NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.7.8, Essential Raw Cooling Water (ERCW) System
ML21306A245
Person / Time
Site: Watts Bar  Tennessee Valley Authority icon.png
Issue date: 11/02/2021
From: Kimberly Green
NRC/NRR/DORL/LPL2-2
To: Wells R
Tennessee Valley Authority
References
L-2021-LLA-0174
Download: ML21306A245 (3)


Text

From: Green, Kimberly Sent: Tuesday, November 2, 2021 11:53 AM To: Wells, Russell Douglas

Subject:

Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.7.8, "Essential Raw Cooling Water (ERCW) System" (EPID L-2021-LLA-0174)

Dear Mr. Wells:

By letter dated September 29, 2021 (Agencywide Documents Access and Management System Accession No. ML21273A046), the Tennessee Valley Authority (TVA) submitted a license amendment request (LAR) for the Watts Bar Nuclear Plant (Watts Bar), Units 1 and 2. The proposed amendments would revise Watts Bar, Unit 1 and 2, Technical Specification (TS) 3.7.8, Essential Raw Cooling Water (ERCW) System, by adding a new Condition A to Watts Bar, Unit 1, TS 3.7.8 to extend the allowed Completion Time to restore one ERCW system train to operable status from 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to 7 days, to support maintenance on the Watts Bar, Unit 2, 6.9 kV shutdown boards. The proposed amendments would also revise the bounding temperature for the ultimate heat sink in Condition A to less than or equal to 78 degrees Fahrenheit.

Additionally, the proposed amendments would: add and/or revise a Note for Condition A to specify when the Condition applies; renumber existing Conditions A and B as Conditions B and C and revise the wording accordingly for Unit 1; and revise the wording for Condition C for Unit 2 to reflect that Condition C applies to both Required Actions A.1 and A.2.

The purpose of this email is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of the proposed LAR. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations, an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. The NRC staff has reviewed TVAs LAR and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendments in terms of regulatory requirements and the protection of public health and safety and the environment.

Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

Based on the information provided in TVAs submittal, the NRC staff has estimated that this licensing request will take approximately 235 hours0.00272 days <br />0.0653 hours <br />3.885582e-4 weeks <br />8.94175e-5 months <br /> to complete and that the review can be completed by November 1, 2022. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates will be communicated, during the routine interactions. These estimates are based on the staffs initial

review of the application and they could change, due to several factors including requests for additional information and unanticipated addition of scope to the review.

If you have any questions, please contact me at (301) 415-1627.

Sincerely, Kimberly J. Green, Senior Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

Hearing Identifier: NRR_DRMA Email Number: 1403 Mail Envelope Properties (BLAPR09MB6979261C70CACBCCD4EFCACF8F8B9)

Subject:

Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.7.8, "Essential Raw Cooling Water (ERCW)

System" (EPID L-2021-LLA-0174)

Sent Date: 11/2/2021 11:53:14 AM Received Date: 11/2/2021 11:53:00 AM From: Green, Kimberly Created By: Kimberly.Green@nrc.gov Recipients:

"Wells, Russell Douglas" <rdwells0@tva.gov>

Tracking Status: None Post Office: BLAPR09MB6979.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 3718 11/2/2021 11:53:00 AM Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: