ML12068A336: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(StriderTol Bot change)
 
(4 intermediate revisions by the same user not shown)
Line 2: Line 2:
| number = ML12068A336
| number = ML12068A336
| issue date = 03/22/2012
| issue date = 03/22/2012
| title = 02/14/2011 Summary of Public Meeting with Tennessee Valley Authority Regarding the Project Schedule for Watts Bar Nuclear Plant, Unit 2
| title = Summary of Public Meeting with Tennessee Valley Authority Regarding the Project Schedule for Watts Bar Nuclear Plant, Unit 2
| author name = Poole J C
| author name = Poole J
| author affiliation = NRC/NRR/DORL/LPWB
| author affiliation = NRC/NRR/DORL/LPWB
| addressee name =  
| addressee name =  
Line 13: Line 13:
| page count = 3
| page count = 3
}}
}}
=Text=
{{#Wiki_filter:i.,,11 REG V(                                  UNITED STATES
    .:::,v'-'            "'I"
  ">-<1',,,                  0"                NUCLEAR REGULATORY COMMISSION
/!!                              ~                      WASHINGTON, D.C. 20555-0001
<<                                0 t;
t;.
1
  '(,1<~                  .i~                              March 22, 2012
            ****+:
LICENSEE:        Tennessee Valley Authority FACILITY:        Watts Bar Nuclear Power Plant, Unit 2
==SUBJECT:==
==SUMMARY==
OF FEBRUARY 14, 2011, PUBLIC MEETING WITH TENNESSEE VALLEY AUTHORITY REGARDING THE PROJECT SCHEDULE FOR WAITS BAR NUCLEAR PLANT, UNIT 2 On February 14,2011, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of the Tennessee Valley Authority (TVA) at NRC Headquarters, Two White Flint North, 11545 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss the operating license application review, including major milestones and potential challenges that may impact the project schedule. A list of participants is enclosed.
The meeting consisted of the NRC and TVA staff discussing the licensing review along with construction inspection activities and other key challenges.
Members of the public did not participate in the meeting.
Please direct any inquiries to me at 301-415-2048 or Justin.Poole@nrc.gov.
                                                                          ~
                                                                        ~ ..      /.,    .~//'
                                                                                                //
                                                                    /    .. /-'/      ~/// ~----
Justin C. Poole, Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-391
==Enclosure:==
List of Participants cc w/encl: Distribution via Listserv
LIST OF PARTICIPANTS FEBRUARY 14, 2011, PUBLIC MEETING WITH TENNESSEE VALLEY AUTHORITY THE PROJECT SCHEDULE FOR WATTS BAR NUCLEAR PLANT, UNIT 2 Positionrritle              Organization Bruce Boger        Deputy Director            Office of Nuclear Reactor Regulation Steve Campbell      Branch Chief                Watts Bar Special Projects Branch (LPWB)\
Division of Operating Reactor Licensing (DORL)
Robert Haag        Branch Chief                R-II\ Division of Construction Projects L. Raghavan        Sr. Project Manager        LPWB\DORL Patrick Milano      Sr. Project Manager        LPWB\DORL Justin Poole        Sr. Project Manager        LPWB\DORL Tennessee Valley Authority (TVA)
==Participants:==
Gordon Arent        Licensing Manager          TVA Watts Bar Unit 2 William Crouch      Engineering                TVA Watts Bar Unit 2 Enclosure
March 22, 2012 LICENSEE:      Tennessee Valley Authority FACILITY:      Watts Bar Nuclear Power Plant, Unit 2
==SUBJECT:==
==SUMMARY==
OF FEBRUARY 14, 2011, PUBLIC MEETING WITH TENNESSEE VALLEY AUTHORITY REGARDING THE PROJECT SCHEDULE FOR WATTS BAR NUCLEAR PLANT, UNIT 2 On February 14, 2011, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of the Tennessee Valley Authority (TVA) at NRC Headquarters, Two White Flint North, 11545 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss the operating license application review, including major milestones and potential challenges that may impact the project schedule. A list of participants is enclosed.
The meeting consisted of the NRC and TVA staff discussing the licensing review along with construction inspection activities and other key challenges.
Members of the public did not participate in the meeting.
Please direct any inquiries to me at 301-415-2048 or Justin.Poole@nrc.gov.
IRA!
Justin C. Poole, Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-391
==Enclosure:==
List of Participants cc w/encl: Distribution via Ustserv DISTRIBUTION:
PUBLIC                                  RidsRgn2MailCenter Resource          LPWB R/F PMNS Resources                          RidsNrrlLABClayton (Hard copy)      RidsOpaMail Resource RidsNrrPMWaUsBar2 Resource              RidsAcrsAcnw_MailCTR Resource        MKotzalas, EDO RidsNrrDorlLp_WB Resource              RidsOgcMailCenter Resource          RidsNrrOd Resource RidsNrrDorl Resource                    RHaag, Rli ADAMS Accession  No'.. ML12068A336 OFFICE          LPWB\PM            LPWB\LA            LPWB\BC NAME            JPoole            BClavton          SCampbell DATE            3122/12            3/16/12            3/22/12 OFFICIAL RECORD COpy}}

Latest revision as of 11:20, 10 March 2020

Summary of Public Meeting with Tennessee Valley Authority Regarding the Project Schedule for Watts Bar Nuclear Plant, Unit 2
ML12068A336
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 03/22/2012
From: Justin Poole
Watts Bar Special Projects Branch
To:
Bavol, Bruce
References
Download: ML12068A336 (3)


Text

i.,,11 REG V( UNITED STATES

.:::,v'-' "'I"

">-<1',,, 0" NUCLEAR REGULATORY COMMISSION

/!! ~ WASHINGTON, D.C. 20555-0001

<< 0 t;

t;.

1

'(,1<~ .i~ March 22, 2012

        • +:

LICENSEE: Tennessee Valley Authority FACILITY: Watts Bar Nuclear Power Plant, Unit 2

SUBJECT:

SUMMARY

OF FEBRUARY 14, 2011, PUBLIC MEETING WITH TENNESSEE VALLEY AUTHORITY REGARDING THE PROJECT SCHEDULE FOR WAITS BAR NUCLEAR PLANT, UNIT 2 On February 14,2011, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of the Tennessee Valley Authority (TVA) at NRC Headquarters, Two White Flint North, 11545 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss the operating license application review, including major milestones and potential challenges that may impact the project schedule. A list of participants is enclosed.

The meeting consisted of the NRC and TVA staff discussing the licensing review along with construction inspection activities and other key challenges.

Members of the public did not participate in the meeting.

Please direct any inquiries to me at 301-415-2048 or Justin.Poole@nrc.gov.

~

~ .. /., .~//'

//

/ .. /-'/ ~/// ~----

Justin C. Poole, Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-391

Enclosure:

List of Participants cc w/encl: Distribution via Listserv

LIST OF PARTICIPANTS FEBRUARY 14, 2011, PUBLIC MEETING WITH TENNESSEE VALLEY AUTHORITY THE PROJECT SCHEDULE FOR WATTS BAR NUCLEAR PLANT, UNIT 2 Positionrritle Organization Bruce Boger Deputy Director Office of Nuclear Reactor Regulation Steve Campbell Branch Chief Watts Bar Special Projects Branch (LPWB)\

Division of Operating Reactor Licensing (DORL)

Robert Haag Branch Chief R-II\ Division of Construction Projects L. Raghavan Sr. Project Manager LPWB\DORL Patrick Milano Sr. Project Manager LPWB\DORL Justin Poole Sr. Project Manager LPWB\DORL Tennessee Valley Authority (TVA)

Participants:

Gordon Arent Licensing Manager TVA Watts Bar Unit 2 William Crouch Engineering TVA Watts Bar Unit 2 Enclosure

March 22, 2012 LICENSEE: Tennessee Valley Authority FACILITY: Watts Bar Nuclear Power Plant, Unit 2

SUBJECT:

SUMMARY

OF FEBRUARY 14, 2011, PUBLIC MEETING WITH TENNESSEE VALLEY AUTHORITY REGARDING THE PROJECT SCHEDULE FOR WATTS BAR NUCLEAR PLANT, UNIT 2 On February 14, 2011, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of the Tennessee Valley Authority (TVA) at NRC Headquarters, Two White Flint North, 11545 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss the operating license application review, including major milestones and potential challenges that may impact the project schedule. A list of participants is enclosed.

The meeting consisted of the NRC and TVA staff discussing the licensing review along with construction inspection activities and other key challenges.

Members of the public did not participate in the meeting.

Please direct any inquiries to me at 301-415-2048 or Justin.Poole@nrc.gov.

IRA!

Justin C. Poole, Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-391

Enclosure:

List of Participants cc w/encl: Distribution via Ustserv DISTRIBUTION:

PUBLIC RidsRgn2MailCenter Resource LPWB R/F PMNS Resources RidsNrrlLABClayton (Hard copy) RidsOpaMail Resource RidsNrrPMWaUsBar2 Resource RidsAcrsAcnw_MailCTR Resource MKotzalas, EDO RidsNrrDorlLp_WB Resource RidsOgcMailCenter Resource RidsNrrOd Resource RidsNrrDorl Resource RHaag, Rli ADAMS Accession No'.. ML12068A336 OFFICE LPWB\PM LPWB\LA LPWB\BC NAME JPoole BClavton SCampbell DATE 3122/12 3/16/12 3/22/12 OFFICIAL RECORD COpy