NRR E-mail Capture - Acceptance Review Results for Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Adopt TSTF-577
ML22123A181
Person / Time
Site: Watts Bar, Sequoyah  Tennessee Valley Authority icon.png
Issue date: 05/03/2022
From: Kimberly Green
Plant Licensing Branch II
To: Wells R
Tennessee Valley Authority
References
Download: ML22123A181 (3)


Text

From: Green, Kimberly Sent: Tuesday, May 3, 2022 11:09 AM To: Wells, Russell Douglas

Subject:

Acceptance Review Results for Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Adopt TSTF-577

Dear Mr. Wells:

By letter dated April 4, 2022 (Agencywide Documents Access and Management System Accession No. ML22095A023), the Tennessee Valley Authority (TVA) submitted a license amendment request (LAR) for the Sequoyah Nuclear Plant, Units 1 and 2, and the Watts Bar Nuclear Plant, Units 1 and 2. The proposed amendments would revise the Technical Specifications (TS) by adopting Technical Specification Task Force (TSTF) Traveler TSTF-577, Revised Frequencies for Steam Generator Tube Inspections.

The purpose of this email is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this LAR. The acceptance review was performed to determine whether the scope and depth of the technical information was sufficient to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of applications regarding the technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.

The NRC staff has reviewed TVAs LAR and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendments in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

Based on the information provided in TVAs submittal, the NRC staff has estimated that this licensing request will take approximately 100 hours0.00116 days <br />0.0278 hours <br />1.653439e-4 weeks <br />3.805e-5 months <br /> to complete and that the review can be completed by November 3, 2022, in accordance with the Consolidated Line Item Improvement Process. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates will be communicated, during our routine interactions. These estimates are based on the staffs initial review of the application and they could change if requests for additional information are needed.

If you have any questions, please contact me at (301) 415-1627.

Sincerely, Kimberly J. Green, Senior Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

Hearing Identifier: NRR_DRMA Email Number: 1620 Mail Envelope Properties (DM6PR09MB5462FE228A0365D36834689B8FC09)

Subject:

Acceptance Review Results for Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Adopt TSTF-577 Sent Date: 5/3/2022 11:08:48 AM Received Date: 5/3/2022 11:08:00 AM From: Green, Kimberly Created By: Kimberly.Green@nrc.gov Recipients:

"Wells, Russell Douglas" <rdwells0@tva.gov>

Tracking Status: None Post Office: DM6PR09MB5462.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 3332 5/3/2022 11:08:00 AM Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: