ML092920128: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(StriderTol Bot change)
 
(4 intermediate revisions by the same user not shown)
Line 14: Line 14:
| page count = 46
| page count = 46
}}
}}
See also: [[followed by::IR 05000280/2009301]]
See also: [[see also::IR 05000280/2009301]]


=Text=
=Text=
{{#Wiki_filter:1. 0026G2.1.7 1 Unit 1 Initial Conditions:  
{{#Wiki_filter:1. 0026G2.1.7 1
 
Unit 1 Initial Conditions:
* The operations team is cooling down the unit in preparation for refueling in accordance with 1-GOP-2.6, "UNIT COOLDOWN, LESS THAN 205 °F TO  
    *   The operations team is cooling down the unit in preparation for refueling in
AMBIENT." * The pressurizer (PRZR) is water-solid , and all PRZR heaters are tagged off. * RCS Pressure is approximately 250 psig.  
        accordance with 1-GOP-2.6, "UNIT COOLDOWN, LESS THAN 205 °F TO
* RCS Temperature is approximately 180 °F.  
        AMBIENT."
* 'A' and 'B' S/G WR levels are approximately 98%. 'C' S/G NR level is 65%.  
    *   The pressurizer (PRZR) is water-solid, and all PRZR heaters are tagged off.
* All RCPs are stopped.
    *   RCS Pressure is approximately 250 psig.
  Current conditions:  
    *   RCS Temperature is approximately 180 °F.
 
    *   'A' and 'B' S/G WR levels are approximately 98%. 'C' S/G NR level is 65%.
* A large unisolable CCW leak caused a complete and sustained loss of CCW.  
    *   All RCPs are stopped.
* The operations team entered 1-AP-27.00, "LOSS OF DECAY HEAT REMOVAL CAPABILITY." * The operators were UNABLE to control RCS temperature using natural circulation cooling.  
  Current conditions:
* CETC temperatures are approaching saturation.  
    *   A large unisolable CCW leak caused a complete and sustained loss of CCW.
   
    *   The operations team entered 1-AP-27.00, "LOSS OF DECAY HEAT REMOVAL
Based on the current conditions, which one of the following is the NEXT method of  
        CAPABILITY."
providing decay heat removal, in accordance with AP-27.00?
    *   The operators were UNABLE to control RCS temperature using natural
 
        circulation cooling.
    *   CETC temperatures are approaching saturation.
  A. Forced feed cooling.
  Based on the current conditions, which one of the following is the NEXT method of
  B. Reflux boiling heat removal.
providing decay heat removal, in accordance with AP-27.00?
  C. Gravity feed cooling.
  A. Forced feed cooling.
  D. Cooling the RCS with the SFP and RWST coolers.
  B. Reflux boiling heat removal.
 
  C. Gravity feed cooling.
  D. Cooling the RCS with the SFP and RWST coolers.
K/A
K/A
Loss of Component Cooling Water: Ability to evaluate plant performance and make  
Loss of Component Cooling Water: Ability to evaluate plant performance and make
operational judgments based on operating characteristics, reactor behavior, and  
operational judgments based on operating characteristics, reactor behavior, and
instrument interpretation.  
instrument interpretation.
(CFR: 41.5/43.5/45.12/45.13) (SRO - 4.7)  
(CFR: 41.5/43.5/45.12/45.13) (SRO - 4.7)
 
K/A Match Analysis
K/A Match Analysis
 
Given a complete loss of component cooling water under S/D and C/D conditions, the
Given a complete loss of component cooling water under S/D and C/D conditions, the  
applicant must use the plant conditions to determine the appropriate course of action.
applicant must use the plant conditions to determine the appropriate course of action
SRO-Only Analysis
 
See attached SRO-only guidance flowchart.  As an amplification, this question is
focusing on the correct procedural selection of the various attachments in AP-27.00 (the
four answer choices are word-for-word the titles of the various attachments in
AP-27.00); and is therefore testing procedural knowledge on a different and more
detailed level than what is expected for a RO.  


SRO-Only Analysis
See attached SRO-only guidance flowchart. As an amplification, this question is
focusing on the correct procedural selection of the various attachments in AP-27.00 (the
four answer choices are word-for-word the titles of the various attachments in
AP-27.00); and is therefore testing procedural knowledge on a different and more
detailed level than what is expected for a RO.
Answer Choice Analysis
Answer Choice Analysis
 
A.     INCORRECT. Attachment 4 of AP-27.00 requires a transition to Attachment 5 to
A.   INCORRECT. Attachment 4 of AP-27.00 requires a transition to Attachment 5 to  
establish reflux boiling heat transfer for the given condition. Plausible because
establish reflux boiling heat transfer for the given condition. Plausible because  
1-OSP-ZZ-004 specifies that forced feed and bleed cooling is a possible "mandatory
1-OSP-ZZ-004 specifies that forced feed and bleed cooling is a possible "mandatory  
backup cooling method" in the initial given plant conditions.
backup cooling method" in the initial given plant conditions.  
B. CORRECT. Attachment 4 of AP-27.00 requires a transition to Attachment 5 to
 
establish reflux boiling heat transfer for this condition.
C. INCORRECT. See analysis of A. above. Plausible because gravity feed cooling is a
B. CORRECT. Attachment 4 of AP-27.00 requires a transition to Attachment 5 to  
method specified as attachment 8 of AP-27.00.
establish reflux boiling heat transfer for this condition.
D. INCORRECT. See comments for A. above. Plausible because cooling the RCS
 
with the SFP and RWST coolers is a cooling method as specified in attachment 10 of
 
AP-27.00.
C. INCORRECT. See analysis of A. above. Plausible because gravity feed cooling is a  
method specified as attachment 8 of AP-27.00.  
 
D. INCORRECT. See comments for A. above. Plausible because cooling the RCS  
with the SFP and RWST coolers is a cooling method as specified in attachment 10 of  
AP-27.00.  
 
Supporting References
Supporting References
 
- 1-GOP-2.6, "UNIT COOLDOWN, LESS THAN 205 F TO AMBIENT," rev 28 (p. 8, 12,
- 1-GOP-2.6, "UNIT COOLDOWN, LESS THAN 205 F TO AMBIENT," rev 28 (p. 8, 12,  
18, 19, 20-22)
18, 19, 20-22)  
-SPS TS Fig. 3.1-2, "RCS COOLDOWN LIMITATIONS."
 
-1-AP-15.00, "LOSS OF COMPONENT COOLING," CAUTION before step 1.
1-AP-27.00, "LOSS OF DECAY HEAT REMOVAL CAPABILITY," rev 18; procedural
-SPS TS Fig. 3.1-2, "RCS COOLDOWN LIMITATIONS."  
flowpath to steps 19, 20, and 21; attachments 4, 5, 6
1-OSP-ZZ-004, "UNIT 1 SAFETY SYSTEMS STATUS LIST FOR COLD
-1-AP-15.00, "LOSS OF COMPONENT COOLING," CAUTION before step 1.  
SHUTDOWN/REFUELING CONDITIONS," rev 35, p. 10 (table of mandatory and
 
non-mandatory backup cooling methods)
1-AP-27.00, "LOSS OF DECAY HEAT REMOVAL CAPABILITY," rev 18; procedural  
flowpath to steps 19, 20, and 21; attachments 4, 5, 6  
 
1-OSP-ZZ-004, "UNIT 1 SAFETY SYSTEMS STATUS LIST FOR COLD  
SHUTDOWN/REFUELING CONDITIONS," rev 35, p. 10 (table of mandatory and  
non-mandatory backup cooling methods)  
 
References Provided to Applicant
References Provided to Applicant
none  
none
Answer: B
Answer: B
2.  0036AA2.03 1
In accordance with the Surry Power Station FSAR Accident Analysis, which one of the
following Fuel Handling Accident conditions result in a HIGHER total effective dose
equivalent (TEDE) received at the Exclusion Area Boundary (EAB) than what is
assumed in the accident analysis?
 
Consider that ALL OTHER assumptions and conservatisms inherent in the analysis
remain UNCHANGED, except for the individual condition below.
 
A. The delay time from reactor shutdown to the initiation of fuel assembly transfer operations is 148 hours.
 
B. The analysis of a postulated fuel handling accident in containment is based on 50% of the fuel assembly Iodine-131 activity assumed to be released into the reactor
cavity water.
 
C. The total activity released from a fuel handling accident in containment is assumed to be released instantaneously.
 
D. The analysis of a postulated fuel handling accident in the spent fuel pool is based on a fuel radionuclide inventory derived from a rated core power level of 2546 MWt.
 
 
K/A 
Ability to determine and interpret the following as they apply to the Fuel Handling
Incidents:  Magnitude of potential radioactive release.
(CFR: 43.5/45.13)  (SRO - 4.2)


2. 0036AA2.03 1
In accordance with the Surry Power Station FSAR Accident Analysis, which one of the
following Fuel Handling Accident conditions result in a HIGHER total effective dose
equivalent (TEDE) received at the Exclusion Area Boundary (EAB) than what is
assumed in the accident analysis?
Consider that ALL OTHER assumptions and conservatisms inherent in the analysis
remain UNCHANGED, except for the individual condition below.
A. The delay time from reactor shutdown to the initiation of fuel assembly transfer
    operations is 148 hours.
B. The analysis of a postulated fuel handling accident in containment is based on 50%
    of the fuel assembly Iodine-131 activity assumed to be released into the reactor
    cavity water.
C. The total activity released from a fuel handling accident in containment is assumed
    to be released instantaneously.
D. The analysis of a postulated fuel handling accident in the spent fuel pool is based
    on a fuel radionuclide inventory derived from a rated core power level of 2546 MWt.
K/A
Ability to determine and interpret the following as they apply to the Fuel Handling
Incidents: Magnitude of potential radioactive release.
(CFR: 43.5/45.13) (SRO - 4.2)
K/A Match Analysis
K/A Match Analysis
 
The question requires the applicant to understand the assumptions that are behind the
The question requires the applicant to understand the assumptions that are behind the  
fuel handling accident (FHA) analysis as presented in the Surry FSAR.
fuel handling accident (FHA) analysis as presented in the Surry FSAR.  
 
SRO-Only Analysis
SRO-Only Analysis
 
The applicant is required to know and understand the severity factors inherent in the
The applicant is required to know and understand the severity factors inherent in the  
FSAR/design basis accidents for fuel handling that are outside the knowledge
FSAR/design basis accidents for fuel handling that are outside the knowledge  
requirement for ROs.
requirement for ROs.  
 
Answer Choice Analysis
Answer Choice Analysis
 
A. INCORRECT. On page 14.4-6 and 14.4-8 of the UFSAR, the accident analyses
A. INCORRECT. On page 14.4-6 and 14.4-8 of the UFSAR, the accident analyses  
assume "a delay time from reactor shutdown to the initiation of fuel assembly transfer
assume "a delay time from reactor shutdown to the initiation of fuel assembly transfer  
operations is at least 100 hours." Furthermore, Surry Technical Specification 3.10
operations is at least 100 hours." Furthermore, Surry Technical Specification 3.10
requires a minimum 100-hour period between the shutdown of a unit and initiation of fuel movement.  Therefore, the wording and the exactitude of the number's
specification (100 hours plus two days) is plausible.  However, the distractor is
incorrect, because a delay time that is longer than the 100 hrs assumed in the analysis
will result in a LOWER dose, NOT a HIGHER dose as required by the question stem. 
 
B.  CORRECT ANSWER.  As specified in the UFSAR page 14.4-6, "9. 5.35 percent of
the fuel assembly Iodine-131 activity is assumed to be released into the reactor cavity
water, as are five percent of the other iodine isotopes present in the fuel assembly,
99.85% being elemental and 0.15% in the organic form.  The decontamination factor
(DF) for elemental ioding is 500 while the DF for organic iodine is 1."  The correct
answer is plausible because 50% of the iodine activity is a plausible design criteria, but much greater than what is actually assumed in the accident analysis. 
 
C.  INCORRECT.  The Surry UFSAR states on p. 14.4-6, that for a fuel handling
accident in containment, "More specific conservative assumptions are: 1.  A puff
release of radioactivity occurs as the result of the rupture of a fuel assembly in the
reactor fuel cavity.  The puff relase is instantaneously and uniformly distributed through
one-half the containment volume."  Therefore, answer "C" is plausible because it is an
actual assumption used in the analysis.  To further add to the plausibility, if the analysis had assumed a certain finite release time, changing this parameter to model the
accident as an instantaneous release would result in a higher dose--which is what the
question stem is asking for.  The distractor is incorrect because it is an assumption in
the analysis, and does not, in fact, result in a HIGHER dose.
 
D.  INCORRECT.  The distractor is derived from one of the actual assumptions used
in the analysis.  Page 14.4-8 of the UFSAR states, "The fuel radionuclide inventory was
based on a core power level of 2605 MWt.  This core power level is conservative
compared to 102% of the uprated power level of 2546 MWt (i.e., 2597 MWt)." 
Therefore, answer "D" is plausible because it uses language from the actual assumption
used in the analysis.  The distractor is incorrect because it states a lower power level
than what is assumed in the analysis, and therefore does not, in fact, result in a
HIGHER dose. 


requires a minimum 100-hour period between the shutdown of a unit and initiation of
fuel movement. Therefore, the wording and the exactitude of the number's
specification (100 hours plus two days) is plausible. However, the distractor is
incorrect, because a delay time that is longer than the 100 hrs assumed in the analysis
will result in a LOWER dose, NOT a HIGHER dose as required by the question stem.
B. CORRECT ANSWER. As specified in the UFSAR page 14.4-6, "9. 5.35 percent of
the fuel assembly Iodine-131 activity is assumed to be released into the reactor cavity
water, as are five percent of the other iodine isotopes present in the fuel assembly,
99.85% being elemental and 0.15% in the organic form. The decontamination factor
(DF) for elemental ioding is 500 while the DF for organic iodine is 1." The correct
answer is plausible because 50% of the iodine activity is a plausible design criteria, but
much greater than what is actually assumed in the accident analysis.
C. INCORRECT. The Surry UFSAR states on p. 14.4-6, that for a fuel handling
accident in containment, "More specific conservative assumptions are: 1. A puff
release of radioactivity occurs as the result of the rupture of a fuel assembly in the
reactor fuel cavity. The puff relase is instantaneously and uniformly distributed through
one-half the containment volume." Therefore, answer "C" is plausible because it is an
actual assumption used in the analysis. To further add to the plausibility, if the analysis
had assumed a certain finite release time, changing this parameter to model the
accident as an instantaneous release would result in a higher dose--which is what the
question stem is asking for. The distractor is incorrect because it is an assumption in
the analysis, and does not, in fact, result in a HIGHER dose.
D. INCORRECT. The distractor is derived from one of the actual assumptions used
in the analysis. Page 14.4-8 of the UFSAR states, "The fuel radionuclide inventory was
based on a core power level of 2605 MWt. This core power level is conservative
compared to 102% of the uprated power level of 2546 MWt (i.e., 2597 MWt)."
Therefore, answer "D" is plausible because it uses language from the actual assumption
used in the analysis. The distractor is incorrect because it states a lower power level
than what is assumed in the analysis, and therefore does not, in fact, result in a
HIGHER dose.
Supporting References
Supporting References
 
-Surry Power Station UFSAR rev 36 section 14.4.1, "Fuel-Handling Accidents."
-Surry Power Station UFSAR rev 36 section 14.4.1, "Fuel-Handling Accidents."  
-Surry Power Station Technical Specifications 1.0 (p. 1.0-1) and 3.10 (p. 3.10-3 and p.
3.10-9).
-Surry Power Station Technical Specifications 1.0 (p. 1.0-1) and 3.10 (p. 3.10-3 and p.  
-The question developer constructed this question by modifying a similar question found
3.10-9).  
in an Indian Point unit 2 ILO exam given in 2005.
-The question developer constructed this question by modifying a similar question found  
in an Indian Point unit 2 ILO exam given in 2005.  
 
References Provided to Applicant
References Provided to Applicant
none
none
Answer: B
3.  0039A2.03 1 Unit 1 Initial Conditions:
 
* 100% Power
* A tube leak in the 'B' Steam Generator (S/G) has been identified.
* Control room operators have transitioned to 1-AP-24.00, "MINOR SG TUBE LEAK." 
Current conditions:
 
* Condenser air ejector radiation monitor, RI-SV-111, alarms but the automatic actions do NOT occur.
* Main Steam (MS) Line B radiation monitor, RI-MS-125, alarms.
* MS Line A and C radiation monitor readings are slightly higher than before.
* The Senior Reactor Operator directs a manual reactor trip and initiation of 1-E-0, "REACTOR TRIP OR SAFETY INJECTION." * Safety Injection (SI) does NOT automatically actuate.
* At step 4 of 1-E-0, it is determined that SI is NOT REQUIRED.
Based on the current conditions, which one of the following is (1) the correct procedural
flowpath, AND (2) the correct method to procedurally address the failure of RV-SI-111
automatic actions? 
 
A. (1)  Transition to 1-ES-0.1, "REACTOR TRIP RESPONSE."  (2)  Perform steps in 1-AP-24.00 to correct the failure of RV-SI-111 automatic
actions, in parallel with 1-ES-0.1.
 
B. (1)  Transition to 1-ES-0.1, "REACTOR TRIP RESPONSE."  (2)  Perform steps in 1-AP-24.01 to correct the failure of RV-SI-111 automatic
actions, in parallel with 1-ES-0.1.
 
C. (1)  Transition to 1-AP-24.01, "LARGE STEAM GENERATOR TUBE LEAK." (2)  Perform steps in  1-AP-24.01 to correct the failure of RV-SI-111 automatic
actions.
D. (1)  Transition to 1-AP-24.01, "LARGE STEAM GENERATOR TUBE LEAK."  (2)  Perform steps in 1-AP-24.00 to correct the failure of RV-SI-111 automatic
actions, in parallel with 1-AP-24.01. 


 
Answer: B
K/A
3. 0039A2.03 1
Ability to (a) predict the impacts of the following malfunctions or operations on the  
Unit 1 Initial Conditions:
MRSS; and (b) based on predictions, use procedures to correct, control, or mitigate the
    *    100% Power
consequences of those malfunctions or operations:  Indications and alarms for main steam and area radiation monitors (during SGTR).
    *    A tube leak in the 'B' Steam Generator (S/G) has been identified.
(CFR: 41.5/43.5/45.3/45.13)  (SRO - 3.7)
    *    Control room operators have transitioned to 1-AP-24.00, "MINOR SG TUBE
        LEAK."
Current conditions:
    *    Condenser air ejector radiation monitor, RI-SV-111, alarms but the automatic
        actions do NOT occur.
    *    Main Steam (MS) Line B radiation monitor, RI-MS-125, alarms.
    *    MS Line A and C radiation monitor readings are slightly higher than before.
    *    The Senior Reactor Operator directs a manual reactor trip and initiation of 1-E-0,
        "REACTOR TRIP OR SAFETY INJECTION."
    *    Safety Injection (SI) does NOT automatically actuate.
    *    At step 4 of 1-E-0, it is determined that SI is NOT REQUIRED.
Based on the current conditions, which one of the following is (1) the correct procedural
flowpath, AND (2) the correct method to procedurally address the failure of RV-SI-111
automatic actions?
A. (1) Transition to 1-ES-0.1, "REACTOR TRIP RESPONSE."
    (2) Perform steps in 1-AP-24.00 to correct the failure of RV-SI-111 automatic
    actions, in parallel with 1-ES-0.1.
B. (1) Transition to 1-ES-0.1, "REACTOR TRIP RESPONSE."
    (2) Perform steps in 1-AP-24.01 to correct the failure of RV-SI-111 automatic
    actions, in parallel with 1-ES-0.1.
C. (1) Transition to 1-AP-24.01, "LARGE STEAM GENERATOR TUBE LEAK."
    (2) Perform steps in 1-AP-24.01 to correct the failure of RV-SI-111 automatic
    actions.
D. (1) Transition to 1-AP-24.01, "LARGE STEAM GENERATOR TUBE LEAK."
    (2) Perform steps in 1-AP-24.00 to correct the failure of RV-SI-111 automatic
    actions, in parallel with 1-AP-24.01.
K/A
Ability to (a) predict the impacts of the following malfunctions or operations on the
MRSS; and (b) based on predictions, use procedures to correct, control, or mitigate the


consequences of those malfunctions or operations:
Indications and alarms for main steam and area radiation monitors (during SGTR).
(CFR: 41.5/43.5/45.3/45.13) (SRO - 3.7)
K/A Match Analysis
K/A Match Analysis
 
Requires the applicant to identify the situation, given a set of conditions, and exercise
Requires the applicant to identify the situation, given a set of conditions, and exercise  
the correct procedures to mitigate both the SGTR and a failure of SJAE radiation
the correct procedures to mitigate both the SGTR and a failure of SJAE radiation  
monitor automatic actions.
monitor automatic actions.  
 
SRO-Only Analysis
SRO-Only Analysis
 
See attached SRO-only guidance flowchart. Internal EOP/AP procedure transition.
See attached SRO-only guidance flowchart. Internal EOP/AP procedure transition.
Knowledge beyond simply entry conditions is required to arrive at the correct answer.
Knowledge beyond simply entry conditions is required to arrive at the correct answer.  
 
Answer Choice Analysis
Answer Choice Analysis
 
A. INCORRECT. Both AP-24.00 and AP-24.01 clearly state that the correct transition
A. INCORRECT. Both AP-24.00 and AP-24.01 clearly state that the correct transition  
is to AP-24.01 instead of ES-0.1. However, ES-0.1 is certainly a plausible choice,
is to AP-24.01 instead of ES-0.1. However, ES-0.1 is certainly a plausible choice,  
because once 1-E-0 is initiated, the RNO of step 4 directs a transition to ES-0.1, without
because once 1-E-0 is initiated, the RNO of step 4 directs a transition to ES-0.1, without  
any notes or cautions in the EOP about this particular case, where a transition to ES-0.1
any notes or cautions in the EOP about this particular case, where a transition to ES-0.1  
is NOT desired.
is NOT desired.  
B. INCORRECT. See analysis for A. above. Although AP-24.01 has specific steps to
 
ensure the proper SJAE alignment, a note before step 1 of AP-24.01 specifically states
 
that ES-0.1 must NOT be performed in parallel.
B. INCORRECT. See analysis for A. above. Although AP-24.01 has specific steps to  
C. CORRECT. Even though 1-E-0 step 4 RNO directs a transition to 1-ES-0.1, the
ensure the proper SJAE alignment, a note before step 1 of AP-24.01 specifically states  
correct flow path is to transition from 1-E-0 to 1-AP-24.01. This is specified in
that ES-0.1 must NOT be performed in parallel.  
AP-24.00, which has as step 2, "Initiate 1-E-0..." and as step 3, "GO TO 1-AP-24.01...."
 
In 1-AP-24.01, step 13 RNO will realign the correct valves and ensure the automatic
 
actions take place.
C. CORRECT. Even though 1-E-0 step 4 RNO directs a transition to 1-ES-0.1, the  
D. INCORRECT. Transitioning to 1-AP-24.01 is correct; however, one should not carry
correct flow path is to transition from 1-E-0 to 1-AP-24.01. This is specified in  
out AP-24.00 actions in parallel with AP-24.01. Step 3 of AP-24.00 specifies that if a
AP-24.00, which has as step 2, "Initiate 1-E-0..." and as step 3, "GO TO 1-AP-24.01...."  
Reactor trip is required, the operator must initiate 1-E-0 and GO TO 1-AP-24.01--that is,
In 1-AP-24.01, step 13 RNO will realign the correct valves and ensure the automatic  
one is NOT to remain in AP-24.00. Once a reactor trip occurs and 1-AP-24.01 is
actions take place.  
entered, there is no other (re-)entry condition into AP-24.00.
 
NOTE: another possible wrong distractor could be "operators are required to be able to
 
correct a radiation monitor automatic action failure from memory ("skill of the craft")" for
D. INCORRECT. Transitioning to 1-AP-24.01 is correct; however, one should not carry  
the second part of choices "B" and "D;" see Lesson Plan ND-93.5-LP-1-DRR.
out AP-24.00 actions in parallel with AP-24.01. Step 3 of AP-24.00 specifies that if a  
Reactor trip is required, the operator must initiate 1-E-0 and GO TO 1-AP-24.01--that is,  
one is NOT to remain in AP-24.00. Once a reactor trip occurs and 1-AP-24.01 is  
entered, there is no other (re-)entry condition into AP-24.00.  
 
NOTE: another possible wrong distractor could be "operators are required to be able to  
correct a radiation monitor automatic action failure from memory ("skill of the craft")" for  
the second part of choices "B" and "D;" see Lesson Plan ND-93.5-LP-1-DRR.  
 
Supporting References
Supporting References
 
- 1-AP-24.00, "MINOR SG TUBE LEAK," rev 10, p. 2 and 3.
- 1-AP-24.00, "MINOR SG TUBE LEAK," rev 10, p. 2 and 3.
- 1-AP-24.01, "LARGE STEAM GENERATOR TUBE LEAK," rev 28, p. 2 and 7
 
- 1-E-0, "REACTOR TRIP OR SAFETY INJECTION," rev. 61, p. 3
-Surry lesson plan ND-93.5-LP-1, "PRE-TMI RADIATION MONITORING SYSTEM," rev 10, p. 2, 16, slide 7


- 1-AP-24.01, "LARGE STEAM GENERATOR TUBE LEAK," rev 28, p. 2 and 7
- 1-E-0, "REACTOR TRIP OR SAFETY INJECTION," rev. 61, p. 3
-Surry lesson plan ND-93.5-LP-1, "PRE-TMI RADIATION MONITORING SYSTEM," rev
10, p. 2, 16, slide 7
References Provided to Applicant
References Provided to Applicant
 
none
none  
Answer: C
4. 003AG2.4.31 8
Answer: C  
Unit 1 Initial Conditions:
4. 003AG2.4.31 8 Unit 1 Initial Conditions:  
    *   Reactor power = 100%
 
    *   Control rod D-6 rod bottom light lit
* Reactor power = 100%  
    *   1G-H2, RPI ROD BOTTOM < 20 STEPS lit
* Control rod D-6 rod bottom light lit  
    *   0-AP-1.00 ROD CONTROL SYSTEM MALFUNCTION is entered
* 1G-H2, RPI ROD BOTTOM < 20 STEPS lit  
Based on the above conditions, which one of the following correctly states (1) if
* 0-AP-1.00 ROD CONTROL SYSTEM MALFUNCTION is entered  
0-AP-1.00 directs the initiation of 0-AP-23.00 RAPID LOAD REDUCTION to reduce
power and (2) the parameter that is required to be monitored to reduce and stabilize
Based on the above conditions, which one of the following correctly states (1) if  
power?
0-AP-1.00 directs the initiation of 0-AP-23.00 RAPID LOAD REDUCTION to reduce power and (2) the parameter that is required to be monitored to reduce and stabilize power? A. (1) Yes (2) Loop T B. (1) Yes (2) the highest reading PRNI  
A. (1) Yes
 
    (2) Loop T
C. (1) No (2) Loop T D. (1) No (2) the highest reading PRNI  
B. (1) Yes
 
    (2) the highest reading PRNI
 
C. (1) No
K/A Dropped Control Rod: Knowledge of annunciator alarms, indications, or response  
    (2) Loop T
procedures.  
D. (1) No
 
    (2) the highest reading PRNI
K/A
Dropped Control Rod: Knowledge of annunciator alarms, indications, or response
procedures.
K/A Match Analysis
K/A Match Analysis
Requires knowledge of response procedures for a dropped control rod.  
Requires knowledge of response procedures for a dropped control rod.


 
SRO-Only Analysis
SRO-Only Analysis
Requires assessing plant conditions and then prescribing a procedure or section of a  
Requires assessing plant conditions and then prescribing a procedure or section of a
procedure to mitigate, recover, or with which to proceed. Knowledge above knowing  
procedure to mitigate, recover, or with which to proceed. Knowledge above knowing
entry conditions for APs is required.  
entry conditions for APs is required.
 
Answer Choice Analysis
Answer Choice Analysis
A. Incorrect; 1
A. Incorrect; 1st part is incorrect because AP/1.00 does not reference AP/23 and
st part is incorrect because AP/1.00 does not reference AP/23 and     AP/1.00 gives an hour to reduce power to 70-74%. 1
      AP/1.00 gives an hour to reduce power to 70-74%. 1st part is plausible because
st part is plausible because     AP/23 is frequently used to reduce power during plant upsets. 2
      AP/23 is frequently used to reduce power during plant upsets. 2nd part is correct
nd part is correct      per a caution in AP/1.00 before step 17. B. Incorrect; 1
       per a caution in AP/1.00 before step 17.
st part is incorrect because AP/1.00 does not reference AP/23 and       AP/1.
B. Incorrect; 1st part is incorrect because AP/1.00 does not reference AP/23 and           AP/1.0
0    AP/23 is frequently used to reduce power during plant upsets.2
      AP/23 is frequently used to reduce power during plant upsets.2nd part is incorrect
nd part is incorrect     because caution in AP/1.00 states that DT must be monitored during the ramp and     used to stabilize power. 2
      because caution in AP/1.00 states that DT must be monitored during the ramp and
nd part is plausible because the highest reading PRNI will  
      used to stabilize power. 2nd part is plausible because the highest reading PRNI
    be more conservative than DT. C. Correct: 1
will
st part is AP/1.00 Step 17. A caution in AP/1.00 states that DT must be     monitored during the ramp and used to stabilize power. D. Incorrect; 1
      be more conservative than DT.
st part is correct. 2
C. Correct: 1st part is AP/1.00 Step 17. A caution in AP/1.00 states that DT must be
nd part is incorrect because caution in AP/1.00 states     that DT must be monitored during the ramp and used to stabilize power. 2
      monitored during the ramp and used to stabilize power.
nd part     is plausible because the highest reading PRNI will be more conservative than DT.
D. Incorrect; 1st part is correct. 2nd part is incorrect because caution in AP/1.00 states
 
      that DT must be monitored during the ramp and used to stabilize power. 2nd part
     is plausible because the highest reading PRNI will be more conservative than DT.
Supporting References
Supporting References
0-AP-1.00, ROD CONTROL SYSTEM MALFUNCTION  
0-AP-1.00, ROD CONTROL SYSTEM MALFUNCTION
 
References Provided to Applicant
References Provided to Applicant
none  
none
Licensee discuss the potential use of AP/23 for the power reduction.
Licensee discuss the potential use of AP/23 for the power reduction.  
Answer: C
Answer: C  
5. 0054G2.2.25 1
5. 0054G2.2.25 1 Which one of the following correctly identifies two reasons for the Feedwater Line  
Which one of the following correctly identifies two reasons for the Feedwater Line
Isolation function, as specified in the bases of Technical Specification 3.7,  
Isolation function, as specified in the bases of Technical Specification 3.7,
"INSTRUMENTATION SYSTEMS?"  
"INSTRUMENTATION SYSTEMS?"
A. (1) Prevent excessive cooldown of the Reactor Coolant System; AND (2) Reduces the consequences of a design basis steam generator tube rupture by  
A. (1) Prevent excessive cooldown of the Reactor Coolant System; AND
preventing steam generator overfill.  
    (2) Reduces the consequences of a design basis steam generator tube rupture by
 
    preventing steam generator overfill.
B. (1) Prevent excessive moisture carry-over that could damage the main turbine blading; AND
B. (1) Prevent excessive moisture carry-over that could damage the main turbine
(2) Reduces the consequences of a design-basis steam generator tube rupture by  
    blading; AND
preventing steam generator overfill.  
    (2) Reduces the consequences of a design-basis steam generator tube rupture by
 
    preventing steam generator overfill.
C. (1) Prevent excessive cooldown of the Reactor Coolant System; AND  
C. (1) Prevent excessive cooldown of the Reactor Coolant System; AND
(2) Reduces the consequences of a steam line break inside the containment by stopping the entry of main feedwater.
 
D. (1) Prevent excessive moisture carry-over that could damage the main turbine blading; AND 
(2) Reduces the consequences of a steam line break inside the containment by
stopping the entry of main feedwater.
K/A 
Loss of Main Feedwater: 
Knowledge of the bases in Technical Specifications for limiting conditions for operations
and safety limits. 
(CFR: 41.5 / 41.7 / 43.2)  (SRO - 4.2)


    (2) Reduces the consequences of a steam line break inside the containment by
    stopping the entry of main feedwater.
D. (1) Prevent excessive moisture carry-over that could damage the main turbine
    blading; AND
    (2) Reduces the consequences of a steam line break inside the containment by
    stopping the entry of main feedwater.
K/A
Loss of Main Feedwater:
Knowledge of the bases in Technical Specifications for limiting conditions for operations
and safety limits.
(CFR: 41.5 / 41.7 / 43.2) (SRO - 4.2)
K/A Match Analysis
K/A Match Analysis
The question is a straighforward link directly to the TS basis for feedwater isolation.  
The question is a straighforward link directly to the TS basis for feedwater isolation.
 
SRO-Only Analysis
SRO-Only Analysis
See attached SRO-only flowchart. TS Basis knowledge required to arrive at correct  
See attached SRO-only flowchart. TS Basis knowledge required to arrive at correct
answer.  
answer.
Answer Choice Analysis
Answer Choice Analysis
 
A. INCORRECT. The distractors are basically reasons for the HI-HI S/G level
A. INCORRECT. The distractors are basically reasons for the HI-HI S/G level  
automatic function, worded to sound like the correct answers from the TS basis.
automatic function, worded to sound like the correct answers from the TS basis.  
B. INCORRECT. see analysis of A. and C.
 
C. CORRECT. Answer is basically word-for-word from TS 3.7, which states: "The
 
feedwater lines are isolated upon actuation of the SIS in order to prevent excessive
B. INCORRECT. see analysis of A. and C.  
cooldown of the Reactor Coolant System. This mitigates the effects of an accident
 
such as a steam line break which in itself causes excessive temperature cooldown.
 
Feedwater line isolation also reduces the consequences of a steam line break inside the
C. CORRECT. Answer is basically word-for-word from TS 3.7, which states: "The  
containment by stopping the entry of feedwater."
feedwater lines are isolated upon actuation of the SIS in order to prevent excessive  
D. INCORRECT. See analysis of A. and C.
cooldown of the Reactor Coolant System. This mitigates the effects of an accident  
such as a steam line break which in itself causes excessive temperature cooldown.
Feedwater line isolation also reduces the consequences of a steam line break inside the  
containment by stopping the entry of feedwater."   D. INCORRECT. See analysis of A. and C.  
 
Supporting References
Supporting References
 
-Surry Technical Specification 3.7, amendment nos. 180 and 180, p. 3.7-5 and 3.7-6
-Surry Technical Specification 3.7, amendment nos. 180 and 180, p. 3.7-5 and 3.7-6  
 
References Provided to Applicant
References Provided to Applicant
 
none
none  
 
Answer: C 6.  0055G2.4.6 1 Unit 1 Initial Conditions:
 
* A steam generator tube rupture caused an automatic reactor trip and SI from 100% power.
* Operations personnel are performing actions in 1-E-3, "STEAM GENERATOR TUBE RUPTURE." 
Current conditions:
 
* A maximum-rate cooldown using steam dumps to the condenser has begun.
* SI has just been reset.
* The RO reports that condenser vacuum is 28 " Hg and slowly lowering.
* The TSC informs the operations team that once all actions of E-3 are complete, it is required to implement the post-SGTR procedure that allows the FASTEST means of depressurizing the RCS and ruptured S/G.
Based on the current conditions, which one of the following is (1) a required action
specified by E-3, AND (2) the correct post-SGTR procedure to implement? 
 
A. (1)  Ensure the condenser air ejector is aligned to containment, and then OPEN 1-SV-TV-102A.
(2)  GO TO 1-ES-3.2, "POST-SGTR COOLDOWN USING BLOWDOWN."
B. (1)  Ensure the condenser air ejector is aligned to containment, and then OPEN 1-SV-TV-102A.
(2)  GO TO 1-ES-3.3, "POST-SGTR COOLDOWN USING STEAM DUMP."
C. (1)  IF a Hi-CLS signal is NOT actuated, THEN realign the condenser air ejector for normal operations.
(2)  GO TO 1-ES-3.2, "POST-SGTR COOLDOWN USING BLOWDOWN."
D. (1)  IF a Hi-CLS signal is NOT actuated, THEN realign the condenser air ejector for normal operations.
(2)  GO TO 1-ES-3.3, "POST-SGTR COOLDOWN USING STEAM DUMP." 
K/A 
055 Condenser Air Removal
Knowledge of EOP mitigation strategies. (as relating to the Condenser Air Removal
system)
(CFR:  41.10 / 43.5 / 45.13)  (SRO - 4.7)


   
Answer: C
6. 0055G2.4.6 1
Unit 1 Initial Conditions:
    * A steam generator tube rupture caused an automatic reactor trip and SI from
      100% power.
    *  Operations personnel are performing actions in 1-E-3, "STEAM GENERATOR
      TUBE RUPTURE."
Current conditions:
    *  A maximum-rate cooldown using steam dumps to the condenser has begun.
    *  SI has just been reset.
    *  The RO reports that condenser vacuum is 28 " Hg and slowly lowering.
    *  The TSC informs the operations team that once all actions of E-3 are complete,
      it is required to implement the post-SGTR procedure that allows the FASTEST
      means of depressurizing the RCS and ruptured S/G.
Based on the current conditions, which one of the following is (1) a required action
specified by E-3, AND (2) the correct post-SGTR procedure to implement?
A. (1) Ensure the condenser air ejector is aligned to containment, and then OPEN
    1-SV-TV-102A.
    (2) GO TO 1-ES-3.2, "POST-SGTR COOLDOWN USING BLOWDOWN."
B. (1) Ensure the condenser air ejector is aligned to containment, and then OPEN
    1-SV-TV-102A.
    (2) GO TO 1-ES-3.3, "POST-SGTR COOLDOWN USING STEAM DUMP."
C. (1) IF a Hi-CLS signal is NOT actuated, THEN realign the condenser air ejector for
    normal operations.
    (2) GO TO 1-ES-3.2, "POST-SGTR COOLDOWN USING BLOWDOWN."
D. (1) IF a Hi-CLS signal is NOT actuated, THEN realign the condenser air ejector for
    normal operations.
    (2) GO TO 1-ES-3.3, "POST-SGTR COOLDOWN USING STEAM DUMP."
K/A
055 Condenser Air Removal
Knowledge of EOP mitigation strategies. (as relating to the Condenser Air Removal
system)
(CFR: 41.10 / 43.5 / 45.13) (SRO - 4.7)
K/A Match Analysis
K/A Match Analysis
 
The question requires the SRO applicant to demonstrate detailed knowledge of EOP
mitigation strategies/transitions as related to expected effects of the condenser air
removal system following an SI.


The question requires the SRO applicant to demonstrate detailed knowledge of EOP
mitigation strategies/transitions as related to expected effects of the condenser air
removal system following an SI.
SRO-Only Analysis
SRO-Only Analysis
 
See attached SRO-only flowchart.
See attached SRO-only flowchart.  
Linked to SRO-only knowledge based on detailed internal EOP transition criteria and
 
procedural selection outside of initial/entry conditions.
Linked to SRO-only knowledge based on detailed internal EOP transition criteria and  
procedural selection outside of initial/entry conditions.
 
Answer Choice Analysis
Answer Choice Analysis
 
A. INCORRECT. The lowering condenser vacuum is an expected condition. In the
A. INCORRECT. The lowering condenser vacuum is an expected condition. In the  
next few steps, 1-E-3 will ensure the proper operation of the air ejectors and mitigate
next few steps, 1-E-3 will ensure the proper operation of the air ejectors and mitigate  
the concern. Therefore the (1) part of this answer is correct. Part (2) is incorrect; the
the concern. Therefore the (1) part of this answer is correct. Part (2) is incorrect; the lesson plan for ES-3.3, "POST SGTR COOLDOWN USING STEAM DUMP," is very  
lesson plan for ES-3.3, "POST SGTR COOLDOWN USING STEAM DUMP," is very
clear that it provides the fastest means of depressurizing the RCS and ruptured SG.
clear that it provides the fastest means of depressurizing the RCS and ruptured SG.
ES-3.2 is plausible, if the applicant believes that the lowering condenser vacuum  
ES-3.2 is plausible, if the applicant believes that the lowering condenser vacuum
precludes the use of ES-3.3 through the steam dumps.  
precludes the use of ES-3.3 through the steam dumps.
 
B. CORRECT. (1) Step 14 of 1-E-3 will align condenser air ejector to containment
 
and improve the degraded vacuum condition. (2) is also correct; see analysis of A.
B. CORRECT. (1) Step 14 of 1-E-3 will align condenser air ejector to containment and improve the degraded vacuum condition. (2) is also correct; see analysis of A.  
above.
above.  
C. INCORRECT. (1) is incorrect, but plausible, because valve TV-SV-102 will (only)
 
close automatically on a Hi-CLS signal. Also plausible because the question stem
C. INCORRECT. (1) is incorrect, but plausible, because valve TV-SV-102 will (only)  
states that vacuum is lowering. Part (2) is also the incorrect procedural transition.
close automatically on a Hi-CLS signal. Also plausible because the question stem  
D. INCORRECT. (1) is incorrect choice, (2) is the correct proceural transition; see
states that vacuum is lowering. Part (2) is also the incorrect procedural transition.  
above analyses.
 
D. INCORRECT. (1) is incorrect choice, (2) is the correct proceural transition; see above analyses.  
 
Supporting References
Supporting References
 
-Surry lesson plan ND-89.3-LP-2, "MAIN CONDENSATE SYSTEM," rev. 18, p. 11.
-Surry lesson plan ND-89.3-LP-2, "MAIN CONDENSATE SYSTEM," rev. 18, p. 11.  
-1-E-3, "STEAM GENERATOR TUBE RUPTURE," rev. 38, p. 10, 12.
 
-Surry lesson plan ND-95.3-LP-16, "ES-3.3 POST SGTR COOLDOWN USING STEAM
DUMP," rev. 12, p. 31.
-1-E-3, "STEAM GENERATOR TUBE RUPTURE," rev. 38, p. 10, 12.  
 
-Surry lesson plan ND-95.3-LP-16, "ES-3.3 POST SGTR COOLDOWN USING STEAM  
DUMP," rev. 12, p. 31.  
 
References Provided to Applicant
References Provided to Applicant
none  
none
Answer: B
Answer: B
7.  006A2.12 12 Initial plant conditions on Unit 1 are as follows:
* A SBLOCA has occurred.
* Radiation levels in the Auxiliary Building are increasing.
* The crew has transitioned to ECA-1.2 "LOCA Outside Containment".
* The crew closed/verified closed SI-MOV-1890A and -1890B.
* RCS pressure was at 1700 psig and slowly dropping.
Current plant conditions on Unit 1 are as follows:
* The crew has closed SI-MOV-1890C.
* RCS pressure is at 1550 psig and slowly rising. Which one of the following describes (1) the status of the LOCA and (2) the required procedure transition?


A. (1) LOCA has been isolated. (2) Go to ECA-1.1, "Loss of Emergency Coolant Recirculation".  
7. 006A2.12 12
 
Initial plant conditions on Unit 1 are as follows:
B. (1) LOCA still exists. (2) Go to ECA-1.1, "Loss of Emergency Coolant Recirculation".  
    *  A SBLOCA has occurred.
 
    *  Radiation levels in the Auxiliary Building are increasing.
C. (1) LOCA has been isolated. (2) Go to 1-E-1, "Loss of Reactor or Secondary Coolant".  
    *  The crew has transitioned to ECA-1.2 LOCA Outside Containment.
 
    *  The crew closed/verified closed SI-MOV-1890A and -1890B.
D. (1) LOCA still exists. (2) Go to 1-E-1, "Loss of Reactor or Secondary Coolant".  
    *  RCS pressure was at 1700 psig and slowly dropping.
 
Current plant conditions on Unit 1 are as follows:
 
    *  The crew has closed SI-MOV-1890C.
K/A Emergency Core Cooling: Ability to (a) predict the impacts of the following  
    *  RCS pressure is at 1550 psig and slowly rising.
malfunctions or operations on the ECCS; and (b) based on those predictions, use  
Which one of the following describes (1) the status of the LOCA and (2) the required
procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Conditions requiring actuation of ECCS.  
procedure transition?
 
A. (1) LOCA has been isolated.
    (2) Go to ECA-1.1, Loss of Emergency Coolant Recirculation.
B. (1) LOCA still exists.
    (2) Go to ECA-1.1, Loss of Emergency Coolant Recirculation.
C. (1) LOCA has been isolated.
    (2) Go to 1-E-1, Loss of Reactor or Secondary Coolant.
D. (1) LOCA still exists.
    (2) Go to 1-E-1, Loss of Reactor or Secondary Coolant.
K/A
Emergency Core Cooling: Ability to (a) predict the impacts of the following
malfunctions or operations on the ECCS; and (b) based on those predictions, use
procedures to correct, control, or mitigate the consequences of those malfunctions or
operations: Conditions requiring actuation of ECCS.
K/A Match Analysis
K/A Match Analysis
Requires applicant to predict the impact of a leak outside containment on the alignment of emergency core cooling equipment and perform the actions from ECA-1.2 for transitioning back to E-1.  
Requires applicant to predict the impact of a leak outside containment on the alignment
 
of emergency core cooling equipment and perform the actions from ECA-1.2 for
transitioning back to E-1.
SRO-Only Analysis
SRO-Only Analysis
The question requires the applicant to assess plant conditions and know the intent of  
The question requires the applicant to assess plant conditions and know the intent of
the specific steps to determine the correct procedural transition..  
the specific steps to determine the correct procedural transition..


 
Answer Choice Analysis
Answer Choice Analysis
A. In-Correct but plausible since the increasing RCS pressure indicates the leak has  
A. In-Correct but plausible since the increasing RCS pressure indicates the leak has
been isolated. In addition, the previous actions have closed all the cold and hot leg  
been isolated. In addition, the previous actions have closed all the cold and hot leg
recirculation valves so it would seem plausible to transition to ECA-1.1, Loss of  
recirculation valves so it would seem plausible to transition to ECA-1.1, Loss of
Emergency Coolant Recirculation". However, the correct action is to transition back to  
Emergency Coolant Recirculation. However, the correct action is to transition back to
E-1.  
E-1.
B. In-Correct but plausible since the actions are correct if the leak still exists. However,
B. In-Correct but plausible since the actions are correct if the leak still exists. However,  
the increasing RCS pressure indicates the leak has been isolated and the crew should
the increasing RCS pressure indicates the leak has been isolated and the crew should  
transition to E-1.
transition to E-1.  
C. Correct - The increasing RCS pressure indicates the leak has been isolated. The
 
correct actions are to place LHSI pumps in PTL, close LHSI pump suction valves and
transition to E-1.
C. Correct - The increasing RCS pressure indicates the leak has been isolated. The  
D. In-Correct but plausible since reopening SI-MOV-1890C is correct if the leak still
correct actions are to place LHSI pumps in PTL, close LHSI pump suction valves and  
exists. The transition to E-1 is correct. However, the leak has been isolated.
transition to E-1.  
 
D. In-Correct but plausible since reopening SI-MOV-1890C is correct if the leak still  
exists. The transition to E-1 is correct. However, the leak has been isolated.  
 
Supporting References
Supporting References
ND-95.3-LP-21, "ECA-1.2, LOCA Outside Containment", Rev. 7, Obj. A  
ND-95.3-LP-21, ECA-1.2, LOCA Outside Containment, Rev. 7, Obj. A
 
References Provided to Applicant
References Provided to Applicant
none  
none
NOTE:Original question used on Surry 02-301 exam - developed by G. Laska
(WE04G2.4.9). Modified conditions to indicate isolation of leak and asked for status of
NOTE:Original question used on Surry 02-301 exam - developed by G. Laska  
leak.
(WE04G2.4.9). Modified conditions to indicate isolation of leak and asked for status of  
Answer: C
leak.  
8. 0073A2.02 1
Answer: C  
Unit 1 Initial Conditions:
8. 0073A2.02 1 Unit 1 Initial Conditions:  
    *   Holding at 30% power for chemistry, following a refueling outage.
 
    *   The Power Range NI input for 1-MS-RM-190, 1-MS-RM-191, and 1-MS-RM-192
* Holding at 30% power for chemistry, following a refueling outage.  
        (Main Steam Line N-16 radiation monitors) has failed to 100% power.
* The Power Range NI input for 1-MS-RM-190, 1-MS-RM-191, and 1-MS-RM-192 (Main Steam Line N-16 radiation monitors) has failed to 100% power.  
  Current conditions:
   
    *   Annunciator 1A-A3, "N-16 HIGH," is NOT LIT
Current conditions:  
    *   Annunciator 1A-B3, "N-16 ALERT," is LIT
 
    *   Annunciator 1A-C3, "N-16 TROUBLE," is NOT LIT
* Annunciator 1A-A3, "N-16 HIGH," is NOT LIT  
    *   Annunciator 1D-E5, "CHG PP TO REGEN HX HI-LO FLOW," is LIT
* Annunciator 1A-B3, "N-16 ALERT," is LIT  
    *   Pressurizer level is STABLE
* Annunciator 1A-C3, "N-16 TROUBLE," is NOT LIT  
    *   VCT level is STABLE
* Annunciator 1D-E5, "CHG PP TO REGEN HX HI-LO FLOW," is LIT  
* Pressurizer level is STABLE  
* VCT level is STABLE
Based on the current conditions, which one of the following (1) is the correct procedural
transition in accordance with the ARP for 1A-B3, "N-16 ALERT," AND (2) if no
corrective actions have been taken for the power range NI input module, the alarm
setpoints for 1-MS-RM-190 through -192 are _______________. ?
 
A. (1)  0-OSP-RC-002, "STEAM GENERATOR PRIMARY TO SECONDARY LEAKAGE MONITORING."
(2)  lower than normal.
 
B. (1)  1-AP-16.00, "EXCESSIVE RCS LEAKAGE." (2)  lower than normal.
 
C. (1)  1-AP-16.00, "EXCESSIVE RCS LEAKAGE." (2)  higher than normal.
 
D. (1)  0-OSP-RC-002, "STEAM GENERATOR PRIMARY TO SECONDARY LEAKAGE MONITORING." (2)  higher than normal.
 
K/A Process Radiation Monitor (PRM) System
Ability to (a) predict the impacts of the following malfunctions or operations on the PRM
system; and (b) based on those predictions, use procedures to correct, control, or
mitigate the conse
quences of those malfunctions or operations: Detector failure. (CFR: 41.5/43.5/45.3/45.13)  (SRO - 3.2)


   
  Based on the current conditions, which one of the following (1) is the correct procedural
transition in accordance with the ARP for 1A-B3, "N-16 ALERT," AND (2) if no
corrective actions have been taken for the power range NI input module, the alarm
setpoints for 1-MS-RM-190 through -192 are _______________. ?
A. (1) 0-OSP-RC-002, "STEAM GENERATOR PRIMARY TO SECONDARY
    LEAKAGE MONITORING."
    (2) lower than normal.
B. (1) 1-AP-16.00, "EXCESSIVE RCS LEAKAGE."
    (2) lower than normal.
C. (1) 1-AP-16.00, "EXCESSIVE RCS LEAKAGE."
    (2) higher than normal.
D. (1) 0-OSP-RC-002, "STEAM GENERATOR PRIMARY TO SECONDARY
    LEAKAGE MONITORING."
    (2) higher than normal.
K/A
Process Radiation Monitor (PRM) System
Ability to (a) predict the impacts of the following malfunctions or operations on the PRM
system; and (b) based on those predictions, use procedures to correct, control, or
mitigate the consequences of those malfunctions or operations: Detector failure.
(CFR: 41.5/43.5/45.3/45.13) (SRO - 3.2)
K/A Match Analysis
K/A Match Analysis
Given a PRM detector failure condition, the SRO applicant will correctly determine the  
Given a PRM detector failure condition, the SRO applicant will correctly determine the
impact on the setpoints; and given an operationally valid situation, the SRO applicant  
impact on the setpoints; and given an operationally valid situation, the SRO applicant
will correctly apply/select procedures to correct, control, or mitigate the issue.  
will correctly apply/select procedures to correct, control, or mitigate the issue.
 
SRO-Only Analysis
SRO-Only Analysis
This is an analysis level question since the candidate must analyze the impact of the  
This is an analysis level question since the candidate must analyze the impact of the
power input to the detector circuitry failing high to determine the effect on the alarm setpoint.  
power input to the detector circuitry failing high to determine the effect on the alarm
 
setpoint.
This is an SRO only question linked to 10CFR55.43(b)(5). The question can NOT be
This is an SRO only question linked to 10CFR55.43(b)(5). The question can NOT be  
answered using system knowledge alone. It can NOT be answered by knowing
answered using system knowledge alone. It can NOT be answered by knowing  
immediate actions, or basic procedure entry conditions (cover page material). To
immediate actions, or basic procedure entry conditions (cover page material). To  
correctly answer this question, the candidate must assess plant conditions and then
correctly answer this question, the candidate must assess plant conditions and then  
decide which procedure should be implemented.
decide which procedure should be implemented.  
Answer Choice Analysis


Answer Choice Analysis
 
******************************************************************************************
******************************************************************************************
 
NOTE TO SURRY: Please validate the Power Range NI input part of this
NOTE TO SURRY: Please validate the Power Range NI input part of this
question with your actual plant response. The lesson plan for the N-16 monitors
question with your actual plant response. The lesson plan for the N-16 monitors  
was not very detailed about power compensation.
was not very detailed about power compensation.  
 
******************************************************************************************
******************************************************************************************
 
A. INCORRECT. (1) The ARPs for both N-16 HIGH and N-16 ALERT specify to
transition to 1-AP-16.00, "EXCESSIVE RCS LEAKAGE," on any of the following
A. INCORRECT. (1) The ARPs for both N-16 HIGH and N-16 ALERT specify to  
conditions: PRZR level - DECREASING; OR Annunciator 1D-E5, CHG PP TO REGEN
transition to 1-AP-16.00, "EXCESSIVE RCS LEAKAGE," on any of the following  
HX HI-LO FLOW-LIT; OR A discernable negative change in VCT level trend has
conditions: PRZR level - DECREASING; OR Annunciator 1D-E5, CHG PP TO REGEN  
developed." 0-OSP-RC-002 is an incorrect, but plausible choice, because it would be
HX HI-LO FLOW-LIT; OR A discernable negative change in VCT level trend has  
correct if the annunciator 1D-E5 were NOT lit. (2) Due to much longer loop transport
developed." 0-OSP-RC-002 is an incorrect, but plausible choice, because it would be  
times at lower power, N-16 has more time to decay prior to reaching the area in the
correct if the annunciator 1D-E5 were NOT lit. (2) Due to much longer loop transport  
main steam lines adjacent to the monitors. Therefore, the alarm setpoint for a given
times at lower power, N-16 has more time to decay prior to reaching the area in the  
leak must be lower than that for 100% power to ensure accuracy. Thus, (2) is incorrect
main steam lines adjacent to the monitors. Therefore, the alarm setpoint for a given  
for this distractor.
leak must be lower than that for 100% power to ensure accuracy. Thus, (2) is incorrect  
B. INCORRECT. (1) is correct choice, (2) incorrect. See above.
for this distractor.  
C. CORRECT. Both (1) and (2) correct as per the above.
 
D. INCORRECT. (1) is incorrect, (2) correct. See above analysis.
 
B. INCORRECT. (1) is correct choice, (2) incorrect. See above.  
 
 
C. CORRECT. Both (1) and (2) correct as per the above.  
 
 
D. INCORRECT. (1) is incorrect, (2) correct. See above analysis.
 
Supporting References
Supporting References
 
-modified from McGuire 2009-301 exam question SRO #94.
-modified from McGuire 2009-301 exam question SRO #94.  
-Surry procedure 1A-A3, "N-16 HIGH," rev. 3.
 
-Surry procedure 1A-B3, "N-16 ALERT," rev. 3.
-Surry procedure 1A-C3, "N-16 TROUBLE," rev. 3.
-Surry procedure 1A-A3, "N-16 HIGH," rev. 3.  
 
-Surry procedure 1A-B3, "N-16 ALERT," rev. 3.  
 
-Surry procedure 1A-C3, "N-16 TROUBLE," rev. 3.  
 
References Provided to Applicant
References Provided to Applicant
none  
none
Answer: C
Answer: C  
9. 0076AA2.02 1
9. 0076AA2.02 1 Unit 1 Initial Conditions:  
Unit 1 Initial Conditions:
 
    * At time 0930, unexpected grid fluctuations caused an automatic turbine trip from
  * At time 0930, unexpected grid fluctuations caused an automatic turbine trip from 100% power.  
        100% power.
* Chemistry personnel drew a post-trip RCS sample at time 1005.
    * Chemistry personnel drew a post-trip RCS sample at time 1005.
* Control room operators have stabilized the unit at 547 &deg;F and normal operating pressure.
Current conditions:
 
* At time 1045, a Chemistry supervisor reports that the post-trip RCS sample total specific activity reading is greater than the 100/(E bar) limit by 28%.
Based on the current conditions, which one of the following (1) is the correct time the
LCO for Technical Specification (TS) 3.1.D, Maximum Reactor Coolant Activity, is NOT met; AND (2) the basis of the requirement to cool down the reactor to less than 500 &deg;F,
in accordance with TS 3.1.D? 


A. (1) LCO not met at 1005; (2) In the unlikely event of an assumed 30 minute radioactive release during the  
    *    Control room operators have stabilized the unit at 547 &deg;F and normal operating
design-basis S/G tube rupture, the iodine partitioning factor below this RCS  
        pressure.
temperature ensures exposure limits are not exceeded at the site boundary.  
Current conditions:
 
    *    At time 1045, a Chemistry supervisor reports that the post-trip RCS sample total
B. (1) LCO not met at 1045; (2) In the unlikely event of a design-basis S/G tube rupture, the saturation pressure  
        specific activity reading is greater than the 100/(E bar) limit by 28%.
corresponding to this RCS temperature is well below the pressure at which the  
Based on the current conditions, which one of the following (1) is the correct time the
atmospheric relief valves on the secondary side would be actuated.  
LCO for Technical Specification (TS) 3.1.D, Maximum Reactor Coolant Activity, is NOT
 
met; AND (2) the basis of the requirement to cool down the reactor to less than 500 &deg;F,
C. (1) LCO not met at 1045; (2) In the unlikely event of an assumed 30 minute radioactive release during the design-basis S/G tube rupture, the iodine partitioning factor below this RCS  
in accordance with TS 3.1.D?
temperature ensures exposure limits are not exceeded at the site boundary.
A. (1) LCO not met at 1005;
 
    (2) In the unlikely event of an assumed 30 minute radioactive release during the
D. (1) LCO not met at 1005; (2) In the unlikely event of a design-basis S/G tube rupture, the saturation pressure  
    design-basis S/G tube rupture, the iodine partitioning factor below this RCS
corresponding to this RCS temperature is well below the pressure at which the  
    temperature ensures exposure limits are not exceeded at the site boundary.
atmospheric relief valves on the secondary side would be actuated.  
B. (1) LCO not met at 1045;
 
    (2) In the unlikely event of a design-basis S/G tube rupture, the saturation pressure
 
    corresponding to this RCS temperature is well below the pressure at which the
K/A High Reactor Coolant Activity  
    atmospheric relief valves on the secondary side would be actuated.
Ability to determine and interpret the following as they apply to High Reactor Coolant  
C. (1) LCO not met at 1045;
Activity: Corrective actions required for high fission product activity in RCS.  
    (2) In the unlikely event of an assumed 30 minute radioactive release during the
(CFR: 43.5/45.13) (SRO - 3.4)  
    design-basis S/G tube rupture, the iodine partitioning factor below this RCS
 
    temperature ensures exposure limits are not exceeded at the site boundary.
D. (1) LCO not met at 1005;
    (2) In the unlikely event of a design-basis S/G tube rupture, the saturation pressure
    corresponding to this RCS temperature is well below the pressure at which the
    atmospheric relief valves on the secondary side would be actuated.
K/A
High Reactor Coolant Activity
Ability to determine and interpret the following as they apply to High Reactor Coolant
Activity: Corrective actions required for high fission product activity in RCS.
(CFR: 43.5/45.13) (SRO - 3.4)
K/A Match Analysis
K/A Match Analysis
The question requires the SRO applicant to correctly demonstrate knowledge of the  
The question requires the SRO applicant to correctly demonstrate knowledge of the
Technical Specifications for RCS activity, as well as the basis for this specification.  
Technical Specifications for RCS activity, as well as the basis for this specification.
SRO-Only Analysis
See attached SRO-only flow chart. TS Basis knowledge needed to arrive at correct


answer.
SRO-Only Analysis
See attached SRO-only flow chart.  TS Basis knowledge needed to arrive at correct 
answer.
Answer Choice Analysis
Answer Choice Analysis
A. INCORRECT. 1005 is the incorrect time, because the initial notification of the  
A. INCORRECT. 1005 is the incorrect time, because the initial notification of the
abnormality is considered the "start time" of inoperability. The second part of the answer is also incorrect; TS 3.1.D. basis states "Rupture of a steam generator tube  
abnormality is considered the "start time" of inoperability. The second part of the
would allow radionuclides in the reactor coolant to enter the secondary system. The  
answer is also incorrect; TS 3.1.D. basis states "Rupture of a steam generator tube
limiting case involves a double-ended tube rupture coincident with loss of the condenser  
would allow radionuclides in the reactor coolant to enter the secondary system. The
and release of steam from the secondary side to the atmosphere via the main steam  
limiting case involves a double-ended tube rupture coincident with loss of the condenser
safety valves or atmospheric relief valves. This is assumed to continue for 30 minutes  
and release of steam from the secondary side to the atmosphere via the main steam
in the analysis. The operator will take action to reduce the primary side temperature to  
safety valves or atmospheric relief valves. This is assumed to continue for 30 minutes
a value below that corresponding to the relief or safety valve setpoint. Once this is  
in the analysis. The operator will take action to reduce the primary side temperature to
accomplished the valves can be closed and the release terminated."   However, the  
a value below that corresponding to the relief or safety valve setpoint. Once this is
distractor is plausible, because everything associated with this specification is  
accomplished the valves can be closed and the release terminated." However, the
concerned with a release during a design basis tube rupture.  
distractor is plausible, because everything associated with this specification is
 
concerned with a release during a design basis tube rupture.
 
B. CORRECT. See above analysis. The statement about the saturation pressure and
B. CORRECT. See above analysis. The statement about the saturation pressure and  
atmospheric relief valves is basically word-for-word from the TS.
atmospheric relief valves is basically word-for-word from the TS.  
C. INCORRECT. Incorrect time, wrong reason for RCS cooldown.
 
D. INCORRECT. See above analysis.
 
C. INCORRECT. Incorrect time, wrong reason for RCS cooldown.  
 
D. INCORRECT. See above analysis.  
 
Supporting References
Supporting References
 
-SPS TS 3.1.D
-SPS TS 3.1.D  
 
References Provided to Applicant
References Provided to Applicant
 
Steam Tables
Steam Tables  
Answer: B
 
10. 010G2.4.20 12
Unit 1 initial conditions:
Answer: B  
    * Reactor power = 100%
10. 010G2.4.20 12 Unit 1 initial conditions:  
    * SGTR = 75 gpm on 1A SG
 
    * Reactor is manually tripped
  * Reactor power = 100%  
    * 1C RCP trips
* SGTR = 75 gpm on 1A SG  
  Current conditions:
* Reactor is manually tripped  
    * 1-E-3 (STEAM GENERATOR TUBE RUPTURE) is in progress
* 1C RCP trips  
    * It is determined that Pzr spray is not adequately reducing RCS pressure and the
   
        decision is made to use the PORV to reduce RCS pressure.
Current conditions:  
 
  * 1-E-3 (STEAM GENERATOR TUBE RUPTURE) is in progress  
* It is determined that Pzr spray is not adequately reducing RCS pressure and the decision is made to use the PORV to reduce RCS pressure.  
 
 
Based on the above conditions, which one of the following states: (1) the reason for minimizing the cycling of the PORV and (2) the procedure that 1-E-3 directs you to
perform if the PORV and its associated block valve fail to close?


A. (1) To prevent rupturing the PRT (2) 1-ECA 3.3 SGTR WITHOUT PRESSURIZER PRESSURE CONTROL  
Based on the above conditions, which one of the following states: (1) the reason for
 
minimizing the cycling of the PORV and (2) the procedure that 1-E-3 directs you to
B. (1) To prevent rupturing the PRT (2) 1-ECA 3.1 SGTR WITH LOSS OF REACTOR COOLANT - SUBCOOLED  
perform if the PORV and its associated block valve fail to close?
RECOVERY
A. (1) To prevent rupturing the PRT
 
    (2) 1-ECA 3.3 SGTR WITHOUT PRESSURIZER PRESSURE CONTROL
C. (1) To prevent the Tube rupture from degrading (2) 1-ECA 3.3 SGTR WITHOUT PRESSURIZER PRESSURE CONTROL  
B. (1) To prevent rupturing the PRT
 
    (2) 1-ECA 3.1 SGTR WITH LOSS OF REACTOR COOLANT - SUBCOOLED
D. (1) To prevent the Tube rupture from degrading (2) 1-ECA 3.1 SGTR WITH LOSS OF REACTOR COOLANT - SUBCOOLED  
    RECOVERY
RECOVERY
C. (1) To prevent the Tube rupture from degrading
 
    (2) 1-ECA 3.3 SGTR WITHOUT PRESSURIZER PRESSURE CONTROL
  K/A Pressurizer Pressure Control: Knowledge of the operational implications of EOP  
D. (1) To prevent the Tube rupture from degrading
warnings, cautions, and notes.  
    (2) 1-ECA 3.1 SGTR WITH LOSS OF REACTOR COOLANT - SUBCOOLED
 
    RECOVERY
K/A
Pressurizer Pressure Control: Knowledge of the operational implications of EOP
warnings, cautions, and notes.
K/A Match Analysis
K/A Match Analysis
Requires knowledge of EOP Cautions.  
Requires knowledge of EOP Cautions.
 
SRO-Only Analysis
SRO-Only Analysis
Requires detailed knowledge of EOP steps having to do with securing PORV use when  
Requires detailed knowledge of EOP steps having to do with securing PORV use when
depressurizing the RCS.  
depressurizing the RCS.
 
Answer Choice Analysis
Answer Choice Analysis
A Incorrect: 1
A Incorrect: 1st part is correct. 2nd part is plausible because it is criteria for closing
st part is correct. 2
              the PORV if Pzr level is > 22%.
nd part is plausible because it is criteria for closing the PORV if Pzr level is > 22%.
B Correct:   The PORV relieves to the PRT so using the PORV will eventually cause
              the PRT rupture disk to rupture. Criteria for securing from using the
B Correct: The PORV relieves to the PRT so using the PORV will eventually cause the PRT rupture disk to rupture. Criteria for securing from using the  
              PORV are:
PORV are:   Pzr level>69%   RCS subcooling < 30  
              Pzr level>69%
0 F  RCS press < Ruptured SG press AND Pzr level > 22%  
              RCS subcooling < 30 0F
              RCS press < Ruptured SG press AND Pzr level > 22%
C Incorrect: 1st part is plausible because the PORVs have failed to reseat (TMI) which
              constitutes a SBLOCA. 2nd part is plausible because it is criteria for
              closing the PORV if Pzr level is > 22%.


C Incorrect: 1
D Incorrect:     1st part is plausible because the PORVs have failed to reseat (TMI)
st part is plausible because the PORVs have failed to reseat (TMI) which constitutes a SBLOCA.  2
which
nd part is plausible because it is criteria for closing the PORV if Pzr level is > 22%.
                        constitutes a SBLOCA. 2nd part is correct.
 
D Incorrect:  1
st part is plausible because the PORVs have failed to reseat (TMI) which                      constitutes a SBLOCA. 2
nd part is correct.  
Supporting References
Supporting References
1-E-3 Steam Generator Tube Rupture. ND-95.3-LP-13 Obj A & B  
1-E-3 Steam Generator Tube Rupture. ND-95.3-LP-13 Obj A & B
 
References Provided to Applicant
References Provided to Applicant
none  
none
Answer: B
Answer: B  
11. 015/17AG2.2.22 1
11. 015/17AG2.2.22 1 Initial plant conditions on Unit 2 are as follows:  
Initial plant conditions on Unit 2 are as follows:
* A power increase is in progress following reactor startup.  
    *   A power increase is in progress following reactor startup.
* Reactor power is at 8%.  
    *   Reactor power is at 8%.
* Pressurizer Spray valve PCV-455A cannot be opened.  
    *   Pressurizer Spray valve PCV-455A cannot be opened.
* All three RCPs are operating.  
    *   All three RCPs are operating.
Current plant conditions on Unit 2 are as follows:
Current plant conditions on Unit 2 are as follows:  
    *   RCP C trips on ground overcurrent.
* RCP 'C' trips on ground overcurrent.  
Based on the above conditions, which one of the following describes whether action
Based on the above conditions, which one of the following describes whether action statements of the following LCOs are required to be performed:  
statements of the following LCOs are required to be performed:
* LCO 3.1.A.4, Reactor Coolant Loops  
    *   LCO 3.1.A.4, Reactor Coolant Loops
* LCO 3.1.A.5, Pressurizer  
    *   LCO 3.1.A.5, Pressurizer
Action statement(s) of
Action statement(s) of- A. LCO 3.1.A.4 is/are required. LCO 3.1.A.5 is/are NOT required.  
A. LCO 3.1.A.4 is/are required.
    LCO 3.1.A.5 is/are NOT required.
B. LCO 3.1.A.4 is/are NOT required.
    LCO 3.1.A.5 is required.
C. both LCO 3.1.A.4 and LCO 3.1.A.5 are required.
D. neither LCO 3.1.A.4 nor LCO 3.1.A.5 are required.
K/A
RCP Malfunctions


B. LCO 3.1.A.4 is/are NOT required.  LCO 3.1.A.5 is required.
Knowledge of limiting conditions for operations and safety limits as it relates RCP
 
Malfunctions.
C. both LCO 3.1.A.4 and LCO 3.1.A.5 are required.
D. neither LCO 3.1.A.4 nor LCO 3.1.A.5 are required.
 
K/A RCP Malfunctions 
Knowledge of limiting conditions for operations and safety limits as it relates RCP Malfunctions.  
 
K/A Match Analysis
K/A Match Analysis
Applicant must recognize that loss of RCP 'C' will require entry into both LCO 3.1.A.4.  
Applicant must recognize that loss of RCP C will require entry into both LCO 3.1.A.4.
and 3.1.A.5.  
and 3.1.A.5.
 
SRO-Only Analysis
SRO-Only Analysis
The question requires a knowledge of the T.S. bases associated with LCO 3.1.A.4  
The question requires a knowledge of the T.S. bases associated with LCO 3.1.A.4
concerning what constitutes an in-service reactor coolant loop to determine whether  
concerning what constitutes an in-service reactor coolant loop to determine whether
actions from LCO 3.1.A.4 are required.  
actions from LCO 3.1.A.4 are required.
 
Answer Choice Analysis
Answer Choice Analysis
A. In-Correct but plausible since LCO 3.1.A.4 would be entered given that LCO       3.1.A.4.b. states, "POWER OPERATION with less than three loops in service
A. In-Correct but plausible since LCO 3.1.A.4 would be entered given that LCO
is     prohibited.". However, LCO 3.1.A.5 would also be entered since LCO 3.1.A.5.a      states, "The reactor shall be maintained subcritical by at least 1% until the steam      bubble is established and the necessary sprays and at least 125 KW of heaters      are operable." With PCV-455A inoperable, PCV-455B becomes inoperable once      RCP 'C' trips. B. In-Correct but plausible if the applicant believes that a running RCP is not required  
    3.1.A.4.b. states, POWER OPERATION with less than three loops in service is
     for an RCS loop to be considered in service. The second half of the answer is      correct. LCO 3.1.A.5 would be entered since LCO 3.1.A.5.a states, "The reactor      shall be maintained subcritical by at least 1% until the steam bubble is established  
     prohibited.. However, LCO 3.1.A.5 would also be entered since LCO 3.1.A.5.a
     and the necessary sprays and at least 125 KW of heaters are operable."
     states, The reactor shall be maintained subcritical by at least 1% until the steam
C. Correct -. Both LCO 3.1.A.4 and LCO 3.1.A.5 would be entered. See previous      distractor discussions for justification.
     bubble is established and the necessary sprays and at least 125 KW of heaters
D. In-Correct but plausible if the applicant believes that a running RCP is not required      for an RCS loop to be considered in service AND does not recognized that both  
     are operable. With PCV-455A inoperable, PCV-455B becomes inoperable once
     Pressurizer Spray valves are inoperable once RCP 'C' trips.  
     RCP C trips.
 
B. In-Correct but plausible if the applicant believes that a running RCP is not required
     for an RCS loop to be considered in service. The second half of the answer is
NOTE TO LICENSEE: The correct answer was based on discussions with facility SME. The Technical Specifications bases do not provide a specific discussion with regards to what constitutes a loop being in service per LCO 3.1.A.4. Please provide documentation as to what constitutes a loop being in service.
     correct. LCO 3.1.A.5 would be entered since LCO 3.1.A.5.a states, The reactor
Also, neither LCO 3.1.A.5 nor its basis states that sprays have an impact on  
     shall be maintained subcritical by at least 1% until the steam bubble is established
Technical Specifications once the reactor is above 1% subcritical. Please provide  
     and the necessary sprays and at least 125 KW of heaters are operable.
documentation for pressurizer operability when sprays are unavailable once a  
C. Correct -. Both LCO 3.1.A.4 and LCO 3.1.A.5 would be entered. See previous
steam bubble is established and power is above 1% subcritical.  
     distractor discussions for justification.
D. In-Correct but plausible if the applicant believes that a running RCP is not required
     for an RCS loop to be considered in service AND does not recognized that both
     Pressurizer Spray valves are inoperable once RCP C trips.
NOTE TO LICENSEE: The correct answer was based on discussions with facility
SME. The Technical Specifications bases do not provide a specific discussion
with regards to what constitutes a loop being in service per LCO 3.1.A.4. Please
provide documentation as to what constitutes a loop being in service.
Also, neither LCO 3.1.A.5 nor its basis states that sprays have an impact on
Technical Specifications once the reactor is above 1% subcritical. Please provide
documentation for pressurizer operability when sprays are unavailable once a
steam bubble is established and power is above 1% subcritical.
Supporting References
Supporting References
Technical Specification 3.1.A  
Technical Specification 3.1.A
Technical Specification 3.0.1  
Technical Specification 3.0.1
ND-88.1-LP-9, Technical Specifications Overview, Rev. 16, Obj. G  
ND-88.1-LP-9, Technical Specifications Overview, Rev. 16, Obj. G
 
References Provided to Applicant
References Provided to Applicant
 
none 
Answer: C
12.  025AA2.05 2 Unit 1 initial conditions:
Time = 0800
Plant was on RHR following shutdown for refueling
SGs are not available  RCS temperature = 190
0F stable  RHR flow = 2200 gpm
RCS level = 10 feet decreasing
AP/27 (LOSS OF DECAY HEAT REMOVAL CAPABILITY) has been initiated
 
Current plant conditions:
Time = 0825
1 CHG pump was started for RCS fill
          RHR pumps have been secured
          RCS level = 11.5 ft increasing            RCS temperature = 205
0F increasing
Based on the above conditions: (1) Classify the event using the Emergency Plan and
(2) Once RHR is restored, state the maximum cooldown rate allowed per 1-AP-27?
(Reference Provided)


A. (1) Alert (2) 25 0F/Hr B. (1) Alert (2) 50 0F/Hr C. (1) Site Area Emergency (2) 50 0F/Hr D. (1) Site Area Emergency (2) 25 0F/Hr  
none
K/A Loss of RHR: Ability to determine and interpret the following as they apply to the Loss of  
Answer: C
Residual Heat Removal System: Limitations on LPI flow and temperature rates of  
12. 025AA2.05 2
change.  
Unit 1 initial conditions:
        Time = 0800
        Plant was on RHR following shutdown for refueling
        SGs are not available
        RCS temperature = 190 0F stable
        RHR flow = 2200 gpm
        RCS level = 10 feet decreasing
        AP/27 (LOSS OF DECAY HEAT REMOVAL CAPABILITY) has been initiated
Current plant conditions:
        Time = 0825
        1 CHG pump was started for RCS fill
            RHR pumps have been secured
            RCS level = 11.5 ft increasing
            RCS temperature = 205 0F increasing
Based on the above conditions: (1) Classify the event using the Emergency Plan and
(2) Once RHR is restored, state the maximum cooldown rate allowed per 1-AP-27?
(Reference Provided)
A. (1) Alert
    (2) 25 0F/Hr
B. (1) Alert
    (2) 50 0F/Hr
C. (1) Site Area Emergency
    (2) 50 0F/Hr
D. (1) Site Area Emergency
    (2) 25 0F/Hr
K/A
Loss of RHR: Ability to determine and interpret the following as they apply to the Loss of
Residual Heat Removal System: Limitations on LPI flow and temperature rates of
change.
K/A Match Analysis
K/A Match Analysis
Requires knowledge of limits on cooldown rate during loss
Requires knowledge of limits on cooldown rate during loss of decay heat removal and
of decay heat removal and
recovery.  Requires the ability to determine the emergency classification based on the reduction
and eventual loss of RHR flow due to invetory loss and requires knowledge of plant
cooldown limits once RHR is restored.


recovery.
Requires the ability to determine the emergency classification based on the reduction
and eventual loss of RHR flow due to invetory loss and requires knowledge of plant
cooldown limits once RHR is restored.
SRO-Only Analysis
SRO-Only Analysis
Requires in depth knowledge of administrative procedures that specify hierarchy,  
Requires in depth knowledge of administrative procedures that specify hierarchy,
implementation, and/or coordination of plant normal, abnormal, and emergency  
implementation, and/or coordination of plant normal, abnormal, and emergency
procedures.  
procedures.
 
Answer Choice Analysis
Answer Choice Analysis
A. Incorrect: 1
A. Incorrect: 1st part is incorrect because CS2 (Loss of Reactor Vessel inventory
st part is incorrect because CS2 (Loss of Reactor Vessel inventory     affecting core decay heat removal capability) existed = SAE. 1st part is plausible  
      affecting core decay heat removal capability) existed = SAE. 1st part is plausible
    because CA 2 (Loss of RCS inventory) and CA3 (Inability to maintain plant in cold     shutdown with irradiated fuel in the Reactor Vessel) apply. 2
      because CA 2 (Loss of RCS inventory) and CA3 (Inability to maintain plant in cold
nd part is incorrect     because 50  
      shutdown with irradiated fuel in the Reactor Vessel) apply. 2nd part is incorrect
0F/Hr is the rate used for recovery once RHR is re-established. It is     plausible because 25  
      because 50 0F/Hr is the rate used for recovery once RHR is re-established. It is
0F/Hr is the cooldown rate for natural circulation cooldown in     Attachment 4 of AP/27. B. Incorrect: 1
      plausible because 25 0F/Hr is the cooldown rate for natural circulation cooldown in
st part is incorrect because CS2 (Loss of Reactor Vessel inventory     affecting core decay heat removal capability) existed = SAE. 1st part is plausible  
      Attachment 4 of AP/27.
    because CA 2 (Loss of RCS inventory) and CA3 (Inability to maintain plant in cold     shutdown with irradiated fuel in the Reactor Vessel) apply. 2
B. Incorrect: 1st part is incorrect because CS2 (Loss of Reactor Vessel inventory
nd part is correct per     1AP/27 , Step 27. C. Correct: 1
      affecting core decay heat removal capability) existed = SAE. 1st part is plausible
st part is incorrect because CS2 (Loss of Reactor Vessel inventory     affecting core decay heat removal capability) existed = SAE. 2
      because CA 2 (Loss of RCS inventory) and CA3 (Inability to maintain plant in cold
nd part is correct per  
      shutdown with irradiated fuel in the Reactor Vessel) apply. 2nd part is correct per
    1AP/27 , Step 27. D. Incorrect: 1
      1AP/27 , Step 27.
st part is incorrect because CS2 (Loss of Reactor Vessel inventory     affecting core decay heat removal capability) existed = SAE.   2
C. Correct: 1st part is incorrect because CS2 (Loss of Reactor Vessel inventory
nd part is incorrect     because 50  
      affecting core decay heat removal capability) existed = SAE. 2nd part is correct
0F/Hr is the rate used for recovery once RHR is re-established. It is     plausible because 25  
per
0F/Hr is the cooldown rate for natural circulation cooldown in     Attachment 4 of AP/27.  
      1AP/27 , Step 27.
 
D. Incorrect: 1st part is incorrect because CS2 (Loss of Reactor Vessel inventory
      affecting core decay heat removal capability) existed = SAE. 2nd part is incorrect
      because 50 0F/Hr is the rate used for recovery once RHR is re-established. It is
      plausible because 25 0F/Hr is the cooldown rate for natural circulation cooldown in
      Attachment 4 of AP/27.
Supporting References
Supporting References
Surry Emergency Plan AP/27 (LOSS OF DECAY HEAT REMOVAL CAPABILITY)  
Surry Emergency Plan         AP/27 (LOSS OF DECAY HEAT REMOVAL CAPABILITY)
References Provided to Applicant
References Provided to Applicant
Emergency Plan  
Emergency Plan
 
Answer: C
13. 027AA2.15 4
Answer: C  
Unit 1 initial conditions:
13. 027AA2.15 4 Unit 1 initial conditions:  
        Time = 1000
Time = 1000  
        Reactor power = 100%
Reactor power = 100%
PORV-1455C indicates open  Both Pzr Spray valves indicate open
RCS Pressure = 2200 psig decreasing 
AP/31 (Increasing or Decreasing RCS Pressure) initiated
 
Current conditions:
Time = 1001
Reactor Power = 97%
RCS Pressure = 2100 psig increasing
          Spray valve in MANUAL and closed
          PORV- 1455C in MANUAL and closed
Based on the above conditions, which one of the following correctly states: (1) the  component that failed high and (2) the status of PORV 1455C operability per Technical Specifications?
 
A. (1) P-444 (2) PORV is considered OPERABLE
 
B. (1) P-444 (2) PORV is NOT considered OPERABLE
 
C. (1) P-445 (2) PORV is considered OPERABLE 
 
D. (1) P-445 (2) PORV is NOT considered OPERABLE
 
 
K/A Pressurizer Pressure Control System Malfunction .  Ability to determine and interpret
the following as they apply to the Pressurizer Pressure Control Malfunctions: Actions to
be taken if PZR pressure instrument fails high


        PORV-1455C indicates open
        Both Pzr Spray valves indicate open
        RCS Pressure = 2200 psig decreasing
        AP/31 (Increasing or Decreasing RCS Pressure) initiated
Current conditions:
        Time = 1001
        Reactor Power = 97%
        RCS Pressure = 2100 psig increasing
            Spray valve in MANUAL and closed
            PORV- 1455C in MANUAL and closed
Based on the above conditions, which one of the following correctly states: (1) the
component that failed high and (2) the status of PORV 1455C operability per Technical
Specifications?
A. (1) P-444
    (2) PORV is considered OPERABLE
B. (1) P-444
    (2) PORV is NOT considered OPERABLE
C. (1) P-445
    (2) PORV is considered OPERABLE
D. (1) P-445
    (2) PORV is NOT considered OPERABLE
K/A
Pressurizer Pressure Control System Malfunction . Ability to determine and interpret
the following as they apply to the Pressurizer Pressure Control Malfunctions: Actions to
be taken if PZR pressure instrument fails high
K/A Match Analysis
K/A Match Analysis
Requires knowledge of how instrument failure affects the Pzr pressure control system  
Requires knowledge of how instrument failure affects the Pzr pressure control system
and actions to mitigate the event.  
and actions to mitigate the event.
 
SRO-Only Analysis
SRO-Only Analysis
Requires ability to interpret plant conditions and select appropriate AP/EOP to mitigate the event.  
Requires ability to interpret plant conditions and select appropriate AP/EOP to mitigate
the event.
Answer Choice Analysis
A. Incorrect. 1st part is correct. 2nd part is incorrect because the PORV is not able
to
    perform its Normal Function at power (prevent challenging the code safetys). 2nd


     part is plausible because it is still operable in MANUAL.
Answer Choice Analysis
B. Correct. Indications are indicative of transmitter P-444 failed high. TS directs the
A.  Incorrect.  1
     Block Valve for that PORV to be closed which renders the PORV inoperable. If
st part is correct.  2
the
nd part is incorrect because the PORV is not able to      perform its Normal Function at power (prevent challenging the code safetys).  2
     PORV was still operable, this action would not be required. In the TS Bases 3.1.5c,
nd 
     it states this action is taken when the PORV is Inoperable.
     part is plausible because it is still operable in MANUAL. B. Correct. Indications are indicative of transmitter P-444 failed high. TS directs the  
C. Incorrect 1st part is incorrect because this transmitter does not control all of the
     Block Valve for that PORV to be closed which renders the PORV inoperable. If  
     functions to create the parameters listed. It is plausible because P-445 controls a
the  
     PORV and will cause RCS pressure to decrease. 2nd part is incorrect because
     PORV was still operable, this action would not be required. In the TS Bases 3.1.5c,      it states this action is taken when the PORV is Inoperable. C. Incorrect 1
the
st part is incorrect because this transmitter does not control all of the      functions to create the parameters listed. It is plausible because P-445 controls a      PORV and will cause RCS pressure to decrease. 2
     PORV is not able to perform its Normal Function at power (prevent challenging the
nd part is incorrect because the  
     code safetys). 2nd part is plausible because it is still operable in MANUAL.
     PORV is not able to perform its Normal Function at power (prevent challenging the      code safetys). 2
D. Incorrect: 1st part is incorrect because this transmitter does not control all of the
nd part is plausible because it is still operable in MANUAL. D. Incorrect: 1
     functions to create the parameters listed. It is plausible because P-445 controls a
st part is incorrect because this transmitter does not control all of the      functions to create the parameters listed. It is plausible because P-445 controls a      PORV and will cause RCS pressure to decrease. 2
     PORV and will cause RCS pressure to decrease. 2nd part is incorrect because
nd part is incorrect because the  
the
     PORV is not able to perform its Normal Function at power (prevent challenging the      code safetys). 2
     PORV is not able to perform its Normal Function at power (prevent challenging the
nd part is correct.  
     code safetys). 2nd part is correct.
Supporting References
Supporting References
TS Section 3.1.4a  
TS Section 3.1.4a
ND-93.3-LP5, Pzr Press Control pg 11 Obj: C  
ND-93.3-LP5, Pzr Press Control pg 11 Obj: C
 
References Provided to Applicant
References Provided to Applicant
none  
none
Licensee to determine operability of PORV
Licensee to determine operability of PORV  
Answer: B
Answer: B  
14. 035A2.01 17
14. 035A2.01 17 Unit 1 initial conditions:  
Unit 1 initial conditions:
Reactor power = 100%   Main Steam Line Break inside containment occurs on the 1B SG   Maximum containment pressure reached = 4 psig  
        Reactor power = 100%
1-E-2 FAULTED STEAM GENERATOR ISOLATION is in progress  
        Main Steam Line Break inside containment occurs on the 1B SG
 
        Maximum containment pressure reached = 4 psig
        1-E-2 FAULTED STEAM GENERATOR ISOLATION is in progress
Current plant conditions:  
Current plant conditions:
RCS Pressure = 1750 psig increasing RCS Subcooling = 95  
        RCS Pressure = 1750 psig increasing
0F increasing A SG NR level = 15% increasing  
        RCS Subcooling = 95 0F increasing
B SG WR level = 5% stable  
        A SG NR level = 15% increasing
C SG NR level = 18% increasing  
        B SG WR level = 5% stable
Pzr level = 35% increasing  
        C SG NR level = 18% increasing
 
        Pzr level = 35% increasing
(1) Which ONE of the following parts of the curve in TS Figure 3.8-1 is based on the
(1) Which ONE of the following parts of the curve in TS Figure 3.8-1 is based on the  
peak calculated pressure criteria from this event and (2) based on the current plant
peak calculated pressure criteria from this event and (2) based on the current plant
conditions, which procedure will 1E2 direct you to GO TO?
(Reference provided)
 
A. (1) Horizontal upper limit line (2) 1-ES-1.1 SI TERMINATION
B. (1) Horizontal upper limit line (2) 1-E-1 LOSS OF REACTOR OR SECONDARY COOLANT
 
C. (1) Sloped line from 70-100
0F SW temp (2) 1-ES-1.1 SI TERMINATION
D. (1) Sloped line from 70-100
0F SW temp (2) 1-E-1 LOSS OF REACTOR OR SECONDARY COOLANT
 
 
K/A Steam Generator:  Ability to (a) predict the impacts of the following malfunctions or
operations on the S/GS; and (b) based on those predictions, use procedures to correct,
control, or mitigate the consequences of those malfunctions or
operations:  Faulted or Ruptured S/Gs.


   
  conditions, which procedure will 1E2 direct you to GO TO?
(Reference provided)
A. (1) Horizontal upper limit line    (2) 1-ES-1.1 SI TERMINATION
B. (1) Horizontal upper limit line
    (2) 1-E-1 LOSS OF REACTOR OR SECONDARY COOLANT
C. (1) Sloped line from 70-100 0F SW temp (2) 1-ES-1.1 SI TERMINATION
D. (1) Sloped line from 70-100 0F SW temp
    (2) 1-E-1 LOSS OF REACTOR OR SECONDARY COOLANT
K/A
Steam Generator: Ability to (a) predict the impacts of the following malfunctions or
operations on the S/GS; and (b) based on those predictions, use procedures to correct,
control, or mitigate the consequences of those malfunctions or
operations: Faulted or Ruptured S/Gs.
K/A Match Analysis
K/A Match Analysis
Requires knowledge of procedures used to mitigate a Faulted SG.  
Requires knowledge of procedures used to mitigate a Faulted SG.
 
SRO-Only Analysis
SRO-Only Analysis
Requires knowledge of Tech Spec bases that is required to analyze Tech Spec required  
Requires knowledge of Tech Spec bases that is required to analyze Tech Spec required
actions and terminology.  
actions and terminology.
Answer Choice Analysis
A. Correct: 1st part is correct per TS 3.8-4. 2nd part is correct per step 8 of 1E-2
    FAULTED STEAM GENERATOR ISOLATION.
B. Incorrect: 1st part is correct per TS 3.8-4. 2nd part is incorrect because per 1E-2
    Step 8 you meet the criteria to GO TO 1ES1 SI Termination. Plausible because if
      the Applicant thinks that Adverse Containment Conditions exist or if they did exist
    (> 5 psig), 1E-2 would direct you to GO TO 1E-1 LOSS OF REACTOR OR
    SECONDARY COOLANT.
C. Incorrect: 1st part is incorrect because it is based on LOCA depressurization
    criteria. 1st part is plausible because it is an upper limit on the curve. 2nd part is
    correct per step 8 of 1E-2 FAULTED STEAM GENERATOR ISOLATION..
D. Incorrect: 1st part is incorrect because it is based on LOCA depressurization
    criteria. 1st part is plausible because it is an upper limit on the curve. 2nd part
is
    incorrect because per 1E-2 Step 8 you meet the criteria to GO TO 1ES1 SI
    Termination. Plausible because if the Applicant thinks that Adverse Containment
    Conditions exist or if they did exist (> 5 psig), 1E-2 would direct you to GO TO


     1E-1 LOSS OF REACTOR OR SECONDARY COOLANT.
Answer Choice Analysis
A.  Correct: 1
st part is correct per TS 3.8-4.  2
nd part is correct per step 8 of 1E-2      FAULTED STEAM GENERATOR ISOLATION. B.  Incorrect: 1
st part is correct per TS 3.8-4.  2
nd part is incorrect because per 1E-2      Step 8 you meet the criteria to GO TO 1ES1 SI Termination.  Plausible because if
      the Applicant thinks that Adverse Containment Conditions exist or if they did exist
    (> 5 psig), 1E-2 would direct you to GO TO 1E-1 LOSS OF REACTOR OR      SECONDARY COOLANT.  C.  Incorrect: 1
st part is incorrect because it is based on LOCA depressurization      criteria.  1
st part is plausible because it is an upper limit on the curve.  2
nd part is      correct per step 8 of 1E-2 FAULTED STEAM GENERATOR ISOLATION.. D.  Incorrect: 1
st part is incorrect because it is based on LOCA depressurization      criteria.  1
st part is plausible because it is an upper limit on the curve.  2
nd part is
    incorrect because per 1E-2 Step 8 you meet the criteria to GO TO 1ES1 SI
    Termination.  Plausible because if the Applicant thinks that Adverse Containment
    Conditions exist or if they did exist (> 5 psig), 1E-2 would direct you to GO TO 
     1E-1 LOSS OF REACTOR OR SECONDARY COOLANT.  
Supporting References
Supporting References
1-E-2  
1-E-2
ND-95.3-LP-12, E-2 Obj: A  
ND-95.3-LP-12, E-2 Obj: A
TS 3.8 Containment  
TS 3.8 Containment
ND-95.3-LP-3 E-0, pg 8 Adverse Containment Criteria  
ND-95.3-LP-3 E-0, pg 8 Adverse Containment Criteria
 
References Provided to Applicant
References Provided to Applicant
TS Figure 3.8-1  
TS Figure 3.8-1
 
Answer: B
15. 051G2.4.11 9
Answer: B  
Unit 1 initial conditions:
15. 051G2.4.11 9 Unit 1 initial conditions:  
            Time = 1500
          Time = 1500  
        Reactor power = 100 %
Reactor power = 100 %
            A loud explosion is heard from the main turbine area (Security reports that
          A loud explosion is heard from the main turbine area (Security reports that
            no suspicious activity noted)
          no suspicious activity noted)  
        Condenser Vacuum = 27" Hg decreasing
Condenser Vacuum = 27" Hg decreasing  
        1AP/14 (LOSS OF MAIN CONDENSER VACUUM) initiated
1AP/14 (LOSS OF MAIN CONDENSER VACUUM) initiated  
Current plant conditions:
 
        Time = 1510
        Reactor Power = 60%
Current plant conditions:  
            Condenser vacuum = 25" Hg decreasing
Time = 1510  
            An operator reports that there was insulation on fire around a Reheat Stop
Reactor Power = 60%  
            valve. The fire is out but he hears a hissing noise
          Condenser vacuum = 25" Hg decreasing  
Based on current plant conditions, which one of the following correctly states: (1) the
          An operator reports that there was insulation on fire around a Reheat Stop  
procedure that will be used to continue the load reduction and (2) the e-plan
          valve. The fire is out but he hears a hissing noise
classification?
 
(Reference provided)
A. (1) 1AP/14 Attachment 2 RAMPING AT GREATER THAN OR EQUAL TO 1%/MIN
Based on current plant conditions, which one of the following correctly states: (1) the  
  (2) UNUSUAL EVENT
procedure that will be used to continue the load reduction and (2) the e-plan  
B. (1) 1AP/14 Attachment 2 RAMPING AT GREATER THAN OR EQUAL TO 1%/MIN
classification?  
  (2) ALERT
 
C. (1) 1AP/23 RAPID LOAD REDUCTION
  (2) UNUSUAL EVENT
(Reference provided)  
D. (1) 1AP/23 RAPID LOAD REDUCTION
 
  (2) ALERT
A. (1) 1AP/14 Attachment 2 RAMPING AT GREATER THAN OR EQUAL TO 1%/MIN (2) UNUSUAL EVENT  
 
B. (1) 1AP/14 Attachment 2 RAMPING AT GREATER THAN OR EQUAL TO 1%/MIN (2) ALERT  
 
C. (1) 1AP/23 RAPID LOAD REDUCTION (2) UNUSUAL EVENT  
 
D. (1) 1AP/23 RAPID LOAD REDUCTION (2) ALERT  
 
 
K/A Loss of Condenser Vacuum:  Knowledge of abnormal condition procedures.


K/A
Loss of Condenser Vacuum: Knowledge of abnormal condition procedures.
K/A Match Analysis
K/A Match Analysis
Requires knowledge of abnormal procedures.  
Requires knowledge of abnormal procedures.
 
SRO-Only Analysis
SRO-Only Analysis
Requires ability to assess plant conditins and then prescribing a procedure or section of a procedure to mitigate, recover or with which to proceed.  
Requires ability to assess plant conditins and then prescribing a procedure or section of
 
a procedure to mitigate, recover or with which to proceed.
Answer Choice Analysis
Answer Choice Analysis
A. Incorrect: 1
A. Incorrect: 1st part incorrect because in attachment 2 of AP14 it states that if power
st part incorrect because in attachment 2 of AP14 it states that if power      decreases to 60% and further power reduction is anticipated, THEN initiate AP/23.
     decreases to 60% and further power reduction is anticipated, THEN initiate AP/23.
     1 st part is plausible because AP/14 Attachment 2 is used for the power reduction to      this point. 2
     1st part is plausible because AP/14 Attachment 2 is used for the power reduction
nd part is correct based on Fire/Explosion in the protected area      boundary. B. Incorrect: 1
to
st part incorrect because in attachment 2 of AP14 it states that if power      decreases to 60% and further power reduction is anticipated, THEN initiate AP/23.
       this point. 2nd part is correct based on Fire/Explosion in the protected area
     1 st part is plausible because AP/14 Attachment 2 is used for the power reduction to      this point. 2
     boundary.
nd part is plausible because it is a fire affecting a normal shutdown       (the condenser) but incorrect because the condenser is not required to establish or  
B. Incorrect: 1st part incorrect because in attachment 2 of AP14 it states that if power
       maintain safe shutdown. C. Correct: 1
     decreases to 60% and further power reduction is anticipated, THEN initiate AP/23.
st part is correct in that in attachment 2 of AP14 it states that if power      decreases to 60% and further power reduction is anticipated, THEN initiate AP/23.  
     1st part is plausible because AP/14 Attachment 2 is used for the power reduction
       2 nd part is correct based on Fire/Explosion in the protected area boundary. D. Incorrect: 1
to
st part is correct in that in attachment 2 of AP14 it states that if power      decreases to 60% and further power reduction is anticipated, THEN initiate AP/23.  
       this point. 2nd part is plausible because it is a fire affecting a normal shutdown
     2 nd part is plausible because it is a fire affecting a normal shutdown       (the condenser) but incorrect because the condenser is not required to establish or  
    (the condenser) but incorrect because the condenser is not required to establish or
       maintain safe shutdown.  
       maintain safe shutdown.
 
C. Correct: 1st part is correct in that in attachment 2 of AP14 it states that if power
     decreases to 60% and further power reduction is anticipated, THEN initiate AP/23.
       2nd part is correct based on Fire/Explosion in the protected area boundary.
D. Incorrect: 1st part is correct in that in attachment 2 of AP14 it states that if power
     decreases to 60% and further power reduction is anticipated, THEN initiate AP/23.
     2nd part is plausible because it is a fire affecting a normal shutdown
    (the condenser) but incorrect because the condenser is not required to establish or
       maintain safe shutdown.
Supporting References
Supporting References
AP/14 LOSS OF MAIN CONDENSER VACUUM.   Emergency Plan  
AP/14 LOSS OF MAIN CONDENSER VACUUM.
ND-95.1-LP-6 Obj: B  
Emergency Plan
 
ND-95.1-LP-6 Obj: B
References Provided to Applicant
References Provided to Applicant
Emergency Plan SEP
Emergency Plan SEP
 
Licensee to determine how much of SEP to be provided.
Answer: C
Licensee to determine how much of SEP to be provided.  
Answer: C
16.  059G2.4.14 14 Unit 1 initial conditions:
Reactor power = 100%
          Loss of offsite power occurs
          Reactor trip
          Both EDGs start but both output breakers fail to close
          TD AFW pump fails to start
          1-ECA-0.0 LOSS OF ALL AC POWER has been initiated
 
Based on the above conditions, which one of the following correctly states (1) the EOP
that will direct supplying AFW to the SG's and (2) whether the initial conditions coincide with the conditions for the loss of auxiliary feedwater design basis accident as stated in
Tech Spec Bases 3.6, TURBINE CYCLE?
 
A. (1) 1-ECA-0.0 before directing emergency buses to be energized (2) No
B. (1) 1-FR-H.1 RESPONSE TO LOSS OF SECONDARY HEAT SINK after      emergency busses are energuzed
(2) No
C. (1) 1-ECA-0.0 before directing emergency buses to be energized (2) Yes
D. (1) 1-FR-H.1 RESPONSE TO LOSS OF SECONDARY HEAT SINK after      emergency busses are energuzed
(2) Yes
 
K/A Main Feedwater:  Knowledge of general guidelines for EOP usage.


   
16. 059G2.4.14 14
  Unit 1 initial conditions:
        Reactor power = 100%
              Loss of offsite power occurs
              Reactor trip
              Both EDGs start but both output breakers fail to close
              TD AFW pump fails to start
              1-ECA-0.0 LOSS OF ALL AC POWER has been initiated
Based on the above conditions, which one of the following correctly states (1) the EOP
that will direct supplying AFW to the SG's and (2) whether the initial conditions coincide
with the conditions for the loss of auxiliary feedwater design basis accident as stated in
Tech Spec Bases 3.6, TURBINE CYCLE?
A. (1) 1-ECA-0.0 before directing emergency buses to be energized
    (2) No
B. (1) 1-FR-H.1 RESPONSE TO LOSS OF SECONDARY HEAT SINK after
            emergency busses are energuzed
    (2) No
C. (1) 1-ECA-0.0 before directing emergency buses to be energized
    (2) Yes
D. (1) 1-FR-H.1 RESPONSE TO LOSS OF SECONDARY HEAT SINK after
            emergency busses are energuzed
    (2) Yes
K/A
Main Feedwater: Knowledge of general guidelines for EOP usage.
K/A Match Analysis
K/A Match Analysis
Requires knowledge of how the EOP directs feedwater restoration after a loss of all  
Requires knowledge of how the EOP directs feedwater restoration after a loss of all
feedwater.  
feedwater.
 
SRO-Only Analysis
SRO-Only Analysis
Requires detailed knowledge of diagnostic steps and decision points in the EOPs that  
Requires detailed knowledge of diagnostic steps and decision points in the EOPs that
involve transitions to event specific sub-procedures or emergency contingency procedures. This beyond knowing CSF path selection.  
involve transitions to event specific sub-procedures or emergency contingency
 
procedures. This beyond knowing CSF path selection.
Answer Choice Analysis
Answer Choice Analysis
A. Correct: 1-ECA-0.0 will direct getting AFW flow to the SGs after verifying Rx and       Turbine trip. TS design bases accident for AFW is a loss of Main Feedwter with  
A. Correct: 1-ECA-0.0 will direct getting AFW flow to the SGs after verifying Rx and
On  
      Turbine trip. TS design bases accident for AFW is a loss of Main Feedwter with
      Site power (RCP's running)
On
B.  Incorrect: 1
      Site power (RCP's running)
st part is incorrect because ECA-0.0 is a higher priority section of the      EOP and it directs restoration fo AFW.  1
st part is plausible because it will address      the loss of feedwater after ECA-0.0 is exited.  2
nd part is correct. C.  Incorrect: 1
st part is correct.  2
nd part is incorrect because TS design bases      accidtne for AFW is a loss of Main Feedwater with On site Power (RCPs running). 
    Plausible because you do not have the TD AFW pump. D.  Incorrect:  1
st part is incorrect because ECA-0.0 is a higher priority section of the      EOP and it directs restoration fo AFW.  1
st part is plausible because it will address      the loss of feedwater after ECA-0.0 is exited.
  2 nd part is incorrect because TS      design bases accidtne for AFW is a loss of Main Feedwater with On site Power
    (RCPs running).  Plausible because you do not have the TD AFW pump.


B. Incorrect: 1st part is incorrect because ECA-0.0 is a higher priority section of the
      EOP and it directs restoration fo AFW. 1st part is plausible because it will address
      the loss of feedwater after ECA-0.0 is exited. 2nd part is correct.
C. Incorrect: 1st part is correct. 2nd part is incorrect because TS design bases
      accidtne for AFW is a loss of Main Feedwater with On site Power (RCPs running).
      Plausible because you do not have the TD AFW pump.
D. Incorrect: 1st part is incorrect because ECA-0.0 is a higher priority section of the
      EOP and it directs restoration fo AFW. 1st part is plausible because it will address
      the loss of feedwater after ECA-0.0 is exited. 2nd part is incorrect because TS
      design bases accidtne for AFW is a loss of Main Feedwater with On site Power
      (RCPs running). Plausible because you do not have the TD AFW pump.
Supporting References
Supporting References
Ref:
Ref:
1-FR-H.1 RESPONSE TO LOSS OF SECONDARY HEAT SINK
1-FR-H.1 RESPONSE TO LOSS OF SECONDARY HEAT SINK
1-ECA-0.0 LOSS OF ALL AC POWER  
1-ECA-0.0 LOSS OF ALL AC POWER
TS 3.6  
TS 3.6
References Provided to Applicant
References Provided to Applicant
none  
none
Answer: A
Answer: A  
17. 062AA2.06 1
17. 062AA2.06 1 Initial plant conditions:  
Initial plant conditions:
Unit 2 shutdown with fuel offloaded  
        Unit 2 shutdown with fuel offloaded
Unit 1 = 100% power  
        Unit 1 = 100% power
Current plant conditions:
            Annunciator 1D-G5, SW OR CC PPS DISCH TO CHRG PPS LO PRESS is
in
            alarm
            1AP/12 SERVICE WATER SYSTEM ABNORMAL CONDITIONS has been
            initiated
            Unit 1 operating CHG pump bearing temperatures:
                1420 = 170 0F
                1430 = 175 0F
                1440 = 180 0F
                1450 = 185 0F
                1500 = 190 0F
Based on the above conditions: (1) which one of the following states the time at which
1-AP-12 directs shifting the operating charging pump and, (2) if all Unit 1 charging
pumps are lost, correctly state the Tech Spec bases for using the designated Unit 2
charging pump?


A. (1) 1440
Current plant conditions:
    (2) To bring the operating unit to cold shutdown
          Annunciator 1D-G5, SW OR CC PPS DISCH TO CHRG PPS LO PRESS is
B. (1) 1440
in
    (2) To bring the operating unit to hot shutdown
          alarm
C. (1) 1450
          1AP/12 SERVICE WATER SYSTEM ABNORMAL CONDITIONS has been
    (2) To bring the operating unit to cold shutdown
          initiated 
D. (1) 1450
          Unit 1 operating CHG pump bearing temperatures:              1420 = 170
    (2) To bring the operating unit to hot shutdown
0F                1430 = 175
K/A
0 F              1440 = 180
Loss of Nuclear Svc Water:
0 F              1450 = 185
The length of time after the loss of SWS flow to a component before that component
0 F              1500 = 190
may be damaged.
0 F 
K/A Match Analysis
Based on the above conditions: (1) which one of the following states the time at which
Requires knowledge of temperature limits on components supplied by SWS.
1-AP-12 directs shifting the operating charging pump and, (2) if all Unit 1 charging
pumps are lost, correctly state the Tech Spec bases for using the designated Unit 2
charging pump?
 
 
A. (1) 1440 (2) To bring the operating unit to cold shutdown  
 
B. (1) 1440 (2) To bring the operating unit to hot shutdown  
 
C. (1) 1450 (2) To bring the operating unit to cold shutdown  
 
D. (1) 1450 (2) To bring the operating unit to hot shutdown  
 
 
K/A Loss of Nuclear Svc Water:
The length of time after the loss of SWS flow to a component before that component  
may be damaged.  
 
K/A Match Analysis
Requires knowledge of temperature limits on components supplied by SWS.  
 
SRO-Only Analysis
SRO-Only Analysis
Requires knowledge of Tech Spec bases that is required to analyze Tech Spec required  
Requires knowledge of Tech Spec bases that is required to analyze Tech Spec required
actions and terminology.  
actions and terminology.
 
Answer Choice Analysis
Answer Choice Analysis
A. Correct: At 180  
A. Correct: At 180 0F, AP/12 directs the charging pumps to be shifted. Per TS 3.2
0F, AP/12 directs the charging pumps to be shifted. Per TS 3.2     C&VCS for a shutdown unit, one charging pump with a source of borated water  
      C&VCS for a shutdown unit, one charging pump with a source of borated water
shall  
shall
    be available for cross-connect with the operating unit so that if the operating units  
      be available for cross-connect with the operating unit so that if the operating units
    charging pumps become inoperable, the shutdown units charging pump can bring  
      charging pumps become inoperable, the shutdown units charging pump can bring
    the disabled unit to cold shutdown. B. Incorrect: 1
      the disabled unit to cold shutdown.
st part is correct because at 180  
B. Incorrect: 1st part is correct because at 180 0F, AP/12 directs the charging pumps
0F, AP/12 directs the charging pumps     to be shifted. 2
      to be shifted. 2nd part is not correct because TS 3.2 states the shutdown units
nd part is not correct because TS 3.2 states the shutdown units     charging pump is used to bring the diabled unit to cold shutdown. 2
      charging pump is used to bring the diabled unit to cold shutdown. 2nd part is
nd part is     plausible because being in hot shutdown would put the plant in a stable condition  
      plausible because being in hot shutdown would put the plant in a stable condition
    while repairs are conducted. C. Incorrect: 1
      while repairs are conducted.
st part is incorrect because per AP/12 directs them to be shifted at      180 0F. 1 st part is plausible because at 185  
C. Incorrect: 1st part is incorrect because per AP/12 directs them to be shifted at
0F, AP/12 directs the charging pump     to be secured. 2
       180 0F. 1st part is plausible because at 185 0F, AP/12 directs the charging pump
nd part is correct. D. Incorrect: 1
      to be secured. 2nd part is correct.
st part is incorrect because per AP/12 directs them to be shifted at      180 0F. 1 st part is plausible because at 185  
D. Incorrect: 1st part is incorrect because per AP/12 directs them to be shifted at
0F, AP/12 directs the charging pump     to be secured.   2
       180 0F. 1st part is plausible because at 185 0F, AP/12 directs the charging pump
nd part is not correct because TS 3.2 states the shutdown units     charging pump is used to bring the diabled unit to cold shutdown. 2
      to be secured. 2nd part is not correct because TS 3.2 states the shutdown units
nd part is
      charging pump is used to bring the diabled unit to cold shutdown. 2nd part is
    plausible because being in hot shutdown would put the plant in a stable condition      while repairs are conducted.


    plausible because being in hot shutdown would put the plant in a stable condition
    while repairs are conducted.
Supporting References
Supporting References
TS 3.2, AP/12 Step 4 & 5, ND-89.5-LP-2 Obj H  
TS 3.2, AP/12 Step 4 & 5, ND-89.5-LP-2 Obj H
 
References Provided to Applicant
References Provided to Applicant
none  
none
Answer: C
Answer: C  
18. 079G2.2.22 1
18. 079G2.2.22 1 Given the following plant conditions:  
Given the following plant conditions:
 
  *   Unit 1 is at 100%
* Unit 1 is at 100%  
  *   A loss of Containment Instrument Air has occurred
* A loss of Containment Instrument Air has occurred  
  *   1B-F6, CTMT INST AIR HDR LO PRESSURE, annunciates
* 1B-F6, CTMT INST AIR HDR LO PRESSURE, annunciates  
  *   1D-C6, PRZR PWR RELIEF VV LO AIR PRESS, annunciates
* 1D-C6, PRZR PWR RELIEF VV LO AIR PRESS, annunciates  
  *   Containment Instrument Air was crosstied with Instrument Air
* Containment Instrument Air was crosstied with Instrument Air  
  *   Containment Instrument Air Pressure = 85 psig and increasing
* Containment Instrument Air Pressure = 85 psig and increasing  
  *   All PORV air bottles are properly aligned with air pressures of 1050 psig
* All PORV air bottles are properly aligned with air pressures of 1050 psig  
Which one of the following correctly states (1) the status of LCO 3.1.A.6, PORV
Operability and (2) the Tech Spec required operator actions, if any?
Which one of the following correctly states (1) the status of LCO 3.1.A.6, "PORV  
A. (1) The LCO is met.
Operability" and (2) the Tech Spec required operator actions, if any?  
  (2) No further action associated with the PORVs is required.
A. (1) The LCO is met.   (2) No further action associated with the PORVs is required.  
B. (1) The LCO is met.
 
  (2) Verify PORV operability by closing PORV Block Valves, manually cycle the
B. (1) The LCO is met.   (2) Verify PORV operability by closing PORV Block Valves, manually cycle the  
        PORVs, and then re-open the PORV Block Valves.
    PORVs, and then re-open the PORV Block Valves.  
C. (1) The LCO is NOT met.
 
  (2) Restore the PORV backup air supply within 14 days OR be in HSD within the
C. (1) The LCO is NOT met.   (2) Restore the PORV backup air supply within 14 days OR be in HSD within the  
        next 6 hours.
    next 6 hours.  
D. (1) The LCO is NOT met.
 
  (2) Close and remove power from both PORV block valves within one hour AND be
D. (1) The LCO is NOT met.   (2) Close and remove power from both PORV block valves within one hour AND be  
        in HSD within the next 6 hours
    in HSD within the next 6 hours  
079 Station Air
 
G2.2.22: Knowledge of limiting conditions for operations and safety limits
 
K/A MATCH ANALYSIS:
079 Station Air  
The question requires knowledge of PORV operability which is impacted by a loss of air.
G2.2.22: Knowledge of limiting conditions for operations and safety limits  
The operability determination causes the conditions of the LCO to not be met.
 
K/A MATCH ANALYSIS:  
The question requires knowledge of PORV operability which is impacted by a loss of air.
The operability determination causes the conditions of the LCO to not be met.
SRO-ONLY ANALYSIS:
Operability is primarily an SRO function unless the determinatation is made at a very
basic level (I.E. if a pump is broke, it is obviously inop - which would be RO knowledge). 
This question requires the SRO to understand how the loss of instrument air affects the
PORV operability, even when the PORV is available for use with cross-tied air.
Answer Choice Analysis:
A.  Incorrect per 1D-C6 CTMT Inst Air P must be > 80 psig for the PORVs to be operable. B.  Incorrect because (per 1D-C6) with CTMT Inst Air P < 80 psig, the PORVs are inoperable. C.  Correct because PORVs are capable of being manually cycled with CTMT Inst Air P > 80 psig.  The PORVs are INOP due to INOP air supply and you start a 14 day
LCO clock.  D.  Incorrect, the PORV is INOP but can be manually cycled. This choice is correct if the PORV could NOT be manually cycled.  This would be a 1 hr LCO.
Surry Requal Bank Question #571 (LARP0001) & 2004-301 NRC Exam
 
References:
ND-92.1-LP-1, Station Air Systems, Rev. 13
ND-88.1-LP-3, Pressurizer and Pressure Relief, Rev. 12
1B-F6, CTMT INST AIR HDR LO PRESS, Rev. 1
1D-C6, PRZR PWR RELIEF VV LO AIR PRESS, Rev. 4
Technical Specification 3.1.A.6.c, Reactor Coolant System / Relief Valves
 
Answer: C
19.  G2.1.20 13 Initial plant conditions on Unit 2 are as follows:
* Reactor power is 100%.
* A 20 gpd leak exists on steam generator 'B'.
Current plant conditions on Unit 2 are as follows:
* Charging flow has slowly increased. Auto-makeup to VCT has started.
VCT level is 29% and slowly rising.
Pressurizer level is stable at 54%.
Pressurizer pressure is stable at 2225 psig.
Crew has entered AP-16, "Excessive RCS Leakage".
Radiation levels on MSL "B" show a slow increasing trend. 
* The leak rate has been calculated at 12 gpm. [MAY NEED TO RAISE LR - DISCUSS WITH LICENSEE]
[REVIEW ALL THE CONDITIONS IN THE STEM WITH THE LICENSEE]
 
Which one of the following describes (1) whether the following procedure transition is
required AND (2) the correct classification for the event? Transition to 2-AP-24.00, "Minor SG Tube Leak" is-
(Reference provided)
 
A. (1) required. (2) Alert
 
B. (1) NOT required. (2) Alert
 
C. (1) required. (2) NOUE
D. (1) NOT required. (2) NOUE 
[DISCUSS WITH THE LICENSEE TO DETERMINE CONDITIONS FOR THE STEM
THAT WILL ENSURE ONE AND ONLY ONE CORRECT ANSWER AS WELL AS
PLAUSIBILITY FOR THE DISTRACTORS]


SRO-ONLY ANALYSIS:
K/A Generics: Ability to interpret and execute procedure steps.  
Operability is primarily an SRO function unless the determinatation is made at a very
basic level (I.E. if a pump is broke, it is obviously inop - which would be RO knowledge).
This question requires the SRO to understand how the loss of instrument air affects the
PORV operability, even when the PORV is available for use with cross-tied air.
Answer Choice Analysis:
A. Incorrect per 1D-C6 CTMT Inst Air P must be > 80 psig for the PORVs to be
    operable.
B. Incorrect because (per 1D-C6) with CTMT Inst Air P < 80 psig, the PORVs are
    inoperable.
C. Correct because PORVs are capable of being manually cycled with CTMT Inst Air
    P > 80 psig. The PORVs are INOP due to INOP air supply and you start a 14 day
    LCO clock.
D. Incorrect, the PORV is INOP but can be manually cycled. This choice is correct if
    the PORV could NOT be manually cycled. This would be a 1 hr LCO.
Surry Requal Bank Question #571 (LARP0001) & 2004-301 NRC Exam
References:
ND-92.1-LP-1, Station Air Systems, Rev. 13
ND-88.1-LP-3, Pressurizer and Pressure Relief, Rev. 12
1B-F6, CTMT INST AIR HDR LO PRESS, Rev. 1
1D-C6, PRZR PWR RELIEF VV LO AIR PRESS, Rev. 4
Technical Specification 3.1.A.6.c, Reactor Coolant System / Relief Valves
Answer: C
19. G2.1.20 13
Initial plant conditions on Unit 2 are as follows:
    *  Reactor power is 100%.
    *  A 20 gpd leak exists on steam generator B.
Current plant conditions on Unit 2 are as follows:
    *  Charging flow has slowly increased.
    Auto-makeup to VCT has started.
    VCT level is 29% and slowly rising.
    Pressurizer level is stable at 54%.
    Pressurizer pressure is stable at 2225 psig.
    Crew has entered AP-16, Excessive RCS Leakage.
    Radiation levels on MSL B show a slow increasing trend.


   
    *  The leak rate has been calculated at 12 gpm. [MAY NEED TO RAISE LR -
        DISCUSS WITH LICENSEE]
  [REVIEW ALL THE CONDITIONS IN THE STEM WITH THE LICENSEE]
Which one of the following describes (1) whether the following procedure transition is
required AND (2) the correct classification for the event?
Transition to 2-AP-24.00, Minor SG Tube Leak is
(Reference provided)
A. (1) required.
    (2) Alert
B. (1) NOT required.
    (2) Alert
C. (1) required.
    (2) NOUE
D. (1) NOT required.
    (2) NOUE
[DISCUSS WITH THE LICENSEE TO DETERMINE CONDITIONS FOR THE STEM
THAT WILL ENSURE ONE AND ONLY ONE CORRECT ANSWER AS WELL AS
PLAUSIBILITY FOR THE DISTRACTORS]
K/A
Generics: Ability to interpret and execute procedure steps.
K/A Match Analysis
K/A Match Analysis
Requires applicant to interpret the leak indications, determine if transition to 1-AP-24.00  
Requires applicant to interpret the leak indications, determine if transition to 1-AP-24.00
is required and determine the correct emergency classification associated with the leak.  
is required and determine the correct emergency classification associated with the leak.
 
SRO-Only Analysis
SRO-Only Analysis
The question requires the applicant to correctly determine if a procedure transition is  
The question requires the applicant to correctly determine if a procedure transition is
required from AP-16-00 and classify the event per the emergency plan. Both of which  
required from AP-16-00 and classify the event per the emergency plan. Both of which
would require SRO- Only knowledge to determine.  
would require SRO- Only knowledge to determine.
 
Answer Choice Analysis
Answer Choice Analysis
A. In-Correct but plausible since a procedure transition to 1-AP-24.00 is required.
A. In-Correct but plausible since a procedure transition to 1-AP-24.00 is required.
B. In-Correct but plausible since a procedure transition would not be required if the
applicant didn't recognize that MSL 'B' radition were increasing.
C. Correct - Transition to 1-AP-24.00 is required.


D. In-Correct. See above.
B.  In-Correct but plausible since a procedure transition would not be required if the
applicant didn't recognize that MSL 'B' radition were increasing. 
 
C.  Correct - Transition to 1-AP-24.00 is required. 
D. In-Correct. See above.  
 
Supporting References
Supporting References
1-AP-16.00, Excessive RCS Leakage, Rev. 16  
1-AP-16.00, Excessive RCS Leakage, Rev. 16
Emergency Plan, Rev. 54  
Emergency Plan, Rev. 54
 
References Provided to Applicant
References Provided to Applicant
Emergency Plan  
Emergency Plan
NOTE: Facility reviewers please validate that the correct emergency classification
was determined.
Answer: C
20. G2.2.14 20
Plant conditions:
        RCS cooldown in progress
        RCS temperature = 350 oF decreasing
        RCS pressure = 300 psig
Based on the above conditions in regards to the Overpressure Mitigation System
(OMS),
(1) which one of the following correctly describes the required equipment configuration
for the 72 hours following RCS temperature decreasing below 350 oF and (2) what is
the TS basis for that configuration? (Consider No TS modifications, LCOs...)?
A. (1) Pzr level is limited to 33%
    (2) This is to allow the operator 10 minutes to take action from inadvertent initiation
        of full (3 pump) charging flow.
B. (1) Two PORVs are required to remain operable
    (2) This is based on the PORVs ability to relieve RCS pressure from the start of a
          RCP with SG temp > RCS temp.
C. (1) Accumulators must be depressurized to less than the PORV setpoint
    (2) This is to prevent exceeding the PORV capability if an inadvertent OMS initiation
    occurs.
D. (1) All but one charging pump shall be removed from service and incapable of
          injecting into the RCS
    (2) This is to ensure any mass addition can be relieved by one PORV.
K/A
Knowledge of the process for controlling equipment configuration or status.


K/A Match Analysis
Requires knowledge of the equipment configuration for specific plant conditions.
NOTE: Facility reviewers please validate that the correct emergency classification
was determined.
Answer: C
20.  G2.2.14 20 Plant conditions: RCS cooldown in progress RCS temperature = 350
oF decreasing RCS pressure = 300 psig
Based on the above conditions in regards to the Overpressure Mitigation System
(OMS), 
(1) which one of the following correctly describes the required equipment configuration for the 72 hours following RCS temperature decreasing below 350
oF and (2) what is the TS basis for that configuration? (Consider No TS modifications, LCOs...)?
A. (1) Pzr level is limited to 33%  (2) This is to allow the operator 10 minutes to take action from inadvertent initiation
    of full (3 pump) charging flow.
 
B. (1) Two PORVs are required to remain operable  (2) This is based on the PORVs ability to relieve RCS pressure from the start of a
      RCP with SG temp > RCS temp.
 
C. (1) Accumulators must be depressurized to less than the PORV setpoint  (2) This is to prevent exceeding the PORV capability if an inadvertent OMS initiation
occurs.
D. (1) All but one charging pump shall be removed from service and incapable of      injecting into the RCS 
(2) This is to ensure any mass addition can be relieved by one PORV.
 
 
K/A Knowledge of the process for controlling equipment configuration or status. 
K/A Match Analysis
Requires knowledge of the equipment configuration for specific plant conditions.  
SRO-Only Analysis
SRO-Only Analysis
Requires knowledge of the plant configuration for cooldown operations and the TS  
Requires knowledge of the plant configuration for cooldown operations and the TS
Bases for that configuration.  
Bases for that configuration.
 
Answer Choice Analysis
Answer Choice Analysis
A. Incorrect: Plausible because the limit is correct but based on only one charging  
A. Incorrect: Plausible because the limit is correct but based on only one charging
     pump injecting. B. Incorrect: 2 PORVs are required for the 1
     pump injecting.
st 72 hours if no vent exists or Pzr level       < 33%. Plausible because the bases stated is for one PORV being operable.  
B. Incorrect: 2 PORVs are required for the 1st 72 hours if no vent exists or Pzr level
C. Incorrect: Accumulators can be isolated and valves de-energized as an alternative  
      < 33%. Plausible because the bases stated is for one PORV being operable.
     to depressurizing. While initiation may cause the PORV to lift, it will not exceed its  
C. Incorrect: Accumulators can be isolated and valves de-energized as an alternative
     capacity. Plausible because depressurizing the accumulators is an option to  
     to depressurizing. While initiation may cause the PORV to lift, it will not exceed its
     isolating them.  
     capacity. Plausible because depressurizing the accumulators is an option to
D. Correct. Per TS 3.1.G  
     isolating them.
 
D. Correct. Per TS 3.1.G
Supporting References
Supporting References
ND-93.3-LP-6 Obj: E  
ND-93.3-LP-6 Obj: E
TS3.1.G  
TS3.1.G
References Provided to Applicant
References Provided to Applicant
none  
none
Answer: D
Answer: D  
21. G2.2.22 1
21. G2.2.22 1 Which one of the following describes how the potential reactivity effects due to Reactor  
Which one of the following describes how the potential reactivity effects due to Reactor
Coolant System cooldown during and following loop backfill are limited to acceptable levels, as specified in the Bases to Technical Specification 3.17, "LOOP STOP VALVE  
Coolant System cooldown during and following loop backfill are limited to acceptable
OPERATION?"
levels, as specified in the Bases to Technical Specification 3.17, "LOOP STOP VALVE
 
OPERATION?"
A. (1) There is a small absolute value of the isothermal temperature coefficient of reactivity at cold and refueling shutdown conditions.  
A. (1) There is a small absolute value of the isothermal temperature coefficient of
 
  reactivity at cold and refueling shutdown conditions.
  (2) Reactivity effects due to boron stratification in the backfilled loop are NOT a
(2)   Reactivity effects due to boron stratification in the backfilled loop are NOT a  
  concern, because stratification is NOT expected to take place at the normal
concern, because stratification is NOT expected to take place at the normal  
  shutdown boron concentrations and temperatures during the time to complete
shutdown boron concentrations and temperatures during the time to complete  
  backfill of the loop and open the loop stop valves fully.
backfill of the loop and open the loop stop valves fully.  
B. (1) There is a large absolute value of the fuel temperature coefficient of reactivity
 
  at cold and refueling shutdown conditions.
B. (1) There is a large absolute value of the fuel temperature coefficient of reactivity at cold and refueling shutdown conditions. 
 
 
(2)  Reactivity effects due to localized boron stratification in the backfilled loop are a concern; the requirements on relief line flow and boron concentration of the reactor
coolant pump seal injection source are designed to mitigate any adverse effects of
localized boron stratification.
 
C. (1)  There is a small absolute value of the isothermal temperature coefficient of reactivity at cold and refueling shutdown conditions.
 
 
(2)  Reactivity effects due to localized boron stratification in the backfilled loop are a concern; the requirements on relief line flow and boron concentration of the reactor
coolant pump seal injection source are designed to mitigate any adverse effects of
localized boron stratification.
 
D. (1)  There is a large absolute value of the fuel temperature coefficient of reactivity at cold and refueling shutdown conditions.  
 
(2)  Reactivity effects due to boron stratification in the backfilled loop are NOT a
concern, because stratification is NOT expected to take place at the normal
shutdown boron concentrations and temperatures during the time to complete
backfill of the loop and open the loop stop valves fully. 
 
 
K/A Knowledge of limiting conditions for operations and safety limits.
(CFR: 41.5/43.2/45.2)  (SRO - 4.7)


    (2) Reactivity effects due to localized boron stratification in the backfilled loop are a
    concern; the requirements on relief line flow and boron concentration of the reactor
    coolant pump seal injection source are designed to mitigate any adverse effects of
    localized boron stratification.
C. (1) There is a small absolute value of the isothermal temperature coefficient of
    reactivity at cold and refueling shutdown conditions.
    (2) Reactivity effects due to localized boron stratification in the backfilled loop are a
    concern; the requirements on relief line flow and boron concentration of the reactor
    coolant pump seal injection source are designed to mitigate any adverse effects of
    localized boron stratification.
D. (1) There is a large absolute value of the fuel temperature coefficient of reactivity
    at cold and refueling shutdown conditions.
    (2) Reactivity effects due to boron stratification in the backfilled loop are NOT a
    concern, because stratification is NOT expected to take place at the normal
    shutdown boron concentrations and temperatures during the time to complete
    backfill of the loop and open the loop stop valves fully.
K/A
Knowledge of limiting conditions for operations and safety limits.
(CFR: 41.5/43.2/45.2) (SRO - 4.7)
K/A Match Analysis
K/A Match Analysis
The K/A is a Tier 3, or "generic" K/A. The question asks the SRO candidate to demonstrate knowledge of the bases for an important Technical Specifications LCO for  
The K/A is a Tier 3, or "generic" K/A. The question asks the SRO candidate to
Loop Stop Valve Operation.  
demonstrate knowledge of the bases for an important Technical Specifications LCO for
 
Loop Stop Valve Operation.
SRO-Only Analysis
SRO-Only Analysis
-see attached flowchart from SRO-only guidance document. TS Basis knowledge  
-see attached flowchart from SRO-only guidance document. TS Basis knowledge
needed to arrive at the correct answer.  
needed to arrive at the correct answer.
 
Answer Choice Analysis
Answer Choice Analysis
 
A. CORRECT. Both choices (1) and (2) are taken word-for-word from the bases of
A. CORRECT. Both choices (1) and (2) are taken word-for-word from the bases of  
TS 3.17, "LOOP STOP VALVE OPERATION," p. TS 3.17-7.
TS 3.17, "LOOP STOP VALVE OPERATION," p. TS 3.17-7.  
B. INCORRECT. (1) is plausible because it uses the exact same language of the
 
correct version of (1), but is incorrect because a large negative value of the Doppler
coefficient would be worse from a reactivity standpoint when considering cold
B. INCORRECT. (1) is plausible because it uses the exact same language of the  
shutdown/refueling conditions. (2) is also incorrect, but plausible, because it specifies
correct version of (1), but is incorrect because a large negative value of the Doppler  
that only localized boron stratification is a concern, and also because it mentions
coefficient would be worse from a reactivity standpoint when considering cold  
(correctly) limits placed on relief line flow rates and time, as well as limits placed on
shutdown/refueling conditions. (2) is also incorrect, but plausible, because it specifies  
that only localized boron stratification is a concern, and also because it mentions  
(correctly) limits placed on relief line flow rates and time, as well as limits placed on
boron concentration of the reactor coolant pump seal injection source, which are actually contained in the TS 3.17.
 
 
C.  INCORRECT.  (1) is correct version; (2) is the incorrect distractor.
 
D.  INCORRECT.  (1) is incorrect distractor; (2) is correct version.


boron concentration of the reactor coolant pump seal injection source, which are
actually contained in the TS 3.17.
C. INCORRECT. (1) is correct version; (2) is the incorrect distractor.
D. INCORRECT. (1) is incorrect distractor; (2) is correct version.
Supporting References
Supporting References
 
SPS TS 3.17 and bases, especially p. 7.
SPS TS 3.17 and bases, especially p. 7.  
 
References Provided to Applicant
References Provided to Applicant
 
None
None  
Answer: A
22. G2.3.12 1
Answer: A  
Unit 1 initial conditions:
22. G2.3.12 1 Unit 1 initial conditions:  
        Date = 6/24
Date = 6/24 Time = 0800 Reactor power = 100%  
        Time = 0800
Waste gas storage tank activity level is reported which exceeds TS 3.11,  
        Reactor power = 100%
          Radioactive Gas Storage, limits  
        Waste gas storage tank activity level is reported which exceeds TS 3.11,
 
            Radioactive Gas Storage, limits
 
Current conditions:
Current conditions:  
        Date = 6/26
Date = 6/26  
        Time = 0800
Time = 0800  
        Reactor power = 100%
Reactor power = 100%  
        Waste gas storage tank activity level still exceeds Tech Spec 3.11 limits
Waste gas storage tank activity level still exceeds Tech Spec 3.11 limits
Based on the above conditions, which one of the following correctly states: (1) if Tech
 
Spec 3.0.1 is applicable and (2) the whole body dose that the tank radioactivity limit is
designed to prevent exceeding at the exclusion area boundary if the tank were released
Based on the above conditions, which one of the following correctly states: (1) if Tech  
IAW Tech Spec Basis?
Spec 3.0.1 is applicable and (2) the whole body dose that the tank radioactivity limit is  
A. (1) Yes
designed to prevent exceeding at the exclusion area boundary if the tank were released  
    (2) 50 mrem
IAW Tech Spec Basis?  
B. (1) Yes
    (2) 0.5 rem
C. (1) No
    (2) 50 mrem
D. (1) No
    (2) 0.5 rem


A. (1) Yes (2) 50 mrem
K/A
B. (1) Yes (2) 0.5 rem
Knowledge of radiological safety principles pertaining to licensed operator l
C. (1) No (2) 50 mrem
duties, such as containment entry requirements, fuel handling responsibilities, l
D. (1) No
(2) 0.5 rem 
  K/A Knowledge of radiological safety principles pertaining to licensed operator l  
duties, such as containment entry requirements, fuel handling responsibilities, l  
access to locked high-radiation areas, aligning filters, etc.
access to locked high-radiation areas, aligning filters, etc.
 
K/A Match Analysis
K/A Match Analysis
Requires knowledge of radiological limits associated with the health and safety of the  
Requires knowledge of radiological limits associated with the health and safety of the
public and how to apply technical specifications to stay within those limits.  
public and how to apply technical specifications to stay within those limits.
 
SRO-Only Analysis
SRO-Only Analysis
Requires knowledge of the facility operation limitations in the technical specifications and their bases.  
Requires knowledge of the facility operation limitations in the technical specifications
 
and their bases.
Answer Choice Analysis
Answer Choice Analysis
A. Incorrect: In TS 3.11.B.3 it states that the requirements fo Specification 3.0.1 are      not applicable. 1
A. Incorrect: In TS 3.11.B.3 it states that the requirements fo Specification 3.0.1 are
st part is plausible because the time for condition 3.11.B.2 has       expired. 2
     not applicable. 1st part is plausible because the time for condition 3.11.B.2 has
nd part is incorrect because in the TS bases 3.11 it states 0.5 rem.  
    expired. 2nd part is incorrect because in the TS bases 3.11 it states 0.5 rem.
     2 nd part is plausible becasue the Surry adminestrative limit for site visitors is       50 mrem.  
     2nd part is plausible becasue the Surry adminestrative limit for site visitors is
B. Incorrect: In TS 3.11.B.3 it states that the requirements fo Specification 3.0.1 are      not applicable. 1
    50 mrem.
st part is plausible because the time for condition 3.11.B.2 has       expired.   2
B. Incorrect: In TS 3.11.B.3 it states that the requirements fo Specification 3.0.1 are
nd part is correct per TS 3.11 bases. C. Incorrect: 1
     not applicable. 1st part is plausible because the time for condition 3.11.B.2 has
st part is correct. 2
    expired.     2nd part is correct per TS 3.11 bases.
nd part is incorrect because in the TS bases 3.11 it      states 0.5 rem.   2
C. Incorrect: 1st part is correct. 2nd part is incorrect because in the TS bases 3.11 it
nd part is plausible becasue the Surry adminestrative limit for       site visitors is 50 mrem. D. Correct: In TS 3.11.B.3 it states that the requirements fo Specification 3.0.1 are  
     states 0.5 rem. 2nd part is plausible becasue the Surry adminestrative limit for
     not applicable. In the tech spec bases for TS 3.11 it states it limited to the quantity  
    site visitors is 50 mrem.
     which provides assurance that in the event of an uncontrolled release of the tank's  
D. Correct: In TS 3.11.B.3 it states that the requirements fo Specification 3.0.1 are
     contents, the resulting total body exposure to an individual at the nearest exclusion  
     not applicable. In the tech spec bases for TS 3.11 it states it limited to the quantity
     area boundary will not exceed 0.5 rem in an event.  
     which provides assurance that in the event of an uncontrolled release of the tank's
 
     contents, the resulting total body exposure to an individual at the nearest exclusion
     area boundary will not exceed 0.5 rem in an event.
Supporting References
Supporting References
TS 3.11  
TS 3.11
ND-81.2-LP3  
ND-81.2-LP3
 
References Provided to Applicant
References Provided to Applicant
none  
none
 
Answer: D
Answer: D  
23. G2.3.4 22
23. G2.3.4 22 Unit 1 initial plant conditions:  
Unit 1 initial plant conditions:
Reactor power = 50%  
        Reactor power = 50%
Plant shutdown in progress due to RCS activity greater than TS limits
        Plant shutdown in progress due to RCS activity greater than TS limits
AFW Pump 1FW 3B OOS
Current plant conditions:
'A' SG tube rupture occurs
          'A' SG pressure = 1000 psig
Reactor has been tripped
1-E-3 STEAM GENERATOR TUBE RUPTURE in progress
The TSC has been established 
An operator is dispatched to close 1-MS-87 (steam from the A SG to the TD
          AFW pump) in order to save valuable equipment
 
Based on the above conditions, which one of the following: (1) states the allowable
dose (TEDE) the operator can receive while isolating steam to the TD AFW pump and
(2) if the valve can not be closed, what procedural actions shall be taken IAW 1-E-3 to
mitigate the failure?


A. (1) 10 Rem (2) Remain in 1-E-3 and trip the TD AFW pump overspeed trip valve.  
        AFW Pump 1FW 3B OOS
 
Current plant conditions:
B. (1) 10 Rem (2) GO TO 1-ECA-3.1, SGTR WITH LOSS OF REACTOR COOLANT -  
        A SG tube rupture occurs
    SUBCOOLED RECOVERY.
              'A' SG pressure = 1000 psig
 
        Reactor has been tripped
C. (1) 5 Rem (2) Remain in 1-E-3 and trip the TD AFW pump overspeed trip valve.  
        1-E-3 STEAM GENERATOR TUBE RUPTURE in progress
 
        The TSC has been established
D. (1) 5 Rem (2) GO TO 1-ECA-3.1, SGTR WITH LOSS OF REACTOR COOLANT -  
        An operator is dispatched to close 1-MS-87 (steam from the A SG to the TD
    SUBCOOLED RECOVERY.
              AFW pump) in order to save valuable equipment
 
Based on the above conditions, which one of the following: (1) states the allowable
 
dose (TEDE) the operator can receive while isolating steam to the TD AFW pump and
K/A Knowledge of radiation exposure limits under normal or emergency conditions.  
(2) if the valve can not be closed, what procedural actions shall be taken IAW 1-E-3 to
 
mitigate the failure?
A. (1) 10 Rem
    (2) Remain in 1-E-3 and trip the TD AFW pump overspeed trip valve.
B. (1) 10 Rem
    (2) GO TO 1-ECA-3.1, SGTR WITH LOSS OF REACTOR COOLANT -
          SUBCOOLED RECOVERY.
C. (1) 5 Rem
    (2) Remain in 1-E-3 and trip the TD AFW pump overspeed trip valve.
D. (1) 5 Rem
    (2) GO TO 1-ECA-3.1, SGTR WITH LOSS OF REACTOR COOLANT -
          SUBCOOLED RECOVERY.
K/A
Knowledge of radiation exposure limits under normal or emergency conditions.
K/A Match Analysis
K/A Match Analysis
Requires knowledge of exposure limits under emergency conditions.  
Requires knowledge of exposure limits under emergency conditions.
 
SRO-Only Analysis
SRO-Only Analysis
Requires knowledge of EOP procedures and transition points.  
Requires knowledge of EOP procedures and transition points.
 
Answer Choice Analysis
Answer Choice Analysis
A. Correct: Allowable dose for equipment = 10 Rem. Per 1-E-3, if at least 1 motor  
A. Correct: Allowable dose for equipment = 10 Rem. Per 1-E-3, if at least 1 motor
    driven AFW pump available, trip the TD AFW pump. B. Incorrect: 1
      driven AFW pump available, trip the TD AFW pump.
st part is correct. 2
B. Incorrect: 1st part is correct. 2nd part is plausible because if the SG with the
nd part is plausible because if the SG with the     rupture could not be isolated from both of the intact SGs, it would be correct. C. Incorrect: 1
      rupture could not be isolated from both of the intact SGs, it would be correct.
st part is plausible because the exposure could be counted towards a
C. Incorrect: 1st part is plausible because the exposure could be counted towards a
    PSE (the PSE limit is 5 Rem / yr).  2
nd part is correct. D.  Incorrect: 1
st part is plausible because the exposure could be counted towards a      PSE (the PSE limit is 5 Rem / yr).  2
nd part is plausible because if the SG with the      rupture could not be isolated from both of the intact SGs, it would be correct.


    PSE (the PSE limit is 5 Rem / yr). 2nd part is correct.
D. Incorrect: 1st part is plausible because the exposure could be counted towards a
    PSE (the PSE limit is 5 Rem / yr). 2nd part is plausible because if the SG with the
    rupture could not be isolated from both of the intact SGs, it would be correct.
Supporting References
Supporting References
ND-81.2-LP-3 Obj: E  
ND-81.2-LP-3 Obj: E
1-E-3  
1-E-3
ND-95.3-LP-13 E-3 Obj: A  
ND-95.3-LP-13 E-3 Obj: A
 
References Provided to Applicant
References Provided to Applicant
none  
none
Answer: A
Answer: A  
24. G2.4.30 1
24. G2.4.30 1 Unit 1 Initial Conditions:  
Unit 1 Initial Conditions:
 
  *   Holding at 30% power for fuel conditioning following a refueling outage.
* Holding at 30% power for fuel conditioning following a refueling outage.  
Current conditions:
  *   Technicians performing a routine surveillance test on the AMSAC logic system
Current conditions:  
        indavertantly cause a half-train Train "A" AMSAC signal to be generated.
 
  *   Annunciator F-B-3, AMSAC INITIATED, is lit
* Technicians performing a routine surveillance test on the AMSAC logic system indavertantly cause a half-train Train "A" AMSAC signal to be generated.  
  *   The technicians are able to reset the Train "A" AMSAC signal in ten (10)
* Annunciator F-B-3, AMSAC INITIATED, is lit  
        seconds.
* The technicians are able to reset the Train "A" AMSAC signal in ten (10) seconds.
Based on the current conditions, which one of the following correctly describes (1)
Based on the current conditions, which one of the following correctly describes (1)  
whether the half-train AMSAC signal should be considered a VALID or INVALID
whether the half-train AMSAC signal should be considered a VALID or INVALID  
actuation, as defined by VPAP-2802, "Notifications and Reports," AND (2) the most
actuation, as defined by VPAP-2802, "Notifications and Reports," AND (2) the most  
restrictive time requirement to report this event to the NRC, as specified by
restrictive time requirement to report this event to the NRC, as specified by VPAP-2802?
VPAP-2802?
 
(Reference provided)
A. (1) VALID actuation
(Reference provided)  
  (2) 4 hour notification
 
B. (1) INVALID actuation
A. (1) VALID actuation (2) 4 hour notification  
  (2) 8 hour notification
 
C. (1) VALID actuation
B. (1) INVALID actuation (2) 8 hour notification  
  (2) 8 hour notification
 
D. (1) INVALID actuation
C. (1) VALID actuation (2) 8 hour notification  
  (2) 4 hour notification
 
D. (1) INVALID actuation (2) 4 hour notification
 
K/A Knowledge of events related to system operation/status that must be reported to
internal organizations or external agencies, such as the State, the NRC, or the
transmission system operator.
(CFR: 41.10/43.5/45.11)  (SRO - 4.1)


K/A
Knowledge of events related to system operation/status that must be reported to
internal organizations or external agencies, such as the State, the NRC, or the
transmission system operator.
(CFR: 41.10/43.5/45.11) (SRO - 4.1)
K/A Match Analysis
K/A Match Analysis
The question requires the applicant to demonstrate knowledge of the definitions  
The question requires the applicant to demonstrate knowledge of the definitions
inherent in the notifications procedure ("system operation/status"), and also show an  
inherent in the notifications procedure ("system operation/status"), and also show an
ability to use the procedure to determine the correct time requirements for the given  
ability to use the procedure to determine the correct time requirements for the given
plant conditions, which are operationally valid.  
plant conditions, which are operationally valid.
 
SRO-Only Analysis
SRO-Only Analysis
This question requires the applicant to know the definitions inherent in the Notifications  
This question requires the applicant to know the definitions inherent in the Notifications
procedure, and to apply them in a practical setting. Therefore, it is a higher-level  
procedure, and to apply them in a practical setting. Therefore, it is a higher-level
comprehension/analysis question that is linked to 10CFR55.43(b)(1), "conditions and  
comprehension/analysis question that is linked to 10CFR55.43(b)(1), "conditions and
limitations in the facility license," in that ROs are not required to know and be able to  
limitations in the facility license," in that ROs are not required to know and be able to
apply reporting requirements.  
apply reporting requirements.
 
Answer Choice Analysis
Answer Choice Analysis
 
A. INCORRECT. (1) Surry/Dominion procedure VPAP-2802, "Notifications and
A. INCORRECT. (1) Surry/Dominion procedure VPAP-2802, "Notifications and  
Reports," section 4.3 specifies that a VALID actuation must result "from an intentional
Reports," section 4.3 specifies that a VALID actuation must result "from an intentional  
manual initiation or from a signal that was initiated in response to actual plant conditions
manual initiation or from a signal that was initiated in response to actual plant conditions  
or parameters satisfying the requirements for initiation, unless part of a preplanned
or parameters satisfying the requirements for initiation, unless part of a preplanned  
test." For the given conditions, the inadvertant AMSAC actuation was caused as a
test." For the given conditions, the inadvertant AMSAC actuation was caused as a  
result of testing, the actuation was a result of human error and was not pre-planned to
result of testing, the actuation was a result of human error and was not pre-planned to  
occur, and was not in response to actual plant conditions. Therefore, to state that the
occur, and was not in response to actual plant conditions. Therefore, to state that the  
actuation was VALID is plausible. (2) 4 hours is the most restrictive notification, to report
actuation was VALID is plausible. (2) 4 hours is the most restrictive notification, to report  
an RPS actuation on a critical reactor.
an RPS actuation on a critical reactor.  
B. INCORRECT. (1) VPAP-2802 section 4.2 specifies that an invalid actuation "is
   
one that does not meet the criteria for being valid and are initiated for reasons other
B. INCORRECT. (1) VPAP-2802 section 4.2 specifies that an invalid actuation "is  
than to mitigate the consequences of an event (e.g., as part of a planned evolution, with
one that does not meet the criteria for being valid and are initiated for reasons other  
the system properly removed from service, or after the safety function has already been
than to mitigate the consequences of an event (e.g., as part of a planned evolution, with  
completed). Invalid actuations include circumstances where instrument drift, spurious
the system properly removed from service, or after the safety function has already been  
signals, human error, or other invalid signals caused actuation (e.g. jarring a cabinet, an
completed). Invalid actuations include circumstances where instrument drift, spurious  
error in the use of jumpers or lifted leads, an error in the actuation of switches or
signals, human error, or other invalid signals caused actuation (e.g. jarring a cabinet, an  
controls, equipment failure, radio frequency interference)." For the given conditions,
error in the use of jumpers or lifted leads, an error in the actuation of switches or  
human error caused the actuation; therefore INVALID actuation is correct. The
controls, equipment failure, radio frequency interference)." For the given conditions,  
candidate must then infer from the question whether the reactor tripped (yes). (2)
human error caused the actuation; therefore INVALID actuation is correct. The  
Based on the provided reference material, the candidate my incorrectly choose an
candidate must then infer from the question whether the reactor tripped (yes). (2)  
8-hour notification based on auxiliary feedwater auto-start, if he/she incorrectly believes
Based on the provided reference material, the candidate my incorrectly choose an  
that the AMSAC actuation at a low power level would not produce a reactor trip (or only
8-hour notification based on auxiliary feedwater auto-start, if he/she incorrectly believes  
that the AMSAC actuation at a low power level would not produce a reactor trip (or only
trip the turbine and not the reactor as well).  The plausibility of this choice is enhanced by the question stem stating that the signal is reset within 10 seconds (where a normal
AMSAC signal is required to remain "in" for 27 seconds to cause an actuation). 


trip the turbine and not the reactor as well). The plausibility of this choice is enhanced
C. INCORRECT. "VALID" actuation is wrong as per the above.  
by the question stem stating that the signal is reset within 10 seconds (where a normal
 
AMSAC signal is required to remain "in" for 27 seconds to cause an actuation).
 
C. INCORRECT. "VALID" actuation is wrong as per the above.
D. CORRECT. "INVALID" actuation is correct as per the above. VPAP-2802 section  
D. CORRECT. "INVALID" actuation is correct as per the above. VPAP-2802 section
6.3.4.a.3. states that a 4-hour report is required for "Any event or condition that results  
6.3.4.a.3. states that a 4-hour report is required for "Any event or condition that results
in actuation of the reactor protection system (RPS) when the reactor is critical except  
in actuation of the reactor protection system (RPS) when the reactor is critical except
when actuation results from and is part of a pre-planned sequence during testing or  
when actuation results from and is part of a pre-planned sequence during testing or
reactor operation." In this case, an automatic reactor trip/RPS actuation did occur with  
reactor operation." In this case, an automatic reactor trip/RPS actuation did occur with
the reactor critical. The reactor trip was not pre-planned; rather, it was caused by  
the reactor critical. The reactor trip was not pre-planned; rather, it was caused by
human error, and therefore the exclusion clause does not apply.  
human error, and therefore the exclusion clause does not apply.
 
Supporting References
Supporting References
 
-VPAP-2802, "Notifications and Reports," rev 30, (p. 20, p. 82, and p. 86)
-VPAP-2802, "Notifications and Reports," rev 30, (p. 20, p. 82, and p. 86)  
- Surry lesson plan ND-93.3-LP-17, "ANTICIPATORY MITIGATING SYSTEM
 
ACTUATING CIRCUITRY (AMSAC)," rev. 11, p. 7 and 9.
- Surry lesson plan ND-93.3-LP-17, "ANTICIPATORY MITIGATING SYSTEM  
ACTUATING CIRCUITRY (AMSAC)," rev. 11, p. 7 and 9.  
 
References Provided to Applicant
References Provided to Applicant
 
-VPAP-2802, "Notifications and Reports," pages 79-91.
-VPAP-2802, "Notifications and Reports," pages 79-91.  
Answer: D
 
25. G2.4.9 24
Unit 1 plant conditions:
        Time = 0200
        RCS cooldown in progress
Answer: D  
        RCS temperature = 250 oF
25. G2.4.9 24 Unit 1 plant conditions:  
        RCS pressure = 320 psig
Time = 0200  
        1A charging pump is the only running charging pump
RCS cooldown in progress   RCS temperature = 250  
  Current plant conditions:
o F  RCS pressure = 320 psig 1A charging pump is the only running charging pump  
        Time = 0210
   
        RCS pressure = 280 psig decreasing
Current plant conditions:  
        The maximum charging flow achieved with the 1A charging pump is 125 gpm
Time = 0210  
  Based on the above conditions, which ONE of the following: (1) states the correct
RCS pressure = 280 psig decreasing  
procedure to be entered and (2) what actions are directed by that procedure?
The maximum charging flow achieved with the 1A charging pump is 125 gpm  
  A. (1) 1AP-16.00 EXCESSIVE RCS LEAKAGE
 
   
Based on the above conditions, which ONE of the following: (1) states the correct  
procedure to be entered and (2) what actions are directed by that procedure?
 
  A. (1) 1AP-16.00 EXCESSIVE RCS LEAKAGE  
(2) Align charging pump suction to the RWST
B. (1) 1AP-16.00 EXCESSIVE RCS LEAKAGE  (2) Align and start 1B and 1C charging pumps


C. (1) 1-AP-16.01 SHUTDOWN LOCA (2) Align charging pump suction to the RWST  
    (2) Align charging pump suction to the RWST
 
B. (1) 1AP-16.00 EXCESSIVE RCS LEAKAGE
D. (1) 1-AP-16.01 SHUTDOWN LOCA (2) Align and start 1B and 1C charging pumps  
    (2) Align and start 1B and 1C charging pumps
 
C. (1) 1-AP-16.01 SHUTDOWN LOCA
 
    (2) Align charging pump suction to the RWST
K/A Knowledge of low power / shutdown implications in accident (e.g., loss of coolant  
D. (1) 1-AP-16.01 SHUTDOWN LOCA
accident or loss of residual heat removal) mitigation strategies.  
    (2) Align and start 1B and 1C charging pumps
 
K/A
Knowledge of low power / shutdown implications in accident (e.g., loss of coolant
accident or loss of residual heat removal) mitigation strategies.
K/A Match Analysis
K/A Match Analysis
Requires knowledge of shutdown procedures/mitigation strategies during an accident.  
Requires knowledge of shutdown procedures/mitigation strategies during an accident.
SRO-Only Analysis
SRO-Only Analysis
Requires in depth knowledge of abnormal procedure guidelines and selection based on  
Requires in depth knowledge of abnormal procedure guidelines and selection based on
plant conditions.  
plant conditions.
 
Answer Choice Analysis
Answer Choice Analysis
A. Incorrect: Note at the top of AP/16.00 states "If SI Accumulators are isolated,  
A. Incorrect: Note at the top of AP/16.00 states If SI Accumulators are isolated,
     1-AP-16.01, SHUTDOWN LOCA, should be used for guidance". Plausible  
     1-AP-16.01, SHUTDOWN LOCA, should be used for guidance. Plausible
because      if > 350  
because
0F, it would be correct. 2
     if > 350 0F, it would be correct. 2nd part is correct.
nd part is correct. B. Incorrect: Note at the top of AP/16.00 states "If SI Accumulators are isolated,      1-AP-16.01, SHUTDOWN LOCA, should be used for guidance". 2
B. Incorrect: Note at the top of AP/16.00 states If SI Accumulators are isolated,
nd part is      plausible because if > 350  
     1-AP-16.01, SHUTDOWN LOCA, should be used for guidance. 2nd part is
0F charging pumps would used as necessary per      AP/16.00 (OPMG not in service). Having OPMG in service requires only 1 Chg  
     plausible because if > 350 0F charging pumps would used as necessary per
     available to inject into the RCS.  
     AP/16.00 (OPMG not in service). Having OPMG in service requires only 1 Chg
C. Correct. If SI Accumulators are isolated, 1-AP-16.01, SHUTDOWN LOCA, should      be used for guidance. Being < 350  
     available to inject into the RCS.
oF requires the accumulators to be isolated.
C. Correct. If SI Accumulators are isolated, 1-AP-16.01, SHUTDOWN LOCA, should
     2 nd part is step 8 d RNO. D. Incorrect: 1
     be used for guidance. Being < 350 oF requires the accumulators to be isolated.
st part is correct.   2
     2nd part is step 8 d RNO.
nd part is plausible because if > 350  
D. Incorrect: 1st part is correct. 2nd part is plausible because if > 350 0F charging
0F charging      pumps would used as necessary per AP/16.00 (OPMG not in service). Having  
     pumps would used as necessary per AP/16.00 (OPMG not in service). Having
     OPMG in service requires only 1 Chg available to inject into the RCS.  
     OPMG in service requires only 1 Chg available to inject into the RCS.
 
Supporting References
Supporting References
Ref: AP/16.00, AP/16.01  
Ref: AP/16.00, AP/16.01
References Provided to Applicant
none


Answer: C
References Provided to Applicant
none 
Answer: C
}}
}}

Latest revision as of 22:12, 21 March 2020

Initial Exam 50-280, 281/2009-301 Draft SRO Written Exam
ML092920128
Person / Time
Site: Surry  Dominion icon.png
Issue date: 10/17/2009
From:
NRC/RGN-II
To:
Virginia Electric & Power Co (VEPCO)
References
50-280/09-301, 50-281/09-301
Download: ML092920128 (46)


See also: IR 05000280/2009301

Text

1. 0026G2.1.7 1

Unit 1 Initial Conditions:

  • The operations team is cooling down the unit in preparation for refueling in

accordance with 1-GOP-2.6, "UNIT COOLDOWN, LESS THAN 205 °F TO

AMBIENT."

  • The pressurizer (PRZR) is water-solid, and all PRZR heaters are tagged off.
  • RCS Pressure is approximately 250 psig.
  • RCS Temperature is approximately 180 °F.
  • 'A' and 'B' S/G WR levels are approximately 98%. 'C' S/G NR level is 65%.
  • All RCPs are stopped.

Current conditions:

  • A large unisolable CCW leak caused a complete and sustained loss of CCW.

CAPABILITY."

  • The operators were UNABLE to control RCS temperature using natural

circulation cooling.

  • CETC temperatures are approaching saturation.

Based on the current conditions, which one of the following is the NEXT method of

providing decay heat removal, in accordance with AP-27.00?

A. Forced feed cooling.

B. Reflux boiling heat removal.

C. Gravity feed cooling.

D. Cooling the RCS with the SFP and RWST coolers.

K/A

Loss of Component Cooling Water: Ability to evaluate plant performance and make

operational judgments based on operating characteristics, reactor behavior, and

instrument interpretation.

(CFR: 41.5/43.5/45.12/45.13) (SRO - 4.7)

K/A Match Analysis

Given a complete loss of component cooling water under S/D and C/D conditions, the

applicant must use the plant conditions to determine the appropriate course of action.

SRO-Only Analysis

See attached SRO-only guidance flowchart. As an amplification, this question is

focusing on the correct procedural selection of the various attachments in AP-27.00 (the

four answer choices are word-for-word the titles of the various attachments in

AP-27.00); and is therefore testing procedural knowledge on a different and more

detailed level than what is expected for a RO.

Answer Choice Analysis

A. INCORRECT. Attachment 4 of AP-27.00 requires a transition to Attachment 5 to

establish reflux boiling heat transfer for the given condition. Plausible because

1-OSP-ZZ-004 specifies that forced feed and bleed cooling is a possible "mandatory

backup cooling method" in the initial given plant conditions.

B. CORRECT. Attachment 4 of AP-27.00 requires a transition to Attachment 5 to

establish reflux boiling heat transfer for this condition.

C. INCORRECT. See analysis of A. above. Plausible because gravity feed cooling is a

method specified as attachment 8 of AP-27.00.

D. INCORRECT. See comments for A. above. Plausible because cooling the RCS

with the SFP and RWST coolers is a cooling method as specified in attachment 10 of

AP-27.00.

Supporting References

- 1-GOP-2.6, "UNIT COOLDOWN, LESS THAN 205 F TO AMBIENT," rev 28 (p. 8, 12,

18, 19, 20-22)

-SPS TS Fig. 3.1-2, "RCS COOLDOWN LIMITATIONS."

-1-AP-15.00, "LOSS OF COMPONENT COOLING," CAUTION before step 1.

1-AP-27.00, "LOSS OF DECAY HEAT REMOVAL CAPABILITY," rev 18; procedural

flowpath to steps 19, 20, and 21; attachments 4, 5, 6

1-OSP-ZZ-004, "UNIT 1 SAFETY SYSTEMS STATUS LIST FOR COLD

SHUTDOWN/REFUELING CONDITIONS," rev 35, p. 10 (table of mandatory and

non-mandatory backup cooling methods)

References Provided to Applicant

none

Answer: B

2. 0036AA2.03 1

In accordance with the Surry Power Station FSAR Accident Analysis, which one of the

following Fuel Handling Accident conditions result in a HIGHER total effective dose

equivalent (TEDE) received at the Exclusion Area Boundary (EAB) than what is

assumed in the accident analysis?

Consider that ALL OTHER assumptions and conservatisms inherent in the analysis

remain UNCHANGED, except for the individual condition below.

A. The delay time from reactor shutdown to the initiation of fuel assembly transfer

operations is 148 hours0.00171 days <br />0.0411 hours <br />2.44709e-4 weeks <br />5.6314e-5 months <br />.

B. The analysis of a postulated fuel handling accident in containment is based on 50%

of the fuel assembly Iodine-131 activity assumed to be released into the reactor

cavity water.

C. The total activity released from a fuel handling accident in containment is assumed

to be released instantaneously.

D. The analysis of a postulated fuel handling accident in the spent fuel pool is based

on a fuel radionuclide inventory derived from a rated core power level of 2546 MWt.

K/A

Ability to determine and interpret the following as they apply to the Fuel Handling

Incidents: Magnitude of potential radioactive release.

(CFR: 43.5/45.13) (SRO - 4.2)

K/A Match Analysis

The question requires the applicant to understand the assumptions that are behind the

fuel handling accident (FHA) analysis as presented in the Surry FSAR.

SRO-Only Analysis

The applicant is required to know and understand the severity factors inherent in the

FSAR/design basis accidents for fuel handling that are outside the knowledge

requirement for ROs.

Answer Choice Analysis

A. INCORRECT. On page 14.4-6 and 14.4-8 of the UFSAR, the accident analyses

assume "a delay time from reactor shutdown to the initiation of fuel assembly transfer

operations is at least 100 hours0.00116 days <br />0.0278 hours <br />1.653439e-4 weeks <br />3.805e-5 months <br />." Furthermore, Surry Technical Specification 3.10

requires a minimum 100-hour period between the shutdown of a unit and initiation of

fuel movement. Therefore, the wording and the exactitude of the number's

specification (100 hours0.00116 days <br />0.0278 hours <br />1.653439e-4 weeks <br />3.805e-5 months <br /> plus two days) is plausible. However, the distractor is

incorrect, because a delay time that is longer than the 100 hrs assumed in the analysis

will result in a LOWER dose, NOT a HIGHER dose as required by the question stem.

B. CORRECT ANSWER. As specified in the UFSAR page 14.4-6, "9. 5.35 percent of

the fuel assembly Iodine-131 activity is assumed to be released into the reactor cavity

water, as are five percent of the other iodine isotopes present in the fuel assembly,

99.85% being elemental and 0.15% in the organic form. The decontamination factor

(DF) for elemental ioding is 500 while the DF for organic iodine is 1." The correct

answer is plausible because 50% of the iodine activity is a plausible design criteria, but

much greater than what is actually assumed in the accident analysis.

C. INCORRECT. The Surry UFSAR states on p. 14.4-6, that for a fuel handling

accident in containment, "More specific conservative assumptions are: 1. A puff

release of radioactivity occurs as the result of the rupture of a fuel assembly in the

reactor fuel cavity. The puff relase is instantaneously and uniformly distributed through

one-half the containment volume." Therefore, answer "C" is plausible because it is an

actual assumption used in the analysis. To further add to the plausibility, if the analysis

had assumed a certain finite release time, changing this parameter to model the

accident as an instantaneous release would result in a higher dose--which is what the

question stem is asking for. The distractor is incorrect because it is an assumption in

the analysis, and does not, in fact, result in a HIGHER dose.

D. INCORRECT. The distractor is derived from one of the actual assumptions used

in the analysis. Page 14.4-8 of the UFSAR states, "The fuel radionuclide inventory was

based on a core power level of 2605 MWt. This core power level is conservative

compared to 102% of the uprated power level of 2546 MWt (i.e., 2597 MWt)."

Therefore, answer "D" is plausible because it uses language from the actual assumption

used in the analysis. The distractor is incorrect because it states a lower power level

than what is assumed in the analysis, and therefore does not, in fact, result in a

HIGHER dose.

Supporting References

-Surry Power Station UFSAR rev 36 section 14.4.1, "Fuel-Handling Accidents."

-Surry Power Station Technical Specifications 1.0 (p. 1.0-1) and 3.10 (p. 3.10-3 and p.

3.10-9).

-The question developer constructed this question by modifying a similar question found

in an Indian Point unit 2 ILO exam given in 2005.

References Provided to Applicant

none

Answer: B

3. 0039A2.03 1

Unit 1 Initial Conditions:

  • 100% Power
  • Control room operators have transitioned to 1-AP-24.00, "MINOR SG TUBE

LEAK."

Current conditions:

  • Condenser air ejector radiation monitor, RI-SV-111, alarms but the automatic

actions do NOT occur.

  • Main Steam (MS) Line B radiation monitor, RI-MS-125, alarms.
  • MS Line A and C radiation monitor readings are slightly higher than before.

"REACTOR TRIP OR SAFETY INJECTION."

  • Safety Injection (SI) does NOT automatically actuate.
  • At step 4 of 1-E-0, it is determined that SI is NOT REQUIRED.

Based on the current conditions, which one of the following is (1) the correct procedural

flowpath, AND (2) the correct method to procedurally address the failure of RV-SI-111

automatic actions?

A. (1) Transition to 1-ES-0.1, "REACTOR TRIP RESPONSE."

(2) Perform steps in 1-AP-24.00 to correct the failure of RV-SI-111 automatic

actions, in parallel with 1-ES-0.1.

B. (1) Transition to 1-ES-0.1, "REACTOR TRIP RESPONSE."

(2) Perform steps in 1-AP-24.01 to correct the failure of RV-SI-111 automatic

actions, in parallel with 1-ES-0.1.

C. (1) Transition to 1-AP-24.01, "LARGE STEAM GENERATOR TUBE LEAK."

(2) Perform steps in 1-AP-24.01 to correct the failure of RV-SI-111 automatic

actions.

D. (1) Transition to 1-AP-24.01, "LARGE STEAM GENERATOR TUBE LEAK."

(2) Perform steps in 1-AP-24.00 to correct the failure of RV-SI-111 automatic

actions, in parallel with 1-AP-24.01.

K/A

Ability to (a) predict the impacts of the following malfunctions or operations on the

MRSS; and (b) based on predictions, use procedures to correct, control, or mitigate the

consequences of those malfunctions or operations:

Indications and alarms for main steam and area radiation monitors (during SGTR).

(CFR: 41.5/43.5/45.3/45.13) (SRO - 3.7)

K/A Match Analysis

Requires the applicant to identify the situation, given a set of conditions, and exercise

the correct procedures to mitigate both the SGTR and a failure of SJAE radiation

monitor automatic actions.

SRO-Only Analysis

See attached SRO-only guidance flowchart. Internal EOP/AP procedure transition.

Knowledge beyond simply entry conditions is required to arrive at the correct answer.

Answer Choice Analysis

A. INCORRECT. Both AP-24.00 and AP-24.01 clearly state that the correct transition

is to AP-24.01 instead of ES-0.1. However, ES-0.1 is certainly a plausible choice,

because once 1-E-0 is initiated, the RNO of step 4 directs a transition to ES-0.1, without

any notes or cautions in the EOP about this particular case, where a transition to ES-0.1

is NOT desired.

B. INCORRECT. See analysis for A. above. Although AP-24.01 has specific steps to

ensure the proper SJAE alignment, a note before step 1 of AP-24.01 specifically states

that ES-0.1 must NOT be performed in parallel.

C. CORRECT. Even though 1-E-0 step 4 RNO directs a transition to 1-ES-0.1, the

correct flow path is to transition from 1-E-0 to 1-AP-24.01. This is specified in

AP-24.00, which has as step 2, "Initiate 1-E-0..." and as step 3, "GO TO 1-AP-24.01...."

In 1-AP-24.01, step 13 RNO will realign the correct valves and ensure the automatic

actions take place.

D. INCORRECT. Transitioning to 1-AP-24.01 is correct; however, one should not carry

out AP-24.00 actions in parallel with AP-24.01. Step 3 of AP-24.00 specifies that if a

Reactor trip is required, the operator must initiate 1-E-0 and GO TO 1-AP-24.01--that is,

one is NOT to remain in AP-24.00. Once a reactor trip occurs and 1-AP-24.01 is

entered, there is no other (re-)entry condition into AP-24.00.

NOTE: another possible wrong distractor could be "operators are required to be able to

correct a radiation monitor automatic action failure from memory ("skill of the craft")" for

the second part of choices "B" and "D;" see Lesson Plan ND-93.5-LP-1-DRR.

Supporting References

- 1-AP-24.00, "MINOR SG TUBE LEAK," rev 10, p. 2 and 3.

- 1-AP-24.01, "LARGE STEAM GENERATOR TUBE LEAK," rev 28, p. 2 and 7

- 1-E-0, "REACTOR TRIP OR SAFETY INJECTION," rev. 61, p. 3

-Surry lesson plan ND-93.5-LP-1, "PRE-TMI RADIATION MONITORING SYSTEM," rev

10, p. 2, 16, slide 7

References Provided to Applicant

none

Answer: C

4. 003AG2.4.31 8

Unit 1 Initial Conditions:

  • Reactor power = 100%
  • 0-AP-1.00 ROD CONTROL SYSTEM MALFUNCTION is entered

Based on the above conditions, which one of the following correctly states (1) if

0-AP-1.00 directs the initiation of 0-AP-23.00 RAPID LOAD REDUCTION to reduce

power and (2) the parameter that is required to be monitored to reduce and stabilize

power?

A. (1) Yes

(2) Loop T

B. (1) Yes

(2) the highest reading PRNI

C. (1) No

(2) Loop T

D. (1) No

(2) the highest reading PRNI

K/A

Dropped Control Rod: Knowledge of annunciator alarms, indications, or response

procedures.

K/A Match Analysis

Requires knowledge of response procedures for a dropped control rod.

SRO-Only Analysis

Requires assessing plant conditions and then prescribing a procedure or section of a

procedure to mitigate, recover, or with which to proceed. Knowledge above knowing

entry conditions for APs is required.

Answer Choice Analysis

A. Incorrect; 1st part is incorrect because AP/1.00 does not reference AP/23 and

AP/1.00 gives an hour to reduce power to 70-74%. 1st part is plausible because

AP/23 is frequently used to reduce power during plant upsets. 2nd part is correct

per a caution in AP/1.00 before step 17.

B. Incorrect; 1st part is incorrect because AP/1.00 does not reference AP/23 and AP/1.0

AP/23 is frequently used to reduce power during plant upsets.2nd part is incorrect

because caution in AP/1.00 states that DT must be monitored during the ramp and

used to stabilize power. 2nd part is plausible because the highest reading PRNI

will

be more conservative than DT.

C. Correct: 1st part is AP/1.00 Step 17. A caution in AP/1.00 states that DT must be

monitored during the ramp and used to stabilize power.

D. Incorrect; 1st part is correct. 2nd part is incorrect because caution in AP/1.00 states

that DT must be monitored during the ramp and used to stabilize power. 2nd part

is plausible because the highest reading PRNI will be more conservative than DT.

Supporting References

0-AP-1.00, ROD CONTROL SYSTEM MALFUNCTION

References Provided to Applicant

none

Licensee discuss the potential use of AP/23 for the power reduction.

Answer: C

5. 0054G2.2.25 1

Which one of the following correctly identifies two reasons for the Feedwater Line

Isolation function, as specified in the bases of Technical Specification 3.7,

"INSTRUMENTATION SYSTEMS?"

A. (1) Prevent excessive cooldown of the Reactor Coolant System; AND

(2) Reduces the consequences of a design basis steam generator tube rupture by

preventing steam generator overfill.

B. (1) Prevent excessive moisture carry-over that could damage the main turbine

blading; AND

(2) Reduces the consequences of a design-basis steam generator tube rupture by

preventing steam generator overfill.

C. (1) Prevent excessive cooldown of the Reactor Coolant System; AND

(2) Reduces the consequences of a steam line break inside the containment by

stopping the entry of main feedwater.

D. (1) Prevent excessive moisture carry-over that could damage the main turbine

blading; AND

(2) Reduces the consequences of a steam line break inside the containment by

stopping the entry of main feedwater.

K/A

Loss of Main Feedwater:

Knowledge of the bases in Technical Specifications for limiting conditions for operations

and safety limits.

(CFR: 41.5 / 41.7 / 43.2) (SRO - 4.2)

K/A Match Analysis

The question is a straighforward link directly to the TS basis for feedwater isolation.

SRO-Only Analysis

See attached SRO-only flowchart. TS Basis knowledge required to arrive at correct

answer.

Answer Choice Analysis

A. INCORRECT. The distractors are basically reasons for the HI-HI S/G level

automatic function, worded to sound like the correct answers from the TS basis.

B. INCORRECT. see analysis of A. and C.

C. CORRECT. Answer is basically word-for-word from TS 3.7, which states: "The

feedwater lines are isolated upon actuation of the SIS in order to prevent excessive

cooldown of the Reactor Coolant System. This mitigates the effects of an accident

such as a steam line break which in itself causes excessive temperature cooldown.

Feedwater line isolation also reduces the consequences of a steam line break inside the

containment by stopping the entry of feedwater."

D. INCORRECT. See analysis of A. and C.

Supporting References

-Surry Technical Specification 3.7, amendment nos. 180 and 180, p. 3.7-5 and 3.7-6

References Provided to Applicant

none

Answer: C

6. 0055G2.4.6 1

Unit 1 Initial Conditions:

100% power.

TUBE RUPTURE."

Current conditions:

  • A maximum-rate cooldown using steam dumps to the condenser has begun.
  • SI has just been reset.
  • The RO reports that condenser vacuum is 28 " Hg and slowly lowering.
  • The TSC informs the operations team that once all actions of E-3 are complete,

it is required to implement the post-SGTR procedure that allows the FASTEST

means of depressurizing the RCS and ruptured S/G.

Based on the current conditions, which one of the following is (1) a required action

specified by E-3, AND (2) the correct post-SGTR procedure to implement?

A. (1) Ensure the condenser air ejector is aligned to containment, and then OPEN

1-SV-TV-102A.

(2) GO TO 1-ES-3.2, "POST-SGTR COOLDOWN USING BLOWDOWN."

B. (1) Ensure the condenser air ejector is aligned to containment, and then OPEN

1-SV-TV-102A.

(2) GO TO 1-ES-3.3, "POST-SGTR COOLDOWN USING STEAM DUMP."

C. (1) IF a Hi-CLS signal is NOT actuated, THEN realign the condenser air ejector for

normal operations.

(2) GO TO 1-ES-3.2, "POST-SGTR COOLDOWN USING BLOWDOWN."

D. (1) IF a Hi-CLS signal is NOT actuated, THEN realign the condenser air ejector for

normal operations.

(2) GO TO 1-ES-3.3, "POST-SGTR COOLDOWN USING STEAM DUMP."

K/A

055 Condenser Air Removal

Knowledge of EOP mitigation strategies. (as relating to the Condenser Air Removal

system)

(CFR: 41.10 / 43.5 / 45.13) (SRO - 4.7)

K/A Match Analysis

The question requires the SRO applicant to demonstrate detailed knowledge of EOP

mitigation strategies/transitions as related to expected effects of the condenser air

removal system following an SI.

SRO-Only Analysis

See attached SRO-only flowchart.

Linked to SRO-only knowledge based on detailed internal EOP transition criteria and

procedural selection outside of initial/entry conditions.

Answer Choice Analysis

A. INCORRECT. The lowering condenser vacuum is an expected condition. In the

next few steps, 1-E-3 will ensure the proper operation of the air ejectors and mitigate

the concern. Therefore the (1) part of this answer is correct. Part (2) is incorrect; the

lesson plan for ES-3.3, "POST SGTR COOLDOWN USING STEAM DUMP," is very

clear that it provides the fastest means of depressurizing the RCS and ruptured SG.

ES-3.2 is plausible, if the applicant believes that the lowering condenser vacuum

precludes the use of ES-3.3 through the steam dumps.

B. CORRECT. (1) Step 14 of 1-E-3 will align condenser air ejector to containment

and improve the degraded vacuum condition. (2) is also correct; see analysis of A.

above.

C. INCORRECT. (1) is incorrect, but plausible, because valve TV-SV-102 will (only)

close automatically on a Hi-CLS signal. Also plausible because the question stem

states that vacuum is lowering. Part (2) is also the incorrect procedural transition.

D. INCORRECT. (1) is incorrect choice, (2) is the correct proceural transition; see

above analyses.

Supporting References

-Surry lesson plan ND-89.3-LP-2, "MAIN CONDENSATE SYSTEM," rev. 18, p. 11.

-1-E-3, "STEAM GENERATOR TUBE RUPTURE," rev. 38, p. 10, 12.

-Surry lesson plan ND-95.3-LP-16, "ES-3.3 POST SGTR COOLDOWN USING STEAM

DUMP," rev. 12, p. 31.

References Provided to Applicant

none

Answer: B

7. 006A2.12 12

Initial plant conditions on Unit 1 are as follows:

  • Radiation levels in the Auxiliary Building are increasing.
  • The crew has transitioned to ECA-1.2 LOCA Outside Containment.
  • The crew closed/verified closed SI-MOV-1890A and -1890B.
  • RCS pressure was at 1700 psig and slowly dropping.

Current plant conditions on Unit 1 are as follows:

  • The crew has closed SI-MOV-1890C.
  • RCS pressure is at 1550 psig and slowly rising.

Which one of the following describes (1) the status of the LOCA and (2) the required

procedure transition?

A. (1) LOCA has been isolated.

(2) Go to ECA-1.1, Loss of Emergency Coolant Recirculation.

B. (1) LOCA still exists.

(2) Go to ECA-1.1, Loss of Emergency Coolant Recirculation.

C. (1) LOCA has been isolated.

(2) Go to 1-E-1, Loss of Reactor or Secondary Coolant.

D. (1) LOCA still exists.

(2) Go to 1-E-1, Loss of Reactor or Secondary Coolant.

K/A

Emergency Core Cooling: Ability to (a) predict the impacts of the following

malfunctions or operations on the ECCS; and (b) based on those predictions, use

procedures to correct, control, or mitigate the consequences of those malfunctions or

operations: Conditions requiring actuation of ECCS.

K/A Match Analysis

Requires applicant to predict the impact of a leak outside containment on the alignment

of emergency core cooling equipment and perform the actions from ECA-1.2 for

transitioning back to E-1.

SRO-Only Analysis

The question requires the applicant to assess plant conditions and know the intent of

the specific steps to determine the correct procedural transition..

Answer Choice Analysis

A. In-Correct but plausible since the increasing RCS pressure indicates the leak has

been isolated. In addition, the previous actions have closed all the cold and hot leg

recirculation valves so it would seem plausible to transition to ECA-1.1, Loss of

Emergency Coolant Recirculation. However, the correct action is to transition back to

E-1.

B. In-Correct but plausible since the actions are correct if the leak still exists. However,

the increasing RCS pressure indicates the leak has been isolated and the crew should

transition to E-1.

C. Correct - The increasing RCS pressure indicates the leak has been isolated. The

correct actions are to place LHSI pumps in PTL, close LHSI pump suction valves and

transition to E-1.

D. In-Correct but plausible since reopening SI-MOV-1890C is correct if the leak still

exists. The transition to E-1 is correct. However, the leak has been isolated.

Supporting References

ND-95.3-LP-21, ECA-1.2, LOCA Outside Containment, Rev. 7, Obj. A

References Provided to Applicant

none

NOTE:Original question used on Surry 02-301 exam - developed by G. Laska

(WE04G2.4.9). Modified conditions to indicate isolation of leak and asked for status of

leak.

Answer: C

8. 0073A2.02 1

Unit 1 Initial Conditions:

  • Holding at 30% power for chemistry, following a refueling outage.
  • The Power Range NI input for 1-MS-RM-190, 1-MS-RM-191, and 1-MS-RM-192

(Main Steam Line N-16 radiation monitors) has failed to 100% power.

Current conditions:

  • Pressurizer level is STABLE
  • VCT level is STABLE

Based on the current conditions, which one of the following (1) is the correct procedural

transition in accordance with the ARP for 1A-B3, "N-16 ALERT," AND (2) if no

corrective actions have been taken for the power range NI input module, the alarm

setpoints for 1-MS-RM-190 through -192 are _______________. ?

A. (1) 0-OSP-RC-002, "STEAM GENERATOR PRIMARY TO SECONDARY

LEAKAGE MONITORING."

(2) lower than normal.

B. (1) 1-AP-16.00, "EXCESSIVE RCS LEAKAGE."

(2) lower than normal.

C. (1) 1-AP-16.00, "EXCESSIVE RCS LEAKAGE."

(2) higher than normal.

D. (1) 0-OSP-RC-002, "STEAM GENERATOR PRIMARY TO SECONDARY

LEAKAGE MONITORING."

(2) higher than normal.

K/A

Process Radiation Monitor (PRM) System

Ability to (a) predict the impacts of the following malfunctions or operations on the PRM

system; and (b) based on those predictions, use procedures to correct, control, or

mitigate the consequences of those malfunctions or operations: Detector failure.

(CFR: 41.5/43.5/45.3/45.13) (SRO - 3.2)

K/A Match Analysis

Given a PRM detector failure condition, the SRO applicant will correctly determine the

impact on the setpoints; and given an operationally valid situation, the SRO applicant

will correctly apply/select procedures to correct, control, or mitigate the issue.

SRO-Only Analysis

This is an analysis level question since the candidate must analyze the impact of the

power input to the detector circuitry failing high to determine the effect on the alarm

setpoint.

This is an SRO only question linked to 10CFR55.43(b)(5). The question can NOT be

answered using system knowledge alone. It can NOT be answered by knowing

immediate actions, or basic procedure entry conditions (cover page material). To

correctly answer this question, the candidate must assess plant conditions and then

decide which procedure should be implemented.

Answer Choice Analysis

NOTE TO SURRY: Please validate the Power Range NI input part of this

question with your actual plant response. The lesson plan for the N-16 monitors

was not very detailed about power compensation.

A. INCORRECT. (1) The ARPs for both N-16 HIGH and N-16 ALERT specify to

transition to 1-AP-16.00, "EXCESSIVE RCS LEAKAGE," on any of the following

conditions: PRZR level - DECREASING; OR Annunciator 1D-E5, CHG PP TO REGEN

HX HI-LO FLOW-LIT; OR A discernable negative change in VCT level trend has

developed." 0-OSP-RC-002 is an incorrect, but plausible choice, because it would be

correct if the annunciator 1D-E5 were NOT lit. (2) Due to much longer loop transport

times at lower power, N-16 has more time to decay prior to reaching the area in the

main steam lines adjacent to the monitors. Therefore, the alarm setpoint for a given

leak must be lower than that for 100% power to ensure accuracy. Thus, (2) is incorrect

for this distractor.

B. INCORRECT. (1) is correct choice, (2) incorrect. See above.

C. CORRECT. Both (1) and (2) correct as per the above.

D. INCORRECT. (1) is incorrect, (2) correct. See above analysis.

Supporting References

-modified from McGuire 2009-301 exam question SRO #94.

-Surry procedure 1A-A3, "N-16 HIGH," rev. 3.

-Surry procedure 1A-B3, "N-16 ALERT," rev. 3.

-Surry procedure 1A-C3, "N-16 TROUBLE," rev. 3.

References Provided to Applicant

none

Answer: C

9. 0076AA2.02 1

Unit 1 Initial Conditions:

  • At time 0930, unexpected grid fluctuations caused an automatic turbine trip from

100% power.

  • Chemistry personnel drew a post-trip RCS sample at time 1005.
  • Control room operators have stabilized the unit at 547 °F and normal operating

pressure.

Current conditions:

  • At time 1045, a Chemistry supervisor reports that the post-trip RCS sample total

specific activity reading is greater than the 100/(E bar) limit by 28%.

Based on the current conditions, which one of the following (1) is the correct time the

LCO for Technical Specification (TS) 3.1.D, Maximum Reactor Coolant Activity, is NOT

met; AND (2) the basis of the requirement to cool down the reactor to less than 500 °F,

in accordance with TS 3.1.D?

A. (1) LCO not met at 1005;

(2) In the unlikely event of an assumed 30 minute radioactive release during the

design-basis S/G tube rupture, the iodine partitioning factor below this RCS

temperature ensures exposure limits are not exceeded at the site boundary.

B. (1) LCO not met at 1045;

(2) In the unlikely event of a design-basis S/G tube rupture, the saturation pressure

corresponding to this RCS temperature is well below the pressure at which the

atmospheric relief valves on the secondary side would be actuated.

C. (1) LCO not met at 1045;

(2) In the unlikely event of an assumed 30 minute radioactive release during the

design-basis S/G tube rupture, the iodine partitioning factor below this RCS

temperature ensures exposure limits are not exceeded at the site boundary.

D. (1) LCO not met at 1005;

(2) In the unlikely event of a design-basis S/G tube rupture, the saturation pressure

corresponding to this RCS temperature is well below the pressure at which the

atmospheric relief valves on the secondary side would be actuated.

K/A

High Reactor Coolant Activity

Ability to determine and interpret the following as they apply to High Reactor Coolant

Activity: Corrective actions required for high fission product activity in RCS.

(CFR: 43.5/45.13) (SRO - 3.4)

K/A Match Analysis

The question requires the SRO applicant to correctly demonstrate knowledge of the

Technical Specifications for RCS activity, as well as the basis for this specification.

SRO-Only Analysis

See attached SRO-only flow chart. TS Basis knowledge needed to arrive at correct

answer.

Answer Choice Analysis

A. INCORRECT. 1005 is the incorrect time, because the initial notification of the

abnormality is considered the "start time" of inoperability. The second part of the

answer is also incorrect; TS 3.1.D. basis states "Rupture of a steam generator tube

would allow radionuclides in the reactor coolant to enter the secondary system. The

limiting case involves a double-ended tube rupture coincident with loss of the condenser

and release of steam from the secondary side to the atmosphere via the main steam

safety valves or atmospheric relief valves. This is assumed to continue for 30 minutes

in the analysis. The operator will take action to reduce the primary side temperature to

a value below that corresponding to the relief or safety valve setpoint. Once this is

accomplished the valves can be closed and the release terminated." However, the

distractor is plausible, because everything associated with this specification is

concerned with a release during a design basis tube rupture.

B. CORRECT. See above analysis. The statement about the saturation pressure and

atmospheric relief valves is basically word-for-word from the TS.

C. INCORRECT. Incorrect time, wrong reason for RCS cooldown.

D. INCORRECT. See above analysis.

Supporting References

-SPS TS 3.1.D

References Provided to Applicant

Steam Tables

Answer: B

10. 010G2.4.20 12

Unit 1 initial conditions:

  • Reactor power = 100%
  • Reactor is manually tripped

Current conditions:

  • It is determined that Pzr spray is not adequately reducing RCS pressure and the

decision is made to use the PORV to reduce RCS pressure.

Based on the above conditions, which one of the following states: (1) the reason for

minimizing the cycling of the PORV and (2) the procedure that 1-E-3 directs you to

perform if the PORV and its associated block valve fail to close?

A. (1) To prevent rupturing the PRT

(2) 1-ECA 3.3 SGTR WITHOUT PRESSURIZER PRESSURE CONTROL

B. (1) To prevent rupturing the PRT

(2) 1-ECA 3.1 SGTR WITH LOSS OF REACTOR COOLANT - SUBCOOLED

RECOVERY

C. (1) To prevent the Tube rupture from degrading

(2) 1-ECA 3.3 SGTR WITHOUT PRESSURIZER PRESSURE CONTROL

D. (1) To prevent the Tube rupture from degrading

(2) 1-ECA 3.1 SGTR WITH LOSS OF REACTOR COOLANT - SUBCOOLED

RECOVERY

K/A

Pressurizer Pressure Control: Knowledge of the operational implications of EOP

warnings, cautions, and notes.

K/A Match Analysis

Requires knowledge of EOP Cautions.

SRO-Only Analysis

Requires detailed knowledge of EOP steps having to do with securing PORV use when

depressurizing the RCS.

Answer Choice Analysis

A Incorrect: 1st part is correct. 2nd part is plausible because it is criteria for closing

the PORV if Pzr level is > 22%.

B Correct: The PORV relieves to the PRT so using the PORV will eventually cause

the PRT rupture disk to rupture. Criteria for securing from using the

PORV are:

Pzr level>69%

RCS subcooling < 30 0F

RCS press < Ruptured SG press AND Pzr level > 22%

C Incorrect: 1st part is plausible because the PORVs have failed to reseat (TMI) which

constitutes a SBLOCA. 2nd part is plausible because it is criteria for

closing the PORV if Pzr level is > 22%.

D Incorrect: 1st part is plausible because the PORVs have failed to reseat (TMI)

which

constitutes a SBLOCA. 2nd part is correct.

Supporting References

1-E-3 Steam Generator Tube Rupture. ND-95.3-LP-13 Obj A & B

References Provided to Applicant

none

Answer: B

11. 015/17AG2.2.22 1

Initial plant conditions on Unit 2 are as follows:

  • A power increase is in progress following reactor startup.
  • Reactor power is at 8%.
  • Pressurizer Spray valve PCV-455A cannot be opened.
  • All three RCPs are operating.

Current plant conditions on Unit 2 are as follows:

  • RCP C trips on ground overcurrent.

Based on the above conditions, which one of the following describes whether action

statements of the following LCOs are required to be performed:

Action statement(s) of

A. LCO 3.1.A.4 is/are required.

LCO 3.1.A.5 is/are NOT required.

B. LCO 3.1.A.4 is/are NOT required.

LCO 3.1.A.5 is required.

C. both LCO 3.1.A.4 and LCO 3.1.A.5 are required.

D. neither LCO 3.1.A.4 nor LCO 3.1.A.5 are required.

K/A

RCP Malfunctions

Knowledge of limiting conditions for operations and safety limits as it relates RCP

Malfunctions.

K/A Match Analysis

Applicant must recognize that loss of RCP C will require entry into both LCO 3.1.A.4.

and 3.1.A.5.

SRO-Only Analysis

The question requires a knowledge of the T.S. bases associated with LCO 3.1.A.4

concerning what constitutes an in-service reactor coolant loop to determine whether

actions from LCO 3.1.A.4 are required.

Answer Choice Analysis

A. In-Correct but plausible since LCO 3.1.A.4 would be entered given that LCO 3.1.A.4.b. states, POWER OPERATION with less than three loops in service is

prohibited.. However, LCO 3.1.A.5 would also be entered since LCO 3.1.A.5.a

states, The reactor shall be maintained subcritical by at least 1% until the steam

bubble is established and the necessary sprays and at least 125 KW of heaters

are operable. With PCV-455A inoperable, PCV-455B becomes inoperable once

RCP C trips.

B. In-Correct but plausible if the applicant believes that a running RCP is not required

for an RCS loop to be considered in service. The second half of the answer is

correct. LCO 3.1.A.5 would be entered since LCO 3.1.A.5.a states, The reactor

shall be maintained subcritical by at least 1% until the steam bubble is established

and the necessary sprays and at least 125 KW of heaters are operable.

C. Correct -. Both LCO 3.1.A.4 and LCO 3.1.A.5 would be entered. See previous

distractor discussions for justification.

D. In-Correct but plausible if the applicant believes that a running RCP is not required

for an RCS loop to be considered in service AND does not recognized that both

Pressurizer Spray valves are inoperable once RCP C trips.

NOTE TO LICENSEE: The correct answer was based on discussions with facility

SME. The Technical Specifications bases do not provide a specific discussion

with regards to what constitutes a loop being in service per LCO 3.1.A.4. Please

provide documentation as to what constitutes a loop being in service.

Also, neither LCO 3.1.A.5 nor its basis states that sprays have an impact on

Technical Specifications once the reactor is above 1% subcritical. Please provide

documentation for pressurizer operability when sprays are unavailable once a

steam bubble is established and power is above 1% subcritical.

Supporting References

Technical Specification 3.1.A

Technical Specification 3.0.1

ND-88.1-LP-9, Technical Specifications Overview, Rev. 16, Obj. G

References Provided to Applicant

none

Answer: C

12. 025AA2.05 2

Unit 1 initial conditions:

Time = 0800

Plant was on RHR following shutdown for refueling

SGs are not available

RCS temperature = 190 0F stable

RHR flow = 2200 gpm

RCS level = 10 feet decreasing

AP/27 (LOSS OF DECAY HEAT REMOVAL CAPABILITY) has been initiated

Current plant conditions:

Time = 0825

1 CHG pump was started for RCS fill

RHR pumps have been secured

RCS level = 11.5 ft increasing

RCS temperature = 205 0F increasing

Based on the above conditions: (1) Classify the event using the Emergency Plan and

(2) Once RHR is restored, state the maximum cooldown rate allowed per 1-AP-27?

(Reference Provided)

A. (1) Alert

(2) 25 0F/Hr

B. (1) Alert

(2) 50 0F/Hr

C. (1) Site Area Emergency

(2) 50 0F/Hr

D. (1) Site Area Emergency

(2) 25 0F/Hr

K/A

Loss of RHR: Ability to determine and interpret the following as they apply to the Loss of

Residual Heat Removal System: Limitations on LPI flow and temperature rates of

change.

K/A Match Analysis

Requires knowledge of limits on cooldown rate during loss of decay heat removal and

recovery.

Requires the ability to determine the emergency classification based on the reduction

and eventual loss of RHR flow due to invetory loss and requires knowledge of plant

cooldown limits once RHR is restored.

SRO-Only Analysis

Requires in depth knowledge of administrative procedures that specify hierarchy,

implementation, and/or coordination of plant normal, abnormal, and emergency

procedures.

Answer Choice Analysis

A. Incorrect: 1st part is incorrect because CS2 (Loss of Reactor Vessel inventory

affecting core decay heat removal capability) existed = SAE. 1st part is plausible

because CA 2 (Loss of RCS inventory) and CA3 (Inability to maintain plant in cold

shutdown with irradiated fuel in the Reactor Vessel) apply. 2nd part is incorrect

because 50 0F/Hr is the rate used for recovery once RHR is re-established. It is

plausible because 25 0F/Hr is the cooldown rate for natural circulation cooldown in

Attachment 4 of AP/27.

B. Incorrect: 1st part is incorrect because CS2 (Loss of Reactor Vessel inventory

affecting core decay heat removal capability) existed = SAE. 1st part is plausible

because CA 2 (Loss of RCS inventory) and CA3 (Inability to maintain plant in cold

shutdown with irradiated fuel in the Reactor Vessel) apply. 2nd part is correct per

1AP/27 , Step 27.

C. Correct: 1st part is incorrect because CS2 (Loss of Reactor Vessel inventory

affecting core decay heat removal capability) existed = SAE. 2nd part is correct

per

1AP/27 , Step 27.

D. Incorrect: 1st part is incorrect because CS2 (Loss of Reactor Vessel inventory

affecting core decay heat removal capability) existed = SAE. 2nd part is incorrect

because 50 0F/Hr is the rate used for recovery once RHR is re-established. It is

plausible because 25 0F/Hr is the cooldown rate for natural circulation cooldown in

Attachment 4 of AP/27.

Supporting References

Surry Emergency Plan AP/27 (LOSS OF DECAY HEAT REMOVAL CAPABILITY)

References Provided to Applicant

Emergency Plan

Answer: C

13. 027AA2.15 4

Unit 1 initial conditions:

Time = 1000

Reactor power = 100%

PORV-1455C indicates open

Both Pzr Spray valves indicate open

RCS Pressure = 2200 psig decreasing

AP/31 (Increasing or Decreasing RCS Pressure) initiated

Current conditions:

Time = 1001

Reactor Power = 97%

RCS Pressure = 2100 psig increasing

Spray valve in MANUAL and closed

PORV- 1455C in MANUAL and closed

Based on the above conditions, which one of the following correctly states: (1) the

component that failed high and (2) the status of PORV 1455C operability per Technical

Specifications?

A. (1) P-444

(2) PORV is considered OPERABLE

B. (1) P-444

(2) PORV is NOT considered OPERABLE

C. (1) P-445

(2) PORV is considered OPERABLE

D. (1) P-445

(2) PORV is NOT considered OPERABLE

K/A

Pressurizer Pressure Control System Malfunction . Ability to determine and interpret

the following as they apply to the Pressurizer Pressure Control Malfunctions: Actions to

be taken if PZR pressure instrument fails high

K/A Match Analysis

Requires knowledge of how instrument failure affects the Pzr pressure control system

and actions to mitigate the event.

SRO-Only Analysis

Requires ability to interpret plant conditions and select appropriate AP/EOP to mitigate

the event.

Answer Choice Analysis

A. Incorrect. 1st part is correct. 2nd part is incorrect because the PORV is not able

to

perform its Normal Function at power (prevent challenging the code safetys). 2nd

part is plausible because it is still operable in MANUAL.

B. Correct. Indications are indicative of transmitter P-444 failed high. TS directs the

Block Valve for that PORV to be closed which renders the PORV inoperable. If

the

PORV was still operable, this action would not be required. In the TS Bases 3.1.5c,

it states this action is taken when the PORV is Inoperable.

C. Incorrect 1st part is incorrect because this transmitter does not control all of the

functions to create the parameters listed. It is plausible because P-445 controls a

PORV and will cause RCS pressure to decrease. 2nd part is incorrect because

the

PORV is not able to perform its Normal Function at power (prevent challenging the

code safetys). 2nd part is plausible because it is still operable in MANUAL.

D. Incorrect: 1st part is incorrect because this transmitter does not control all of the

functions to create the parameters listed. It is plausible because P-445 controls a

PORV and will cause RCS pressure to decrease. 2nd part is incorrect because

the

PORV is not able to perform its Normal Function at power (prevent challenging the

code safetys). 2nd part is correct.

Supporting References

TS Section 3.1.4a

ND-93.3-LP5, Pzr Press Control pg 11 Obj: C

References Provided to Applicant

none

Licensee to determine operability of PORV

Answer: B

14. 035A2.01 17

Unit 1 initial conditions:

Reactor power = 100%

Main Steam Line Break inside containment occurs on the 1B SG

Maximum containment pressure reached = 4 psig

1-E-2 FAULTED STEAM GENERATOR ISOLATION is in progress

Current plant conditions:

RCS Pressure = 1750 psig increasing

RCS Subcooling = 95 0F increasing

A SG NR level = 15% increasing

B SG WR level = 5% stable

C SG NR level = 18% increasing

Pzr level = 35% increasing

(1) Which ONE of the following parts of the curve in TS Figure 3.8-1 is based on the

peak calculated pressure criteria from this event and (2) based on the current plant

conditions, which procedure will 1E2 direct you to GO TO?

(Reference provided)

A. (1) Horizontal upper limit line (2) 1-ES-1.1 SI TERMINATION

B. (1) Horizontal upper limit line

(2) 1-E-1 LOSS OF REACTOR OR SECONDARY COOLANT

C. (1) Sloped line from 70-100 0F SW temp (2) 1-ES-1.1 SI TERMINATION

D. (1) Sloped line from 70-100 0F SW temp

(2) 1-E-1 LOSS OF REACTOR OR SECONDARY COOLANT

K/A

Steam Generator: Ability to (a) predict the impacts of the following malfunctions or

operations on the S/GS; and (b) based on those predictions, use procedures to correct,

control, or mitigate the consequences of those malfunctions or

operations: Faulted or Ruptured S/Gs.

K/A Match Analysis

Requires knowledge of procedures used to mitigate a Faulted SG.

SRO-Only Analysis

Requires knowledge of Tech Spec bases that is required to analyze Tech Spec required

actions and terminology.

Answer Choice Analysis

A. Correct: 1st part is correct per TS 3.8-4. 2nd part is correct per step 8 of 1E-2

FAULTED STEAM GENERATOR ISOLATION.

B. Incorrect: 1st part is correct per TS 3.8-4. 2nd part is incorrect because per 1E-2

Step 8 you meet the criteria to GO TO 1ES1 SI Termination. Plausible because if

the Applicant thinks that Adverse Containment Conditions exist or if they did exist

(> 5 psig), 1E-2 would direct you to GO TO 1E-1 LOSS OF REACTOR OR

SECONDARY COOLANT.

C. Incorrect: 1st part is incorrect because it is based on LOCA depressurization

criteria. 1st part is plausible because it is an upper limit on the curve. 2nd part is

correct per step 8 of 1E-2 FAULTED STEAM GENERATOR ISOLATION..

D. Incorrect: 1st part is incorrect because it is based on LOCA depressurization

criteria. 1st part is plausible because it is an upper limit on the curve. 2nd part

is

incorrect because per 1E-2 Step 8 you meet the criteria to GO TO 1ES1 SI

Termination. Plausible because if the Applicant thinks that Adverse Containment

Conditions exist or if they did exist (> 5 psig), 1E-2 would direct you to GO TO

1E-1 LOSS OF REACTOR OR SECONDARY COOLANT.

Supporting References

1-E-2

ND-95.3-LP-12, E-2 Obj: A

TS 3.8 Containment

ND-95.3-LP-3 E-0, pg 8 Adverse Containment Criteria

References Provided to Applicant

TS Figure 3.8-1

Answer: B

15. 051G2.4.11 9

Unit 1 initial conditions:

Time = 1500

Reactor power = 100 %

A loud explosion is heard from the main turbine area (Security reports that

no suspicious activity noted)

Condenser Vacuum = 27" Hg decreasing

1AP/14 (LOSS OF MAIN CONDENSER VACUUM) initiated

Current plant conditions:

Time = 1510

Reactor Power = 60%

Condenser vacuum = 25" Hg decreasing

An operator reports that there was insulation on fire around a Reheat Stop

valve. The fire is out but he hears a hissing noise

Based on current plant conditions, which one of the following correctly states: (1) the

procedure that will be used to continue the load reduction and (2) the e-plan

classification?

(Reference provided)

A. (1) 1AP/14 Attachment 2 RAMPING AT GREATER THAN OR EQUAL TO 1%/MIN

(2) UNUSUAL EVENT

B. (1) 1AP/14 Attachment 2 RAMPING AT GREATER THAN OR EQUAL TO 1%/MIN

(2) ALERT

C. (1) 1AP/23 RAPID LOAD REDUCTION

(2) UNUSUAL EVENT

D. (1) 1AP/23 RAPID LOAD REDUCTION

(2) ALERT

K/A

Loss of Condenser Vacuum: Knowledge of abnormal condition procedures.

K/A Match Analysis

Requires knowledge of abnormal procedures.

SRO-Only Analysis

Requires ability to assess plant conditins and then prescribing a procedure or section of

a procedure to mitigate, recover or with which to proceed.

Answer Choice Analysis

A. Incorrect: 1st part incorrect because in attachment 2 of AP14 it states that if power

decreases to 60% and further power reduction is anticipated, THEN initiate AP/23.

1st part is plausible because AP/14 Attachment 2 is used for the power reduction

to

this point. 2nd part is correct based on Fire/Explosion in the protected area

boundary.

B. Incorrect: 1st part incorrect because in attachment 2 of AP14 it states that if power

decreases to 60% and further power reduction is anticipated, THEN initiate AP/23.

1st part is plausible because AP/14 Attachment 2 is used for the power reduction

to

this point. 2nd part is plausible because it is a fire affecting a normal shutdown

(the condenser) but incorrect because the condenser is not required to establish or

maintain safe shutdown.

C. Correct: 1st part is correct in that in attachment 2 of AP14 it states that if power

decreases to 60% and further power reduction is anticipated, THEN initiate AP/23.

2nd part is correct based on Fire/Explosion in the protected area boundary.

D. Incorrect: 1st part is correct in that in attachment 2 of AP14 it states that if power

decreases to 60% and further power reduction is anticipated, THEN initiate AP/23.

2nd part is plausible because it is a fire affecting a normal shutdown

(the condenser) but incorrect because the condenser is not required to establish or

maintain safe shutdown.

Supporting References

AP/14 LOSS OF MAIN CONDENSER VACUUM.

Emergency Plan

ND-95.1-LP-6 Obj: B

References Provided to Applicant

Emergency Plan SEP

Licensee to determine how much of SEP to be provided.

Answer: C

16. 059G2.4.14 14

Unit 1 initial conditions:

Reactor power = 100%

Loss of offsite power occurs

Reactor trip

Both EDGs start but both output breakers fail to close

TD AFW pump fails to start

1-ECA-0.0 LOSS OF ALL AC POWER has been initiated

Based on the above conditions, which one of the following correctly states (1) the EOP

that will direct supplying AFW to the SG's and (2) whether the initial conditions coincide

with the conditions for the loss of auxiliary feedwater design basis accident as stated in

Tech Spec Bases 3.6, TURBINE CYCLE?

A. (1) 1-ECA-0.0 before directing emergency buses to be energized

(2) No

B. (1) 1-FR-H.1 RESPONSE TO LOSS OF SECONDARY HEAT SINK after

emergency busses are energuzed

(2) No

C. (1) 1-ECA-0.0 before directing emergency buses to be energized

(2) Yes

D. (1) 1-FR-H.1 RESPONSE TO LOSS OF SECONDARY HEAT SINK after

emergency busses are energuzed

(2) Yes

K/A

Main Feedwater: Knowledge of general guidelines for EOP usage.

K/A Match Analysis

Requires knowledge of how the EOP directs feedwater restoration after a loss of all

feedwater.

SRO-Only Analysis

Requires detailed knowledge of diagnostic steps and decision points in the EOPs that

involve transitions to event specific sub-procedures or emergency contingency

procedures. This beyond knowing CSF path selection.

Answer Choice Analysis

A. Correct: 1-ECA-0.0 will direct getting AFW flow to the SGs after verifying Rx and

Turbine trip. TS design bases accident for AFW is a loss of Main Feedwter with

On

Site power (RCP's running)

B. Incorrect: 1st part is incorrect because ECA-0.0 is a higher priority section of the

EOP and it directs restoration fo AFW. 1st part is plausible because it will address

the loss of feedwater after ECA-0.0 is exited. 2nd part is correct.

C. Incorrect: 1st part is correct. 2nd part is incorrect because TS design bases

accidtne for AFW is a loss of Main Feedwater with On site Power (RCPs running).

Plausible because you do not have the TD AFW pump.

D. Incorrect: 1st part is incorrect because ECA-0.0 is a higher priority section of the

EOP and it directs restoration fo AFW. 1st part is plausible because it will address

the loss of feedwater after ECA-0.0 is exited. 2nd part is incorrect because TS

design bases accidtne for AFW is a loss of Main Feedwater with On site Power

(RCPs running). Plausible because you do not have the TD AFW pump.

Supporting References

Ref:

1-FR-H.1 RESPONSE TO LOSS OF SECONDARY HEAT SINK

1-ECA-0.0 LOSS OF ALL AC POWER

TS 3.6

References Provided to Applicant

none

Answer: A

17. 062AA2.06 1

Initial plant conditions:

Unit 2 shutdown with fuel offloaded

Unit 1 = 100% power

Current plant conditions:

Annunciator 1D-G5, SW OR CC PPS DISCH TO CHRG PPS LO PRESS is

in

alarm

1AP/12 SERVICE WATER SYSTEM ABNORMAL CONDITIONS has been

initiated

Unit 1 operating CHG pump bearing temperatures:

1420 = 170 0F

1430 = 175 0F

1440 = 180 0F

1450 = 185 0F

1500 = 190 0F

Based on the above conditions: (1) which one of the following states the time at which

1-AP-12 directs shifting the operating charging pump and, (2) if all Unit 1 charging

pumps are lost, correctly state the Tech Spec bases for using the designated Unit 2

charging pump?

A. (1) 1440

(2) To bring the operating unit to cold shutdown

B. (1) 1440

(2) To bring the operating unit to hot shutdown

C. (1) 1450

(2) To bring the operating unit to cold shutdown

D. (1) 1450

(2) To bring the operating unit to hot shutdown

K/A

Loss of Nuclear Svc Water:

The length of time after the loss of SWS flow to a component before that component

may be damaged.

K/A Match Analysis

Requires knowledge of temperature limits on components supplied by SWS.

SRO-Only Analysis

Requires knowledge of Tech Spec bases that is required to analyze Tech Spec required

actions and terminology.

Answer Choice Analysis

A. Correct: At 180 0F, AP/12 directs the charging pumps to be shifted. Per TS 3.2

C&VCS for a shutdown unit, one charging pump with a source of borated water

shall

be available for cross-connect with the operating unit so that if the operating units

charging pumps become inoperable, the shutdown units charging pump can bring

the disabled unit to cold shutdown.

B. Incorrect: 1st part is correct because at 180 0F, AP/12 directs the charging pumps

to be shifted. 2nd part is not correct because TS 3.2 states the shutdown units

charging pump is used to bring the diabled unit to cold shutdown. 2nd part is

plausible because being in hot shutdown would put the plant in a stable condition

while repairs are conducted.

C. Incorrect: 1st part is incorrect because per AP/12 directs them to be shifted at

180 0F. 1st part is plausible because at 185 0F, AP/12 directs the charging pump

to be secured. 2nd part is correct.

D. Incorrect: 1st part is incorrect because per AP/12 directs them to be shifted at

180 0F. 1st part is plausible because at 185 0F, AP/12 directs the charging pump

to be secured. 2nd part is not correct because TS 3.2 states the shutdown units

charging pump is used to bring the diabled unit to cold shutdown. 2nd part is

plausible because being in hot shutdown would put the plant in a stable condition

while repairs are conducted.

Supporting References

TS 3.2, AP/12 Step 4 & 5, ND-89.5-LP-2 Obj H

References Provided to Applicant

none

Answer: C

18. 079G2.2.22 1

Given the following plant conditions:

  • Unit 1 is at 100%
  • A loss of Containment Instrument Air has occurred
  • 1D-C6, PRZR PWR RELIEF VV LO AIR PRESS, annunciates
  • Containment Instrument Air was crosstied with Instrument Air
  • Containment Instrument Air Pressure = 85 psig and increasing
  • All PORV air bottles are properly aligned with air pressures of 1050 psig

Which one of the following correctly states (1) the status of LCO 3.1.A.6, PORV

Operability and (2) the Tech Spec required operator actions, if any?

A. (1) The LCO is met.

(2) No further action associated with the PORVs is required.

B. (1) The LCO is met.

(2) Verify PORV operability by closing PORV Block Valves, manually cycle the

PORVs, and then re-open the PORV Block Valves.

C. (1) The LCO is NOT met.

(2) Restore the PORV backup air supply within 14 days OR be in HSD within the

next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.

D. (1) The LCO is NOT met.

(2) Close and remove power from both PORV block valves within one hour AND be

in HSD within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />

079 Station Air

G2.2.22: Knowledge of limiting conditions for operations and safety limits

K/A MATCH ANALYSIS:

The question requires knowledge of PORV operability which is impacted by a loss of air.

The operability determination causes the conditions of the LCO to not be met.

SRO-ONLY ANALYSIS:

Operability is primarily an SRO function unless the determinatation is made at a very

basic level (I.E. if a pump is broke, it is obviously inop - which would be RO knowledge).

This question requires the SRO to understand how the loss of instrument air affects the

PORV operability, even when the PORV is available for use with cross-tied air.

Answer Choice Analysis:

A. Incorrect per 1D-C6 CTMT Inst Air P must be > 80 psig for the PORVs to be

operable.

B. Incorrect because (per 1D-C6) with CTMT Inst Air P < 80 psig, the PORVs are

inoperable.

C. Correct because PORVs are capable of being manually cycled with CTMT Inst Air

P > 80 psig. The PORVs are INOP due to INOP air supply and you start a 14 day

LCO clock.

D. Incorrect, the PORV is INOP but can be manually cycled. This choice is correct if

the PORV could NOT be manually cycled. This would be a 1 hr LCO.

Surry Requal Bank Question #571 (LARP0001) & 2004-301 NRC Exam

References:

ND-92.1-LP-1, Station Air Systems, Rev. 13

ND-88.1-LP-3, Pressurizer and Pressure Relief, Rev. 12

1B-F6, CTMT INST AIR HDR LO PRESS, Rev. 1

1D-C6, PRZR PWR RELIEF VV LO AIR PRESS, Rev. 4

Technical Specification 3.1.A.6.c, Reactor Coolant System / Relief Valves

Answer: C

19. G2.1.20 13

Initial plant conditions on Unit 2 are as follows:

  • Reactor power is 100%.

Current plant conditions on Unit 2 are as follows:

  • Charging flow has slowly increased.

Auto-makeup to VCT has started.

VCT level is 29% and slowly rising.

Pressurizer level is stable at 54%.

Pressurizer pressure is stable at 2225 psig.

Crew has entered AP-16, Excessive RCS Leakage.

Radiation levels on MSL B show a slow increasing trend.

  • The leak rate has been calculated at 12 gpm. [MAY NEED TO RAISE LR -

DISCUSS WITH LICENSEE]

[REVIEW ALL THE CONDITIONS IN THE STEM WITH THE LICENSEE]

Which one of the following describes (1) whether the following procedure transition is

required AND (2) the correct classification for the event?

Transition to 2-AP-24.00, Minor SG Tube Leak is

(Reference provided)

A. (1) required.

(2) Alert

B. (1) NOT required.

(2) Alert

C. (1) required.

(2) NOUE

D. (1) NOT required.

(2) NOUE

[DISCUSS WITH THE LICENSEE TO DETERMINE CONDITIONS FOR THE STEM

THAT WILL ENSURE ONE AND ONLY ONE CORRECT ANSWER AS WELL AS

PLAUSIBILITY FOR THE DISTRACTORS]

K/A

Generics: Ability to interpret and execute procedure steps.

K/A Match Analysis

Requires applicant to interpret the leak indications, determine if transition to 1-AP-24.00

is required and determine the correct emergency classification associated with the leak.

SRO-Only Analysis

The question requires the applicant to correctly determine if a procedure transition is

required from AP-16-00 and classify the event per the emergency plan. Both of which

would require SRO- Only knowledge to determine.

Answer Choice Analysis

A. In-Correct but plausible since a procedure transition to 1-AP-24.00 is required.

B. In-Correct but plausible since a procedure transition would not be required if the

applicant didn't recognize that MSL 'B' radition were increasing.

C. Correct - Transition to 1-AP-24.00 is required.

D. In-Correct. See above.

Supporting References

1-AP-16.00, Excessive RCS Leakage, Rev. 16

Emergency Plan, Rev. 54

References Provided to Applicant

Emergency Plan

NOTE: Facility reviewers please validate that the correct emergency classification

was determined.

Answer: C

20. G2.2.14 20

Plant conditions:

RCS cooldown in progress

RCS temperature = 350 oF decreasing

RCS pressure = 300 psig

Based on the above conditions in regards to the Overpressure Mitigation System

(OMS),

(1) which one of the following correctly describes the required equipment configuration

for the 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> following RCS temperature decreasing below 350 oF and (2) what is

the TS basis for that configuration? (Consider No TS modifications, LCOs...)?

A. (1) Pzr level is limited to 33%

(2) This is to allow the operator 10 minutes to take action from inadvertent initiation

of full (3 pump) charging flow.

B. (1) Two PORVs are required to remain operable

(2) This is based on the PORVs ability to relieve RCS pressure from the start of a

RCP with SG temp > RCS temp.

C. (1) Accumulators must be depressurized to less than the PORV setpoint

(2) This is to prevent exceeding the PORV capability if an inadvertent OMS initiation

occurs.

D. (1) All but one charging pump shall be removed from service and incapable of

injecting into the RCS

(2) This is to ensure any mass addition can be relieved by one PORV.

K/A

Knowledge of the process for controlling equipment configuration or status.

K/A Match Analysis

Requires knowledge of the equipment configuration for specific plant conditions.

SRO-Only Analysis

Requires knowledge of the plant configuration for cooldown operations and the TS

Bases for that configuration.

Answer Choice Analysis

A. Incorrect: Plausible because the limit is correct but based on only one charging

pump injecting.

B. Incorrect: 2 PORVs are required for the 1st 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> if no vent exists or Pzr level

< 33%. Plausible because the bases stated is for one PORV being operable.

C. Incorrect: Accumulators can be isolated and valves de-energized as an alternative

to depressurizing. While initiation may cause the PORV to lift, it will not exceed its

capacity. Plausible because depressurizing the accumulators is an option to

isolating them.

D. Correct. Per TS 3.1.G

Supporting References

ND-93.3-LP-6 Obj: E

TS3.1.G

References Provided to Applicant

none

Answer: D

21. G2.2.22 1

Which one of the following describes how the potential reactivity effects due to Reactor

Coolant System cooldown during and following loop backfill are limited to acceptable

levels, as specified in the Bases to Technical Specification 3.17, "LOOP STOP VALVE

OPERATION?"

A. (1) There is a small absolute value of the isothermal temperature coefficient of

reactivity at cold and refueling shutdown conditions.

(2) Reactivity effects due to boron stratification in the backfilled loop are NOT a

concern, because stratification is NOT expected to take place at the normal

shutdown boron concentrations and temperatures during the time to complete

backfill of the loop and open the loop stop valves fully.

B. (1) There is a large absolute value of the fuel temperature coefficient of reactivity

at cold and refueling shutdown conditions.

(2) Reactivity effects due to localized boron stratification in the backfilled loop are a

concern; the requirements on relief line flow and boron concentration of the reactor

coolant pump seal injection source are designed to mitigate any adverse effects of

localized boron stratification.

C. (1) There is a small absolute value of the isothermal temperature coefficient of

reactivity at cold and refueling shutdown conditions.

(2) Reactivity effects due to localized boron stratification in the backfilled loop are a

concern; the requirements on relief line flow and boron concentration of the reactor

coolant pump seal injection source are designed to mitigate any adverse effects of

localized boron stratification.

D. (1) There is a large absolute value of the fuel temperature coefficient of reactivity

at cold and refueling shutdown conditions.

(2) Reactivity effects due to boron stratification in the backfilled loop are NOT a

concern, because stratification is NOT expected to take place at the normal

shutdown boron concentrations and temperatures during the time to complete

backfill of the loop and open the loop stop valves fully.

K/A

Knowledge of limiting conditions for operations and safety limits.

(CFR: 41.5/43.2/45.2) (SRO - 4.7)

K/A Match Analysis

The K/A is a Tier 3, or "generic" K/A. The question asks the SRO candidate to

demonstrate knowledge of the bases for an important Technical Specifications LCO for

Loop Stop Valve Operation.

SRO-Only Analysis

-see attached flowchart from SRO-only guidance document. TS Basis knowledge

needed to arrive at the correct answer.

Answer Choice Analysis

A. CORRECT. Both choices (1) and (2) are taken word-for-word from the bases of

TS 3.17, "LOOP STOP VALVE OPERATION," p. TS 3.17-7.

B. INCORRECT. (1) is plausible because it uses the exact same language of the

correct version of (1), but is incorrect because a large negative value of the Doppler

coefficient would be worse from a reactivity standpoint when considering cold

shutdown/refueling conditions. (2) is also incorrect, but plausible, because it specifies

that only localized boron stratification is a concern, and also because it mentions

(correctly) limits placed on relief line flow rates and time, as well as limits placed on

boron concentration of the reactor coolant pump seal injection source, which are

actually contained in the TS 3.17.

C. INCORRECT. (1) is correct version; (2) is the incorrect distractor.

D. INCORRECT. (1) is incorrect distractor; (2) is correct version.

Supporting References

SPS TS 3.17 and bases, especially p. 7.

References Provided to Applicant

None

Answer: A

22. G2.3.12 1

Unit 1 initial conditions:

Date = 6/24

Time = 0800

Reactor power = 100%

Waste gas storage tank activity level is reported which exceeds TS 3.11,

Radioactive Gas Storage, limits

Current conditions:

Date = 6/26

Time = 0800

Reactor power = 100%

Waste gas storage tank activity level still exceeds Tech Spec 3.11 limits

Based on the above conditions, which one of the following correctly states: (1) if Tech Spec 3.0.1 is applicable and (2) the whole body dose that the tank radioactivity limit is

designed to prevent exceeding at the exclusion area boundary if the tank were released

IAW Tech Spec Basis?

A. (1) Yes

(2) 50 mrem

B. (1) Yes

(2) 0.5 rem

C. (1) No

(2) 50 mrem

D. (1) No

(2) 0.5 rem

K/A

Knowledge of radiological safety principles pertaining to licensed operator l

duties, such as containment entry requirements, fuel handling responsibilities, l

access to locked high-radiation areas, aligning filters, etc.

K/A Match Analysis

Requires knowledge of radiological limits associated with the health and safety of the

public and how to apply technical specifications to stay within those limits.

SRO-Only Analysis

Requires knowledge of the facility operation limitations in the technical specifications

and their bases.

Answer Choice Analysis

A. Incorrect: In TS 3.11.B.3 it states that the requirements fo Specification 3.0.1 are

not applicable. 1st part is plausible because the time for condition 3.11.B.2 has

expired. 2nd part is incorrect because in the TS bases 3.11 it states 0.5 rem.

2nd part is plausible becasue the Surry adminestrative limit for site visitors is

50 mrem.

B. Incorrect: In TS 3.11.B.3 it states that the requirements fo Specification 3.0.1 are

not applicable. 1st part is plausible because the time for condition 3.11.B.2 has

expired. 2nd part is correct per TS 3.11 bases.

C. Incorrect: 1st part is correct. 2nd part is incorrect because in the TS bases 3.11 it

states 0.5 rem. 2nd part is plausible becasue the Surry adminestrative limit for

site visitors is 50 mrem.

D. Correct: In TS 3.11.B.3 it states that the requirements fo Specification 3.0.1 are

not applicable. In the tech spec bases for TS 3.11 it states it limited to the quantity

which provides assurance that in the event of an uncontrolled release of the tank's

contents, the resulting total body exposure to an individual at the nearest exclusion

area boundary will not exceed 0.5 rem in an event.

Supporting References

TS 3.11

ND-81.2-LP3

References Provided to Applicant

none

Answer: D

23. G2.3.4 22

Unit 1 initial plant conditions:

Reactor power = 50%

Plant shutdown in progress due to RCS activity greater than TS limits

AFW Pump 1FW 3B OOS

Current plant conditions:

A SG tube rupture occurs

'A' SG pressure = 1000 psig

Reactor has been tripped

1-E-3 STEAM GENERATOR TUBE RUPTURE in progress

The TSC has been established

An operator is dispatched to close 1-MS-87 (steam from the A SG to the TD

AFW pump) in order to save valuable equipment

Based on the above conditions, which one of the following: (1) states the allowable

dose (TEDE) the operator can receive while isolating steam to the TD AFW pump and

(2) if the valve can not be closed, what procedural actions shall be taken IAW 1-E-3 to

mitigate the failure?

A. (1) 10 Rem

(2) Remain in 1-E-3 and trip the TD AFW pump overspeed trip valve.

B. (1) 10 Rem

(2) GO TO 1-ECA-3.1, SGTR WITH LOSS OF REACTOR COOLANT -

SUBCOOLED RECOVERY.

C. (1) 5 Rem

(2) Remain in 1-E-3 and trip the TD AFW pump overspeed trip valve.

D. (1) 5 Rem

(2) GO TO 1-ECA-3.1, SGTR WITH LOSS OF REACTOR COOLANT -

SUBCOOLED RECOVERY.

K/A

Knowledge of radiation exposure limits under normal or emergency conditions.

K/A Match Analysis

Requires knowledge of exposure limits under emergency conditions.

SRO-Only Analysis

Requires knowledge of EOP procedures and transition points.

Answer Choice Analysis

A. Correct: Allowable dose for equipment = 10 Rem. Per 1-E-3, if at least 1 motor

driven AFW pump available, trip the TD AFW pump.

B. Incorrect: 1st part is correct. 2nd part is plausible because if the SG with the

rupture could not be isolated from both of the intact SGs, it would be correct.

C. Incorrect: 1st part is plausible because the exposure could be counted towards a

PSE (the PSE limit is 5 Rem / yr). 2nd part is correct.

D. Incorrect: 1st part is plausible because the exposure could be counted towards a

PSE (the PSE limit is 5 Rem / yr). 2nd part is plausible because if the SG with the

rupture could not be isolated from both of the intact SGs, it would be correct.

Supporting References

ND-81.2-LP-3 Obj: E

1-E-3

ND-95.3-LP-13 E-3 Obj: A

References Provided to Applicant

none

Answer: A

24. G2.4.30 1

Unit 1 Initial Conditions:

  • Holding at 30% power for fuel conditioning following a refueling outage.

Current conditions:

  • Technicians performing a routine surveillance test on the AMSAC logic system

indavertantly cause a half-train Train "A" AMSAC signal to be generated.

  • The technicians are able to reset the Train "A" AMSAC signal in ten (10)

seconds.

Based on the current conditions, which one of the following correctly describes (1)

whether the half-train AMSAC signal should be considered a VALID or INVALID

actuation, as defined by VPAP-2802, "Notifications and Reports," AND (2) the most

restrictive time requirement to report this event to the NRC, as specified by

VPAP-2802?

(Reference provided)

A. (1) VALID actuation

(2) 4 hour4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> notification

B. (1) INVALID actuation

(2) 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> notification

C. (1) VALID actuation

(2) 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> notification

D. (1) INVALID actuation

(2) 4 hour4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> notification

K/A

Knowledge of events related to system operation/status that must be reported to

internal organizations or external agencies, such as the State, the NRC, or the

transmission system operator.

(CFR: 41.10/43.5/45.11) (SRO - 4.1)

K/A Match Analysis

The question requires the applicant to demonstrate knowledge of the definitions

inherent in the notifications procedure ("system operation/status"), and also show an

ability to use the procedure to determine the correct time requirements for the given

plant conditions, which are operationally valid.

SRO-Only Analysis

This question requires the applicant to know the definitions inherent in the Notifications

procedure, and to apply them in a practical setting. Therefore, it is a higher-level

comprehension/analysis question that is linked to 10CFR55.43(b)(1), "conditions and

limitations in the facility license," in that ROs are not required to know and be able to

apply reporting requirements.

Answer Choice Analysis

A. INCORRECT. (1) Surry/Dominion procedure VPAP-2802, "Notifications and

Reports," section 4.3 specifies that a VALID actuation must result "from an intentional

manual initiation or from a signal that was initiated in response to actual plant conditions

or parameters satisfying the requirements for initiation, unless part of a preplanned

test." For the given conditions, the inadvertant AMSAC actuation was caused as a

result of testing, the actuation was a result of human error and was not pre-planned to

occur, and was not in response to actual plant conditions. Therefore, to state that the

actuation was VALID is plausible. (2) 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> is the most restrictive notification, to report

an RPS actuation on a critical reactor.

B. INCORRECT. (1) VPAP-2802 section 4.2 specifies that an invalid actuation "is

one that does not meet the criteria for being valid and are initiated for reasons other

than to mitigate the consequences of an event (e.g., as part of a planned evolution, with

the system properly removed from service, or after the safety function has already been

completed). Invalid actuations include circumstances where instrument drift, spurious

signals, human error, or other invalid signals caused actuation (e.g. jarring a cabinet, an

error in the use of jumpers or lifted leads, an error in the actuation of switches or

controls, equipment failure, radio frequency interference)." For the given conditions,

human error caused the actuation; therefore INVALID actuation is correct. The

candidate must then infer from the question whether the reactor tripped (yes). (2)

Based on the provided reference material, the candidate my incorrectly choose an

8-hour notification based on auxiliary feedwater auto-start, if he/she incorrectly believes

that the AMSAC actuation at a low power level would not produce a reactor trip (or only

trip the turbine and not the reactor as well). The plausibility of this choice is enhanced

by the question stem stating that the signal is reset within 10 seconds (where a normal

AMSAC signal is required to remain "in" for 27 seconds to cause an actuation).

C. INCORRECT. "VALID" actuation is wrong as per the above.

D. CORRECT. "INVALID" actuation is correct as per the above. VPAP-2802 section

6.3.4.a.3. states that a 4-hour report is required for "Any event or condition that results

in actuation of the reactor protection system (RPS) when the reactor is critical except

when actuation results from and is part of a pre-planned sequence during testing or

reactor operation." In this case, an automatic reactor trip/RPS actuation did occur with

the reactor critical. The reactor trip was not pre-planned; rather, it was caused by

human error, and therefore the exclusion clause does not apply.

Supporting References

-VPAP-2802, "Notifications and Reports," rev 30, (p. 20, p. 82, and p. 86)

- Surry lesson plan ND-93.3-LP-17, "ANTICIPATORY MITIGATING SYSTEM

ACTUATING CIRCUITRY (AMSAC)," rev. 11, p. 7 and 9.

References Provided to Applicant

-VPAP-2802, "Notifications and Reports," pages 79-91.

Answer: D

25. G2.4.9 24

Unit 1 plant conditions:

Time = 0200

RCS cooldown in progress

RCS temperature = 250 oF

RCS pressure = 320 psig

1A charging pump is the only running charging pump

Current plant conditions:

Time = 0210

RCS pressure = 280 psig decreasing

The maximum charging flow achieved with the 1A charging pump is 125 gpm

Based on the above conditions, which ONE of the following: (1) states the correct

procedure to be entered and (2) what actions are directed by that procedure?

A. (1) 1AP-16.00 EXCESSIVE RCS LEAKAGE

(2) Align charging pump suction to the RWST

B. (1) 1AP-16.00 EXCESSIVE RCS LEAKAGE

(2) Align and start 1B and 1C charging pumps

C. (1) 1-AP-16.01 SHUTDOWN LOCA

(2) Align charging pump suction to the RWST

D. (1) 1-AP-16.01 SHUTDOWN LOCA

(2) Align and start 1B and 1C charging pumps

K/A

Knowledge of low power / shutdown implications in accident (e.g., loss of coolant

accident or loss of residual heat removal) mitigation strategies.

K/A Match Analysis

Requires knowledge of shutdown procedures/mitigation strategies during an accident.

SRO-Only Analysis

Requires in depth knowledge of abnormal procedure guidelines and selection based on

plant conditions.

Answer Choice Analysis

A. Incorrect: Note at the top of AP/16.00 states If SI Accumulators are isolated,

1-AP-16.01, SHUTDOWN LOCA, should be used for guidance. Plausible

because

if > 350 0F, it would be correct. 2nd part is correct.

B. Incorrect: Note at the top of AP/16.00 states If SI Accumulators are isolated,

1-AP-16.01, SHUTDOWN LOCA, should be used for guidance. 2nd part is

plausible because if > 350 0F charging pumps would used as necessary per

AP/16.00 (OPMG not in service). Having OPMG in service requires only 1 Chg

available to inject into the RCS.

C. Correct. If SI Accumulators are isolated, 1-AP-16.01, SHUTDOWN LOCA, should

be used for guidance. Being < 350 oF requires the accumulators to be isolated.

2nd part is step 8 d RNO.

D. Incorrect: 1st part is correct. 2nd part is plausible because if > 350 0F charging

pumps would used as necessary per AP/16.00 (OPMG not in service). Having

OPMG in service requires only 1 Chg available to inject into the RCS.

Supporting References

Ref: AP/16.00, AP/16.01

References Provided to Applicant

none

Answer: C