| title = Acceptance Review Email, Relief Request Nos. VRR-01, PRR-03, PRR-02, and PRR-01 for the Third 10-Year Inservice Testing Program Interval (TAC Nos. ME3515, ME3516, ME3517, ME3518, ME3519, ME3520, ME3521, and ME3522)
| title = Acceptance Review Email, Relief Request Nos. VRR-01, PRR-03, PRR-02, and PRR-01 for the Third 10-Year Inservice Testing Program Interval
| author name = Thadani M C
| author name = Thadani M
| author affiliation = NRC/NRR/DORL/LPLIV
| author affiliation = NRC/NRR/DORL/LPLIV
| addressee name = Harrison A
| addressee name = Harrison A
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:From: Thadani, Mohan Sent: Tuesday, April 06, 2010 3:23 PM To: aharrison@stpegs.com Cc: Lingam, Siva; Feintuch, Karl; Burkhardt, Janet; Lent, Susan  
{{#Wiki_filter:From:                       Thadani, Mohan Sent:                       Tuesday, April 06, 2010 3:23 PM To:                         aharrison@stpegs.com Cc:                         Lingam, Siva; Feintuch, Karl; Burkhardt, Janet; Lent, Susan


==Subject:==
==Subject:==
ACCEPTANCE REVIEW OF INSERVICE TESTING PROGRAM DESCRIPTION FOR THE THIRD 10-YEAR TNTERVAL  
ACCEPTANCE REVIEW OF INSERVICE TESTING PROGRAM DESCRIPTION FOR THE THIRD 10-YEAR TNTERVAL Mr. Edward D. Halpin Chief Nuclear Officer STP Nuclear Operating Company South Texas Project P. O. Box 289 Wadsworth, TX 77483
 
Mr. Edward D. Halpin Chief Nuclear Officer STP Nuclear Operating Company South Texas Project P. O. Box 289 Wadsworth, TX 77483  


==SUBJECT:==
==SUBJECT:==
SOUTH TEXAS PROJECT, UNITS 1 AND 2 - RE: REQUEST FOR RELIEFS FOR THIRD 10-YEAR INSERVICE TESTING PROGRAM INTERVAL (TAC NOS. ME3515, ME3516, ME3517, ME3518, ME3519, ME3520, ME3521, AND ME3522)  
SOUTH TEXAS PROJECT, UNITS 1 AND 2 - RE: REQUEST FOR RELIEFS FOR THIRD 10-YEAR INSERVICE TESTING PROGRAM INTERVAL (TAC NOS. ME3515, ME3516, ME3517, ME3518, ME3519, ME3520, ME3521, AND ME3522)


==Dear Mr. Halpin:==
==Dear Mr. Halpin:==


By letter dated February 22, 2010 (ADAMS Accession No. ML100640120), STP Nuclear Operating Company (the licensee) requested the U.S. Nuclear Regulatory Commission (NRC) staff approval of a relief requests PRR-01, PRR-02, PRR-03, and VRR-01 for South Texas Project, Units 1 an2 third 10-year inservise testing (IST) program interval.  
By letter dated February 22, 2010 (ADAMS Accession No. ML100640120), STP Nuclear Operating Company (the licensee) requested the U.S. Nuclear Regulatory Commission (NRC) staff approval of a relief requests PRR-01, PRR-02, PRR-03, and VRR-01 for South Texas Project, Units 1 an2 third 10-year inservise testing (IST) program interval.
 
The proposed request seeks reliefs to allow use of alternative examinations or test requirements of 2004 Edition of American Society of Mechanical Engineers Operations and Maintenance Code.
The proposed request seeks reliefs to allow use of alternative examinations or test requirements of 2004 Edition of American Society of Mechanical Engineers Operations and Maintenance Code.
The purpose of this letter is to provide the results of the NRC staff=s acceptance review of these relief requests. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
 
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed relief request in terms of regulatory requirements and the protection of public health and safety and the environment. If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence.
The purpose of this letter is to provide the results of the NRC staff
If you have any questions, please contact me at (301) 415-1476.
=s acceptance review of these relief requests. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.  
Mohan C Thadani Senior Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
 
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed relief request in terms of regulatory requirements and the protection of public health and safety and the environment. If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence.  
 
If you have any questions, please contact me at (301) 415-1476.  


Mohan C Thadani Senior Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation (301) 415-1476     Mohan.Thadani@nrc.gov}}
(301) 415-1476 Mohan.Thadani@nrc.gov}}

Latest revision as of 18:44, 21 March 2020

Acceptance Review Email, Relief Request Nos. VRR-01, PRR-03, PRR-02, and PRR-01 for the Third 10-Year Inservice Testing Program Interval
ML100960515
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 04/06/2010
From: Thadani M
Plant Licensing Branch IV
To: Harrison A
South Texas
Thadani, M C, NRR/DORL/LPL4, 415-1476
References
TAC ME3515, TAC ME3516, TAC ME3517, TAC ME3518, TAC ME3519, TAC ME3520, TAC ME3521, TAC ME3522
Download: ML100960515 (2)


Text

From: Thadani, Mohan Sent: Tuesday, April 06, 2010 3:23 PM To: aharrison@stpegs.com Cc: Lingam, Siva; Feintuch, Karl; Burkhardt, Janet; Lent, Susan

Subject:

ACCEPTANCE REVIEW OF INSERVICE TESTING PROGRAM DESCRIPTION FOR THE THIRD 10-YEAR TNTERVAL Mr. Edward D. Halpin Chief Nuclear Officer STP Nuclear Operating Company South Texas Project P. O. Box 289 Wadsworth, TX 77483

SUBJECT:

SOUTH TEXAS PROJECT, UNITS 1 AND 2 - RE: REQUEST FOR RELIEFS FOR THIRD 10-YEAR INSERVICE TESTING PROGRAM INTERVAL (TAC NOS. ME3515, ME3516, ME3517, ME3518, ME3519, ME3520, ME3521, AND ME3522)

Dear Mr. Halpin:

By letter dated February 22, 2010 (ADAMS Accession No. ML100640120), STP Nuclear Operating Company (the licensee) requested the U.S. Nuclear Regulatory Commission (NRC) staff approval of a relief requests PRR-01, PRR-02, PRR-03, and VRR-01 for South Texas Project, Units 1 an2 third 10-year inservise testing (IST) program interval.

The proposed request seeks reliefs to allow use of alternative examinations or test requirements of 2004 Edition of American Society of Mechanical Engineers Operations and Maintenance Code.

The purpose of this letter is to provide the results of the NRC staff=s acceptance review of these relief requests. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed relief request in terms of regulatory requirements and the protection of public health and safety and the environment. If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence.

If you have any questions, please contact me at (301) 415-1476.

Mohan C Thadani Senior Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation