Line 2: |
Line 2: |
| | number = ML16327A018 | | | number = ML16327A018 |
| | issue date = 11/23/2016 | | | issue date = 11/23/2016 |
| | title = Perry Nuclear Power Plant, Unit 1 - Request for Additional Information Related to License Amendment Request for Upper Containment Pool Gate Installation and Drain Down of the Reactor Cavity Portion of the Upper Containment Pool (TAC MF7476) | | | title = Request for Additional Information Related to License Amendment Request for Upper Containment Pool Gate Installation and Drain Down of the Reactor Cavity Portion of the Upper Containment Pool (TAC MF7476) (L-16-083) |
| | author name = Green K J | | | author name = Green K |
| | author affiliation = NRC/NRR/DORL/LPLIII-1 | | | author affiliation = NRC/NRR/DORL/LPLIII-1 |
| | addressee name = Hamilton D B | | | addressee name = Hamilton D |
| | addressee affiliation = FirstEnergy Nuclear Operating Co | | | addressee affiliation = FirstEnergy Nuclear Operating Co |
| | docket = 05000440 | | | docket = 05000440 |
| | license number = NPF-058 | | | license number = NPF-058 |
| | contact person = Green K J | | | contact person = Green K |
| | case reference number = L-16-083, TAC MF7476 | | | case reference number = L-16-083, TAC MF7476 |
| | document type = Letter, Request for Additional Information (RAI) | | | document type = Letter, Request for Additional Information (RAI) |
Line 18: |
Line 18: |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Mr. David B. Hamilton Site Vice President November 23, 2016 FirstEnergy Nuclear Operating Company Mail Stop A-PY-A290 P.O. Box 97, 10 Center Road Perry, OH 44081-0097 | | {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 November 23, 2016 Mr. David B. Hamilton Site Vice President FirstEnergy Nuclear Operating Company Mail Stop A-PY-A290 P.O. Box 97, 10 Center Road Perry, OH 44081-0097 |
|
| |
|
| ==SUBJECT:== | | ==SUBJECT:== |
| PERRY NUCLEAR POWER PLANT, UNIT NO. 1 -REQUEST FOR ADDITIONAL INFORMATION RELATED TO LICENSE AMENDMENT REQUEST FOR UPPER CONTAINMENT POOL GATE INSTALLATION AND DRAIN DOWN OF THE REACTOR CAVITY PORTION OF THE UPPER CONTAINMENT POOL (TAC NO. MF7476) (L-16-083) | | PERRY NUCLEAR POWER PLANT, UNIT NO. 1 - REQUEST FOR ADDITIONAL INFORMATION RELATED TO LICENSE AMENDMENT REQUEST FOR UPPER CONTAINMENT POOL GATE INSTALLATION AND DRAIN DOWN OF THE REACTOR CAVITY PORTION OF THE UPPER CONTAINMENT POOL (TAC NO. MF7476) (L-16-083) |
|
| |
|
| ==Dear Mr. Hamilton:== | | ==Dear Mr. Hamilton:== |
| By letter to the U.S. Nuclear Regulatory Commission (NRC) dated March 15, 2016, FirstEnergy Nuclear Operating Company (FENOC) submitted a request to modify the technical specifications to allow installation of the reactor well to steam dryer storage pool gate in the upper containment pool (UCP) in MODES 1, 2, and 3, and draining of the reactor well portion of the UCP in MODE 3, for the Perry Nuclear Power Plant, Unit No. 1. The NRC staff is reviewing your submittal and has determined that additional information is required to complete the review. The specific information requested is addressed in the enclosure to this letter. A draft request for additional information (RAI) was transmitted to your staff by email dated November 21, 2016. A clarification call with FENOC was held on November 22, 2016. As a result of the call, the staff revised wording to request number 4. Also, the staff identified one additional request that was discussed during the call. This request is identified as request number 6. During the call, it was agreed that FENOC would provide a response within 30 days from the date of this letter. | | |
| D. Hamilton The NRC staff considers that timely responses to requests for additional information help ensure sufficient time is available for staff review and contribute toward the NRC's goal of efficient and effective use of staff resources. If circumstances result in the need to revise the requested response date, please contact me at (301) 415-1627. Docket No. 50-440 | | By letter to the U.S. Nuclear Regulatory Commission (NRC) dated March 15, 2016, FirstEnergy Nuclear Operating Company (FENOC) submitted a request to modify the technical specifications to allow installation of the reactor well to steam dryer storage pool gate in the upper containment pool (UCP) in MODES 1, 2, and 3, and draining of the reactor well portion of the UCP in MODE 3, for the Perry Nuclear Power Plant, Unit No. 1. |
| | The NRC staff is reviewing your submittal and has determined that additional information is required to complete the review. The specific information requested is addressed in the enclosure to this letter. |
| | A draft request for additional information (RAI) was transmitted to your staff by email dated November 21, 2016. A clarification call with FENOC was held on November 22, 2016. As a result of the call, the staff revised wording to request number 4. Also, the staff identified one additional request that was discussed during the call. This request is identified as request number 6. During the call, it was agreed that FENOC would provide a response within 30 days from the date of this letter. |
| | |
| | D. Hamilton The NRC staff considers that timely responses to requests for additional information help ensure sufficient time is available for staff review and contribute toward the NRC's goal of efficient and effective use of staff resources. If circumstances result in the need to revise the requested response date, please contact me at (301) 415-1627. |
| | Sincerely, |
| | :~n~anager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-440 |
|
| |
|
| ==Enclosure:== | | ==Enclosure:== |
| Request for Additional Information cc w/encl: Distribution via ListServ Sincerely, Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation REQUEST FOR ADDITIONAL INFORMATION FIRSTENERGY NUCLEAR OPERATING COMPANY PERRY NUCLEAR POWER PLANT. UNIT NO. 1 DOCKET NO. 50-440 In reviewing the FirstEnergy Nuclear Operating Company's (FENOC) submittal dated March 15, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 16075A411 ), related to license amendment request for installation of the gate in upper containment pool (UCP) in MODES 1, 2, and 3, and draining of the reactor well portion of the UCP in MODE 3, for Perry Nuclear Power Plant, Unit No. 1, the U.S. Nuclear Regulatory Commission (NRC) staff has determined that the following information is needed in order to complete its review: Title 10 of the Code of Federal Regulations (CFR), paragraph 50.34(f), "Additional TM I-related requirements," requires that state-of-the-art human factors principles are used to satisfy all specific regulatory requirements. NUREG-0800, "Standard Review Plan [SRP] for the Review of Safety Analysis Reports for Nuclear Power Plants: LWR Edition," is used by the NRC staff to perform safety evaluations of license applications submitted by applicants pursuant to 10 CFR Part 50. The following chapters in the SRP were used to evaluate the human performance aspect of the license amendment request: Chapter 18, "Human Factors Engineering," Revision 2, discusses the processes for evaluating operator actions. This chapter also identifies specific areas of review that are needed for successful integration of human characteristics and capabilities into nuclear power plant design. Chapter 13.5.2.1, "Operating and Emergency Operating Procedures," Revision 2, is used to maintain the applicant's operating procedures that will be used by the operating organization to ensure that the routine operating, off-normal, and emergency activities will be conducted in a safe manner. 1. Describe any new or changed operator actions that are required as a result of the proposed installation of the reactor well to steam dryer storage pool gate in the upper containment pool in MODES 1, 2, and 3. 2. Describe any new or changed operator actions as a result of the proposed creation of the new Special Operations TS, TS 3.10.9, "Suppression Pool Makeup -MODE 3 Upper Containment Pool Drain-Down." 3. Section 3.2.1, "Reactor Well Gate Installation (MODES 1, 2, and 3)," and Section 3.2.2 "Reactor Well Drained in MODE 3," of the enclosure to the license amendment request provide a brief discussion on current emergency operating procedures (EOPs). Enclosure Describe any changes to manual operator actions covered by EOPs or abnormal procedures that may occur as a result of this amendment. If so, describe any evaluation of the EOPs for potential modifications. 4. State if the operators will be trained on the proposed license amendment prior to the end of the implementation period. 5. Based on FENOC's response to the above requests 1 and 2, describe the verification and validation activities associated with any required changes. 6. Section 3.2.1 of the enclosure to the license amendment request states that the suppression pool water level can be managed by plant operations during the short duration that the condition will exist. Explain how long the "short duration" will last.
| |
|
| |
|
| ML 16327A018 OFFICE DORL/LPL3-1/PM DORL/LPL3-2/LA
| | Request for Additional Information cc w/encl: Distribution via ListServ |
| * NAME KGreen SRohrer (KGoldstein for) DATE 11/22/16 11/22/16 Sincerely, IRA/ Kimberly J. Green, Senior Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation RidsNrrPMPerry Resource RidsNrrLASRohrer Resource RidsRgn3MailCenter Resource DKi, NRR VHuckabay, NRR *via email/memo dated DRA/APHB/BC* DORL/LPL3-1 /BC DORL/LPL3-1/PM SWeerakkody DWrona KGreen (JCircle for) 11/21/16 11/23/16 11/23/16}}
| | |
| | REQUEST FOR ADDITIONAL INFORMATION FIRSTENERGY NUCLEAR OPERATING COMPANY PERRY NUCLEAR POWER PLANT. UNIT NO. 1 DOCKET NO. 50-440 In reviewing the FirstEnergy Nuclear Operating Company's (FENOC) submittal dated March 15, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML16075A411 ), related to license amendment request for installation of the gate in upper containment pool (UCP) in MODES 1, 2, and 3, and draining of the reactor well portion of the UCP in MODE 3, for Perry Nuclear Power Plant, Unit No. 1, the U.S. Nuclear Regulatory Commission (NRC) staff has determined that the following information is needed in order to complete its review: |
| | Title 10 of the Code of Federal Regulations (CFR), paragraph 50.34(f), "Additional TM I-related requirements," requires that state-of-the-art human factors principles are used to satisfy all specific regulatory requirements. |
| | NUREG-0800, "Standard Review Plan [SRP] for the Review of Safety Analysis Reports for Nuclear Power Plants: LWR Edition," is used by the NRC staff to perform safety evaluations of license applications submitted by applicants pursuant to 10 CFR Part 50. The following chapters in the SRP were used to evaluate the human performance aspect of the license amendment request: |
| | Chapter 18, "Human Factors Engineering," Revision 2, discusses the processes for evaluating operator actions. This chapter also identifies specific areas of review that are needed for successful integration of human characteristics and capabilities into nuclear power plant design. |
| | Chapter 13.5.2.1, "Operating and Emergency Operating Procedures," Revision 2, is used to maintain the applicant's operating procedures that will be used by the operating organization to ensure that the routine operating, off-normal, and emergency activities will be conducted in a safe manner. |
| | : 1. Describe any new or changed operator actions that are required as a result of the proposed installation of the reactor well to steam dryer storage pool gate in the upper containment pool in MODES 1, 2, and 3. |
| | : 2. Describe any new or changed operator actions as a result of the proposed creation of the new Special Operations TS, TS 3.10.9, "Suppression Pool Makeup - MODE 3 Upper Containment Pool Drain-Down." |
| | : 3. Section 3.2.1, "Reactor Well Gate Installation (MODES 1, 2, and 3)," and Section 3.2.2 "Reactor Well Drained in MODE 3," of the enclosure to the license amendment request provide a brief discussion on current emergency operating procedures (EOPs). |
| | Enclosure |
| | |
| | Describe any changes to manual operator actions covered by EOPs or abnormal procedures that may occur as a result of this amendment. If so, describe any evaluation of the EOPs for potential modifications. |
| | : 4. State if the operators will be trained on the proposed license amendment prior to the end of the implementation period. |
| | : 5. Based on FENOC's response to the above requests 1 and 2, describe the verification and validation activities associated with any required changes. |
| | : 6. Section 3.2.1 of the enclosure to the license amendment request states that the suppression pool water level can be managed by plant operations during the short duration that the condition will exist. Explain how long the "short duration" will last. |
| | |
| | ML16327A018 *via email/memo dated OFFICE DORL/LPL3-1/PM DORL/LPL3-2/LA* DRA/APHB/BC* DORL/LPL3-1 /BC DORL/LPL3-1/PM SRohrer SWeerakkody NAME KGreen DWrona KGreen (KGoldstein for) (JCircle for) |
| | DATE 11/22/16 11/22/16 11/21/16 11/23/16 11/23/16}} |
Letter Sequence RAI |
---|
|
|
MONTHYEARL-16-083, License Amendment Request for Upper Containment Pool (Ucp) Gate Installation in Modes 1, 2, and 3, and Drain-Down of the Reactor Cavity Portion of the Ucp in Mode 32016-03-15015 March 2016 License Amendment Request for Upper Containment Pool (Ucp) Gate Installation in Modes 1, 2, and 3, and Drain-Down of the Reactor Cavity Portion of the Ucp in Mode 3 Project stage: Request L-16-298, Response to a Request for Additional Information Regarding a License Amendment Request for Upper Containment Pool (Ucp) Gate Installation in Modes 1, 2, and 3, and Drain-Down of the Reactor Cavity Portion of the Ucp in Mode 32016-11-0707 November 2016 Response to a Request for Additional Information Regarding a License Amendment Request for Upper Containment Pool (Ucp) Gate Installation in Modes 1, 2, and 3, and Drain-Down of the Reactor Cavity Portion of the Ucp in Mode 3 Project stage: Response to RAI ML16327A0182016-11-23023 November 2016 Request for Additional Information Related to License Amendment Request for Upper Containment Pool Gate Installation and Drain Down of the Reactor Cavity Portion of the Upper Containment Pool (TAC MF7476) (L-16-083) Project stage: RAI ML17004A2952017-01-0505 January 2017 Safety Evaluation Report- Application for Amendment Perry Nuclear Power Plant Project stage: Approval 2016-11-07
[Table View] |
Similar Documents at Perry |
---|
Category:Letter
MONTHYEARL-24-208, License Renewal Application for the Perry Nuclear Power Plant - Responses to Request for Additional Information - Round 1 (Set 2)2024-10-0202 October 2024 License Renewal Application for the Perry Nuclear Power Plant - Responses to Request for Additional Information - Round 1 (Set 2) ML24134A1522024-09-17017 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - Letter L-24-207, License Renewal Application for the Perry Nuclear Power Plant-Response to Request for Additional Information - Set 12024-09-16016 September 2024 License Renewal Application for the Perry Nuclear Power Plant-Response to Request for Additional Information - Set 1 ML24225A0512024-09-13013 September 2024 Issuance of Alternative Request VR-9, Revision 0, Associated with the Fourth 10-Year Inservice Testing Interval ML24256A0872024-09-11011 September 2024 Fws to NRC, Concurrence with Endangered Species Act Nlaa Determinations for Perry License Renewal L-24-201, Spent Fuel Storage Cask Registration2024-09-0909 September 2024 Spent Fuel Storage Cask Registration ML24250A0412024-09-0606 September 2024 Fws to NRC, Perry Nuclear Plant, Unit 1, License Renewal List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected ML24249A0882024-09-0606 September 2024 Letter to Rickey Armstrong, President_ Re. NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24249A0752024-09-0606 September 2024 Letter to Charles Diebold, Chief_ Re. NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24249A0782024-09-0606 September 2024 Ltr. to Kenneth Meshigaud, Chairperson, _ Re., NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24249A0862024-09-0606 September 2024 Letter to Regina Gasco-Bentley, Chairperson_ Re. NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24249A0762024-09-0606 September 2024 Letter to Douglas Lankford, Chief_ Re. NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24166A0172024-09-0606 September 2024 Ltr. to Glenna Wallace, Chief, Eastern Shawnee Tribe of Oklahoma; Re., NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24247A0212024-09-0606 September 2024 NRC Request for Concurrence with Endangered Species Act Determinations for Perry License Renewal, Issuance of Draft Supplemental Environmental Impact Statement, and Opportunity for Public Comment (Consultation Code: 2024-0006782) L-24-200, License Renewal Application for Revision to Supplement 4 for Editorial Corrections2024-09-0505 September 2024 License Renewal Application for Revision to Supplement 4 for Editorial Corrections ML24228A1702024-09-0303 September 2024 Ltr to Rod L. Penfield-Perry Nuclear Power Plant Unit 1-Notice of Avail of the Draft Supp 61 to the GEIS for License Renew of Nuclear Plants ML24228A1712024-09-0303 September 2024 Ltr to Brian Dickens, EPA-Perry Nuclear Power Plant Unit 1-Notice of Avail of the Draft Supp 61 to the GEIS for License Renew of Nuclear Plants ML24240A1482024-08-27027 August 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information L-24-188, Submittal of Quality Assurance Program Manual, Revision 302024-08-27027 August 2024 Submittal of Quality Assurance Program Manual, Revision 30 L-24-190, Spent Fuel Storage Cask Registration2024-08-26026 August 2024 Spent Fuel Storage Cask Registration ML24239A7782024-08-26026 August 2024 Aging Management Audit - Perry Unit 1 - License Renewal Application August 26 2024 IR 05000440/20240052024-08-22022 August 2024 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2024005) L-24-186, Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule L-24-174, Response to Perry Nuclear Power Plant License Renewal Environmental Report Severe Accident Mitigation Alternatives 2nd Round Request for Additional Information2024-08-15015 August 2024 Response to Perry Nuclear Power Plant License Renewal Environmental Report Severe Accident Mitigation Alternatives 2nd Round Request for Additional Information IR 05000440/20240022024-08-0808 August 2024 Integrated Inspection Report 05000440/2024002 L-24-178, License Renewal Application Revision O - Supplement 42024-08-0808 August 2024 License Renewal Application Revision O - Supplement 4 L-24-189, License Renewal Application for Revision O - Supplement 12024-08-0707 August 2024 License Renewal Application for Revision O - Supplement 1 L-24-171, Spent Fuel Storage Cask Registration2024-07-30030 July 2024 Spent Fuel Storage Cask Registration ML24150A2022024-07-25025 July 2024 Letter to Rod L. Penfield-Perry Nuclear Power Plant Unit 1-License Renewal Scoping Summary Rpt L-24-108, License Renewal Application, Revision 0 - Supplement 32024-07-24024 July 2024 License Renewal Application, Revision 0 - Supplement 3 L-24-168, Technical Specification Required Shutdown Due to Increase in RCS Unidentified Leakage2024-07-15015 July 2024 Technical Specification Required Shutdown Due to Increase in RCS Unidentified Leakage IR 05000440/20244012024-07-0909 July 2024 Security Baseline Inspection Report 05000440/2024401 L-24-155, Reactor Water Clean Up Leak Detection Loss of Safety Function2024-06-27027 June 2024 Reactor Water Clean Up Leak Detection Loss of Safety Function L-24-036, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2024-06-27027 June 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-24-020, License Renewal Application for the Perry Nuclear Power Plant Revision 0, Supplement 22024-06-27027 June 2024 License Renewal Application for the Perry Nuclear Power Plant Revision 0, Supplement 2 L-24-140, Operation of the Residual Heat Removal Loops B and C Alternate Keep Fill Configuration Was Prohibited by Technical Specifications and Resulted in an Unanalyzed Condition2024-06-20020 June 2024 Operation of the Residual Heat Removal Loops B and C Alternate Keep Fill Configuration Was Prohibited by Technical Specifications and Resulted in an Unanalyzed Condition IR 05000440/20240112024-06-17017 June 2024 Fire Protection Team Inspection Report 05000440/2024011 ML24157A3782024-06-0606 June 2024 – Revised Request for Information for NRC License Renewal Inspection: Inspection Report 05000440/2024010 ML24141A1632024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection L-24-116, Response to License Renewal Environmental Report Severe Accident Mitigation Alternatives Requests for Additional Information and Request for Clarification2024-05-16016 May 2024 Response to License Renewal Environmental Report Severe Accident Mitigation Alternatives Requests for Additional Information and Request for Clarification L-24-085, Nudear Power Plant, Submittal of Emergency Plan, Revision 622024-05-0606 May 2024 Nudear Power Plant, Submittal of Emergency Plan, Revision 62 L-24-103, Response to NRC Regulatory Issue Summary 2024-01, Preparation & Scheduling of Operator Licensing Exams2024-05-0202 May 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation & Scheduling of Operator Licensing Exams ML24117A1222024-04-26026 April 2024 Confirmation of Initial License Examination IR 05000440/20240012024-04-24024 April 2024 Integrated Inspection Report 05000440/2024001 L-24-097, Submittal of 2023 Annual Radiological Effluent Release Report2024-04-22022 April 2024 Submittal of 2023 Annual Radiological Effluent Release Report L-24-096, Submittal of Annual Radiological Environmental Operating Report2024-04-22022 April 2024 Submittal of Annual Radiological Environmental Operating Report ML24095A3282024-04-19019 April 2024 License Renewal Revised Schedule Letter L-24-066, Response to Request for Additional Information Regarding 10 CFR 50.55a Request Number VR-9, Feedwater Check Valve Exercising Test Frequency2024-04-15015 April 2024 Response to Request for Additional Information Regarding 10 CFR 50.55a Request Number VR-9, Feedwater Check Valve Exercising Test Frequency L-24-083, Response to License Renewal Environmental Report Requests for Additional Information and Request for Clarification2024-04-15015 April 2024 Response to License Renewal Environmental Report Requests for Additional Information and Request for Clarification ML24088A1922024-03-28028 March 2024 Request for Information for NRC License Renewal Inspection: Inspection Report 05000440/2024010 2024-09-09
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24276A1292024-10-0202 October 2024 LRA - Request for Additional Information - Set 3 ML24276A1282024-10-0202 October 2024 LRA - Requests for Additional Information - Round 1 (Set 3) - Email to Applicant ML24241A1002024-08-28028 August 2024 LRA - Requests for Additional Information - Round 1 (Set 2) ML24240A1482024-08-27027 August 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML24227A9562024-08-14014 August 2024 LRA - Requests for Additional Information - Set 1 ML24204A0012024-07-17017 July 2024 NRR E-mail Capture - Request for Additional Information Vistraops Fleet Exemption for the Requirements in 10 CFR 50.71 Pertaining to the Submittal of Updated Final Safety Analysis Reports ML24190A0802024-07-0808 July 2024 Second Round Request for Additional Information ML24141A1632024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML24064A2202024-03-14014 March 2024 PNPP Unit 1 LRA Environmental Review RCI and RAI-Enclosure 2 ML24074A4272024-03-14014 March 2024 NRR E-mail Capture - Final RAI - Perry Request for Relief - Proposed Inservice Inspection Alternative VR-9 ML23227A2202023-08-15015 August 2023 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Perry Nuclear Power Plant ML23198A2842023-07-17017 July 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection ML22234A1482022-08-22022 August 2022 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML22182A4442022-07-0202 July 2022 Information Request for NRC Triennial Evaluations of Changes, Tests, and Experiments (50.59) Baseline Inspection Report 05000440/2022010 ML22136A2122022-05-16016 May 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information Regarding Proposed Inservice Inspection Alternative IR-063 ML22130A5662022-05-12012 May 2022 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML22089A2452022-03-30030 March 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Request VR-12 ML21168A0662021-06-17017 June 2021 Notification of NRC Fire Protection Team Inspection Request for Information; Inspection Report 05000440/2021010 ML21110A6852021-04-19019 April 2021 NRR E-mail Capture - Final RAI - Perry - Request to Review the Emergency Plan ML21050A1032021-02-18018 February 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Requests VR-3, Rev. 0 and VR-5, Rev. 0 ML21050A1072021-02-18018 February 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Request VR-7, Rev. 0 ML21050A1112021-02-18018 February 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Requests VR-4, Rev. 0 and VR-6, Rev. 0 ML21049A2702021-02-16016 February 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Request SR-2, Rev. 0 (EPID: L-2021-LLR-0005) (2nd Round RAI) ML21032A3422021-02-0101 February 2021 NRR E-mail Capture - Final RAI - Perry Request for Relief - Proposed Alternative Request SR-2, Rev. 0 ML21020A0392021-01-20020 January 2021 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000440/2021010 ML20325A2782020-11-20020 November 2020 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Part 73 Force-on-Force Exemption ML20289A1012020-10-0505 October 2020 NRR E-mail Capture - Final 2nd Round RAI - Perry Request for Relief - Proposed Alternative Request IR-056, Rev. 3 ML20191A0192020-07-0101 July 2020 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Extension to License Expiration Date by Recapturing Low-Power Testing Time ML20133K0632020-05-14014 May 2020 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML20127H8692020-05-0606 May 2020 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Request IR-054, Rev. 2 ML20127H8672020-05-0606 May 2020 NRR E-mail Capture - Beaver Valley, Davis-Besse, and Perry - Request for Additional Information Regarding Request for Exemptions from Part 73 Security Requalification Requirements ML19192A2222019-07-18018 July 2019 Request for Additional Information Regarding Application for Order Consenting to Transfer of Licenses and Conforming License Amendments ML19143A0732019-05-29029 May 2019 FENOC Fleet - Beaver Valley, Units 1 and 2; Davis-Besse, Unit 1, Perry, Unit 1 - Supplemental Information Needed for Acceptance of Requested Licensing Action; Application for Order Consenting to License Transfer and Conforming Amendments ML19035A6552019-02-19019 February 2019 Request for Additional Information Related to the Deferral of Actions Related to Beyond-Design-Basis Flooding Hazard Reevaluations for Perry Nuclear Power Plant. ML18277A2372018-10-0202 October 2018 NRR E-mail Capture - RAI Related to Perry Request for Alternative PR-2 ML18271A2082018-09-27027 September 2018 NRR E-mail Capture - RAI Related to Request to Revise Perry'S Technical Specifications to Extend Containment Leak Rate Test Intervals ML18102B0852018-04-12012 April 2018 NRR E-mail Capture - Follow-up Request for Additional Information (RAI) FENOC FLEET-- Exemption Request for a Physical Barrier Requirement for Beaver ML18043A0102018-02-0909 February 2018 NRR E-mail Capture - FENOC--MG0010-MG0011, MG-0012, MG0013-- Request for Additional Information (RAI) - Exemption Request Security Barrier in Physical Plans ML18009A0112018-01-0808 January 2018 NRR E-mail Capture - Final RAI for Perry LAR Related to AST Implementation ML18008A0282017-12-13013 December 2017 NRR E-mail Capture - Draft RAI for Perry LAR to Revise TSs for AST ML17303B1582017-11-0707 November 2017 FENOC-Beaver Valley Power Station, Units 1 and 2, Davis-Besse Nuclear Power Station, Unit 1, Perry Nuclear Power Plant Unit 1 - Generic Letter 2016-01, Request for Supplemental Information ML17160A1102017-06-0707 June 2017 17 Perry Nuclear Power Plant - Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Mxg) ML17143A3592017-05-22022 May 2017 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team): Inspection Report 05000440/2017008 (Njfa) ML17115A4212017-04-25025 April 2017 NRR E-mail Capture - Withdrawal of Draft RAI Regarding Perry'S LAR Re TSTF-501, Revision 1 ML17114A1532017-04-0606 April 2017 NRR E-mail Capture - Draft RAI for Perry LAR Re TSTF-501, Revision 1 ML16364A2482016-12-28028 December 2016 Notification of NRC Baseline Inspection and Request for Information 05000440/2017001 ML16327A0182016-11-23023 November 2016 Request for Additional Information Related to License Amendment Request for Upper Containment Pool Gate Installation and Drain Down of the Reactor Cavity Portion of the Upper Containment Pool (TAC MF7476) (L-16-083) ML16279A0432016-10-0606 October 2016 Request for Additional Information Related to License Amendment Request for Upper Containment Pool Gate Installation During Modes 1, 2, & Drain Down of Upper Containment Pool During Mode 3 IR 05000440/20215012016-04-19019 April 2016 Perry Nuclear Power Plant - Request for Additional Information Regarding VIO 05000440/215010-01 ML16067A2812016-03-10010 March 2016 Request for Additional Information Related to Emergency Action Level Scheme Change License Amendment Request (CAC No. MF7046)(L-15-257) 2024-08-28
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 November 23, 2016 Mr. David B. Hamilton Site Vice President FirstEnergy Nuclear Operating Company Mail Stop A-PY-A290 P.O. Box 97, 10 Center Road Perry, OH 44081-0097
SUBJECT:
PERRY NUCLEAR POWER PLANT, UNIT NO. 1 - REQUEST FOR ADDITIONAL INFORMATION RELATED TO LICENSE AMENDMENT REQUEST FOR UPPER CONTAINMENT POOL GATE INSTALLATION AND DRAIN DOWN OF THE REACTOR CAVITY PORTION OF THE UPPER CONTAINMENT POOL (TAC NO. MF7476) (L-16-083)
Dear Mr. Hamilton:
By letter to the U.S. Nuclear Regulatory Commission (NRC) dated March 15, 2016, FirstEnergy Nuclear Operating Company (FENOC) submitted a request to modify the technical specifications to allow installation of the reactor well to steam dryer storage pool gate in the upper containment pool (UCP) in MODES 1, 2, and 3, and draining of the reactor well portion of the UCP in MODE 3, for the Perry Nuclear Power Plant, Unit No. 1.
The NRC staff is reviewing your submittal and has determined that additional information is required to complete the review. The specific information requested is addressed in the enclosure to this letter.
A draft request for additional information (RAI) was transmitted to your staff by email dated November 21, 2016. A clarification call with FENOC was held on November 22, 2016. As a result of the call, the staff revised wording to request number 4. Also, the staff identified one additional request that was discussed during the call. This request is identified as request number 6. During the call, it was agreed that FENOC would provide a response within 30 days from the date of this letter.
D. Hamilton The NRC staff considers that timely responses to requests for additional information help ensure sufficient time is available for staff review and contribute toward the NRC's goal of efficient and effective use of staff resources. If circumstances result in the need to revise the requested response date, please contact me at (301) 415-1627.
Sincerely,
- ~n~anager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-440
Enclosure:
Request for Additional Information cc w/encl: Distribution via ListServ
REQUEST FOR ADDITIONAL INFORMATION FIRSTENERGY NUCLEAR OPERATING COMPANY PERRY NUCLEAR POWER PLANT. UNIT NO. 1 DOCKET NO. 50-440 In reviewing the FirstEnergy Nuclear Operating Company's (FENOC) submittal dated March 15, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML16075A411 ), related to license amendment request for installation of the gate in upper containment pool (UCP) in MODES 1, 2, and 3, and draining of the reactor well portion of the UCP in MODE 3, for Perry Nuclear Power Plant, Unit No. 1, the U.S. Nuclear Regulatory Commission (NRC) staff has determined that the following information is needed in order to complete its review:
Title 10 of the Code of Federal Regulations (CFR), paragraph 50.34(f), "Additional TM I-related requirements," requires that state-of-the-art human factors principles are used to satisfy all specific regulatory requirements.
NUREG-0800, "Standard Review Plan [SRP] for the Review of Safety Analysis Reports for Nuclear Power Plants: LWR Edition," is used by the NRC staff to perform safety evaluations of license applications submitted by applicants pursuant to 10 CFR Part 50. The following chapters in the SRP were used to evaluate the human performance aspect of the license amendment request:
Chapter 18, "Human Factors Engineering," Revision 2, discusses the processes for evaluating operator actions. This chapter also identifies specific areas of review that are needed for successful integration of human characteristics and capabilities into nuclear power plant design.
Chapter 13.5.2.1, "Operating and Emergency Operating Procedures," Revision 2, is used to maintain the applicant's operating procedures that will be used by the operating organization to ensure that the routine operating, off-normal, and emergency activities will be conducted in a safe manner.
- 1. Describe any new or changed operator actions that are required as a result of the proposed installation of the reactor well to steam dryer storage pool gate in the upper containment pool in MODES 1, 2, and 3.
- 2. Describe any new or changed operator actions as a result of the proposed creation of the new Special Operations TS, TS 3.10.9, "Suppression Pool Makeup - MODE 3 Upper Containment Pool Drain-Down."
- 3. Section 3.2.1, "Reactor Well Gate Installation (MODES 1, 2, and 3)," and Section 3.2.2 "Reactor Well Drained in MODE 3," of the enclosure to the license amendment request provide a brief discussion on current emergency operating procedures (EOPs).
Enclosure
Describe any changes to manual operator actions covered by EOPs or abnormal procedures that may occur as a result of this amendment. If so, describe any evaluation of the EOPs for potential modifications.
- 4. State if the operators will be trained on the proposed license amendment prior to the end of the implementation period.
- 5. Based on FENOC's response to the above requests 1 and 2, describe the verification and validation activities associated with any required changes.
- 6. Section 3.2.1 of the enclosure to the license amendment request states that the suppression pool water level can be managed by plant operations during the short duration that the condition will exist. Explain how long the "short duration" will last.
ML16327A018 *via email/memo dated OFFICE DORL/LPL3-1/PM DORL/LPL3-2/LA* DRA/APHB/BC* DORL/LPL3-1 /BC DORL/LPL3-1/PM SRohrer SWeerakkody NAME KGreen DWrona KGreen (KGoldstein for) (JCircle for)
DATE 11/22/16 11/22/16 11/21/16 11/23/16 11/23/16