F. Stolz, NRR R. Weller, NRR G. Arndt, NRR

5. Ebneter, R1 J. Paperiello, RIII E. Johnson, RIV D. Kirsch, RV bcc w/ enc 1:

V. Brownlee F. Jape H. Whitener

                                                                          /

y' RII RII . RI] R11 Wy , w'n ww/,G- ARHerdt VBr lee ' Reyes FJape HWhitener:1s 07/f/86 07/%/86 07/\\ /86 7/f/86 _ 07/ 7 /86

s p JUN $0 W Docket No. 50-269 -., License No. OPR-38 Duke Power Company ATTN: Mr. N. B. Tucker, Vice President Nuclear Production Department -

          .-            422 South Church Street                            *
  • Charlotte, NC 28242 Gentlemen: ,

SUBJECT:

HRC INSPECTION REPORT NO. 50-265/86-13 This refers to the Nuclear Regulatory Commission (NRC) inspec H. L. Whitener en April 4-9, 1986. At the conclusion of the inspection, ties authorized for- your Oconee facility.the findings were discus enclosed inspection report. Within these Areas examined during the inspection are identified in the report. areas, the inspection consisted of selective ex in progress. Your attention is invited to unresolved items identified in the inspec This matter will be pursued during future inspections. In accordance with Section,2.790 of the NRC's " Rules of Practice

Title 10, Code of Federal Regulations,- a copy of this letter and its e will be placed in the NRC Public Document Room.

Should you have any questions concerning this letter, please contact us. Sincerely,

                                                                                                                               ' It M   -

Virgil L. Brow-lee, Chief beactor Projects Branch 3

  • Division of Rea: tor Projects

Enclosure:

(See page 2) l b (? % A d%$ /f- -- - _-_- ----"---"---___m,,__,

       .-                                                                                     JUN 3 0 966 q

I

                                       ..         2 Duke Power Company

Enclosure:

RRC Inspection Report , cc w/ enc 1: M. 5. Tuckr.an. Station Manager . bec w/ enc 1: WRC Resident inspector H. Micolaras, MRR State of South Caroline Document Control Desk i RII R}  !! R11 RI 4/ C ger V nice FJa AHe d 86 h tener:ble pf/86 85 6/ 6/u/86 6/A/86

r-

       ..                                                        efeeftto eT ATES muettan atGULATOnY CObeldl88tOh
                 /e48se%g.      -                                    .t o.. ..

I

                              >    S etitAAmitT1 A ef tt(1.082.

A1Lakt A.etono: A seus

                \.....

Repert No.: 50-269/86-23

  • Licensee: Duke Power Company 422 South Church Street Charlotte, NC 28242 License No.: DPR-38 Docket No.: 50-269 Facility Name: Oconee 1 Inspection Conducted: April 4-9, 1986

[ d b .e A d- 26- b Inspector: N , H: L. Whitener Date signed A s2 , YAb fh Date Signed Approved by: F. Jape, Section Chief g/ Engineering Branch Division of Reactor Safety StWARY Scope: This routine, announced inspection involved witnessing the containtnent integrated leak rate test and reviewing the test procedure. Results: No violations or deviations were identified. i Lh [

                                    --7
        @ v, 7 s^ 'I UUJ U s

REPORT DETAILS

1. Persons Contacted ,

Licensee Employees

                                  'M. 5. Tuckman, Station knager
                          -       *T. Barr, Superintendent Technical Services
                                   *R. Todd, Performance
                                   *K. Rohde, Performance W. Suslick, General Office R. Bond, Performance-
                                    *D. Compton, Compliance                                                                         .

NRC Resident Inspectors J. Bryant, Senior Resident Inspector

                                     *K. Sasser, Resident Inspector
  • Attended exit interview
2. Exit Interview The inspection scope and findings were summartred on hApril 9,19 those persons indicated in paragraph I above and in subseque calls on m y 27 and 29, 1986. The following new items and discussed in detat1'the inspection findings.

were identified: Review any developments which may alter Further, Unresolved item 269/86-13-01: the Region 11 position on paragraph 7.6 of ANSI N45.4-1972. review the results of the licensee's investigation as to the caus the problems which occurred during the test results based on less than 24 hours of data. Verify the licensee's validation of RTD Unresolved accuracyItem over 269/86-13-D2: the range of use and any data corrections, if re paragraph 5.d.(2)(b). The licensee did not identify as proprietary any of the sateri , to or reviewed by the inspector during this inspection.

3. Licensee Action on Previous Enforcement Matters This subject was not addressed in the inspection.

I

4 t J

4. Unresolved Itees Unresolved itees are matters aboutorwhich acceptable mere information may involve violations or is 1 require determine whether they ,areTwo new unresolved items identified during this . inspec deviations.

discussed in paragraphs 5.d.1, 5.d.(2)(a), and 5.d.(2)(b). 1 (70313) (70307)

5. Containment . integrated Leak Rate Test - Unit The inspector reviewed and witnessed test activities to determine tha primary containment Technical integrated teak rate Specification test Appendix 4.4.1 was performed J to in ac with the requirements of test procedure PT/1/A/0150/03A, " React or 10 CFR 50, ANSI-N45.4 and the Building Integrated Leak Rate Test."

licensee's activities which were inspected Selected sampling of the included: (1) review of the test procedure to verify that the procedure and' conformed with the regulatory requirements; w properly approved (2) observation of test performance to detemine that test prere li-were coepleted, special equipment was installed, instrumentation was brated, and appropriate data were recorded; and (3) preliminary of leakage rate test results to verify that leak rate limits were met. Pertinent aspects are discussed in the following paragraphs.

a. General Observations The inspector witnetsed and reviewed portionsand stabilization of the data test prepa containment pressurization, temperature The following areas processing during the period of April 4-g, 1956.

were inspected: The test was conducted in accordance with an approved proce (3) (2) Test prerequisites selected for review wre found to be com Selected plant systems required to maintain test control were (3) found to be operational. (4) Special test instrumentation was reviewed and found to stalled and calibrated. Data required for the performance of the containment leat. (5) calculations were recorded at five-sinute intervals. , Problems encountered during the test wre described in the ' (6) event log. ,

3 (7). Temperature, pressure, dew point, and flow data were recor five-minute intervals. evaluation and analysis by the licensee. A final ILRT report will be submitted to the NRC. h tion of j' . No problems were ide'ntified in the above areas with t e excepTh iters (4) and (5).

b. Procedure Review
                -     The inspector reviewed portions of PT/1/A/0150/03A to verify                                     that test specified.

controls, valve alignments and acceptance criteria were Some problems were identified relating to the duration of the Type A test and application of the limits for the imposed leal rate. Regarding the calculation In calev1 ofsting thetheimposed limits of the lest rate in convert - scfm to wt 5/ day. d l

                      , verification test per Enclosure.13.3 the licensee had inaThese                                vertent                   y minor 20.25(0.75La) rather than 20.25La.

used an error band ofdiscrepancies were resolved and htd no impa the . test results. , Regarding the test duration, the acceptance criteria in test procedure PT/1/A/0150/03A specified a short duration test, minimum length the of eight hours. Step 9.1 of this procedure further specified thatAppendix J into the mass plot method would be used to calculate th leak rate test regulations. < that, as'part of the regulations, ANSI-N45.4, parag l the NRC. At this time, the only test of less than 24-hour duration ) which is acceptable to the NRC is the method specified in BN-TOP-1, Revision 1. This test method requires total time a ANSI /ANS-56.8 which delineates the error analysis forI analysis method.

                                                                                                                                                      \
c. Integrated Leat Rate Test
  • After Containment pressurization was started at h15 psig was obtained and the compressors were isolated at 12:24 a.m. -

April 6. 1 on Containment temperature stabilization was achieved at 11:00 a.m. l April 6,1986. The Type A leakage rate test (data collection) was started at this time and continued untti 11:00 test method mass point analysis:

                                                                                                                             )
                                                                                                                            .j 4                                                       i 9.0965 wt. t/ day Calculated leakage rate                                0.1053 wt. $/ day   s Upper 95%confidencelevel(UCL)                          0.25 wt Eday Maximum allowable leakage rate                         0.1875 wt. Eday 75% of maximum allowable leakage rate                                                  >

The acceptance criteria for the CILRT requires that the'opper bound of the leakage rate calculated at the 95% UCL, plus any required leakage rateThe additions, shall be less than 75% of the maximum licensee did not find it necessary to make adjust-leakage rate. i.e., me isolation or repair of ments to account for local leakage, However, certain problems were leaks were made during the test. These problems are discussed identified with the above test results. further in paragraph 5.d.(3), " Test Results." A four hour supplemental test was performed Theinlicensee's accordance wi recommendations of Appendix C of ANSI-N45.4-1972. measured composite leak rate was within the upper and lower acce limit specified by the equation Lam + Lo - 0.25La '< Le < Lam + 0.25La for the Mass Point ar.alysis as indicated below: 0.187 wt. E < 0.2BB wt.% < 0.312 wt.% These values meet the requirements of Appendix J.

d. Identified Issues (1) Test Duration The issue of test duration was discussed with indicated in paragraph 5.b.that the Deputy a recent Director,NRCNRR staff to the review issued April 1, 1986, from Inspection Prograes, IE, confirms the Director, Division of This memorandum clearly states position stated in paragraph 5.b. l i that the NRC staff is in agreement that th for mass point analysis is at least that the test 24 hours.

the exit interview, the inspector stated that At duration extended over a 24-hour period, although the Type A test 11:00 a.m. , April 7, 1986, instrument 11:00 a.m. , April 6, tofailures and less a discontinuity than 24 hours (see in the m the effective test data span to The inspector stated that paragraphs 5.d.(2)(a) and 5.d.(3)).in violation of Technical this situation appears to be Spectitcation 4.4.1 and Appendix J to 10 CFR 50 whic AN57-N45.4-1972 into the regulations. as an unresolved item pending review by Region In subsequent telephone11 m further discussionsevaluation with of thethe test data.Region II identified the fai licensee, record a consistent mass trend of indep = = = = = = - __ - _ _ __ _ ___ - __-___ _ _ __ ___ -___

            .                         o I  '

l. c ., . e 5 ,

                                                                                 .                                                                     .                                l apparent violation.                                                             In these discussions, the' licensee stated that he. believes the requirements of AN51-ti45.4-1972, paragraph 7.6 gives authority to the leak rate test engineers to alter the 24-hour time requirement. The first sentence of paragraph 7.6 clearly states that, "The leakage rate test period, for any method, shall extend to 24 hours..." The second sentence of paragraph 7.6 states that, *1f it can be demonstrated to the satisfaction of those responsible for the acceptance of the                                                                          ,

J containment structure that the leakage rate can be accurately detemined during a shorter test period, the agreed-upon shorter period may be used." The licensee contends that this statement allows his engineers to agree upon a shorter time period and deviate from the time period of 24' hours specified in the first sentence of paragraph 7.6. Region 11 does not concur with the licensee's position on paragraph 7.6 of ANSI-N45.4-1972. The Region believes that the second sentence is simply a statement of the obvious; specifically, that with the review and approval of the regulatory body that initially approved the rule, in this case the NRC, an acceptable alternate to the requirements of that rule may be teplemented. The Region also believes that the NRC staff review discussed above supports this position. However, upon request from the licensee for time to pursue clarification of the meaning of paragraph 7.6, Region management has categorized this matter as unresolved as follows: Unresolv~ed Item 269/86-13-01: Review any developments which may alter the Region II position or paragraph 7.6 of ANSI N45.4-1972. Further, review the results of the licensee's investigation as to the cause of the problems which occurred during the test, the ef fect these problems may have on test results, and the justification for acceptance of test results based on less than 24 hours of data. (2) Instrumentation (a) Loss of Temperature Sensors At about 3:00 p.m., on April 6, the licensee realized that a process board had failed in a manner which caused RTDs 2 through 7 to read about 10 degrees high from the start of the Rather than test at 11:00 a.m.. The board was replaced. l restarting the test at 3:45 p.m. on April 6, when the RTDs were returned to service, the licensee ssed the difference between the repaired RTDs and RTDs in steilar locations, which had mot f ailed, to generate the temperatures for RTDs 2 through 7 for the time period 11:00 a.m. to 3:45 p.m. on April 6. The same board failed again and data for RTDs 2 through 7 was lost from 7:25 a.m. to 8:15 a.m. on April 7. In this case, the last functional reading for RTDs 2 through

I h %, - (, l: I 7 was used. The licensee concluded that the manipulation of these data did not affect test results because the containment air temperature was stable and only, very small-changes in temperature would occur ever the time period for which these data were artiff cially generated. , The inspector's position on this matter was that the basis of the mass point analysis is a statistical analysis to determine the best fit line to the data and to calculate confidence error. The statistical analysis assumes random scatter Forcing in the 25%data, (six determined from independent observations. RTDs) of the temperature sensors to track other sensors has . the potential to affect both the least If square these datafit and the from confidence interval calculations. 11:00 a.m. to 3:45 p.m. on April 6 are excluded, the Attest the time is reduced to less than the required 24-hours. exit interview, the inspector identified this matter as a potential violation for the -following reasons: Specification 4.4.1 and

                         -          The licensee's Technical Appendix J to 10 CFR 50, paragraph          III incorporate the into the regulations.

requirements of AN51-N45.4-1972 the test

                          -         Paragraph 7.6 of AN51-N45.4 requires that period shall extend to 24-hours.

leak Para' graph 7.9 of ANSI-N45.4 further state for 24 consecutive hours. pressure i

                            -         Paragraph 7.8 of ANSI-N45.4 requires .that temperature      and humidity independent observations shall be) observations made at hourly (analysis or more frequent intervals.

Contrary to the above, the licensee did not record

independent data observations on an hourly or more freque interval in the time period from 11:00 a.m. to 3:45 p.m. en April 6, 1986. Rejection of this Further, time period results in a a perturbation in l test duration of about 19-hours.

the mass trend at 10:00 p.m. (details in , I about 9-hours (10:05 p.m. April 6 to 7:20 a.m 1986). (seeparagraph5.d.(1)). a

7 l (b) Instrument Calibration In review of- instrument calibrations, the inspector

  • found that the RTDs had been calibrated at only one point, 32*F.  !

The licensee stated that any probles with the RTDs would be ) evident at the ice point. This matter was discussed with personnel of the temperature measurements department a true of the National Bureau of Standards who indicated that calibration would include comparison with a known standard at Further, paragraph 6.2 of , a minimum of three points. I AN51-N45.4 indicates that a comparison with a In known furtherstandard should be made over a range of temperatures.- discussions on this item, the licensee Hestated that believes a that l misunderstanding may have occurred. This

                                                          ~

documentation of a multipoint calibration exists. matter was identified as unresolved pending reviewReview of the documentation: Unresolved . Item 269/P6-13-02: an temperature calibration documentation to verify that l adequate calibration over the range of use was performed, (3) Test Results Examination of the mas's plots at the end of the test showed Thethat a discontinuity occurred in the data et 10:05 p.m. on April 6. mass plot showed a step increase of about 180 pounds. The only perturbation which could be identified at this time wasThis is c an increase of 0.02 psi in the pres'sure readings.The mass trend rem tent with the mass change. leak rate calculation of the earlier data which renders theBased on a preliminary evaluation of 0.096 wt. 5/ day inaccurate.a portion Althoughofthis theleak data, ratethe stillleak rat with a UCL of 0.145 wt. 5 per day. appears to be within the limit of 0.1875 wt. 5 perFurther, day the a margin I for error is reduced to about 0.04 wt. 5 per day. consistent mass trend for analysis is reduced to about 9-hours, 10:05 p.m. on April 6 to 7:20 a.m. on April 7,1986. Re-evaluation of the Type A test data at the Region II office - showed the following results: l 1. Due to instrument failures and an unexplained discontinuity in mass trend, 24 hours of independent data observations yielding a linear mass vs. time relationship (based on assumption of a constant leak rate) were not available for analysis by the approved 24-hour total time 24-hout mass point analysis by the methods specified in ANSI /ANS 56.8.

     . w
       .                                    ~

S ,

2. Analysis of data free 30:05 p.m. April 6 to 7:20 a.m. on April 7, in which there are no apparent 1mstement failures or discontinuity in the linear mass trend show that the test does not meet the criteria of the NRC accepted methodology of BH-TOP-1, Rev.1 for the temination of a Type A test in less than 24 hours. Specifically, the total time analysis per BN-TOP-1, REv. I shows ah upper confidence limit of about 0.42 wt% per day which is greater than the allowable-limit of 4 0.1875 wt% per day.

As indicated above, the 9k hour span of consistent data show a leat rate of 0.138 wt% per day and a UCL of 0.145 wt.% per day by

                 . sass point analysis. tfhile this leak rate may be a reasonable representation of the containment leakage, the inspector does not have specific NRC approved and issued criteria to judge the acceptability of a short duration, mass-point test.

Final acceptance of the Type A test result is deferred pending a review of the cause of the instrument f ailures and the perturbation in the mass trend and the possible effect of thes problems on the test results. stated that an evaluation and analysis of these events would be included in the containment leak rate test report to the NRC. Review of this comitment has been incorporated into unresolved item 269/86-13-01, paragraph 5.d.(1). (4) As-Found Leak Rate The The licensee bid not yet determined the as-found leak rate. inspector stated that his understanding is that determination the as-found leak rate is a requirement but the Resolution of this Type A test is appropriate corrective action. matter w rate. (5) Outstanding Item Review concerned improvement in Inspection followup item (287/84-12-01) - control of field activity relative to making repairs or The adjustments to boundary valves during a Type A test. inspector found that specific instructions have been includ the test procedure adjustment PT/3/A/0150/03B to prohibit any repair or to valves prior to review and approval by the tes director. This item is closed. l

I APPENDIX J CLARIFICATION REQUEST 6/12/86 Caller: Clifford Clark,414* (FTS) 463-3741 Question: A plant's "24-hour CILRT had the following results: Total Time (TT): L,, ( tech specs 95%UCL)techspecs Mass Point (MP): L,( tech specs 95% UCL ( tech specs Licensee claimed this CILRT was acceptable because TT 951 UCL is not applicable to a 24-hour test. Survey: Discussion with Y.S. Huang, NRR, confinned that this ILRT was technically acceptable, but that the licensee's reasoning was incorrect. The 95% UCL would continue to be applicable regardless of test duration. However, based on the 4/1/86 Eisenhut, NRR, memo to Partlow, IE, this test, having met its tech spec limits by use of the MP method, would be considered technically acceptable. Response: G. Arndt infonned C. Clark of the above clarification. He also advised C. Clark that this was a technical clarification, and recomended'that its acceptability be checked through this particular plant's nonnal NRC licensing chain. E.)3unter Arn t MJEB/DET/RES Subsequently, G. Arlotto, RES, sent a memo to W. Olmstead, ELD, on Note: l July 8,1986, requesting ELD clarification of the legal acceptability of I using the 4/1/86 memo as a basis for passing a CILRT. i i l l = _ _ _ _ - _ _ . _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ . _ . . _ _ _ _ ._}}