Line 2: |
Line 2: |
| | number = ML092020349 | | | number = ML092020349 |
| | issue date = 08/13/2009 | | | issue date = 08/13/2009 |
| | title = Request for Additional Information Regarding the Upgrade of Emergency Core Cooling System Requirements Per NUREG-1431 (TAC No. ME1115 and ME1116) | | | title = Request for Additional Information Regarding the Upgrade of Emergency Core Cooling System Requirements Per NUREG-1431 |
| | author name = Lingam S | | | author name = Lingam S |
| | author affiliation = NRC/NRR/DORL/LPLII-2 | | | author affiliation = NRC/NRR/DORL/LPLII-2 |
Letter Sequence RAI |
---|
|
|
MONTHYEARML0911201932009-04-21021 April 2009 Technical Specification Change No. 07-05, Emergency Core Cooling System (Eccs). Project stage: Other ML0920203492009-08-13013 August 2009 Request for Additional Information Regarding the Upgrade of Emergency Core Cooling System Requirements Per NUREG-1431 Project stage: RAI ML0927207722009-10-0202 October 2009 Request for Additional Information Regarding the Upgrade of Emergency Core Cooling System Requirements Per NUREG-1431 Project stage: RAI ML0929602402009-10-0909 October 2009 Response to Request for Additional Information Concerning Technical Specifications Change 07-05 - Upgrade of Emergency Core Cooling System Requirements Project stage: Response to RAI ML1002900232010-01-26026 January 2010 Correction of Errata for Technical Specifications Change 07-05 - Upgrade of Emergency Core Cooling System Requirements Project stage: Other ML0933104032010-01-28028 January 2010 Issuance of Amendments Regarding Upgrade of Emergency Core Cooling System Requirements Per NUREG-1431 (TS 07-05) Project stage: Approval ML1003607402010-02-16016 February 2010 Corrections for Amendment Nos. 326 and 319 Project stage: Other 2009-08-13
[Table View] |
|
---|
Category:Letter
MONTHYEARML24298A1172024-10-24024 October 2024 Cycle 26, 180-Day Steam Generator Tube Inspection Report CNL-24-074, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-10-23023 October 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 05000327/LER-2024-001, Reactor Trip Due to a Turbine Trip2024-10-17017 October 2024 Reactor Trip Due to a Turbine Trip ML24282B0412024-10-15015 October 2024 Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2 and Watts Bar Nuclear Plant, Units 1 and 2 ML24260A1682024-10-0404 October 2024 Regulatory Audit Summary Related to Request to Add and Revise Notes Related to Technical Specification Table 3.3.2-1, Function 5 ML24284A1072024-09-26026 September 2024 Affidavit for Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2 05000328/LER-2024-001, Reactor Trip Due to an Electrical Trouble Turbine Trip2024-09-25025 September 2024 Reactor Trip Due to an Electrical Trouble Turbine Trip CNL-24-060, Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description2024-09-24024 September 2024 Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description CNL-24-047, Decommitment of Flood Mode Mitigation Improvement Systems2024-09-24024 September 2024 Decommitment of Flood Mode Mitigation Improvement Systems ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24267A0402024-09-19019 September 2024 Cycle 27 Core Operating Limits Report Revision 0 ML24185A1742024-09-18018 September 2024 Cover Letter - Issuance of Exemption Related to Non-Destructive Examination Compliance Regarding Sequoyah Nuclear Plant Independent Spent Fuel Storage Installation CNL-24-065, Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-09-18018 September 2024 Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24253A0152024-09-0808 September 2024 Emergency Plan Implementing Procedure Revisions ML24247A2212024-08-29029 August 2024 Notification of Deviation from Pressurized Water Reactor Owners Group (PWROG) Letter OG-21-160, NEI 03-08 Needed Guidance: PWR Lower Radial Support Clevis Insert X-750 Bolt Inspection Requirements, September 1, 2021 ML24247A1802024-08-28028 August 2024 Application to Revise the Fuel Handling Accident Analysis, to Delete Technical Specification 3.9.4, Containment Penetrations, and to Modify Technical Specification 3.3.6, Containment Ventilation Isolation Instrumentation for Sequoyah Nuclea IR 05000327/20240052024-08-26026 August 2024 Updated Inspection Plan for Sequoyah Nuclear Plant, Units 1 and 2 - Report 05000327/2024005 and 05000328/2024005 ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 CNL-24-061, Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08),2024-08-19019 August 2024 Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08), IR 05000327/20240022024-07-31031 July 2024 Integrated Inspection Report 05000327/2024002 and 05000328/2024002 ML24211A0572024-07-29029 July 2024 Submittal of Emergency Plan Implementing Procedure Revision ML24211A0542024-07-29029 July 2024 Operator License Examination Report ML24211A0412024-07-26026 July 2024 Unit 1 Cycle 26 Refueling Outage - 90-Day Inservice Inspection Summary Report ML24199A0012024-07-22022 July 2024 Clarification and Correction to Exemption from Requirement of 10 CFR 37.11(c)(2) ML24172A1342024-07-15015 July 2024 Exemptions from 10 CFR 37.11(C)(2) (EPID L-2023-LLE-0024) - Letter ML24191A4652024-07-0909 July 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24177A0282024-06-25025 June 2024 Emergency Plan Implementing Procedure Revisions ML24176A0222024-06-24024 June 2024 Retraction of Interim Report of a Deviation or Failure to Comply – Transducer Model 8005N ML24089A1152024-06-21021 June 2024 Transmittal Letter, Environmental Assessments and Findings of No Significant Impact Related to Exemption Requests from 10 CFR 37.11(c)(2) ML24145A0852024-05-30030 May 2024 1B-B Diesel Generator Failure - Final Significance Determination Letter ML24145A1052024-05-29029 May 2024 301 Exam Approval Letter ML24134A1762024-05-13013 May 2024 Submittal of 2023 Annual Radiological Environmental Operating Report CNL-24-040, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-05-0808 May 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24128A0352024-05-0707 May 2024 Providing Supplemental Information to Apparent Violation ML24120A0582024-04-26026 April 2024 10 CFR 50.46 Annual Report for Sequoyah Nuclear Plant Units 1 and 2 ML24116A2612024-04-25025 April 2024 Interim Report of a Deviation or Failure to Comply - Transducer Model 8005N ML24114A0482024-04-23023 April 2024 Annual Radioactive Effluent Release Report for 2023 Monitoring Period CNL-24-037, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 422024-04-22022 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 42 ML24144A2322024-04-20020 April 2024 Tennessee Multi-Sector Permit (Tmsp), 2024 Annual Discharge Monitoring Report for Outfalls SW-3, SW-3, and SW-9 ML24144A2362024-04-20020 April 2024 Discharge Monitoring Report (Dmr), March 2024 ML24089A0882024-04-18018 April 2024 – Exemption from Select Requirements of 10 CFR Part 73; Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24102A1212024-04-18018 April 2024 Summary of Conference Call with Tennessee Valley Authority Regarding Sequoyah Nuclear Plant, Unit 1 Spring 2024 Steam Generator Tube Inspections CNL-24-024, Hydrologic Engineering Center River Analysis System Project Milestone Status Update2024-04-17017 April 2024 Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-24-033, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-04-17017 April 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000327/20240012024-04-17017 April 2024 Integrated Inspection Report 05000327/2024001 and 05000328/2024001 ML24109A0272024-04-16016 April 2024 Cycle 27 Core Operating Limits Report Revision 0 CNL-23-006, Application to Modify Technical Specifications 3.8.1, AC Sources – Operating, and 3.8.2, AC Sources – Shutdown, for Sequoyah Nuclear Plant (SQN-TSC-22-03)2024-04-15015 April 2024 Application to Modify Technical Specifications 3.8.1, AC Sources – Operating, and 3.8.2, AC Sources – Shutdown, for Sequoyah Nuclear Plant (SQN-TSC-22-03) ML24106A0502024-04-12012 April 2024 Discharge Monitoring Report (Dmr), February 2024 ML24100A0162024-04-11011 April 2024 Request for Regulatory Conference (Tennessee Valley Authority - Sequoyah Nuclear Plant) CNL-24-020, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Units 1 and 2, Request for Approval of Quality Assurance Program Description and Application to Revise the Technical Specifications Associated with QAPD Requirements2024-04-0101 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Units 1 and 2, Request for Approval of Quality Assurance Program Description and Application to Revise the Technical Specifications Associated with QAPD Requirements 2024-09-08
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24152A1542024-05-31031 May 2024 Document Request for Sequoyah Nuclear Plant - Radiation Protection Inspection - Inspection Report 2024-03 ML24116A2012024-04-17017 April 2024 Nrctva ISFSI CBS (RFI) ML24045A1002024-02-13013 February 2024 NRR E-mail Capture - Request for Additional Information Related to the Sequoyah Exemption Request for the 10 CFR Part 73 Enhanced Weapons Rule ML23307A0822023-11-0808 November 2023 Request for Additional Information August 4, 2022, Exemption Request for Deviating from the Conditions of Certificate of Compliance No. 1032, Amendment No. 3, Related to Sequoyah Nuclear Plant Independent Spent Fuel Storage Installation ML23307A0832023-11-0808 November 2023 Enclosure - Request for Additional Information HDI-Sequoyah NDE Exemption Request 10-30-2023 ML23062A5942023-02-27027 February 2023 Enclosure - NRC SQN Exemption Rsi Response Staff Follow Up Questions ML23062A5952023-02-27027 February 2023 Staff follow-up Questions to Tva'S 12/19/2022 Response of the Staff'S Rsi Regarding 08/04/2022 SQN Exemption Request ML22343A0692022-12-0808 December 2022 NRR E-mail Capture - Request for Additional Information - Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.4.12 (L-2022-LLA-0103) ML22257A0622022-09-14014 September 2022 Requalification Program Inspection - Sequoyah Nuclear Plant ML22255A0842022-09-0909 September 2022 Document Request for Sequoyah Nuclear Plant - Radiation Protection Inspection - Inspection Report 2022-04 ML22227A0272022-08-11011 August 2022 NRR E-mail Capture - Request for Additional Information Related to Alternative Requests RP-11 for Sequoyah Nuclear Plant, Units 1 and 2, and IST-RR-9 for Watts Bar Nuclear Plant, Units 1 and 2 ML22214A1582022-08-0202 August 2022 NRR E-mail Capture - Request for Additional Information for Sequoyah Units 1 and 2 License Amendment Request for Fire and Seismic PRA Modification to 10 CFR 50.69 (L-2022-LLA-0033) ML22151A0102022-05-27027 May 2022 NRR E-mail Capture - Revised Request for Additional Information Re Sequoyah Nuclear Plant Alternative Request RV-02 ML22146A3322022-05-26026 May 2022 NRR E-mail Capture - Request for Additional Information Related to Sequoyah Nuclear Plant'S LAR to Adopt TSTF-505 ML22151A0092022-05-26026 May 2022 NRR E-mail Capture - Request for Additional Information Re Sequoyah Nuclear Plant Alternative Request RV-02 ML22144A1002022-05-12012 May 2022 NRR E-mail Capture - Request for Additional Information Related to Tva'S Request to Revised the TVA Plants' Radiological Emergency Plans ML21237A4952021-08-25025 August 2021 Document Request for Sequoyah Nuclear Plant - Radiation Protection Inspection - Inspection Report 2021-04 ML21160A0352021-06-0303 June 2021 Document Request for Sequoyah Nuclear Plant - Radiation Protection Inspection - Inspection Report 2021-03 ML21095A0482021-04-0505 April 2021 NRR E-mail Capture - Sequoyah Nuclear Plant, Units 1 and 2 - Request for Additional Information Regarding Request to Transition to Westinghouse Fuel ML21092A0972021-04-0202 April 2021 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML20259A4782020-09-15015 September 2020 Emergency Preparedness Program Inspection Request for Information ML20261H4172020-09-14014 September 2020 NRR E-mail Capture - Sequoyah Nuclear Plant, Units 1 and 2 - Request for Additional Information Regarding Hydrologic UFSAR Update ML20261H4162020-09-0202 September 2020 NRR E-mail Capture - Draft Request for Additional Information - Sequoyah Nuclear Plant, Units 1 and 2, Request to Revise UFSAR Hydrologic Analysis ML20189A2112020-07-0101 July 2020 Request for Additional Information Regarding Hydrologic UFSAR Update ML20106F1042020-04-14014 April 2020 Request for Additional Information Regarding the Hydrologic Analysis LAR ML20161A3902020-04-0909 April 2020 Request for Supporting Information for the Sequoyah SPRA Audit Review - Follow-up to Plant Response Question 5 ML20098D8612020-04-0707 April 2020 Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000327/2020012 and 05000328/2020012) and Request for Information) ML20036E2842020-02-0505 February 2020 20200123 - Sequoyah Radiation Safety Inspection Document Request Letter ML19323D7562019-11-18018 November 2019 Nrc'S Request for Additional Information - Exigent Amendment ML19235A0992019-08-22022 August 2019 Emergency Preparedness Program Inspection Request for Information ML19162A2462019-06-11011 June 2019 RP Inspection Document Request 2019-03 ML19149A6222019-05-29029 May 2019 NRR E-mail Capture - Request for Additional Information - Sequoyah Nuclear Plant, Units 1 and 2, Request for Alternative to 18-ISI-1 EPID: L-2019-LLR-0006 ML19148A7912019-05-28028 May 2019 NRR E-mail Capture - Sequoyah Nuclear Plant and Watts Bar Nuclear Plant - Final Request for Additional Information Related to Request for Alternative to OM Code Requirements ML19015A4192019-01-15015 January 2019 NRR E-mail Capture - RAI - Sequoyah Nuclear Plant, Units 1 and 2, LAR to Adopt 10 CFR50.69 Risk-informed SSC ML18344A0752018-12-10010 December 2018 NRR E-mail Capture - Request for Additional Information - Sequoyah 1 and 2, Request to Modify Essential Raw Cooling Water Motor Control Center Breakers and to Revise Updated Final Analysis Report (SQN-TS-17-04) ML18296A0022018-10-22022 October 2018 NRR E-mail Capture - Additional Information Needs - Sequoyah Units 1 and 2, Request to Modify Essential Raw Cooling Water Motor Control Center Breakers Revise Updated Final Analysis Report (SQN-TS-17-04) ML18283B0592018-10-10010 October 2018 NRR E-mail Capture - Additional Information Needs Identified During Audit - Sequoyah 1 and 2, Request to Modify Essential Raw Cooling Water Motor Control Center Breakers Revise Updated Final Analysis Report (SQN-TS-17-04) ML18283A6232018-09-25025 September 2018 04 RP Inspection Document Request ML18233A1942018-08-21021 August 2018 NRR E-mail Capture - Additional Information Needs Identified - Sequoyah 1 and 2, Request to Modify Essential Raw Cooling Water Motor Control Center Breakers and to Revise Updated Final Analysis Report (SQN-TS-17-04) ML18138A1102018-05-17017 May 2018 Enclosurequest for Additional Information (Letter to E. D. Schrull Request for Additional Information Regarding Tennessee Valley Authority'S Decommissioning Funding Plan Update for Browns Ferry and Sequoyah Isfsis) ML18057A6372018-02-23023 February 2018 NRR E-mail Capture - Request for Additional Information Related to TVA Fleet Topical Report TVA-NPG-AWA16 - EPIC: L-2016-TOP-0011) ML17191A2062017-07-0606 July 2017 NRR E-mail Capture - Sequoyah Nuclear Station, Unit 1 & 2 - Request for Additional Information Related to LAR for Technical Specification 3.8.1.17 Note Modification (CAC Nos. MF9398 and MF9399) ML17150A0792017-05-23023 May 2017 NRR E-mail Capture - Request for Additional Information Related to TVA Fleet LAR for EAL Change to Adopt NEI-99-01 Rev.6 (CAC Nos. MF9054 - MF9060) ML17112A0402017-04-20020 April 2017 NRR E-mail Capture - Sequoyah Nuclear Station, Unit 1 & 2 - Request for Additional Information Related to LAR for Technical Specification 3.8.1, AC SOURCES-OPERATING ML17004A0612017-01-0404 January 2017 Notification of NRC Triennial Fire Protection Inspection (Team)(Report 05000327/2017007 and 05000328/2017007) ML15194A3882015-07-13013 July 2015 Request for Additional Information Related to LAR to Revise Ice Condenser Ice Mas Tech Spec ML15175A2912015-06-24024 June 2015 E-mail Re. Request for Additional Information RR RP-07 ML15159B1642015-06-22022 June 2015 Requests for Additional Information for the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application-Set 25 (TAC Nos. MF0481 and MF0482) ML15050A0962015-02-19019 February 2015 E-mail Re. Request for Additional Information Related to LAR to Ice Condendser Inc Mass Tech Spec ML15042A4702015-02-11011 February 2015 E-mail Re. Request for Additional Information Related to License Amendment Request to Revise Technical Specification on Ultimate Heat Sink 2024-05-31
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 August 13, 2009 Mr. Preston D. Swafford Chief Nuclear Officer and Executive Vice President Tennessee Valley Authority 3R Lookout Place 1101 Market Street Chattanooga, TN 37402-2801
SUBJECT:
SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION REGARDING THE UPGRADE OF EMERGENCY CORE COOLING SYSTEM REQUIREMENTS PER NUREG-1431 (TAC NO. ME1115 AND ME1116)
Dear Mr. Swafford:
By letter dated April 21,2009, you submitted an application for license amendment to revise the Sequoyah Nuclear Plant, Units 1 and 2 (SQN) Technical Specifications (TSs), and upgrade the Emergency Core Cooling System (ECCS) requirements to be more consistent with NUREG-1431, Revision 3, "Standard Technical Specifications - Westinghouse Plants." The upgrade revises SQN TS Section 3/4.5.2, "ECCS Subsystems - T avg Greater Than or Equal to 350 of, TS Section 3/4.5.3, "ECCS Subsystems - Tavg Less Than 350 of, and the corresponding surveillance requirements (SRs) that will resolve a nonconforming condition associated with SR 4.5.2.f.
The Nuclear Regulatory Commission staff is reviewing the submittal and has determined that additional information is required to complete its evaluation. This request was discussed with Mr. Rusty Proffitt of your staff on August 13, 2009, and it was agreed that a response would be provided within 30 days from the date of this letter.
If you have any questions regarding this matter, I can be reached at 301-415-1564.
Sincerely,
~~~'~
Siva P. Lingam, Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-327 and 50-328
Enclosure:
Request for Additional Information cc w/encl: Distribution via Listserv
REQUEST FOR ADDITIONAL INFORMATION REGARDING TECHNICAL SPECIFICATION CHANGES AND UPGRADE OF EMERGENCY CORE COOLING SYSTEM REQUIREMENTS PER NUREG-1431. REVISION 3 SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2 DOCKET NOS. 50-327 AND 50-328 By letter dated April 21, 2009 (Agencywide Documents Access and Management System Accession No. ML091120193). the Tennessee Valley Authority (the licensee), submitted a license amendment request to revise the Sequoyah Nuclear Plant, Units 1 and 2 (SQN)
Technical Specifications (TSs) and upgrade the Emergency Core Cooling System (ECCS) requirements to be more consistent with NUREG-1431, Revision 3, "Standard Technical Specifications - Westinghouse Plants." The upgrade revises SQN TS Section 3/4.5.2, "ECCS Subsystems - Tavg Greater Than or Equal to 350 of, TS Section 3/4.5.3, "ECCS Subsystems Tavg Less Than 350 of, and the corresponding surveillance requirements (SRs) that will resolve a nonconforming condition associated with SR 4.5.2.f. In order to complete its review of the above document, the Nuclear Regulatory Commission (NRC) staff needs the following additional information:
- 1. Numerous statements in the submittal used phrases such as, "standard language,"
"standard action requirements," "standard surveillance," "standard title," etc. Please confirm whether the term "standard" used in such phrases implied Improved Standard Technical Specifications (ISTS). If any of those statements did not mean ISTS, then clarify.
- 2. In page E-4 of the submittal, the Iicensee's proposed change to SR 4.5.2.b states, "Verify ECCS piping is full of water by venting the ECCS pump casings and accessible piping high points ...." Please provide the following additional information:
a) Define the phrase "full of water." Does this mean zero voids? If not, what is the acceptance criterion for void dimension and what is the basis for that?
b) In light of the proposed TS Change No. 07-05 for SQN ECCS, discuss your plan to implement the NRC Generic Letter (GL) 2008-01, "Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems," for SQN, including modification of the TSs and the SRs, to make the plant consistent with the GL requirements related to ECCS voids.
- 3. In page E-1 of the submittal, it was stated, "SR 4.5.2.f contains specific pump discharge pressure requirements for emergency core cooling system (ECCS) quarterly minimum flow recirculation testing. The discharge pressure values for the safety injection pumps and the centrifugal charging pumps are non-conservative to ensure that the performance of the ECCS pumps is consistent with the minimum performance credited by the plant safety Enclosure
-2 analyses and ASME [American Society of Mechanical Engineers] Section XI test criteria.
Although compliance with SR 4.5.2.f is being met, surveillance testing of the EGGS pumps is being performed in accordance with ASME Section XI inservice inspection requirements, in accordance with TS 4.0.5." Please provide the following additional information:
a) Discuss the minimum pump performance requirements that were credited in the SON safety analyses, and the above mentioned nonconservatism in the current SR 4.5.2.f discharge pressure values for the safety injection pumps and the centrifugal charging pumps.
b) Discuss how compliance with ASME Section XI in-service testing criteria ensured that the safety analyses minimum performance requirements are satisfied.
- 4. As part of the modification of the SON EGGS TS, several SRs, such as SR 4.5.2.c, SR 4.5.2.g, and SR 4.5.2.h, items have been relocated to plant procedures. The NRG staff believes that relocating an item from the TSs to plant procedures is a significant relaxation of the required action from the standpoint of regulatory enforcement because plant procedures are licensee controlled actions. Please justify why it was necessary to relocate the SR items from the TSs to plant procedure, when the same task was being performed under the TSs, without any problem.
August 13, 2009 Mr. Preston D. Swafford Chief Nuclear Officer and Executive Vice President Tennessee Valley Authority 3R Lookout Place 1101 Market Street Chattanooga, TN 37402-2801
SUBJECT:
SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION REGARDING THE UPGRADE OF EMERGENCY CORE COOLING SYSTEM REQUIREMENTS PER NUREG-1431 (TAC NO. ME1115 AND ME1116)
Dear Mr. Swafford:
By letter dated April 21, 2009, you submitted an application for license amendment to revise the Sequoyah Nuclear Plant, Units 1 and 2 (SQN) Technical Specifications (TSs), and upgrade the Emergency Core Cooling System (ECCS) requirements to be more consistent with NUREG-1431, Revision 3, "Standard Technical Specifications - Westinghouse Plants." The upgrade revises SQN TS Section 3/4.5.2, "ECCS Subsystems - Tavg Greater Than or Equal to 350 of, TS Section 3/4.5.3, "ECCS Subsystems - T avg Less Than 350 of, and the corresponding surveillance requirements (SRs) that will resolve a nonconforming condition associated with SR 4.5.2.f.
The Nuclear Regulatory Commission staff is reviewing the submittal and has determined that additional information is required to complete its evaluation. This request was discussed with Mr. Rusty Proffitt of your staff on August 13, 2009, and it was agreed that a response would be provided within 30 days from the date of this letter.
If you have any questions regarding this matter, I can be reached at 301-415-1564.
Sincerely, IRA!
Siva P. Lingam, Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-327 and 50-328
Enclosure:
Request for Additional Information cc w/encl: Distribution via Listserv DISTRIBUTION:
PUBLIC LPL2-2 R/F RidsNrrDorlLpl2-2 RidsNrrPMSequoyah RidsNrrLACSola RidsOgcMailCenter RidsNrrDorlDpr RidsAcrsAcnw_MailCTR RidsNrrDssSrxb RidsRgn2MailCenter MRazzaque, SRXB ADAMS Accession No: ML092020349 . db>y memo date d transmltte OFFICE LPL2-2/PM LPL2-2/LA NRR/DSS/SRXB/BC LPL2-21BC NAME SLingam CSoia GCranston TBoyce DATE 08/13/09 7122109 7/21/09* 08/13/09 OFFICIAL RECORD COpy