NRR E-mail Capture - South Texas Project - Acceptance of License Amendment Request to Revise the Emergency Plan (L-2020-LLA-0057)
ML20125A331
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 05/04/2020
From: Dennis Galvin
NRC/NRR/DORL/LPL4
To: Richards D
South Texas
References
L-2020-LLA-0057
Download: ML20125A331 (3)


Text

From: Galvin, Dennis Sent: Monday, May 4, 2020 1:48 PM To: Drew Richards (amrichards@stpegs.com)

Cc: Lance Sterling (Business Fax); AJ Albaaj (ajalbaaj@stpegs.com)

Subject:

South Texas Project - Acceptance of License Amendment Request to Revise the Emergency Plan (L-2020-LLA-0057)

Dear Mr. Richards,

By letter dated March 30, 2020 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20090B745), as supplemented by letter dated April 29, 2020 (ADAMS Accession No. ML20120A618), the STP Nuclear Operating Company submitted a license amendment request (LAR) for South Texas Project Units 1 and 2. The proposed amendment would revise the South Texas Project Electric Generating Station (STPEGS), Units Emergency Plan based on guidance in NUREG-0654/FEMA-REP-1 (NUREG-0654), Criteria for Preparation and Evaluation of Radiological Emergency Response Plans and Preparedness in Support Nuclear Power Plants, Revision 2.

The purpose of this correspondence is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

Consistent with 10 CFR 50.90, an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.

The NRC staff has reviewed your application as supplemented and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staffs detailed technical review by separate correspondence.

Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 750 hours0.00868 days <br />0.208 hours <br />0.00124 weeks <br />2.85375e-4 months <br /> to complete. The NRC staff expects to complete this review by May 2021. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.

These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, and unanticipated

addition of scope to the review. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.

If you have any questions, please contact me at (301) 415-6256.

Respectfully, Dennis Galvin, Project Manager Plant Licensing Branch 4 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-498, 50-499

Hearing Identifier: NRR_DRMA Email Number: 566 Mail Envelope Properties (SA9PR09MB5519200BD522EF43EEF27331FBA60)

Subject:

South Texas Project - Acceptance of License Amendment Request to Revise the Emergency Plan (L-2020-LLA-0057)

Sent Date: 5/4/2020 1:47:37 PM Received Date: 5/4/2020 1:47:00 PM From: Galvin, Dennis Created By: Dennis.Galvin@nrc.gov Recipients:

"Lance Sterling (Business Fax)" <Lance Sterling@+1 (361) 972-4707>

Tracking Status: None "AJ Albaaj (ajalbaaj@stpegs.com)" <ajalbaaj@stpegs.com>

Tracking Status: None "Drew Richards (amrichards@stpegs.com)" <amrichards@stpegs.com>

Tracking Status: None Post Office: SA9PR09MB5519.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 3703 5/4/2020 1:47:00 PM Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: