ML12066A140: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 15: Line 15:


=Text=
=Text=
{{#Wiki_filter:UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555-0001 March 26, 2012 LICENSEE:
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 26, 2012 LICENSEE:       Tennessee Valley Authority FACILITY:       Watts Bar Nuclear Power Plant, Unit 2
Tennessee Valley Authority FACILITY:
Watts Bar Nuclear Power Plant, Unit 2  


==SUBJECT:==
==SUBJECT:==


==SUMMARY==
==SUMMARY==
OF JANUARY AND FEBRUARY 2011, PUBLIC MEETINGS WITH TENNESSEE VALLEY AUTHORITY REGARDING SUBMITTAL OF WATTS BAR NUCLEAR PLANT, UNIT 2, FIRE PROTECTION REPORT On January 21, February 3 and 15, 2011, three Category 1 public meetings were held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of the Tennessee Valley Authority (TVA) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland.
OF JANUARY AND FEBRUARY 2011, PUBLIC MEETINGS WITH TENNESSEE VALLEY AUTHORITY REGARDING SUBMITTAL OF WATTS BAR NUCLEAR PLANT, UNIT 2, FIRE PROTECTION REPORT On January 21, February 3 and 15, 2011, three Category 1 public meetings were held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of the Tennessee Valley Authority (TVA) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meetings was to discuss the initial submittal of Watts Bar Nuclear Plant Unit 2 Fire Protection Report, in support of TVA's application for an operating license. A list of participants is enclosed.
The purpose of the meetings was to discuss the initial submittal of Watts Bar Nuclear Plant Unit 2 Fire Protection Report, in support of TVA's application for an operating license. A list of participants is enclosed.
The meetings consisted of the NRC and TVA staff discussing draft requests for additional information (RAI) based on the content of the fire protection report under technical review. As a result of the meetings, the staff issued RAls that can be found in the Agencywide Documents Access and Management System at Accession Numbers ML110280128 and ML110610745.
The meetings consisted of the NRC and TVA staff discussing draft requests for additional information (RAI) based on the content of the fire protection report under technical review. As a result of the meetings, the staff issued RAls that can be found in the Agencywide Documents Access and Management System at Accession Numbers ML110280128 and ML110610745. A member of the public attended the meeting on February 15, 2011. No feedback form was submitted.
A member of the public attended the meeting on February 15, 2011. No feedback form was submitted.
Please direct any inquiries to me at 301-415-2048 or Justin.Poole@nrc.gov.
Please direct any inquiries to me at 301-415-2048 or Justin.Poole@nrc.gov.
Justin C. Poole, Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No.
Justin C. Poole, Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-391
List of cc w/encl: Distribution via LIST OF JANUARY AND FEBRUARY 2011, PUBLIC MEETINGS TENNESSEE VALLEY SUBMITTAL OF WATTS BAR NUCLEAR PLANT, UNIT INITIAL FIRE PROTECTION Positionffitle Organization Bruce Boger Deputy Director Office of Nuclear Reactor Regulation Allen Howe Deputy Director Division of Operating Reactor Licensing (DORL) Steve Campbell Branch Chief Watts Bar Special Projects Branch (LPWB) DORL Patrick Milano Sr. Project Manager LPWB\DORL Justin Poole Sr. Project Manager LPWB\DORL Alex Klein Branch Chief Fire Protection Branch (AFPB) Division of Risk Assessment (DRA) Daniel Frumkin Team Leader AFPB/DRA Charles Moulton Fire Protection Engineer AFPB/DRA Gary Cooper Fire Protection Engineer AFPBfDRA Harry Barrett Fire Protection Engineer AFPB/DRA Bob Haag Branch Chief RII Rebecca Nease Branch Chief RII Tennessee Valley Authority (TVA) Participants:
Masoud Bajestani Vice President TVA Watts Bar Unit 2 Gordon Arent Licensing Manager TVA Watts Bar Unit 2 Terry Knuettel Licensing Engineer TVA Watts Bar Unit 2 William Crouch Engineering TVA Watts Bar Unit 2 Enclosure 
-PositionlTitie Organization Steve Hilmes Instrumentation and Electrical Manager TVA Watts Bar Unit 2 Brenda Simril Fire Protection Manager TVA Charles Brush Electrical Engineer EPM George Seniez Fire Protection Engineer Bechtel March 26, 2012 Tennessee Valley Authority Watts Bar Nuclear Power Plant, Unit 2


==SUMMARY==
==Enclosure:==
OF JANUARY AND FEBRUARY 2011, PUBLIC MEETINGS WITH TENNESSEE VALLEY AUTHORITY REGARDING SUBMITTAL OF WATTS BAR NUCLEAR PLANT, UNIT 2, FIRE PROTECTION REPORT On January 21, February 3 and 15, 2011, three Category 1 public meetings were held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of the Tennessee Valley Authority (TVA) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland.
 
The purpose of the meetings was to discuss the initial submittal of Watts Bar Nuclear Plant Unit 2 Fire Protection Report, in support of TVA's application for an operating license. A list of partiCipants is enclosed.
List of Participants cc w/encl: Distribution via Listserv
The meetings consisted of the NRC and TVA staff discussing draft requests for additional information (RAI) based on the content of the fire protection report under technical review. As a result of the meetings, the staff issued RAls that can be found in the Agencywide Documents Access and Management System at Accession Numbers ML110280128 and ML110610745.
 
A member of the public attended the meeting on February 15, 2011. No feedback form was submitted.
LIST OF PARTICIPANTS JANUARY AND FEBRUARY 2011, PUBLIC MEETINGS WITH TENNESSEE VALLEY AUTHORITY SUBMITTAL OF WATTS BAR NUCLEAR PLANT, UNIT 2 INITIAL FIRE PROTECTION REPORT Positionffitle            Organization Bruce Boger        Deputy Director            Office of Nuclear Reactor Regulation Allen Howe          Deputy Director            Division of Operating Reactor Licensing (DORL)
Please direct any inquiries to me at 301-415-2048 or Justin.Poole@nrc.gov. IRA! Justin C. Poole, Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No.
Steve Campbell      Branch Chief              Watts Bar Special Projects Branch (LPWB)
List of cc w/encl: Distribution via DISTRIBUTION:
DORL Patrick Milano      Sr. Project Manager        LPWB\DORL Justin Poole        Sr. Project Manager        LPWB\DORL Alex Klein          Branch Chief              Fire Protection Branch (AFPB)
PUBLIC RidsRgn2MailCenter Resource LPWB RfF RidsNrrLABClayton (Hard copy) RidsNrrPMWattsBar2 Resource RidsAcrsAcnw_MailCTR Resource RidsNrrDorlLp_WB Resource RidsOgcMailCenler Resource RidsNrrOd Resource RidsNrrDorl Resource CMoulton, NRR RidsNRRDraAfpb DFrumkin, NRR CSteger, NRR GCooper, NRR MKotzalas, EDO PMilano, NRR HBarrett, NRR ADAMS Accession No'.. ML12066A140 OFFICE LPWB\PM LPWB\LA LPWB\BC NAME JPoole BClayton SCampbell DATE 3/23/12 3/22/12 3/26/12 OFFICIAL RECORD COPY}}
Division of Risk Assessment (DRA)
Daniel Frumkin      Team Leader                AFPB/DRA Charles Moulton    Fire Protection Engineer AFPB/DRA Gary Cooper        Fire Protection Engineer AFPBfDRA Harry Barrett      Fire Protection Engineer AFPB/DRA Bob Haag            Branch Chief              RII Rebecca Nease      Branch Chief              RII Tennessee Valley Authority (TVA) Participants:
Masoud Bajestani    Vice President            TVA Watts Bar Unit 2 Gordon Arent        Licensing Manager          TVA Watts Bar Unit 2 Terry Knuettel      Licensing Engineer        TVA Watts Bar Unit 2 William Crouch      Engineering                TVA Watts Bar Unit 2 Enclosure
 
                                    - 2 PositionlTitie          Organization Steve Hilmes  Instrumentation and      TVA Watts Bar Unit 2 Electrical Manager Brenda Simril Fire Protection Manager TVA Charles Brush Electrical Engineer      EPM George Seniez Fire Protection Engineer Bechtel
 
'.. ML12066A140 OFFICE             LPWB\PM               LPWB\LA               LPWB\BC NAME               JPoole               BClayton             SCampbell DATE               3/23/12               3/22/12               3/26/12}}

Revision as of 07:10, 12 November 2019

January 21, 2011 & February 3 and 15, 2011 - Summary of Public Meetings with Tennessee Valley Authority Regarding Submittal of Watts Bar Nuclear Plant, Unit 2, Fire Protection Report
ML12066A140
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 03/26/2012
From: Justin Poole
Watts Bar Special Projects Branch
To:
Bavol, Bruce
References
Download: ML12066A140 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 26, 2012 LICENSEE: Tennessee Valley Authority FACILITY: Watts Bar Nuclear Power Plant, Unit 2

SUBJECT:

SUMMARY

OF JANUARY AND FEBRUARY 2011, PUBLIC MEETINGS WITH TENNESSEE VALLEY AUTHORITY REGARDING SUBMITTAL OF WATTS BAR NUCLEAR PLANT, UNIT 2, FIRE PROTECTION REPORT On January 21, February 3 and 15, 2011, three Category 1 public meetings were held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of the Tennessee Valley Authority (TVA) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meetings was to discuss the initial submittal of Watts Bar Nuclear Plant Unit 2 Fire Protection Report, in support of TVA's application for an operating license. A list of participants is enclosed.

The meetings consisted of the NRC and TVA staff discussing draft requests for additional information (RAI) based on the content of the fire protection report under technical review. As a result of the meetings, the staff issued RAls that can be found in the Agencywide Documents Access and Management System at Accession Numbers ML110280128 and ML110610745.

A member of the public attended the meeting on February 15, 2011. No feedback form was submitted.

Please direct any inquiries to me at 301-415-2048 or Justin.Poole@nrc.gov.

Justin C. Poole, Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-391

Enclosure:

List of Participants cc w/encl: Distribution via Listserv

LIST OF PARTICIPANTS JANUARY AND FEBRUARY 2011, PUBLIC MEETINGS WITH TENNESSEE VALLEY AUTHORITY SUBMITTAL OF WATTS BAR NUCLEAR PLANT, UNIT 2 INITIAL FIRE PROTECTION REPORT Positionffitle Organization Bruce Boger Deputy Director Office of Nuclear Reactor Regulation Allen Howe Deputy Director Division of Operating Reactor Licensing (DORL)

Steve Campbell Branch Chief Watts Bar Special Projects Branch (LPWB)

DORL Patrick Milano Sr. Project Manager LPWB\DORL Justin Poole Sr. Project Manager LPWB\DORL Alex Klein Branch Chief Fire Protection Branch (AFPB)

Division of Risk Assessment (DRA)

Daniel Frumkin Team Leader AFPB/DRA Charles Moulton Fire Protection Engineer AFPB/DRA Gary Cooper Fire Protection Engineer AFPBfDRA Harry Barrett Fire Protection Engineer AFPB/DRA Bob Haag Branch Chief RII Rebecca Nease Branch Chief RII Tennessee Valley Authority (TVA) Participants:

Masoud Bajestani Vice President TVA Watts Bar Unit 2 Gordon Arent Licensing Manager TVA Watts Bar Unit 2 Terry Knuettel Licensing Engineer TVA Watts Bar Unit 2 William Crouch Engineering TVA Watts Bar Unit 2 Enclosure

- 2 PositionlTitie Organization Steve Hilmes Instrumentation and TVA Watts Bar Unit 2 Electrical Manager Brenda Simril Fire Protection Manager TVA Charles Brush Electrical Engineer EPM George Seniez Fire Protection Engineer Bechtel

'.. ML12066A140 OFFICE LPWB\PM LPWB\LA LPWB\BC NAME JPoole BClayton SCampbell DATE 3/23/12 3/22/12 3/26/12