Letter Sequence Acceptance Review |
---|
EPID:L-2021-LLA-0118, Request to Amend License SNM-42, Chapter 5, Nuclear Criticality Safety (Approved, Closed) |
|
MONTHYEARML21175A1192021-06-11011 June 2021 Request to Amend License SNM-42, Chapter 5, Nuclear Criticality Safety Project stage: Request ML21190A1562021-07-26026 July 2021 Acceptance of Request to Amend License SNM-42, License Application Chapter 5, Nuclear Criticality Safety - Enterprise Project Identifier L-2021-LLA-0118 Project stage: Acceptance Review ML21250A3882021-09-10010 September 2021 Request for Additional Information Regarding Proposed Changes to License Application Chapter 5, Nuclear Criticality Safety- Enterprise Project Identifier L-2021-LLA-0118 Project stage: RAI ML21286A1522021-10-0808 October 2021 Bwx Technologies, Inc., Response to Request for Additional Information to Amend License SNM-42, Chapter 5, Nuclear Criticality Safety Project stage: Response to RAI ML21320A2392021-11-29029 November 2021 Enclosure 3 - Safety Evaluation Report Project stage: Approval ML21320A2352021-11-29029 November 2021 BWXT NOG-L License Amendment 42 Project stage: Request ML21320A2372021-11-29029 November 2021 Enclosure 1 - Amendment 42 to Materials License SNM-42 Project stage: Other ML21320A2362021-11-29029 November 2021 Cover Letter Project stage: Other 2021-06-11
[Table View] |
|
---|
Category:Letter
MONTHYEARML24297A5722024-11-13013 November 2024 BWXT Nuclear Operating Group, Inc.-Lynchburg - Notice of Violation; NRC Inspection Report 07000027/2024008 ML24289A1052024-10-31031 October 2024 Cover Letter - Request for Additional Information Regarding License Amendment Request for Proposed Changes to Fundamental Nuclear Material Control Plan - EPID L-2024-LLA-0094 ML24303A3692024-10-30030 October 2024 BWXT Nuclear Operations Group, Inc. - Integrated Inspection Report 07000027/2024003 ML24281A1382024-10-0707 October 2024 BWXT Mca IR 2024405 Public Cover Letter ML24233A2702024-09-10010 September 2024 Cover Letter: Return of Argonaut Insurance Company Surety Bond ML24236A7672024-08-26026 August 2024 BWXT Nuclear Operations Group - Lynchburg - Physical Security Core Inspection Report 07000027-2024403 ML24234A0592024-08-16016 August 2024 BWXT Nuclear Operations Group, Inc., Semi-Annual Effluent Monitoring Report ML24205A0802024-07-24024 July 2024 BWXT Nuclear Operations Group, Inc. – Integrated Inspection Report 07000027/2024002 ML24179A1982024-06-27027 June 2024 BWXT Nuclear Operations Group, Inc. - Lynchburg Inspection Schedule for Calendar Year 2025 ML24151A4602024-06-20020 June 2024 BWXT Nuclear Operations Group, Inc. – NRC Core Inspection Report 07000027/2024006 and Apparent Violation ML24135A0762024-05-0101 May 2024 BWXT Nuclear Operations Group, Inc. - Lynchburg - Decommissioning Surety Bond ML24116A2842024-04-26026 April 2024 BWXT Nuclear Operations Group, Inc. - Integrated Inspection Report 07000027-2024001 ML24060A2822024-04-18018 April 2024 Cover Letter BWXT Amendment 47 (Public) ML24089A1862024-03-29029 March 2024 BWXT Nuclear Generating Group, Inc. - Material Control and Accounting Program Inspection Report 07000027/2024404 - Public ML24064A2142024-03-0404 March 2024 BWXT Nuclear Operations Group- Lynchburg - Physical Security Core Inspection Report 07000027/2024402 - Public Cover Letter ML24065A0142024-02-29029 February 2024 Response to Request for Additional Information Regarding Submittal for Exemption from Implementation of Security Event Notification and Suspicious Activity Reporting ML24061A0222024-02-27027 February 2024 BWXT Nuclear Operations Group, Inc., Lynchburg - Semi-Annual Effluent Monitoring Report ML24064A0352024-02-27027 February 2024 BWXT Nuclear Operations Group- Lynchburg, Inc., Submittal of Fitness for Duty Program Annual Data Report for 2023 ML24036A2482024-02-0808 February 2024 Request for Additional Information from BWXT NOG-L Regarding Submittal for Security Exemption-Enterprise Project Identifier L-2023-SPR-0013 ML24024A1502024-01-25025 January 2024 BWXT Nuclear Operations Group, Inc. – Integrated Inspection Report 07000027/2023004 ML24019A1492024-01-24024 January 2024 BWXT Nuclear Operations Group, Inc. -Lynchburg, U.S. NRC Inspection Report 0700027/2022006 and Notice of Violation ML24016A1912024-01-17017 January 2024 TRISO-X - U.S. Nuclear Regulatory Commission Inspection Report 07007027/2023006 ML23325A0402023-11-16016 November 2023 BWXT Nuclear Operations Group, Inc - Lynchburgs (BWXT NOG-L) - 30 Day Written Report of Event Notification EN-56768 ML23325A0382023-11-16016 November 2023 BWXT Nuclear Operations Group, Inc. - Lynchburg, Request for Exemption from Security Event Notification and Suspicious Activity Reporting Implementation in Accordance with 10 CFR 73.5 ML23292A1252023-10-25025 October 2023 BWXT Nuclear Operations Group, Inc. - Integrated Inspection Report 07000027/2023003 ML23269A0242023-09-26026 September 2023 BWXT Nuclear Operations Group, Inc. - Material Control and Accounting Program Inspection Report 07000027/2023402 (Cover Letter) ML23253A0012023-09-15015 September 2023 BWXT NOG-L - Physical Security Core Inspection Report 07000027/2023405 - Cover ML23256A0092023-09-14014 September 2023 BWXT Nuclear Operations Group, Inc. – Lynchburg Inspection Schedule for Calendar Year 2024 ML23257A2052023-09-0606 September 2023 Bwx Technologies, Inc. Submittal of Revision 1 to Chapter 1, General Information and Chapter 2, Organization & Administration, of License SNM-42 License Application - Redacted Cover Letter ML23248A3072023-09-0505 September 2023 Lynchburg Technology Center - Physical Security Core Inspection Report 07000027/2023406 ML23243A8582023-09-0101 September 2023 License Amendment 46 – Approval of Physical Protection Plan, Revision 27 (Enterprise Project Identifier L-2023-SPR-0000) ML23209A8272023-08-24024 August 2023 BWXT Nuclear Operations Group, Inc. - Lynchburg - Notice of Violation and Proposed Imposition of Civil Penalty - $87,500; NRC Inspection Report No. 07000027/2023007 ML23241A0432023-08-24024 August 2023 Bwx Technologies, Inc., Semi-Annual Effluent Monitoring Report for First Half of 2023 ML23171A9302023-06-12012 June 2023 BWXT Nuclear Operations Group, Inc., Submittal of Mt. Athos Site Emergency Plan, Revision 36 ML23171A9282023-06-12012 June 2023 BWXT Nuclear Operations Group, Inc., Submittal of Emergency Plan, Revision 36 ML23115A0202023-05-0505 May 2023 BWXT Nuclear Operations Group, Inc., - Lynchburg - NRC Inspection Report 07000027/2023006 and Apparent Violations ML23116A0862023-04-27027 April 2023 BWXT Nuclear Operations Group, Inc. – Integrated Inspection Report 07000027/2023001 ML23108A3262023-04-25025 April 2023 Cover Letter - BWXT Amendment 45 ML23100A0532023-04-0606 April 2023 BWXT Nuclear Operations Group - Lynchburg - Physical Security Core Inspection Report 07000027 2023403 Cover Letter ML23096A2252023-04-0404 April 2023 BWXT Nuclear Operations Group, Inc., Submittal of 60-Day Written Report for Event Notification Number EN-56336 ML23212A9182023-04-0404 April 2023 BWXT EN 56336 60 Day Report_Redacted ML23089A3842023-03-31031 March 2023 BWXT Nuclear Operations Group, Inc - Material Control and Accounting Program Inspection Report 07000027/2023401 ML23060A1122023-03-0606 March 2023 BWXT Nuclear Operations Group, Inc. - Licensee Performance Review (Nuclear Regulatory Commission Inspection Report 07000027/2023005) ML23059A2802023-02-23023 February 2023 BWXT Nuclear Operations Group, Inc. Submittal of Lynchburg Facility Semi-Annual Effluent Report for 2022 ML23046A0872023-02-0909 February 2023 BWXT Nuclear Operations Group- Lynchburg, Inc., Fatigue Management Program Annual Data Report ML23025A0912023-01-30030 January 2023 BWXT Nuclear Operations Group, Inc. – Integrated Inspection Report 07000027/2022004 ML22341A2132022-12-15015 December 2022 Letter - BWXT Amendment 44 ML22340A5982022-11-30030 November 2022 11-30-2022 Letter from BWXT NOG-L: Request to Amend License SNM-42 in Accordance with the Revised Fundamental Nuclear Material Control Plan (FNMCP) ML22318A2632022-11-14014 November 2022 BWXT-NOG L – Physical Security Core Inspection Report 07000027/2022405 (Cover Letter) ML22297A1342022-10-27027 October 2022 BWXT Nuclear Operations Group, Inc. - Integrated Inspection Report 07000027/2022003 2024-09-10
[Table view] |
Text
er UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 26, 2021 Mr. Chris Terry, Manager Licensing and Safety Analysis BWXT Nuclear Operations Group, Inc.
P.O. Box 785 Lynchburg, VA 24505-0785
SUBJECT:
ACCEPTANCE OF REQUEST TO AMEND LICENSE SNM-42, LICENSE APPLICATION CHAPTER 5, NUCLEAR CRITICALITY SAFETY -
ENTERPRISE PROJECT IDENTIFIER L-2021-LLA-0118
Dear Mr. Terry:
The U.S. Nuclear Regulatory Commission (NRC) staff has received your submittal dated June 11, 2021 (Agencywide Documents Access and Management System [ADAMS] Accession Number ML21175A119), transmitted by Letter 21-030. The incoming cover letter and its enclosures have been made publicly available.
We have completed our acceptance review of your submittal and have identified no administrative omissions or deficiencies that would prevent us from proceeding with a detailed review. Your submittal has been assigned Enterprise Project Identifier (EPID)
L-2021-LLA-0118. Please reference this EPID number and Docket Number 70-27 in any future correspondence associated with this request.
Please note that the NRC staffs technical review of your submittal may identify issues that require additional information. Based on our preliminary evaluation and projection of current review schedules, we anticipate completing our formal review by December 20, 2021. This date could change depending on the findings of our technical review, urgent assignments, or other factors. We will promptly communicate any significant changes to this schedule. In addition, the NRC staff estimates that completing the review of your submittal will require up to 140 staff hours, which corresponds to about $39,060.00 ($279.00/hour).
In accordance with Title 10 of the Code of Federal Regulations, Section 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room, or from the Publicly Available Records component of the NRCs ADAMS. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
C. Terry 2 If you have any questions regarding this communication, please contact me at 301-415-7744 or by email at James.Downs@nrc.gov.
Sincerely, James R. Digitally signed by James R. Downs Downs Date: 2021.07.26 09:56:10 -04'00' James R. Downs, P.E.
Senior Project Manager Fuel Facility Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 70-27 License No. SNM-42 cc: bwxt@listmgr.nrc.gov
C. Terry 3
SUBJECT:
ACCEPTANCE OF REQUEST TO AMEND LICENSE SNM-42, LICENSE APPLICATION CHAPTER 5, NUCLEAR CRITICALITY SAFETY -
ENTERPRISE PROJECT IDENTIFIER L-2021-LLA-0118 DATED: July 26, 2021 DISTRIBUTION: DFM r/f KRamsey,DFM/FFLB JMunson, DFM/NARAB TSippel, RII/DFFI NPitoniak, RII/DFFI PGlenn, RII/DFFI AAlen, RII/DFFI ADAMS Accession Number: ML21190A156 *via email NMSS/DFM/ NMSS/DFM/ NMSS/DFM/ NMSS/DFM/
OFFICE FFLB/PM* FFLB/LA* FFLB/BC* FFLB/PM*
NAME JDowns ELee JZimmerman JDowns DATE 07/09/2021 07/22/2021 07/26/2021 07/26/2021 OFFICIAL RECORD COPY