ML11187A335: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 55: Line 55:


Boundary returned to original location 11/1/11 Security Plan Update - Boundary to be restored by 9/30/11  Lic/Crouch 15. Part 70 License EA - 6/13/11A FL - 6/15/11 NRC to issue Part 70 license. Fuel receipt is 6/20/11.
Boundary returned to original location 11/1/11 Security Plan Update - Boundary to be restored by 9/30/11  Lic/Crouch 15. Part 70 License EA - 6/13/11A FL - 6/15/11 NRC to issue Part 70 license. Fuel receipt is 6/20/11.
Milano 16. ACRS Topics 7/12/11 Improvements, Inspection status, Refurb status, Construction Status, Japan, IST Re-Presentation, Cyber Security, Ch 7 digital upgrades. Agenda has been finalized.  
Milano 16. ACRS Topics 7/12/11 Improvements, Inspection status, Refurb status, Construction Status, Japan, IST Re-Presentation, Cyber Security, Ch 7 digital upgrades. Agenda has been finalized.
: 17. SAMDA RAIs 6/17/11A 5 questions regarding 2nd submittal  18. SSER 22/23 Open Items Response 7/15/11 7/15 is the target date for the next SSER update. The expanded HH list and it's status is provided at the end of this letter.  
: 17. SAMDA RAIs 6/17/11A 5 questions regarding 2nd submittal  18. SSER 22/23 Open Items Response 7/15/11 7/15 is the target date for the next SSER update. The expanded HH list and it's status is provided at the end of this letter.
: 19. Chapter 12 RAI on Instrument Channel Operability Tests 6/24/11  ENG/Hilmes 20. Transient Analysis issues Additional Follow up Audit 6/28-30/11 &
: 19. Chapter 12 RAI on Instrument Channel Operability Tests 6/24/11  ENG/Hilmes 20. Transient Analysis issues Additional Follow up Audit 6/28-30/11 &
7/1/11 until noon, if necessary 6/13/11A TVA/WEC confirming availability of personnel. Final audit plan to come.
7/1/11 until noon, if necessary 6/13/11A TVA/WEC confirming availability of personnel. Final audit plan to come.
Line 75: Line 75:


ML092151155)
ML092151155)
Closed by IR 2010604
Closed by IR 2010604
: 5. Verify timely submittal of pre-startup core map and perform technical review.  (TVA letter dated September 7, 2007, ADAMS  
: 5. Verify timely submittal of pre-startup core map and perform technical review.  (TVA letter dated September 7, 2007, ADAMS  


Line 88: Line 88:
Review  8. Verify rod control system operability during Response provided in TVA Page 7 of 23    SSER Item No. SSER Item Description TVA Status NRC Status power ascension. TVA should provide a pre-startup map to the NRC staff indicating the rodded fuel assemblies and a projected end of cycle burnup of each rodded assembly for the initial fuel cycle 6-months prior to fuel load.  (NRC safety evaluation dated May 3, 2010, ADAMS Accession No. ML101200035)to NRC letter dated April 6, 2011. 9. Confirm that education and experience of management and principal supervisory  
Review  8. Verify rod control system operability during Response provided in TVA Page 7 of 23    SSER Item No. SSER Item Description TVA Status NRC Status power ascension. TVA should provide a pre-startup map to the NRC staff indicating the rodded fuel assemblies and a projected end of cycle burnup of each rodded assembly for the initial fuel cycle 6-months prior to fuel load.  (NRC safety evaluation dated May 3, 2010, ADAMS Accession No. ML101200035)to NRC letter dated April 6, 2011. 9. Confirm that education and experience of management and principal supervisory  


positions down through the shift supervisory level conform to Regulatory Guide 1.8.  
positions down through the shift supervisory level conform to Regulatory Guide 1.8.
(Section 13.1.3)
(Section 13.1.3)
For NRC Inspection /
For NRC Inspection /
Review  10. Confirm that TVA has an adequate number of licensed and non-licensed operators in the  
Review  10. Confirm that TVA has an adequate number of licensed and non-licensed operators in the  


training pipeline to s upport the preoperational test program, fuel loading, and dual unit operation. (Section 13.1.3)TVA to answer later.
training pipeline to s upport the preoperational test program, fuel loading, and dual unit operation. (Section 13.1.3)TVA to answer later.
: 11. The plant administrative procedures should clearly state that, w hen the Assistant Shift Engineer assumes his duties as Fire Brigade Leader, his control room duties are temporarily assumed by the Shift Supervisor (Shift Engineer), or by another SRO, if one is available. The plant administrative procedures should clearly describe this transfer of control room duties. (Section  
: 11. The plant administrative procedures should clearly state that, w hen the Assistant Shift Engineer assumes his duties as Fire Brigade Leader, his control room duties are temporarily assumed by the Shift Supervisor (Shift Engineer), or by another SRO, if one is available. The plant administrative procedures should clearly describe this transfer of control room duties. (Section  


Line 125: Line 125:


environmental conditions on equipment during the layup period.
environmental conditions on equipment during the layup period.
  (Section 3.11.2.2)Response provided in TVA to NRC letter dated April 6, 2011.
(Section 3.11.2.2)Response provided in TVA to NRC letter dated April 6, 2011.
Page 9 of 23    SSER Item No. SSER Item Description TVA Status NRC Status 19. The NRC staff should complete its review of TVA's EQ Program procedures for WBN Unit  
Page 9 of 23    SSER Item No. SSER Item Description TVA Status NRC Status 19. The NRC staff should complete its review of TVA's EQ Program procedures for WBN Unit  


Line 154: Line 154:


than 1x10 3 rads for electronic components Response provided in TVA to NRC letter dated April 6, 2011.
than 1x10 3 rads for electronic components Response provided in TVA to NRC letter dated April 6, 2011.
Page 10 of 23    SSER Item No. SSER Item Description TVA Status NRC Status such as semiconductors or electronic components containing organic material.  
Page 10 of 23    SSER Item No. SSER Item Description TVA Status NRC Status such as semiconductors or electronic components containing organic material.
(Section 3.11.2.2.1)
(Section 3.11.2.2.1)
: 25. Prior to the issuance of an operating license, TVA is required to provide satisfactory documentation that it has obtained the maximum secondary liability insurance  
: 25. Prior to the issuance of an operating license, TVA is required to provide satisfactory documentation that it has obtained the maximum secondary liability insurance  
Line 165: Line 165:
insurance, and the NR C staff has reviewed and approved the documentation. (Section  
insurance, and the NR C staff has reviewed and approved the documentation. (Section  


22.3) TVA to answer later.
22.3) TVA to answer later.
: 26. For the scenario with an accident in one unit and concurrent shutdown of the second unit  
: 26. For the scenario with an accident in one unit and concurrent shutdown of the second unit  


without offsite power, T VA stated that Unit 2 pre-operational testing will validate the diesel response to sequencing of loads on the Unit 2 emergency diesel generators (EDGs). The NRC staff will evaluate the status of this issue and will update the status of the EDG load response in a future SSER. (Section  
without offsite power, T VA stated that Unit 2 pre-operational testing will validate the diesel response to sequencing of loads on the Unit 2 emergency diesel generators (EDGs). The NRC staff will evaluate the status of this issue and will update the status of the EDG load response in a future SSER. (Section  


8.1) Response provided in TVA to NRC letter dated April 6, 2011. 27. TVA should provide a summary of margin studies based on scenarios described in Section 8.1 for CSSTs A, B, C, and D.  
8.1) Response provided in TVA to NRC letter dated April 6, 2011. 27. TVA should provide a summary of margin studies based on scenarios described in Section 8.1 for CSSTs A, B, C, and D.
(Section 8.2.2)
(Section 8.2.2)
Response provided in TVA to NRC letter dated April 6, 2011. 28. TVA should provide to the NRC staff a detailed discussion sho wing that the load tap changer is able to maintain the 6.9 kV bus  
Response provided in TVA to NRC letter dated April 6, 2011. 28. TVA should provide to the NRC staff a detailed discussion sho wing that the load tap changer is able to maintain the 6.9 kV bus  
Line 178: Line 178:
: 29. TVA should provide the transmission system specifics (grid stability analyses) to the NRC staff. In order to verify compliance with GDC 17, the results of the grid stability analyses must indicate that loss of the largest electric  
: 29. TVA should provide the transmission system specifics (grid stability analyses) to the NRC staff. In order to verify compliance with GDC 17, the results of the grid stability analyses must indicate that loss of the largest electric  


supply to the grid, loss of the largest load from the grid, loss of the most critical transmission line, or loss of both units themselves, will not cause grid instability.  
supply to the grid, loss of the largest load from the grid, loss of the most critical transmission line, or loss of both units themselves, will not cause grid instability.
(Section 8.2.2)
(Section 8.2.2)
Response provided in TVA to NRC letter dated June 7, 2011. 30. TVA should confirm that all other safety-related equipment (in addition to the Class 1E motors) will have adequate starting and running voltage at the most limiting safety  
Response provided in TVA to NRC letter dated June 7, 2011. 30. TVA should confirm that all other safety-related equipment (in addition to the Class 1E motors) will have adequate starting and running voltage at the most limiting safety  
Line 190: Line 190:
for the degraded voltage settings. (Section  
for the degraded voltage settings. (Section  


8.3.1.2) TVA to answer later.
8.3.1.2) TVA to answer later.
: 31. TVA should evaluate the re-sequencing of loads, with time delays involved, in the scenario of a LOCA followed by a delayed  
: 31. TVA should evaluate the re-sequencing of loads, with time delays involved, in the scenario of a LOCA followed by a delayed  


Line 214: Line 214:
the Unit 2 OL to confirm (1) that the proposed Unit 2 changes were incorporated into Appendix C, and (2) that changes made to  
the Unit 2 OL to confirm (1) that the proposed Unit 2 changes were incorporated into Appendix C, and (2) that changes made to  


Appendix C for Unit 1 since Revision 92 and the changes made to the NP-REP since Revision 92 do not affect the bases of the staff's findings in this SER supplement.  
Appendix C for Unit 1 since Revision 92 and the changes made to the NP-REP since Revision 92 do not affect the bases of the staff's findings in this SER supplement.
(Section 13.3.2)
(Section 13.3.2)
TVA to answer later.
TVA to answer later.
: 38. The NRC staff will confirm the availability and operability of the ERDS for Unit 2 prior to issuance of the Unit 2 OL. (Section 13.3.2.6)
: 38. The NRC staff will confirm the availability and operability of the ERDS for Unit 2 prior to issuance of the Unit 2 OL. (Section 13.3.2.6)
For NRC Inspection /
For NRC Inspection /
Line 242: Line 242:


13.3.2.18)
13.3.2.18)
TVA to answer later.
TVA to answer later.
: 44. TVA should provide additional information to clarify how the initial and irradiated RT NDT was determined.  (Section 5.3.1)Response provided in TVA to NRC letter dated April 6, 2011. 45. TVA stated in its res ponse to RAI 5.3.2-2, dated July 31, 2010, that the PTLR would be  
: 44. TVA should provide additional information to clarify how the initial and irradiated RT NDT was determined.  (Section 5.3.1)Response provided in TVA to NRC letter dated April 6, 2011. 45. TVA stated in its res ponse to RAI 5.3.2-2, dated July 31, 2010, that the PTLR would be  


Line 298: Line 298:
calculate the fuel temperature and other impacted  
calculate the fuel temperature and other impacted  


variables, such as stored energy, given the lack of a fuel thermal conductivity degradation model.
variables, such as stored energy, given the lack of a fuel thermal conductivity degradation model.
(Section 4.2.2.1) Will result in a License Condition.
(Section 4.2.2.1) Will result in a License Condition.
62[E] Confirm TVA's change to FSAR Section 10.4.9 to reflect its intention to operate with each CST Response provided in TVA to NRC letter dated June 7, Page 18 of 23    SSER Item No. SSER Item Description TVA Status NRC Status isolated from the other.  (Section 10.4.9) 2011. 63[F] TVA should confirm to the NRC staff that testing prior to Unit 2 fuel load has demonstrated that two-way communications is impossible with the Eagle 21 communications interface.  (Section  
62[E] Confirm TVA's change to FSAR Section 10.4.9 to reflect its intention to operate with each CST Response provided in TVA to NRC letter dated June 7, Page 18 of 23    SSER Item No. SSER Item Description TVA Status NRC Status isolated from the other.  (Section 10.4.9) 2011. 63[F] TVA should confirm to the NRC staff that testing prior to Unit 2 fuel load has demonstrated that two-way communications is impossible with the Eagle 21 communications interface.  (Section  
Line 309: Line 309:
pending NRC review of the testing results.
pending NRC review of the testing results.
For NRC Inspection /
For NRC Inspection /
Review  65[H] TVA should provide justi fication to the staff regarding why differen t revisions of WCAP-13869 are referenced in WBN Unit 1 and Unit 2.
Review  65[H] TVA should provide justi fication to the staff regarding why differen t revisions of WCAP-13869 are referenced in WBN Unit 1 and Unit 2.
(Section 7.2.1.1) Response provided in TVA to NRC letter dated June 7, 2011. 66[I] TVA should clarify FSAR Section 9.2.5 to add the capability of the UHS to bring the non accident  
(Section 7.2.1.1) Response provided in TVA to NRC letter dated June 7, 2011. 66[I] TVA should clarify FSAR Section 9.2.5 to add the capability of the UHS to bring the non accident  


Line 356: Line 356:
initiation and control and flow indication are  
initiation and control and flow indication are  


completed in WBN Unit 2 before fuel load.
completed in WBN Unit 2 before fuel load.
(Section 7.8.2)
(Section 7.8.2)
For NRC Inspection /
For NRC Inspection /
Line 371: Line 371:
Instrumentation for Nuclear Power Plants to Assess Plant and Environs Conditions During and Following an Accident (Regulatory Guide 1.97)."  (Section 7.5.2.1.4) 93 TVA should confirm to the staff that testing of the Eagle 21  
Instrumentation for Nuclear Power Plants to Assess Plant and Environs Conditions During and Following an Accident (Regulatory Guide 1.97)."  (Section 7.5.2.1.4) 93 TVA should confirm to the staff that testing of the Eagle 21  


Page 22 of 23    SSER Item No. SSER Item Description TVA Status NRC Status system has sufficiently demonstrated that two-way communication to the ICS is precluded with the described configurations.  (Section 7.9.3.2) 94 TVA should provide to the staff either information that demonstrates that the WBN Unit 2 Common Q PAMS meets the applicable requirements in IEEE Std. 603-1991, or justification for why the Common Q PAMS should not meet those requirements.  (Section 7.5.2.2.3) 95 TVA should update FSAR Table 7.1-1, "Watts Bar Nuclear Plant NRC Regulatory Guide Conformance," to reference IEEE Std. 603-1991 for the WBN Unit 2 Common Q PAMS.  (Section 7.5.2.2.3) 96 TVA should (1) update FSAR Table 7.1-1 to include RG 1.100, Revision 3, for the Common Q PAMS, or (2) demonstrate that the Common Q PAMS is in conformance with RG 1.100, Revision 1, or provide justification for not conforming.  (Section 7.5.2.2.3) 97 TVA should demonstrate that the WBN Unit 2 Common Q PAMS is in conformance with RG 1.153, Revision 1, or provide justification for not conforming.  (Section 7.5.2.2.3) 98 TVA should demonstrate that the WBN Unit 2 Common Q PAMS is in conformance with RG 1.152, Revision 2, or provide justification for not conforming.  (Section 7.5.2.2.3) 99 TVA should update FSAR Table 7.1-1 to reference IEEE 7-4.3.2-2003 as being applicable to the WBN Unit 2 Common Q PAMS.  (Section 7.5.2.2.3) 100 TVA should update FSAR Table 7.1-1 to reference RG 1.168, Revision 1; IEEE 1012-1998; and IEEE 1020-1997 as being applicable to the WBN Unit 2 Common Q PAMS.
Page 22 of 23    SSER Item No. SSER Item Description TVA Status NRC Status system has sufficiently demonstrated that two-way communication to the ICS is precluded with the described configurations.  (Section 7.9.3.2) 94 TVA should provide to the staff either information that demonstrates that the WBN Unit 2 Common Q PAMS meets the applicable requirements in IEEE Std. 603-1991, or justification for why the Common Q PAMS should not meet those requirements.  (Section 7.5.2.2.3) 95 TVA should update FSAR Table 7.1-1, "Watts Bar Nuclear Plant NRC Regulatory Guide Conformance," to reference IEEE Std. 603-1991 for the WBN Unit 2 Common Q PAMS.  (Section 7.5.2.2.3) 96 TVA should (1) update FSAR Table 7.1-1 to include RG 1.100, Revision 3, for the Common Q PAMS, or (2) demonstrate that the Common Q PAMS is in conformance with RG 1.100, Revision 1, or provide justification for not conforming.  (Section 7.5.2.2.3) 97 TVA should demonstrate that the WBN Unit 2 Common Q PAMS is in conformance with RG 1.153, Revision 1, or provide justification for not conforming.  (Section 7.5.2.2.3) 98 TVA should demonstrate that the WBN Unit 2 Common Q PAMS is in conformance with RG 1.152, Revision 2, or provide justification for not conforming.  (Section 7.5.2.2.3) 99 TVA should update FSAR Table 7.1-1 to reference IEEE 7-4.3.2-2003 as being applicable to the WBN Unit 2 Common Q PAMS.  (Section 7.5.2.2.3) 100 TVA should update FSAR Table 7.1-1 to reference RG 1.168, Revision 1; IEEE 1012-1998; and IEEE 1020-1997 as being applicable to the WBN Unit 2 Common Q PAMS.
(Section 7.5.2.2.3) 101 TVA should demonstrate that the WBN Unit 2 Common Q PAMS application software is in conformance with RG 1.168, Revision 1, or provide justification for not conforming.  (Section 7.5.2.2.3) 102 TVA should update FSAR Table 7.1-1 to reference RG 1.209 and IEEE Std. 323-2003 as being applicable to the WBN Unit 2 Common Q PAMS.  (Section 7.5.2.2.3) 103 TVA should demonstrate that the WBN Unit 2 Common Q PAMS conforms to RG 1.209 and IEEE Std. 323-2003, or  
(Section 7.5.2.2.3) 101 TVA should demonstrate that the WBN Unit 2 Common Q PAMS application software is in conformance with RG 1.168, Revision 1, or provide justification for not conforming.  (Section 7.5.2.2.3) 102 TVA should update FSAR Table 7.1-1 to reference RG 1.209 and IEEE Std. 323-2003 as being applicable to the WBN Unit 2 Common Q PAMS.  (Section 7.5.2.2.3) 103 TVA should demonstrate that the WBN Unit 2 Common Q PAMS conforms to RG 1.209 and IEEE Std. 323-2003, or  


Page 23 of 23    SSER Item No. SSER Item Description TVA Status NRC Status provide justification for not conforming.  (Section 7.5.2.2.3)104 The NRC staff will review the WEC self assessment to verify that it the WBN Unit 2 PAMS is compliant to the V&V requirements in the SPM or that deviations from the requirements are adequately justified.  (Section 7.5.2.2.3.4.2) 105 TVA should produce an acceptable description of how the WBN Unit 2 Common Q PAMS SysRS and SRS implement the design basis requirements of IEEE Std. 603-1991 Clause 4.  (Section 7.5.2.2.3.4.3.1) 106 TVA should produce a final WBN Unit 2 Common Q PAMS SRS that is independently reviewed.  (Section 7.5.2.2.3.4.3.1) 107 TVA should provide to the NRC staff documentation to confirm that the final WBN Unit 2 Common Q PAMS SDDs that are independently reviewed.  (Section 7.5.2.2.3.4.3.2) 108 TVA should demonstrate to the NRC staff that there are no synergistic effects between temperature and humidity for the Common Q PAMS equipment.  (Section 7.5.2.2.3.5.2) 109 TVA should demonstrate to the NRC staff acceptable data storm testing of the Common Q PAMS.  (Section 7.5.2.2.3.7.1.8) 110 TVA should provide information to the NRC staff describing how the WBN Unit 2 Common Q PAMS design supports periodic testing of the RVLIS function. (Section 7.5.2.2.3.9.2.6) 111 TVA should provide the technical specifications for the Common Q PAMS to the NRC staff for review.  (Section 7.5.2.2.3.11)}}
Page 23 of 23    SSER Item No. SSER Item Description TVA Status NRC Status provide justification for not conforming.  (Section 7.5.2.2.3)104 The NRC staff will review the WEC self assessment to verify that it the WBN Unit 2 PAMS is compliant to the V&V requirements in the SPM or that deviations from the requirements are adequately justified.  (Section 7.5.2.2.3.4.2) 105 TVA should produce an acceptable description of how the WBN Unit 2 Common Q PAMS SysRS and SRS implement the design basis requirements of IEEE Std. 603-1991 Clause 4.  (Section 7.5.2.2.3.4.3.1) 106 TVA should produce a final WBN Unit 2 Common Q PAMS SRS that is independently reviewed.  (Section 7.5.2.2.3.4.3.1) 107 TVA should provide to the NRC staff documentation to confirm that the final WBN Unit 2 Common Q PAMS SDDs that are independently reviewed.  (Section 7.5.2.2.3.4.3.2) 108 TVA should demonstrate to the NRC staff that there are no synergistic effects between temperature and humidity for the Common Q PAMS equipment.  (Section 7.5.2.2.3.5.2) 109 TVA should demonstrate to the NRC staff acceptable data storm testing of the Common Q PAMS.  (Section 7.5.2.2.3.7.1.8) 110 TVA should provide information to the NRC staff describing how the WBN Unit 2 Common Q PAMS design supports periodic testing of the RVLIS function. (Section 7.5.2.2.3.9.2.6) 111 TVA should provide the technical specifications for the Common Q PAMS to the NRC staff for review.  (Section 7.5.2.2.3.11)}}

Revision as of 13:25, 30 April 2019

2011/06/17 Watts Bar 2 OL - FW: NRC PM Open Items List 6-20-11.docx
ML11187A335
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 06/17/2011
From:
- No Known Affiliation
To:
Division of Operating Reactor Licensing
References
Download: ML11187A335 (25)


Text

1 WBN2Public Resource From: Boyd, Desiree L [dlboyd@tva.gov]

Sent: Friday, June 17, 2011 9:28 AM To: Poole, Justin; Milano, Patrick; Campbell, Stephen Cc: Arent, Gordon; Smith, James D; Br yan, Robert H Jr; Smith, James D

Subject:

FW: NRC PM Open Items List 6-20-11.docx Attachments:

NRC PM Open Items List 6-20-11.docx Fornextphonecall.

~*~*~*~*~*~*~*~*~*~*~*~ Désireé L. Boyd WBN2LicensingSupportSunTechnicalServices dlboyd@tva.gov

4233658764 Hearing Identifier: Watts_Bar_2_Operating_LA_Public Email Number: 422 Mail Envelope Properties (7AB41F650F76BD44B5BCAB7C0CCABFAF1FFA529F)

Subject:

FW: NRC PM Open Items List 6-20-11.docx Sent Date: 6/17/2011 9:28:19 AM Received Date: 6/17/2011 9:28:54 AM From: Boyd, Desiree L Created By: dlboyd@tva.gov Recipients: "Arent, Gordon" <garent@tva.gov>

Tracking Status: None "Smith, James D" <jdsmith@tva.gov>

Tracking Status: None "Bryan, Robert H Jr" <rhbryan@tva.gov> Tracking Status: None "Smith, James D" <smith1jd@westinghouse.com> Tracking Status: None "Poole, Justin" <Justin.Poole@nrc.gov>

Tracking Status: None "Milano, Patrick" <Patrick.Milano@nrc.gov> Tracking Status: None "Campbell, Stephen" <Stephen.Campbell@nrc.gov> Tracking Status: None

Post Office: TVANUCXVS2.main.tva.gov Files Size Date & Time MESSAGE 243 6/17/2011 9:28:54 AM NRC PM Open Items List 6-20-11.docx 59824

Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: Recipients Received:

Page 1 of 23 NRC PM Open Items List 6/20/11 (423) 751-6338 ID 657601 No. Description Status Additional Comments Resp Org/Person 1. Cyber Security Plan/Controls and Implementation Plan for Common Systems 6/8/11A Identify Required Exemptions 6/8/11A Provide forecast for Inspection Readiness 6/8/11A

NRC TI issued TBD NRC Table Top/Pilot

Oct 2011 Procedures complete 9/30/11

Inspection Dec 2011 NRC Inspection in 2011 Provide detail for systems (unit specific and common) which will be complete and which will not be complete for Unit 2 fuel load.

Heinrich/Snyder (Bryan)

Page 2 of 23 No. Description Status Additional Comments Resp Org/Person 2. Instrumentation RAI List (Knuettel)

Ongoing 6/22/11 RAI Responses Provide response to Q377 and Q375, item 9 Eng/Hilmes (Smith) 3. Resolve Licensing Basis Preservation Self Assessment PERs (Crouch) 6/17/11A TVA to provide QA audit results. Audit is complete. Will docket the audit. Eng/Freeman (Smith) 4. Status of GSI 199 Eastern Seismicity (Crouch) Fall 2011 No action pending upcoming Generic Letter TVA/NRR 5. Complete Implementation (Hemmer)

Diesel 8/1/11 Pump Relocation 10/1/11 Procedures Issued 6/30/11 Inspection - November 2011 Phase I commitments 8/1/11 Diesel is onsite, need support equipment Additional clarification to phase I actions will be needed. Fleet wide issue. Hemmer (Smith) 6. Provide feedback on the status of NRC review of Integrated Safeguards Test submittal SSER 23 NRC to provide status of review in SSER 23 NRR Page 3 of 23 No. Description Status Additional Comments Resp Org/Person 7. Document Control Issues for two letters 6/15/11 7/15, 10/5, 10/21 and 10/29 letters. NRC to reprint 7/15 letter and provide to NRC Document control.

TVA/Bechtel to provide non-proprietary version of documents that can be released to the public. TVA to provide revised letter that says non-prop once prop documents removed. NRC action to contact Kenny Nguyen, NRC Document Control regarding A102. Additional copy of A102 provided to NRC on 6/7/11. Licensing/Boyd 8. Chapter 15.5 RAIs TBD Additional question regarding meteorology data from 2008-2009. Calc revisions required. TVA formulating plan/schedule. Small increases in doses expected except control room which will decrease. NRC is targeting SSER 24 (early August) to contain this updated information. NRC to perform confirmatory runs in parallel. Will provide data by 6/27/11. Wastrack (Bryan) 9. Fire Protection Report Questions regarding OMA TBD 6/21/11 TBD 6/30/11 TBD Justifications - date will be determined by 6/17/11.

Set 5 RAIs Clarification to 5/26/11 ltr Qs VII-2, VIII-13,14 and 6/7/11 ltr Qs II-43, VIII telecom week of 6/13/11 Technical Meeting - pipe corrosion Group 6 RAIs to come shortly.

ENG/Hilmes (Crouch) 10. IST Tech Spec Change 6/17/11 Schedule by 6/17/11. Pre-submittal meeting being arranged.

TVA Corporate Licensing (Shea) 11. Tech Spec Revisions from latest T/S markup and NRC Review comments 6/20/11 TBD June, 2011 June, 2011 Submittal to address NRC review comments CSST A & B I-131 DEI Diesel Generator Frequency Licensing/Elton (Bryan)

Page 4 of 23 No. Description Status Additional Comments Resp Org/Person 12. ASME III to XI transition Need NRC Letter When does ISI program begin with partial plant N-3?

Are repairs/mods after N-5 controlled under Section III or Section XI? The timing for the NIS-2 in the letter does not comply with the ASME Code . The NIS-2 must be before commercial operation.

Review Code Cases 801/802 vs TVA letter for conflicts. Review complete - no impact. Eng/Helms (Crouch) 13. Chapter 11/FSEIS RAIs 6/20/11 7/29/11 complete NRC Computer Code Input Request Cost Benefit Analyses - need to improve date NRC to provide additional RAIs Chem/Woods (Bryan) 14. Letter to notify NRC when Vital Area

Boundary returned to original location 11/1/11 Security Plan Update - Boundary to be restored by 9/30/11 Lic/Crouch 15. Part 70 License EA - 6/13/11A FL - 6/15/11 NRC to issue Part 70 license. Fuel receipt is 6/20/11.

Milano 16. ACRS Topics 7/12/11 Improvements, Inspection status, Refurb status, Construction Status, Japan, IST Re-Presentation, Cyber Security, Ch 7 digital upgrades. Agenda has been finalized.

17. SAMDA RAIs 6/17/11A 5 questions regarding 2nd submittal 18. SSER 22/23 Open Items Response 7/15/11 7/15 is the target date for the next SSER update. The expanded HH list and it's status is provided at the end of this letter.
19. Chapter 12 RAI on Instrument Channel Operability Tests 6/24/11 ENG/Hilmes 20. Transient Analysis issues Additional Follow up Audit 6/28-30/11 &

7/1/11 until noon, if necessary 6/13/11A TVA/WEC confirming availability of personnel. Final audit plan to come.

NRC to provide audit questions ENG/Koontz WEC/Morgan 21. FSAR A105 7/29/11 Lic/Stockton Page 5 of 23 No. Description Status Additional Comments Resp Org/Person 22. IEB 88-02 SG Tube Cracking 6/13-17/11 NRC to setup telecon What are the SG inspection plans in light of the experience with a French reactor exhibiting SG tube cracking early? Is TVA planning to change the inspection plan due to this operating experience?

Corp SG/ Webber ISI/Tinley 23. Develop list of planned License Conditions, Exemptions and Relief Requests (Crouch) 9/1/11 Review Unit 1 SER for exemptions. NRR/TVA (Bryan) 24. Submit final REP prior to fuel load (Spink) 10/1/11 Submit Final REP and EPIPs 180 days prior to OL.

EP/ Detchemendy (Bryan) 25. Issue two Unit Offsite Dose Calculation Manual (Beach) Review TS Chapter 5 programs also 9/1/11 Chemistry/

Woods (Bryan) 26. Copy of Site Plan for NSIR TBD No action until inspection scheduled. NRC to determine level of detail is needed.

Fire Ops/Sterchi 27. Issue Unit 2 Completion Letter (Crouch) 3/1/12 Licensing 28. Combined U1/U2 FSAR (Stockton) 3/1/12 Licensing 29. Submit final as-constructed FSAR figures 10/1/11 Licensing/ Stockton 30. Verify Tech Spec Setpoints match calcs 8/1/11 Eng/Hilmes (Bryan) 31. Letter to terminate Part 30/40 License after receipt of Part 50 License 4/1/12 Licensing (Crouch) 32. B 2011-01 60 day response Licensing (Gordon) 33. TMI action items Review list Licensing (Gordon)

Page 6 of 23 SSER Item No. SSER Item Description TVA Status NRC Status 1. Review evaluations and corrective actions associated with a power assisted cable pull. (NRC safety evaluation dated August 31, 2009, ADAMS Accession No. ML092151155)

For NRC Inspection /

Review 2. Conduct appropriate inspection activities to verify cable lengths used in calculations and analysis match as-installed configuration. (NRC safety evaluation dated August 31, 2009, ADAMS Accession No. ML092151155)

For NRC Inspection /

Review 3. Confirm TVA submitted update to FSAR section 8.3.1.4.1. (NRC safety evaluation dated August 31, 2009, ADAMS Accession

No. ML092151155)Response provided in TVA to NRC letter dated April 6, 2011. 4. Conduct appropriate inspection activities to verify that TVA's maximum SWBP criteria for signal level and coaxial cables do not exceed the cable manufacturers maximum SWBP

criteria. (NRC safety evaluation dated August 31, 2009, ADAMS Accession No.

ML092151155)

Closed by IR 2010604

5. Verify timely submittal of pre-startup core map and perform technical review. (TVA letter dated September 7, 2007, ADAMS

Accession No. ML072570676)Response provided in TVA to NRC letter dated April 6, 2011. 6. Verify implementation of TSTF-449. (TVA letter dated September 7, 2007, ADAMS

Accession No. ML072570676)Response provided in TVA to NRC letter dated April 6, 2011. 7. Verify commitment completion and review electrical design calculations. (TVA letter

dated October 9, 1990, ADAMS Accession

No. ML073551056)

For NRC Inspection /

Review 8. Verify rod control system operability during Response provided in TVA Page 7 of 23 SSER Item No. SSER Item Description TVA Status NRC Status power ascension. TVA should provide a pre-startup map to the NRC staff indicating the rodded fuel assemblies and a projected end of cycle burnup of each rodded assembly for the initial fuel cycle 6-months prior to fuel load. (NRC safety evaluation dated May 3, 2010, ADAMS Accession No. ML101200035)to NRC letter dated April 6, 2011. 9. Confirm that education and experience of management and principal supervisory

positions down through the shift supervisory level conform to Regulatory Guide 1.8.

(Section 13.1.3)

For NRC Inspection /

Review 10. Confirm that TVA has an adequate number of licensed and non-licensed operators in the

training pipeline to s upport the preoperational test program, fuel loading, and dual unit operation. (Section 13.1.3)TVA to answer later.

11. The plant administrative procedures should clearly state that, w hen the Assistant Shift Engineer assumes his duties as Fire Brigade Leader, his control room duties are temporarily assumed by the Shift Supervisor (Shift Engineer), or by another SRO, if one is available. The plant administrative procedures should clearly describe this transfer of control room duties. (Section

13.1.3) For NRC Inspection /

Review 12. TVA's implementation of NGDC PP-20 and EDCR Appendix J is subject to future NRC

audit and inspection. (Section 25.9)

For NRC Inspection /

Review 13. TVA is expected to submit an IST program and specific relief requests for WBN Unit 2 TVA to answer later.

Page 8 of 23 SSER Item No. SSER Item Description TVA Status NRC Status nine months before the projected date of OL

issuance. (Section 3.9.6)

14. TVA stated that the Unit 2 PTLR is included in the Unit 2 System Description for the Reactor Coolant System (WBN2-68-4001),

which will be revised to reflect required

revisions to the PTLR by September 17, 2010. (Section 5.3.1)Response provided in TVA to NRC letter dated April 6, 2011. 15. TVA should confirm to the NRC staff the completion of Primary Stress Corrosion Cracking (PWSCC) mitigation activities on the Alloy 600 dissimilar metal butt welds (DMBWs) in the primary loop piping. (Section

3.6.3) Response provided in TVA to NRC letter dated April 6, 2011. 16. Based on the uniqueness of EQ, the NRC staff must perform a detailed inspection and evaluation prior to fuel load to determine how the WBN Unit 2 EQ program complies with

the requirements of 10 CFR 50.49. (Section

3.11.2) For NRC Inspection /

Review 17. The NRC staff should verify the accuracy of the WBN Unit 2 EQ list prior to fuel load. (Section 3.11.2.1)

For NRC Inspection /

Review 18. Based on the extensive layup period of equipment within WBN Un it 2, the NRC staff must review, prior to fuel load, the assumptions used by TVA to re-establish a

baseline for the qualified life of equipment.

The purpose of the staff's review is to ensure

that TVA has addressed the effects of

environmental conditions on equipment during the layup period.

(Section 3.11.2.2)Response provided in TVA to NRC letter dated April 6, 2011.

Page 9 of 23 SSER Item No. SSER Item Description TVA Status NRC Status 19. The NRC staff should complete its review of TVA's EQ Program procedures for WBN Unit

2 prior to fuel load. (Section 3.11.2.2.1)

For NRC Inspection /

Review 20. Resolve whether or not routine maintenance activities should result in increasing the EQ of the 6.9 kV motors to Category I status in accordance with 10 CFR 50.49. (Section

3.11.2.2.1).

Response provided in TVA to NRC letter dated April 6, 2011. 21. The NRC staff should confirm that the Electrical Penetration Assemblies (EPAs) are installed in the tested configuration, and that the feedthrough module is manufactured by the same company and is consistent with the

EQ test report fo r the EPA. (Section 3.11.2.2.1)

For NRC Inspection /

Review 22. TVA must clarify its use of the term "equivalent" (e.g., identical, similar) regarding the replacement terminal blocks to the NRC

staff. If the blocks are similar, then a similarity analysis should be completed and

presented to the NRC for review. (Section

3.11.2.2.1)

Response provided in TVA to NRC letter dated April 6, 2011. 23. Resolve whether or not TVA's reasoning for not upgrading the MSIV solenoid valves to

Category I is a sound reason to the contrary, as specified in 10 CFR 50.49(l). (Section

3.11.2.2.1)

Response provided in TVA to NRC letter dated April 6, 2011. 24. The NRC staff requires supporting documentation from TVA to justify its establishment of a mild environment

threshold for total integrated dose of less

than 1x10 3 rads for electronic components Response provided in TVA to NRC letter dated April 6, 2011.

Page 10 of 23 SSER Item No. SSER Item Description TVA Status NRC Status such as semiconductors or electronic components containing organic material.

(Section 3.11.2.2.1)

25. Prior to the issuance of an operating license, TVA is required to provide satisfactory documentation that it has obtained the maximum secondary liability insurance

coverage pursuant to 10 CFR 140.11(a)(4),

and not less than the amount required by 10

CFR 50.54(w) with respect to property

insurance, and the NR C staff has reviewed and approved the documentation. (Section

22.3) TVA to answer later.

26. For the scenario with an accident in one unit and concurrent shutdown of the second unit

without offsite power, T VA stated that Unit 2 pre-operational testing will validate the diesel response to sequencing of loads on the Unit 2 emergency diesel generators (EDGs). The NRC staff will evaluate the status of this issue and will update the status of the EDG load response in a future SSER. (Section

8.1) Response provided in TVA to NRC letter dated April 6, 2011. 27. TVA should provide a summary of margin studies based on scenarios described in Section 8.1 for CSSTs A, B, C, and D.

(Section 8.2.2)

Response provided in TVA to NRC letter dated April 6, 2011. 28. TVA should provide to the NRC staff a detailed discussion sho wing that the load tap changer is able to maintain the 6.9 kV bus

voltage control band given the normal and post-contingency transmission operating Response provided in TVA to NRC letter dated April 6, 2011.

Page 11 of 23 SSER Item No. SSER Item Description TVA Status NRC Status voltage band, bounding voltage drop on the grid, and plant conditions. (Section 8.2.2)

29. TVA should provide the transmission system specifics (grid stability analyses) to the NRC staff. In order to verify compliance with GDC 17, the results of the grid stability analyses must indicate that loss of the largest electric

supply to the grid, loss of the largest load from the grid, loss of the most critical transmission line, or loss of both units themselves, will not cause grid instability.

(Section 8.2.2)

Response provided in TVA to NRC letter dated June 7, 2011. 30. TVA should confirm that all other safety-related equipment (in addition to the Class 1E motors) will have adequate starting and running voltage at the most limiting safety

related components (such as motor operated

valves, contactors, solenoid valves or relays)

at the degraded voltage relay setpoint dropout setting. TVA should also confirm that the final Technica l Specifications are properly derived from these analytical values

for the degraded voltage settings. (Section

8.3.1.2) TVA to answer later.

31. TVA should evaluate the re-sequencing of loads, with time delays involved, in the scenario of a LOCA followed by a delayed

LOOP, and ensure that all loads will be sequenced within the time assumed in the

accident analysis. (Section 8.3.1.11)Response provided in TVA to NRC letter dated April 6, 2011. 32. TVA should provide to the NRC staff the details of the administrative limits of EDG TVA to answer later.

Page 12 of 23 SSER Item No. SSER Item Description TVA Status NRC Status voltage and speed range, and the basis for

its conclusion that the impact is negligible, and describe how it accounts for the administrative limits in the Technical Specification surveillance requirements for EDG voltage and frequency. (Section

8.3.1.14) 33. TVA stated in Attachment 9 of its letter dated July 31, 2010, that certain design change

notices (DCNs) are r equired or anticipated for completion of WBN Unit 2, and that these DCNs were unverified assumptions used in its analysis of the 125 V dc vital battery system. Verification of completion of these

DCNs to the NRC staff is necessary prior to issuance of the operating license. (Section

8.3.2.3) Response provided in TVA to NRC letter dated April 6, 2011. 34. TVA stated that the method of compliance with Phase I guidelines would be substantially similar to the current Unit 1 program and that a ne w Section 3.12 will be added to the Unit 2 FSAR that will be

materially equivalent to Section 3.12 of the current Unit 1 FSAR. (Section 9.1.4)Response provided in TVA to NRC letter dated April 6, 2011. 35. TVA should provide information to the NRC staff that the CCS will produce feedwater purity in accordance with BTP MTEB 5-3 or, alternatively, provide justification for producing feedwater purity to another acceptable standard. (Section 10.4.6)Response provided in TVA to NRC letter dated June 7, 2011. 36. TVA should provide information to the NRC staff to enable verification that the SGBS Response provided in TVA to NRC letter dated April 6, Page 13 of 23 SSER Item No. SSER Item Description TVA Status NRC Status meets the requirements and guidance

specified in the SER or provide justification that the SGBS meets other standards that demonstrate conformance to GDC 1 and GDC 14. (Section 10.4.8) 2011. 37. The NRC staff will review the combined WBN Unit 1 and 2 Appendix C prior to issuance of

the Unit 2 OL to confirm (1) that the proposed Unit 2 changes were incorporated into Appendix C, and (2) that changes made to

Appendix C for Unit 1 since Revision 92 and the changes made to the NP-REP since Revision 92 do not affect the bases of the staff's findings in this SER supplement.

(Section 13.3.2)

TVA to answer later.

38. The NRC staff will confirm the availability and operability of the ERDS for Unit 2 prior to issuance of the Unit 2 OL. (Section 13.3.2.6)

For NRC Inspection /

Review 39. The NRC staff will confirm the adequacy of the communications capability to support

dual unit operations prior to issuance of the

Unit 2 OL. (Section 13.3.2.6)

For NRC Inspection /

Review 40. The NRC staff will confirm the adequacy of the emergency facilities and equipment to support dual unit operations prior to issuance

of the Unit 2 OL. (Section 13.3.2.8)

For NRC Inspection /

Review 41. TVA committed to (1) update plant data displays as necessary to include Unit 2, and (2) to update dose assessment models to

provide capabilities for assessing releases from both WBN units. The NRC staff will confirm the adequacy of these items prior to For NRC Inspection /

Review Page 14 of 23 SSER Item No. SSER Item Description TVA Status NRC Status issuance of the Unit 2 OL. (Section 13.3.2.9)

42. The NRC staff will confirm the adequacy of the accident assessment capabilities to support dual unit operations prior to issuance

of the Unit 2 OL. (Section 13.3.2.9)

For NRC Inspection /

Review 43.Section V of Appendix E to 10 CFR Part 50 requires TVA to submit its detailed implementing procedures for its emergency plan no less than 180 days before the

scheduled issuance of an operating license. Completion of this requirement will be confirmed by the NRC staff prior to the issuance of an operating license. (Section

13.3.2.18)

TVA to answer later.

44. TVA should provide additional information to clarify how the initial and irradiated RT NDT was determined. (Section 5.3.1)Response provided in TVA to NRC letter dated April 6, 2011. 45. TVA stated in its res ponse to RAI 5.3.2-2, dated July 31, 2010, that the PTLR would be

revised to incorpor ate the COMS arming temperature. (Section 5.3.2)Response provided in TVA to NRC letter dated April 6, 2011. 46. The LTOP lift settings were not included in the PTLR, but were provided in TVA's

response to RAI 5.3.2-2 in its letter dated

July 31, 2010. TVA stated in its RAI

response that the PTLR would be revised to incorporate the LTOP lift settings into the

PTLR. (Section 5.3.2)Response provided in TVA to NRC letter dated April 6, 2011. 47. The NRC staff noted that TVA's changes to Section 6.2.6 in FSAR Amendment 97, regarding the implementation of Option B of Appendix J, were incomplete, because Response provided in TVA to NRC letter dated June 7, 2011.

Page 15 of 23 SSER Item No. SSER Item Description TVA Status NRC Status several statements remained regarding performing water-sealed valve leakage tests "as specified in 10 CFR [Part] 50, Appendix

J." With the adopti on of Option B, the specified testing requirements are no longer applicable; Option A to Appendix J retains these requirements. The NRC discussed this discrepancy with TVA in a telephone

conference on September 28, 2010. TVA

stated that it would re move the inaccurate reference to Appendix J for specific water testing requirements in a future FSAR amendment. (Section 6.2.6)

48. The NRC staff should verify that its conclusions in the review of FSAR Section

15.4.1 do not affect the conclusions of the

staff regarding the acc eptability of Section 6.5.3. (Section 6.5.3)Response provided in TVA to NRC letter dated June 7, 2011. 49. The NRC staff was unable to determine how TVA linked the traini ng qualification requirements of ANSI N45.2-1971 to TVA

Procedure TI-119.

Therefore, the implementation of training and qualification

for inspectors will be the subject of future NRC staff inspections. (NRC letter dated July 2, 2010, ADAMS Accession No.

ML101720050)

For NRC Inspection /

Review 50. TVA stated that about 5 percent of the anchor bolts for safety-related pipe supports

do not have quality cont rol documentation, because the pull tests have not yet been performed. Since the documentation is still For NRC Inspection /

Review Page 16 of 23 SSER Item No. SSER Item Description TVA Status NRC Status under development, the NRC staff will conduct inspections to follow-up on the

adequate implementation of this construction refurbishment program requirement. (NRC letter dated July 2, 2010, ADAMS Accession No. ML101720050)

51. The implementation of TVA Procedure TI-119 will be the subjec t of NRC follow-up inspection to determine if the construction refurbishment program requirements are being adequately implemented. (NRC letter dated July 2, 2010, ADAMS Accession No.

ML101720050)

For NRC Inspection /

Review 52[A] TVA should provide an update to the FSAR replacing Table 12.2-3 with the expected source strength values of the fr eshly irradiated IITAs. (Section 12.3) Response provided in TVA to NRC letter dated June 7, 2011. 53 TVA should provide an update to the FSAR reflecting the information provided in its letter dated October 4, 2010, regarding the WBN radiation protection design features, including controlled access areas, decontamination areas, and onsite laboratories and counting rooms. (Section 12.4) 54 TVA should provide adequate technical justification to the staff to relax the frequency of the radiation monitor channel quarterly operability tests. TVA should provide sufficient information to the staff to determine that the portable airborne radiation monitors comply with the requirements of 10 CFR 20.1501. TVA should provide sufficient information to the staff to determine that the licensing or TVA program requirements for the calibration and operability testing of area radiation monitors are sufficient to meet the regulatory requirements of 10 CFR 20.1501. (Section 12.4) 55 TVA should provide sufficient information to the staff to demonstrate that the two area radiation monitors for the Spent Fuel Pit comply with the requirements of 10 CFR

Page 17 of 23 SSER Item No. SSER Item Description TVA Status NRC Status 70.24 and 10 CFR 50.68 for radiation monitoring in areas where fuel is handled or stored. (Section 12.4) 56 TVA should update the FSAR to reflect the information regarding the dose assessment program provided in its letter the the NRC dated June 3, 2010. (Section 12.5) 57 TVA should update the FSAR to reflect the qualification standards of the RPM as provided in its letter to the NRC dated October 4, 2010. (Section 12.6) 58 The staff has insufficient information to conclude that TVA has taken appropriate actions to reduce radiation levels and increase the capability of operators to control and mitigate the consequences of an accident at WBN Unit 2, in accordance with the guidance of NUREG-0737, Item II.B.2, or can maintain occupational doses to plant operators within the requirements of GDC 19. Therefore, the staff cannot conclude that the plant shielding for WBN Unit 2 is acceptable. (Section 12.7.1) 59[B] The staff's evaluation of the compatibility of the ESF system materials with containment sprays and core cooling water in the event of a LOCA is

incomplete pending resolution of GSI-191 for

WBN Unit 2. (Section 6.1.1.4) Response provided in TVA to NRC letter dated June 7, 2011. 60[C] TVA should amend the FSAR description of the design and operation of the spent fuel pool

cooling and cleanup system in FSAR Section 9.1.3

as proposed in its December 21, 2010, letter to the NRC. (Section 9.1.3) Response provided in TVA to NRC letter dated June 7, 2011. 61[D] TVA should provide information to the NRC staff to demonstrate that PAD 4.0 can conservatively

calculate the fuel temperature and other impacted

variables, such as stored energy, given the lack of a fuel thermal conductivity degradation model.

(Section 4.2.2.1) Will result in a License Condition.

62[E] Confirm TVA's change to FSAR Section 10.4.9 to reflect its intention to operate with each CST Response provided in TVA to NRC letter dated June 7, Page 18 of 23 SSER Item No. SSER Item Description TVA Status NRC Status isolated from the other. (Section 10.4.9) 2011. 63[F] TVA should confirm to the NRC staff that testing prior to Unit 2 fuel load has demonstrated that two-way communications is impossible with the Eagle 21 communications interface. (Section

7.2.1.1) TVA to answer later.

64[G] TVA stated that, "Post modification testing will be performed to verify that the design change

corrects the Eagle 21, Ra ck 2 RTD accuracy issue prior to WBN Unit 2 fuel load. This issue is open

pending NRC review of the testing results.

For NRC Inspection /

Review 65[H] TVA should provide justi fication to the staff regarding why differen t revisions of WCAP-13869 are referenced in WBN Unit 1 and Unit 2.

(Section 7.2.1.1) Response provided in TVA to NRC letter dated June 7, 2011. 66[I] TVA should clarify FSAR Section 9.2.5 to add the capability of the UHS to bring the non accident

unit to cold shutdown within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. (SRP

Section 9.2.5)

TVA to answer later.

67[J] TVA should confirm, and the NRC staff should verify, that the component cooling booster pumps for Unit 2 are above PMF level. (Section 9.2.2)

For NRC Inspection /

Review 68[K] TVA should clarify to the NRC staff how the CSS complies with GDC 5. (Section 9.2.2) TVA to answer later.

69[L] The WBN Unit 2 RCS vent system is acceptable, pending verification that the RCS vent system is installed. (Section 5.4.5)

For NRC Inspection /

Review 70[M] TVA should provide the revised WBN Unit 2 PSI program ASME Class 1, 2, and 3 Supports "Summary Tables," to include numbers of

components so that the NRC staff can verify that

the numbers meet the reference ASME Code.

TVA to answer later.

Page 19 of 23 SSER Item No. SSER Item Description TVA Status NRC Status (Section 3.2.3 of Appendix Z of this SSER) 71[N] TVA should confirm to the staff the replacement of the current Unit 2 clevis insert bolts to the

latest design, which uses an X-750 alloy with an

HTH process, rolled threads, and a larger radius

on the undercut of the cap screw head. (Section

3.9.5) Response provided in TVA to NRC letter dated June 7, 2011. 72[O] Based on its review, the staff asked TVA several questions regarding the ICC instrumentation.

TVA responded to the staff questions by letter dated October 26, 2010 (ADAMS Accession No.

ML103020322). The NRC staff has not

completed the review of the additional

information provided by TVA. The staff will

provide its evaluation afte r completion of that review. (Section 4.4.8)

For NRC Inspection /

Review 73[P] The NRC staff will inspect to confirm that TVA has completed the WBN Unit 2 EOPs prior to fuel

load. (Section 7.5.3)

For NRC Inspection /

Review 74[Q] The NRC staff will verify installation of the acoustic-monitoring system for the power-operated relief valve (PORV) position indication in WBN Unit 2 before fuel load. (Section 7.8.1)

For NRC Inspection /

Review 75[R] The NRC staff will verify that the test procedures and qualification testing for auxiliary feedwater

initiation and control and flow indication are

completed in WBN Unit 2 before fuel load.

(Section 7.8.2)

For NRC Inspection /

Review 76[S] The NRC staff will verify that the derivative time constant is set to zero in WBN Unit 2 before fuel

load. (Section 7.8.3)

For NRC Inspection /

Review 77 It is unclear to the NRC staff which software V&V documents are applicable to the HRCAR monitors. TVA

Page 20 of 23 SSER Item No. SSER Item Description TVA Status NRC Status should clarify which software V&V documents are applicable, in order for the staff to complete its evaluation. (Section 7.5.2.3) 78 TVA intends to issue a revised calculation reflecting that the TID in the control room is less than 10 3 rads, which will be evaluated by the NRC staff. (Section 7.5.2.3) 79 TVA should perform a radiated susceptibility survey, after the installation of the hardware but prior to the RM-1000 being placed in service, to establish the need for exclusion distance for the HRCAR monitors while using handheld portable devices (e.g., walkie-talkie) in the control room, as documented in Attachment 23 to TVA's letter dated February 25, 2011, and item number 355 of TVA's letter dated April 15, 2011. (Section 7.5.2.3) 80 TVA should provide clarification to the staff on how TVA Standard Specification SS-E18-14.1 meets the guidance of RG 1.180, and should address any deviations from the guidance of the RG. (Section 7.5.2.3) 81 The extent to which TVA's supplier, General Atomics (GA), complies with EPRI TR-106439 and the methods that GA used for its commercial dedication process should be provided by TVA to the NRC staff for review. (Section 7.5.2.3) 82 The staff concluded that the information provided by TVA pertaining to the in-containment LPMS equipment qualification for vibration was incomplete. TVA should provide (item number 362 of ADAMS Accession No.

ML111050009), documentation that demonstrates the LPMS in-containment equipment has been qualified to remain functional in its normal operating vibration environment, per RG 1.133, Revision 1. (Section 7.6.1) 83 TVA should confirm to the NRC staff the completion of the data storm test on the DCS. (Section 7.7.1.4) 84 TVA should provide additional information for the NRC staff to complete its review of post-LOCA long term cooling boric acid precipitation. (Section 15.3.1) 85 The 95/95 peak local oxidation was calculated to be 1.04 percent, while core-wide oxidation was calculated to be much less than 0.1 percent. TVA should provide to the

Page 21 of 23 SSER Item No. SSER Item Description TVA Status NRC Status NRC staff the value of the decay heat multiplier used for this limiting large break, in order for the staff to complete its evaluation. (Section 15.3.1) 86 TVA should demonstrate to the staff, in the WCOBRA/TRAC analysis of the limiting break, that the core remains covered with a two-phase mixture and can be cooled for an indefinite period of time. (Section 15.3.1) 87 In order for the staff to complete its evaluation, TVA should provide (1) a time step sensitivity study for the limiting break displaying downcomer boiling, (2) a list of ten key parameter plots for the worst case downcomer boiling transien t, (3) values for the lateral k-factors used in the evaluation, and (4) the manner in which condensation was modeled in the downcomer. (Section 15.3.1) 88 It is also unclear to the staff that the entrainment correlation information has been incorporated into the EOP, to ensure that operators do not initiate hot and cold side injection during the period of time that entrainment could preclude injection into the hot legs. TVA should provide the EOP guidance/instructions for the operators to the staff for review. (Section 15.3.1) 89 TVA should demonstrate, quantitatively, the applicability of the generic analysis to WBN Unit 2, to demonstrate that the EOP instructions to the operators can effectively deal with the failure of a bottom mounted instrument tube in the lower head. (Section 15.3.1) 90 Verify that the ERCW pumps meet GDC 5 requirements for two unit operation. (Section 9.2.1) 91 TVA should update the FSAR with information describing how WBN Unit 2 meets GDC 5, assuming the worst case single failure and a LOOP, as provided in TVA's letter dated April 13, 2011. (Section 9.2.1) 92 The NRC staff should perform an inspection in accordance with NRC Temporary Instruction 2515/087, "Inspection of Licensee's Implementation of Multi-Plant Action A-17:

Instrumentation for Nuclear Power Plants to Assess Plant and Environs Conditions During and Following an Accident (Regulatory Guide 1.97)." (Section 7.5.2.1.4) 93 TVA should confirm to the staff that testing of the Eagle 21

Page 22 of 23 SSER Item No. SSER Item Description TVA Status NRC Status system has sufficiently demonstrated that two-way communication to the ICS is precluded with the described configurations. (Section 7.9.3.2) 94 TVA should provide to the staff either information that demonstrates that the WBN Unit 2 Common Q PAMS meets the applicable requirements in IEEE Std. 603-1991, or justification for why the Common Q PAMS should not meet those requirements. (Section 7.5.2.2.3) 95 TVA should update FSAR Table 7.1-1, "Watts Bar Nuclear Plant NRC Regulatory Guide Conformance," to reference IEEE Std. 603-1991 for the WBN Unit 2 Common Q PAMS. (Section 7.5.2.2.3) 96 TVA should (1) update FSAR Table 7.1-1 to include RG 1.100, Revision 3, for the Common Q PAMS, or (2) demonstrate that the Common Q PAMS is in conformance with RG 1.100, Revision 1, or provide justification for not conforming. (Section 7.5.2.2.3) 97 TVA should demonstrate that the WBN Unit 2 Common Q PAMS is in conformance with RG 1.153, Revision 1, or provide justification for not conforming. (Section 7.5.2.2.3) 98 TVA should demonstrate that the WBN Unit 2 Common Q PAMS is in conformance with RG 1.152, Revision 2, or provide justification for not conforming. (Section 7.5.2.2.3) 99 TVA should update FSAR Table 7.1-1 to reference IEEE 7-4.3.2-2003 as being applicable to the WBN Unit 2 Common Q PAMS. (Section 7.5.2.2.3) 100 TVA should update FSAR Table 7.1-1 to reference RG 1.168, Revision 1; IEEE 1012-1998; and IEEE 1020-1997 as being applicable to the WBN Unit 2 Common Q PAMS.

(Section 7.5.2.2.3) 101 TVA should demonstrate that the WBN Unit 2 Common Q PAMS application software is in conformance with RG 1.168, Revision 1, or provide justification for not conforming. (Section 7.5.2.2.3) 102 TVA should update FSAR Table 7.1-1 to reference RG 1.209 and IEEE Std. 323-2003 as being applicable to the WBN Unit 2 Common Q PAMS. (Section 7.5.2.2.3) 103 TVA should demonstrate that the WBN Unit 2 Common Q PAMS conforms to RG 1.209 and IEEE Std. 323-2003, or

Page 23 of 23 SSER Item No. SSER Item Description TVA Status NRC Status provide justification for not conforming. (Section 7.5.2.2.3)104 The NRC staff will review the WEC self assessment to verify that it the WBN Unit 2 PAMS is compliant to the V&V requirements in the SPM or that deviations from the requirements are adequately justified. (Section 7.5.2.2.3.4.2) 105 TVA should produce an acceptable description of how the WBN Unit 2 Common Q PAMS SysRS and SRS implement the design basis requirements of IEEE Std. 603-1991 Clause 4. (Section 7.5.2.2.3.4.3.1) 106 TVA should produce a final WBN Unit 2 Common Q PAMS SRS that is independently reviewed. (Section 7.5.2.2.3.4.3.1) 107 TVA should provide to the NRC staff documentation to confirm that the final WBN Unit 2 Common Q PAMS SDDs that are independently reviewed. (Section 7.5.2.2.3.4.3.2) 108 TVA should demonstrate to the NRC staff that there are no synergistic effects between temperature and humidity for the Common Q PAMS equipment. (Section 7.5.2.2.3.5.2) 109 TVA should demonstrate to the NRC staff acceptable data storm testing of the Common Q PAMS. (Section 7.5.2.2.3.7.1.8) 110 TVA should provide information to the NRC staff describing how the WBN Unit 2 Common Q PAMS design supports periodic testing of the RVLIS function. (Section 7.5.2.2.3.9.2.6) 111 TVA should provide the technical specifications for the Common Q PAMS to the NRC staff for review. (Section 7.5.2.2.3.11)