Information Notice 1993-84, Determination of Westinghouse Reactor Coolant Pump Seal Failure: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 14: Line 14:
| page count = 16
| page count = 16
}}
}}
{{#Wiki_filter:UNITED STATESNUCLEAR'REGULATORY COMMISSIONOFFICE OF NUCLEAR REACTOR REGULATIONWASHINGTON, D.C. 20555October 20, 1993NRC INFORMATION NOTICE 93-84: DETERMINATION OF WESTINGHOUSE REACTOR COOLANTPUMP SEAL FAILURE
{{#Wiki_filter:UNITED STATES NUCLEAR'REGULATORY
 
COMMISSION
 
===OFFICE OF NUCLEAR REACTOR REGULATION===
WASHINGTON, D.C. 20555 October 20, 1993 NRC INFORMATION
 
NOTICE 93-84: DETERMINATION
 
OF WESTINGHOUSE
 
REACTOR COOLANT PUMP SEAL FAILURE


==Addressees==
==Addressees==
All holders of operating licenses or construction permits for pressurizedwater reactors (PWRs).PurDoseThe U.S. Nuclear Regulatory Commission (NRC) is'issuing this informationnotice to alert addressees to a potential problem that could result from theuse of Westinghouse-designed reactor coolant pump (RCP) shutdown proceduresfor pumps whose No. 1 seals have failed. It is expected that recipients willreview the information for applicability to their facilities and consideractions, as appropriate, to avoid similar problems. However, suggestionscontained in this information notice are not NRC requirements; therefore, nospecific action or written response is required.BackgroundWestinghouse supplied the Braidwood Station RCPs, incorporating a three-stageseal series arrangement to limit coolant flow up the pump shaft. The No. 1seal, the main seal of the pump, is a controlled-leakage, film riding faceseal. The No. 2 and No. 3 seals are rubbing face seals. During normaloperation, an injection flow of nominally 30.3 liters [8 gallons] per minuteenters the pump below the No. 1 seal (see Attachment 1). Here the flowsplits. A portion (approximately 18.9 liters [5 gallons] per minute) flowsdown through the thermal barrier heat exchanger and enters the reactor coolantsystem. In this manner, the primary coolant is prevented from entering theradial bearing and seal section of the pump unit. The remainder (11.4 liters[3 gallons] per minute) (controlled leakage) passes through the pump radialbearing and enters the No. 1 seal. Above the No. 1 seal, most of the flowleaves the pump through the No. 1 seal leakoff line and returns to thechemical and volume control system. Minor flow passes through the No. 2 sealand its leakoff line to the reactor coolant drain tank. A back flushinjection of 0.8 liters [0.21 gallons] per hour from a head tank flows intothe No. 3 seal between its "double dam" seal area. At this point, half of theflow passes through one side of the seal and out the No. 2 seal leakoff linewhile the remaining flow passes through the other side and out the No. 3 sealleakoff line. This arrangement ensures essentially zero leakage of reactorcoolant from the pump.9310140192 o W q 3.O3;Afe4% ;IivftC
All holders of operating
 
licenses or construction
 
permits for pressurized
 
water reactors (PWRs).PurDose The U.S. Nuclear Regulatory
 
Commission (NRC) is'issuing
 
this information
 
notice to alert addressees
 
to a potential
 
problem that could result from the use of Westinghouse-designed
 
reactor coolant pump (RCP) shutdown procedures
 
for pumps whose No. 1 seals have failed. It is expected that recipients
 
will review the information
 
for applicability
 
to their facilities
 
and consider actions, as appropriate, to avoid similar problems.
 
===However, suggestions===
contained
 
in this information
 
notice are not NRC requirements;  
therefore, no specific action or written response is required.Background
 
Westinghouse
 
supplied the Braidwood
 
Station RCPs, incorporating
 
a three-stage
 
seal series arrangement
 
to limit coolant flow up the pump shaft. The No. 1 seal, the main seal of the pump, is a controlled-leakage, film riding face seal. The No. 2 and No. 3 seals are rubbing face seals. During normal operation, an injection
 
flow of nominally
 
30.3 liters [8 gallons] per minute enters the pump below the No. 1 seal (see Attachment
 
1). Here the flow splits. A portion (approximately
 
18.9 liters [5 gallons] per minute) flows down through the thermal barrier heat exchanger
 
and enters the reactor coolant system. In this manner, the primary coolant is prevented
 
from entering the radial bearing and seal section of the pump unit. The remainder
 
(11.4 liters[3 gallons] per minute) (controlled
 
leakage) passes through the pump radial bearing and enters the No. 1 seal. Above the No. 1 seal, most of the flow leaves the pump through the No. 1 seal leakoff line and returns to the chemical and volume control system. Minor flow passes through the No. 2 seal and its leakoff line to the reactor coolant drain tank. A back flush injection
 
of 0.8 liters [0.21 gallons] per hour from a head tank flows into the No. 3 seal between its "double dam" seal area. At this point, half of the flow passes through one side of the seal and out the No. 2 seal leakoff line while the remaining
 
flow passes through the other side and out the No. 3 seal leakoff line. This arrangement
 
ensures essentially
 
zero leakage of reactor coolant from the pump.9310140192 o W q 3.O3;Afe4% ;IivftC
 
IN 93-84 Octoer 20, 1993 During normal operation, the No. 1 seal is subject to full reactor coolant system pressure.
 
When the injection
 
flow passes through the No. 1 seal, it produces a pressure drop of approximately
 
15.41 MPa [2235 psi]. The No. 2 seal has the capability
 
to withstand
 
full operating
 
pressure, and its major function is to act as a backup in case the No. 1 seal fails. If the No. 1 seal fails, leakage through the No. 2 seal increases.
 
The No. 2 seal high leak flow alarm actuates at 3.8 liters [1 gallon] per minute.Description
 
of Circumstances
 
In the middle of 1992, while developing
 
shutdown procedures
 
for the RCPs at the Braidwood


IN 93-84Octoer 20, 1993 During normal operation, the No. 1 seal is subject to full reactor coolantsystem pressure. When the injection flow passes through the No. 1 seal, itproduces a pressure drop of approximately 15.41 MPa [2235 psi]. The No. 2seal has the capability to withstand full operating pressure, and its majorfunction is to act as a backup in case the No. 1 seal fails. If the No. 1seal fails, leakage through the No. 2 seal increases. The No. 2 seal highleak flow alarm actuates at 3.8 liters [1 gallon] per minute.
Station, Commonwealth


==Description of Circumstances==
Edison Company (the licensee)  
In the middle of 1992, while developing shutdown procedures for the RCPs atthe Braidwood Station, Commonwealth Edison Company (the licensee) found thatits abnormal operating procedure contained inadequate instructions forresponding to a failure of the RCP No. 1 seal. On a high RCP No. 1 sealleakoff condition, the abnormal operating procedure directed the operatingpersonnel to check the condition of the No. 2 seal. If the No. 2 seal wasacting as the primary pressure boundary on the basis of leakage of at least3.8 liters [1 gallon] per minute from the No. 2 seal, the procedure requiredthat the RCP be shut down. If the condition of the No. 2 seal was normal, theprocedure required no further action and gave no further guidance.Discussions with Westinghouse indicated that the condition of the No. 2 sealmight not be a sufficient indication of the operability of the No. 1 seal.DiscussionThe inadequacies in the operating procedure stem from the limitations of theinstrumentation used to monitor the leakage. The relevant No. 1 sealinstrumentation limits maximum readings to 22.7 liters [6 gallons] per minute.Although the No. 2 seal high leak flow alarm was set at 3.8 liters [1 gallon]per minute, very high No. 1 seal leak rates, more than 113.6 liters(30 gallons] per minute, are needed for the No. 2 seal to reach this flowrate. Thus, the No. 1 seal could have substantial leakage (e.g., 22.7-113.6liters (6-30 gallons] per minute) even though the No. 2 seal high leak flowalarm was not actuated. In the mean time, the RCP seal system might beseverely damaged if loss of injection were to occur or the No. 1 seal leakrates were more than 30.3 liters [8 gallons] per minute. Therefore,monitoring for high No. 2 seal leakage is not a reliable method of determiningwhether the No. 1 seal has failed.After finding that the condition of the No. 2 seal might not indicate theoperability of the No. 1 seal, Westinghouse provided guidance for theBraidwood Station that significantly enhances operator ability to determine ifimmediate shutdown of an RCP is required or if a more orderly shutdown can beconducted. Westinghouse completed a safety evaluation and issued TechnicalBulletin, NSD-TB-93-01-RO, "Revised Procedures for RCP Shutdown with No. 1Seal Leakage Outside Operating Limits," dated March 30, 1993, to other PWRsthat might be affected. An excerpt from this document is attached to thisinformation notice (see Attachment 2).
found that its abnormal operating


IN 93-84October 14, 1993 This information notice requires no specific action or written response. Ifyou have any questions about the information in this notice, please contactone of the technical contacts listed below or the appropriate Office ofNuclear Reactor Regulation (NRR) project manager.Brian K. Grimes, DirectorDivision of Operating Reactor SupportOffice of Nuclear Reactor RegulationTechnical contacts: Steve DuPont, RIII(815) 458-2852Martin Farber, RIII(708) 790-5774Chu-Yu Liang, NRR(301) 504-2878Attachments:1. Simplified Braidwood Seal Water Injectionand Leakoff Flow Diagram2. Excerpt from Westinghouse TechnicalBulletin, NSD-TB-93-01-RO, "RevisedProcedures for RCP Shutdown with No. 1Seal Leakage Outside Operating Limits"3. List of Recently Issued NRC Information Notices
procedure


2=."I 'I'TO SEAL WATER HAT EXCHANGERCO IrRo.D myLEVEL IN STAOPIPETOREGENERATIWE1HEATEXCHANGERDR DRAIN IIMPgo 0 Zrtaq ct(D j xD Om 00 MS0 tI-'.II-h' LAl -NIN sAN ThERLARRHER HEAT EXCHANGERF"U.t,&IDwSIMPLIFIED BRAIDWOOD SEAL WATER INJECTION AND LEAKOFF FLOW DIAGRAM
contained


I>Attachment 2IN 93-84October 20 1993Page 1 of INuclearServicesDivisionWestinghouseTechnical BulletinAn advisory notice of a recent technical development pertining to th- irts.ation or operation of Wastghous&suppi*d NudrPlant equipment. Recipients shouSd evaluate the Information and recomnM aIRonl, and initite action wh-r aomopriabt.P.O. SOX 35, Pltttxzu PA 15oSubject REVISED PROCEDURES FOR ROP SHUTDOWN WITH NO.'.FAl I FAKA(LF OUTSIDE OPERATING UMITS.oNSD-TB- 93-01-ROSystem(s) REACTOR COOLANT SYSTEM Date 03r3/9PLant ALL WESTINGHOUSE REACTOR COOLANT PUMPS WITH lr SO(s) 125CONTROLLED LEAKAGE SEALS (See Aftacivelt B)References _- -- C , .nA~. cten Is Safety Related Yes 0 Page 1 Of 8h M L) rilv Vl..I Vr-ij' 1 Q %- W I E2o m e t adgqNo O1
inadequate
 
instructions
 
for responding
 
to a failure of the RCP No. 1 seal. On a high RCP No. 1 seal leakoff condition, the abnormal operating
 
procedure
 
directed the operating personnel
 
to check the condition
 
of the No. 2 seal. If the No. 2 seal was acting as the primary pressure boundary on the basis of leakage of at least 3.8 liters [1 gallon] per minute from the No. 2 seal, the procedure
 
required that the RCP be shut down. If the condition
 
of the No. 2 seal was normal, the procedure
 
required no further action and gave no further guidance.Discussions
 
with Westinghouse
 
indicated
 
that the condition
 
of the No. 2 seal might not be a sufficient
 
indication
 
of the operability
 
of the No. 1 seal.Discussion
 
The inadequacies
 
in the operating
 
procedure
 
stem from the limitations
 
of the instrumentation
 
used to monitor the leakage. The relevant No. 1 seal instrumentation
 
limits maximum readings to 22.7 liters [6 gallons] per minute.Although the No. 2 seal high leak flow alarm was set at 3.8 liters [1 gallon]per minute, very high No. 1 seal leak rates, more than 113.6 liters (30 gallons] per minute, are needed for the No. 2 seal to reach this flow rate. Thus, the No. 1 seal could have substantial
 
leakage (e.g., 22.7-113.6 liters (6-30 gallons] per minute) even though the No. 2 seal high leak flow alarm was not actuated.
 
In the mean time, the RCP seal system might be severely damaged if loss of injection
 
were to occur or the No. 1 seal leak rates were more than 30.3 liters [8 gallons] per minute. Therefore, monitoring
 
for high No. 2 seal leakage is not a reliable method of determining
 
whether the No. 1 seal has failed.After finding that the condition
 
of the No. 2 seal might not indicate the operability
 
of the No. 1 seal, Westinghouse
 
provided guidance for the Braidwood
 
Station that significantly
 
enhances operator ability to determine
 
if immediate
 
shutdown of an RCP is required or if a more orderly shutdown can be conducted.
 
Westinghouse
 
completed
 
a safety evaluation
 
and issued Technical Bulletin, NSD-TB-93-01-RO, "Revised Procedures
 
for RCP Shutdown with No. 1 Seal Leakage Outside Operating
 
Limits," dated March 30, 1993, to other PWRs that might be affected.
 
An excerpt from this document is attached to this information
 
notice (see Attachment
 
2).
 
IN 93-84 October 14, 1993 This information
 
notice requires no specific action or written response.
 
If you have any questions
 
about the information
 
in this notice, please contact one of the technical
 
contacts listed below or the appropriate
 
Office of Nuclear Reactor Regulation (NRR) project manager.Brian K. Grimes, Director Division of Operating
 
===Reactor Support Office of Nuclear Reactor Regulation===
Technical
 
contacts:
Steve DuPont, RIII (815) 458-2852 Martin Farber, RIII (708) 790-5774 Chu-Yu Liang, NRR (301) 504-2878 Attachments:
1. Simplified
 
Braidwood
 
Seal Water Injection and Leakoff Flow Diagram 2. Excerpt from Westinghouse
 
Technical Bulletin, NSD-TB-93-01-RO, "Revised Procedures
 
for RCP Shutdown with No. 1 Seal Leakage Outside Operating
 
Limits" 3. List of Recently Issued NRC Information
 
Notices
 
2=."I 'I'TO SEAL WATER HAT EXCHANGER CO IrRo.D my LEVEL IN STAOPIPE TO REGENERATIWE1 HEAT EXCHANGER DR DRAIN IIMP go 0 Zrt aq ct (D j xD O m 00 MS 0 t I-'.II-h' LAl -NIN sAN ThERL ARRHER HEAT EXCHANGERF"U.t,&ID w SIMPLIFIED
 
BRAIDWOOD
 
SEAL WATER INJECTION
 
AND LEAKOFF FLOW DIAGRAM
 
I>Attachment
 
2 IN 93-84 October 20 1993 Page 1 of I Nuclear Services Division Westinghouse
 
Technical
 
Bulletin An advisory notice of a recent technical
 
development
 
pertining
 
to th- irts.ation
 
or operation
 
of Wastghous&suppi*d
 
Nudr Plant equipment.
 
Recipients
 
shouSd evaluate the Information
 
and recomnM aIRonl, and initite action wh-r aomopriabt.
 
P.O. SOX 35, Pltttxzu PA 15o Subject REVISED PROCEDURES
 
FOR ROP SHUTDOWN WITH NO.'.FAl I FAKA(LF OUTSIDE OPERATING
 
UMITS.o NSD-TB- 93-01-RO System(s)  
REACTOR COOLANT SYSTEM Date 03r3/9 PLant ALL WESTINGHOUSE
 
REACTOR COOLANT PUMPS WITH lr SO(s) 125 CONTROLLED
 
LEAKAGE SEALS (See Aftacivelt
 
B)References
 
_- -- C , .nA~. cten Is Safety Related Yes 0 Page 1 Of 8 h M L) rilv Vl..I Vr-ij' 1 Q %- W I E2o m e t adgq No O1  


==BACKGROUND==
==BACKGROUND==
Years of Westinghouse RCP operating experience has demonstrated that complete failure of the No. 1seal is a rare occurrence. A complete failure is defined as excessive No. 1 seal leakage in conjunctionwith pump bearing/seal inlet and/or No. 1 leakoff temperatures approaching or exceeding the maximumlimits. Current operating procedures for failed No. 1 seals direct that the No. I seal leakoff be isolatedwithin 5 minutes and RCP shutdown witlin 30 minutes. These procedures are specified in the RCPinstruction books or addenda to the books.After a review of current operating procedures and actual operating experiences with high and low leakingNo. 1 seals, it was concluded ftht distinct procedures could specify steps for both emergency and orderlyRCP shutdowns. The two iems that follow have been incorporated into the revised procedures in thistechnical bulletin. As used within this bulletin, the term 'emergeflym refers to a condition that is relatedonly to RCP operation and in no way pertains to emergency conditions for plant operation as defined ina plant hnal Safety Analysis Report (FSAR).I) A damaged No. 1 seal may produce debris or leak at a high enough rate to exceed theinjection rate and introduce unfiltered, high temperature reactor coolant into the seals. In thepresence of debris. the ability of the No. 2 seal to survive and function as a backup for theNo. 1 seal is more favorable under static conditions. Thus, it is preferred to have pumpshutdown precede No. 1 seal leakoff isolation.AJol" W omutfi. Flequd. may be Obhuned fron @fe 0rawc Teb hoffl 412- 963-5634 or (W) 29-5634Appmvi.T. W. Dunn, Manager, Fied Service & RCP EngineerngL J. HaperEner Systes Saes Suport'q7- -t-. NR. F pleiter. mwnA~e CR 4 -& Seal Engineainat tr* gwonmul)Of corame in W"t "Pon or -an wy reqpo-"kdy 1b "ik&ym dafiQ$ ~iC flf umastamtom am of mooh irdofflol.
Years of Westinghouse
 
RCP operating
 
experience
 
has demonstrated
 
that complete failure of the No. 1 seal is a rare occurrence.
 
A complete failure is defined as excessive
 
===No. 1 seal leakage in conjunction===
with pump bearing/seal
 
inlet and/or No. 1 leakoff temperatures
 
approaching
 
or exceeding
 
the maximum limits. Current operating
 
procedures
 
for failed No. 1 seals direct that the No. I seal leakoff be isolated within 5 minutes and RCP shutdown witlin 30 minutes. These procedures
 
are specified
 
in the RCP instruction
 
books or addenda to the books.After a review of current operating
 
procedures
 
and actual operating
 
experiences
 
with high and low leaking No. 1 seals, it was concluded
 
ftht distinct procedures
 
could specify steps for both emergency
 
and orderly RCP shutdowns.
 
The two iems that follow have been incorporated
 
into the revised procedures
 
in this technical
 
bulletin.
 
As used within this bulletin, the term 'emergefly
 
m refers to a condition
 
that is related only to RCP operation
 
and in no way pertains to emergency
 
conditions
 
for plant operation
 
as defined in a plant hnal Safety Analysis Report (FSAR).I) A damaged No. 1 seal may produce debris or leak at a high enough rate to exceed the injection
 
rate and introduce
 
unfiltered, high temperature
 
reactor coolant into the seals. In the presence of debris. the ability of the No. 2 seal to survive and function as a backup for the No. 1 seal is more favorable
 
under static conditions.
 
Thus, it is preferred
 
to have pump shutdown precede No. 1 seal leakoff isolation.
 
AJol" W omutfi. Flequd. may be Obhuned fron @fe 0rawc Teb hoffl 412- 963-5634 or (W) 29-5634 Appmvi.T. W. Dunn, Manager, Fied Service & RCP Engineerng
 
L J. Haper Ener Systes Saes Suport'q7- -t-. N R. F pleiter. mwnA~e CR 4 -& Seal Engineain at tr* gwonmul)Of
 
corame in W"t "Pon or -an wy reqpo-"kdy
 
1b "ik&ym dafiQ$ ~iC flf umastamtom
 
am of mooh irdofflol.
 
Attachment
 
2 IN 93-84 October 20, 1993 NSD-TB-93-01-RO 2) High No. 1 seal leakage (> 6.0 9pm) or low No. 1 seal leakage (< 0.8 gpen) can occur while no other RCP parameter
 
limits are approached
 
or violated.
 
In these cases. pump shutdowns
 
within several hours are within the capabilities
 
of the RCPs and are more conducive
 
to orderly plant shutdowns.
 
The following
 
new procedures
 
are provided to address each of four conditions
 
that irncate No. 1 seal flow outside of the operating
 
limits (0.8-6.0 gpm). The first three conditiors
 
address high No. I seal leakage and the fourth condition
 
addresses
 
low leakage. Each condition
 
with its respective
 
procedure
 
is specified
 
below and is summarized
 
in Attachment
 
===A.PROCEDURES===
The following
 
procedures
 
supersede
 
those in the RCP instruction
 
books or addenda to the books relative to: 1) RCP emergency
 
operation
 
and shutdown procedures
 
for high or low No. 1 seal leakage. Apply the Conditions
 
1 through 4 procedures
 
that follow.2) RCP emergency
 
operation
 
and shutdown procedure
 
for No. 2 and No. 3 seals. Apply the procedure
 
for shutdown specified
 
under Condition
 
1 below. The No. 2 and No. 3 seal parameters
 
tat indicate emergency
 
operation
 
remain the same as specified
 
in the RCP instruction
 
books.Definitions:
No. 1 seal leakoff indication:
Flowmeter
 
readout of No. 1 seal leak rate No. 2 seal leakoff indication:
Flowmeter
 
readout or estimate of No. 2 seal leak rate Total No. 1 Seal Flow: Sum of No. 1 and No. 2 seal leakoff indications
 
Immediate
 
Shutdown:
RCP shutdown and isolation
 
of No. 1 seal leakoff within 5 minutes Orderly Shutdown:
RCP shutdown within 8 hours of higtow No. 1 seal leakoff flow indication
 
NOTE; A manual plant trip must precede an "Emergency
 
or 'Ordery RCP shutdown.
 
This will prevent an automatic
 
plant tip on a low flows signal which represents
 
an unnecessary
 
challenge
 
to installed
 
safety systems.
 
Attachment
 
2 IN 93-84 October 20, 1993 NSD-TB-93-011-RO If no alternative
 
Westinghouse
 
direction
 
has been provided to address a specfic RCP seal performance
 
condition
 
at a plant, the following
 
are the recommended
 
shutdown procedures
 
for No. 1 seal leak rates outside the operating
 
limits (08-6.0 gpm).Condition
 
1: a) No. 1 sea leakoff indication
 
> 6.0 gpcn.b) Increasing
 
pump beanngfseal
 
inlet temnperature.
 
and/or increasing
 
No. I seal leakoff temperature.
 
Procedure:
1)Shut down the RCP immediately.
 
2) Isolate the No. 1 seal leakoff after the RCP has come to a complete stop.3) Monitor component
 
cooling water (CCW) to ensure adequate flow and manually override automatic
 
isotation
 
as required. (Local boiling in the thermal barrier of the affected pump may cause isolation
 
of the CCW system.)4) Do not restart the pump until the cause of the seal malfunction
 
has been determined
 
and corrected.
 
Condition
 
2;a)No. I seal leakoff indication
 
> 6.0 gpm.andfor Total No. 1 seal flow > 6.0 gpm and < 8.0 gpm.b) Ppump bearing/seal
 
inlet temperature
 
is not increasing.
 
c) No. 1 seal leakoff temPerature (if equipped)
is not increasing.
 
Procedure:
1)Prepare for an orderly pump shutdown to take effect within 8 hours of exceeding
 
6.0 gpm No. I seal flow. Ensure that seal injection
 
flow rate is 9 gpm or greater to the affected RCR
 
Attachment
 
2 IN 93-84 October 20, 1993 NSD-TB-93-o -RO 2) Continue to monitor the No. 1 seal for further degradation
 
durng the orderly shutdown.
 
If the total No. 1 seal flow exceeds 8.0 gpm or temperatures
 
begn to increase, proceed with immediate
 
shutdown in accordance
 
with the Condition
 
3 procedure.
 
Otherwise, proceed with the orderly shutdown.3) Secure the pump within 8 hours of exceeding
 
a No. 1 seal eamkof indication
 
or total No. 1 seal flow of 6.0 gpn.4) Moritor component
 
cooing waler (CCOW to ensure adequate flow and manually override as required. (Local boiling in the thermal banier of the affected pump may cause isolaton of the CCW system.)5) No. I seal leakoff may be isolated at the discretion
 
of operations
 
to mitigate inventory
 
loss and to assure that seal injection
 
flow exceeds total No. 1 seal flow on the affected pump.6) Do not restart the pump until the cause of the seal malfunction
 
has been determined
 
and corrected.
 
Condition
 
3: a) Total No. 1 seal flow x 8.0 gpm.Procedure:
1) Shut down the RCP immediately.
 
2) Isolate the No. 1 seal leakoff after the RCP has come to a complete stop.3) Monitor component
 
cooling water (CCW) to ensure adequate flow and rnanaly override automatic
 
Isolation
 
as required. (Local boiling in the thermal banier of the affected pump may cause isolation
 
of the CCW system.)4) .Do not restart the pump until the cause of the seal malfunction
 
has been determined
 
and corected.Condition
 
4: a) No. I seal leakoff indication
 
c 0.8 gpm.b) Zero (or negligible)
No. 2 seal leak rate such that total No. 1 seal flow < 0.8 gprn.c) Pump bearingfseal
 
inlet temperature
 
and No. 1 seal leakoff temperature (if equipped)
are stable (i.e.. not coninuously
 
increasing)
and within limits.
 
Attachient
 
2 IN 93-84 October 20, 1993 NSD-TB-93"01-RO Procedure:
1) Prepare for an orderly pump shutdown to take effect within 8 hours of violating
 
the rninimum 0.8 No. 1 seal leak rate Knit 2) Continue to monitor the No. 1 seal for further degradation
 
duing the orderly shutdown.
 
If the bw No. 1 sa lealkge reverses to high leakage (> 6.0 gpim) or temperatures
 
start to increase, proceed with immeciate shutdown in accordance
 
with the Condcion 1 procedure.
 
Otherwise, proceed with the orderly shutdown.3) Secure the pump within 8 hours of violasts the rnirnmum 0.8 No. 1 seal leak rate limit.4) Do not restart the pump until the cause of the seal malfunction
 
has been determined
 
and corrected.
 
ATTACHMENT
 
A No. 1 Leakotf No. 2 Leakoft Total Pump Bearing/Seal
 
Condition
 
Indication
 
Indication
 
No. 1 Seal Flow Inlet and/or RCP Shutdown No. 1 Leakoff Temp.1 > 6.0 gpm > 6.0 gpm Increasing
 
Immediate (wilhin 5 minutes)2 > 6.0 gpm > 6.0 and < 8.0 gpm Stable Orderly (within 8 hours)3 > 8.0 gpm Stable or Immediate increasing (within 5 minutes)4 < 0.8 gpm zero < 0.8 gpm Stable Orderly (or negligible) (within 8 hours)Note: Total No. 1 seal flow a No. 1 leakoff plus No. 2 leakoff indications
 
(0 0 q4 0 oz 3 IF wo I'd Pz n MD 0 a% ID 0 0'-P-a (J.%D rt*r1-U) 0 i2w~,r
 
Attachment
 
3 IN 93-84 October 20, 1993 LIST OF RECENTLY ISSUED NRC INFORMATION
 
NOTICES Information
 
Date of Notice No. Subject Issuance Issued to 93-83 Potential
 
Loss of Spent Fuel Pool Cooling Following
 
A Loss of Coolant Accident (LOCA)10/07/93 All holders for boiling (BWRs).of OLs or CPs water reactors 93-82 93-81 93-80 93-79 93-78 93-77 93-76 93-75 Recent Fuel and Core Performance
 
Problems in Operating
 
Reactors Implementation
 
of Engineering
 
Expertise on Shift Implementation
 
of the Revised 10 CFR Part 20 Core Shroud Cracking at Beltline Region Welds in Boiling-Water
 
Reactors Inoperable
 
Safety Systems At A Non-Power
 
Reactor Human Errors that Result in Inadvertent
 
Transfers of Special Nuclear Material at Fuel Cycle Facilities
 
Inadequate
 
Control of Paint and Cleaners for Safety-Related
 
Equipment Spurious Tripping of Low-Voltage
 
Power Circuit Breakers with GE'RMS-9 Digital Trip Units 10/12/93 10/12/93 10/08/93 09/30/93 10/04/93 10/04/93 09/21/93 09/17/93 All holders of OLs or CPs for nuclear power reactors and all NRC-approved
 
fuel suppliers.
 
All holders of OLs or CPs for nuclear power reactors.All byproduct, source, and and special nuclear material licensees.
 
===All holders of operating licenses or construction===
permits for boiling-water
 
reactors (BWRs).All holders of OLs or CPs for test and research reactors.All nuclear fuel cycle licensees.
 
All holders of OLs or CPs for nuclear power reactors.All holders of OLs or CPs for nuclear power reactors.OL = Operating
 
License CP = Construction
 
Permit
 
IN 93-84 October 14, 1993 This information
 
notice requires no specific action or written response.
 
If you have any questions
 
about the information
 
in this notice, please contact one of the technical
 
contacts listed below or the appropriate
 
Office of Nuclear Reactor Regulation (NRR) project manager.Original signed bY Brian K. Grimef Brian K. Grimes, Director Division of Operating
 
===Reactor Support Office of Nuclear Reactor Regulation===
Technical
 
contacts: Steve (815)DuPont, RIII 458-2852 Martin Farber, RIII (708) 790-5774 Chu-Yu Liang, NRR (301) 504-2878 Attachments:
1. Simplified
 
Braidwood
 
Seal Water Injection and Leakoff Flow Diagram 2. Excerpt from Westinghouse
 
Technical Bulletin, NSD-TB-93-01-RO, "Revised Procedures
 
for RCP Shutdown with No. I Seal Leakage Outside Operating
 
Limits" 3. List of Recently Issued NRC Information
 
Notices*SEE PREVIOUS CONCURRENCE
 
OFF NAME DATE*OGCB:DORS
 
PCWen 07/26/93*SRXB:DSSA
 
CYLiang 07/26/93*SRI:DRP:RIII
 
SGDuPont 07/26/93*TECH ED MMejac 07/27/93*SC/DRP:RIII
 
MJFarber 07/29/93*D/DSSA ACThadani 09/23/93*C/DRP:RIII
 
BClayton 07/29/93*C/OGCB:DORS
 
GHMarcus 09/28/93*SC/SRXB:DSSA
 
MACaruso 08/05-93.4:;tes 10// r 93*C/SRXB:DSSA
 
RCJones 08/09/93 DOCUMENT NAME: 93-84.IN
 
IN 93-xx October xx, 1993 This information
 
notice requires no specific action or written response.
 
If you have any questions
 
about the information
 
in this notice, please contact one of the technical
 
contacts listed below or the appropriate
 
Office of Nuclear Reactor Regulation (NRR) project manager.Brian K. Grimes, Director Division of Operating
 
===Reactor Support Office of Nuclear Reactor Regulation===
Technical
 
contacts: Steve DuPont, RIII (815) 458-2852 Martin Farber, RIII (708) 790-5774 Chu-Yu Liang, NRR (301) 504-2878 Attachments:
1. Simplified
 
Braidwood
 
Seal Water Injection
 
and Leakoff Flow Diagram 2. Excerpt from Westinghouse
 
Technical
 
Bulletin, NSD-TB-93-01-RO, "Revised Procedures
 
for RCP Shutdown with No. 1 Seal Leakage Outside Operating Limits" 3. List of Recently Issued NRC Information
 
Notices*SEE PREVIOUS CONCURRENCE
 
OFF NAME DATE*OGCB:DORS
 
PCWen 07/26/93*SRXB:DSSA
 
CYLiang 07/26/93*SRI:DRP:RIII
 
SGDuPont 07/26/93*TECH ED MMejac 07/27/93*SC/DRP:RIII
 
MJFarber 07/29/93*C/DRP:RIII
 
BClayton 07/29/93*SC/SRXB:DSSA
 
MACaruso 08/05/93*C/SRXB:DSSA
 
RCJones 08/09/93*D/DSSA ACThadani 09/23/93 DOCUMENT NAME: C/OGCB:DOi,_
D/DORS PcEY GHMarcu$s&
!:' BKGrimesng
 
P4it P (so-.-qI),MAM
 
WRCPSEAL.We
 
0fFnfS T HE 049 /9o o3eevat lro 1hE NftC 41TA03rA*
THS g*Sr*qWS C _ %,A _ } U. .O ' 0a* W S~--.W""i r. MOFbV4' ( H& S5ef ) vvia %;nfgnri&
dr i tw LWI44n44t
 
et-K'%$ U -te pnvi.d %e ,W Tec6-,.p^
MoTtwcdL.
 
?et hk~
IN 93-xx September
 
xx, 1993 This information
 
notice requires no specific action or written response.
 
If you have any questions
 
about the information
 
in this notice, please contact one of the technical
 
contacts listed below or the appropriate
 
Office of Nuclear Reactor Regulation (NRR) project manager.Brian K. Grimes, Director Division of Operating
 
===Reactor Support Office of Nuclear Reactor Regulation===
Technical
 
contacts: Steve DuPont, RIII (815) 458-2852 Martin Farber, RIII (708) 790-5774 Chu-Yu Liang, NRR (301) 504-2878 Attachments:
1. Simplified
 
Braidwood
 
Seal Water Injection
 
and Leakoff Flow Diagram 2. Excerpt from Westinghouse
 
Technical
 
Bulletin, NSD-TB-93-01-RO, 'Revised Procedures
 
for RCP Shutdown with No. 1 Seal Leakage Outside Operating Limits'3. List of Recently Issued NRC Information
 
Notices*SEE PREVIOUS CONCURRENCE
 
OFF NAME DATE*OGCB:DORS
 
PCWen 07/26/93*SRXB:DSSA
 
CYLiang 07/26/93*SRI:DRP:RIII
 
SGDuPont 07/26/93*TECH ED MMejac 07/27/93*SC/DRP:RIII
 
MJFarber 07/29/ AF D/DSS ai' _ACThadani 09/2_/93 DOCUMENT NAME:*C/DRP:RIII
 
BClayton 07/29/93 C/OGCB:DORS
 
GHMarcus 09/ /93 WRCPSEAL.WEN
 
*SC/SRXB:DSSA
 
MACaruso 08/05/93*C/SRXB:DSSA
 
RCJones 08/09/93 D/DORS BKGrimes 09/ /93 Brian K. Grimes, Director Division of Operating
 
===Reactor Support Office of Nuclear Reactor Regulation===
Technical
 
contacts: Steve DuPont, RIII (815) 458-2852 Martin Farber, RIII (708) 790-5774 Chu-Yu Liang, NRR (301) 504-2878 Attachments:
1. Simplified
 
Braidwood
 
Seal Water Injection
 
and Leakoff Flow Diagram 2. Excerpt from Westinghouse
 
Technical
 
Bulletin, NSD-TB-93-01-RO, 'Revised Procedures
 
for RCP Shutdown with No. 1 Seal Leakage Outside Operating Limits" 3. List of Recently Issued NRC Information
 
Notices*SEE PREVIOUS CONCURRENCE
 
OFF *OGCB:DORS
 
*SRXB:DSSA
 
NAME PCWen CYLiang DATE 07/26/93 O7/26/93 STW RD I :I I C/R J.:RIII MJFarber 4 BClayton 07ial/93 J 07/< /93 we 74FCoo .7,6/93 D/DSSA C/OGCB:DORS
 
ACThadani
 
GHMarcus 07/ /93 07/ /93*SRI:DRP:RIII
 
SGDuPont 07/26/93 ,JSRXB:DSSA
 
C ones?/ /93*TECH ED MMejac 07/27/93 SC/SRXB:DSSAL
 
MACaruso `y r r/4r/93 / r D/DORS BKGrimes 07/ /93
\s-/Martin Farber, RIII (708) 790-5774 Chu-Yu Liang, NRR (301) 504-2878 Attachments:
1. Braidwood
 
Seal Water Injection


Attachment 2IN 93-84October 20, 1993 NSD-TB-93-01-RO ) High No. 1 seal leakage (> 6.0 9pm) or low No. 1 seal leakage (< 0.8 gpen) can occurwhile no other RCP parameter limits are approached or violated. In these cases. pumpshutdowns within several hours are within the capabilities of the RCPs and are moreconducive to orderly plant shutdowns.The following new procedures are provided to address each of four conditions that irncate No. 1seal flow outside of the operating limits (0.8-6.0 gpm). The first three conditiors address highNo. I seal leakage and the fourth condition addresses low leakage. Each condition with itsrespective procedure is specified below and is summarized in Attachment A.PROCEDURESThe following procedures supersede those in the RCP instruction books or addenda to the booksrelative to:1) RCP emergency operation and shutdown procedures for high or low No. 1 sealleakage. Apply the Conditions 1 through 4 procedures that follow.2) RCP emergency operation and shutdown procedure for No. 2 and No. 3 seals. Applythe procedure for shutdown specified under Condition 1 below. The No. 2 and No. 3seal parameters tat indicate emergency operation remain the same as specified inthe RCP instruction books.Definitions:No. 1 seal leakoff indication: Flowmeter readout of No. 1 seal leak rateNo. 2 seal leakoff indication: Flowmeter readout or estimate of No. 2 seal leak rateTotal No. 1 Seal Flow: Sum of No. 1 and No. 2 seal leakoff indicationsImmediate Shutdown: RCP shutdown and isolation of No. 1 seal leakoff within5 minutesOrderly Shutdown: RCP shutdown within 8 hours of higtow No. 1 seal leakoffflow indicationNOTE; A manual plant trip must precede an "Emergency or 'Ordery RCP shutdown. This willprevent an automatic plant tip on a low flows signal which represents an unnecessarychallenge to installed safety systems.
and Leakoff Flow Diagram..r-
2. Excerpt from Westinghouse


Attachment 2IN 93-84October 20, 1993 NSD-TB-93-011-RO If no alternative Westinghouse direction has been provided to address a specfic RCP sealperformance condition at a plant, the following are the recommended shutdown procedures forNo. 1 seal leak rates outside the operating limits (08-6.0 gpm).Condition 1:a) No. 1 sea leakoff indication > 6.0 gpcn.b) Increasing pump beanngfseal inlet temnperature.and/orincreasing No. I seal leakoff temperature.Procedure:1)Shut down the RCP immediately.2) Isolate the No. 1 seal leakoff after the RCP has come to a complete stop.3) Monitor component cooling water (CCW) to ensure adequate flow andmanually override automatic isotation as required. (Local boiling in thethermal barrier of the affected pump may cause isolation of the CCWsystem.)4) Do not restart the pump until the cause of the seal malfunction has beendetermined and corrected.Condition 2;a)No. I seal leakoff indication > 6.0 gpm.andforTotal No. 1 seal flow > 6.0 gpm and < 8.0 gpm.b) Ppump bearing/seal inlet temperature is not increasing.c) No. 1 seal leakoff temPerature (if equipped) is not increasing.Procedure: 1)Prepare for an orderly pump shutdown to take effect within 8 hours ofexceeding 6.0 gpm No. I seal flow. Ensure that seal injection flow rate is9 gpm or greater to the affected RCR
Technical


Attachment 2IN 93-84October 20, 1993 NSD-TB-93-o -RO ) Continue to monitor the No. 1 seal for further degradation durng the orderlyshutdown. If the total No. 1 seal flow exceeds 8.0 gpm or temperaturesbegn to increase, proceed with immediate shutdown in accordance withthe Condition 3 procedure. Otherwise, proceed with the orderly shutdown.3) Secure the pump within 8 hours of exceeding a No. 1 seal eamkof indicationor total No. 1 seal flow of 6.0 gpn.4) Moritor component cooing waler (CCOW to ensure adequate flow andmanually override as required. (Local boiling in the thermal banier of theaffected pump may cause isolaton of the CCW system.)5) No. I seal leakoff may be isolated at the discretion of operations to mitigateinventory loss and to assure that seal injection flow exceeds total No. 1 sealflow on the affected pump.6) Do not restart the pump until the cause of the seal malfunction has beendetermined and corrected.Condition 3: a) Total No. 1 seal flow x 8.0 gpm.Procedure: 1) Shut down the RCP immediately.2) Isolate the No. 1 seal leakoff after the RCP has come to a complete stop.3) Monitor component cooling water (CCW) to ensure adequate flow andrnanaly override automatic Isolation as required. (Local boiling in thethermal banier of the affected pump may cause isolation of the CCWsystem.)4) .Do not restart the pump until the cause of the seal malfunction has beendetermined and corected.Condition 4: a) No. I seal leakoff indication c 0.8 gpm.b) Zero (or negligible) No. 2 seal leak rate such that total No. 1 sealflow < 0.8 gprn.c) Pump bearingfseal inlet temperature and No. 1 seal leakoff temperature(if equipped) are stable (i.e.. not coninuously increasing) and within limits.
Bulletin, NSD-TB-93-01-RO, "Revised Procedures


Attachient 2IN 93-84October 20, 1993 NSD-TB-93"01-RO Procedure: 1) Prepare for an orderly pump shutdown to take effect within 8 hours ofviolating the rninimum 0.8 No. 1 seal leak rate Knit2) Continue to monitor the No. 1 seal for further degradation duing theorderly shutdown. If the bw No. 1 sa lealkge reverses to high leakage(> 6.0 gpim) or temperatures start to increase, proceed with immeciateshutdown in accordance with the Condcion 1 procedure. Otherwise,proceed with the orderly shutdown.3) Secure the pump within 8 hours of violasts the rnirnmum 0.8 No. 1 seal leakrate limit.4) Do not restart the pump until the cause of the seal malfunction has beendetermined and corrected.
for RCP Shutdown with No. 1 Seal Leakage Outside Operating Limits" 3. -List-ef Recently IssueFd4RC-4nf-4fmation.-Not-ies-.-
OFF NAME DATE OCB:DORS PCWen 07/a6/93 SRXB L SA S I RIII CYLiang _ SGDuPont MR-07/;xb/93 V~ 07/Vb/93 T1-e'A.@TECH ED MMejac *M i 07/1.7/93 SC/SRXB:DSSA


ATTACHMENT ANo. 1 Leakotf No. 2 Leakoft Total Pump Bearing/SealCondition Indication Indication No. 1 Seal Flow Inlet and/or RCP ShutdownNo. 1 Leakoff Temp.1 > 6.0 gpm > 6.0 gpm Increasing Immediate(wilhin 5 minutes)2 > 6.0 gpm > 6.0 and < 8.0 gpm Stable Orderly(within 8 hours)3 > 8.0 gpm Stable or Immediateincreasing (within 5 minutes)4 < 0.8 gpm zero < 0.8 gpm Stable Orderly(or negligible) (within 8 hours)Note:Total No. 1 seal flow a No. 1 leakoff plus No. 2 leakoff indications(00q40oz3IFwoI'dPz nMD 0a% ID00'-P-a(J.%Drt*r1-U) 0i2w~,r
MACaruso 07/ /93 SC/DRP:RIII


Attachment 3IN 93-84October 20, 1993 LIST OF RECENTLY ISSUEDNRC INFORMATION NOTICESInformation Date ofNotice No. Subject Issuance Issued to93-83Potential Loss of SpentFuel Pool CoolingFollowing A Loss ofCoolant Accident (LOCA)10/07/93All holdersfor boiling(BWRs).of OLs or CPswater reactors93-8293-8193-8093-7993-7893-7793-7693-75Recent Fuel and CorePerformance Problems inOperating ReactorsImplementation ofEngineering Expertiseon ShiftImplementation of theRevised 10 CFR Part 20Core Shroud Cracking atBeltline Region Weldsin Boiling-Water ReactorsInoperable Safety SystemsAt A Non-Power ReactorHuman Errors that Resultin Inadvertent Transfersof Special NuclearMaterial at Fuel CycleFacilitiesInadequate Control ofPaint and Cleaners forSafety-Related EquipmentSpurious Tripping ofLow-Voltage Power CircuitBreakers with GE'RMS-9Digital Trip Units10/12/9310/12/9310/08/9309/30/9310/04/9310/04/9309/21/9309/17/93All holders of OLs or CPsfor nuclear power reactorsand all NRC-approved fuelsuppliers.All holders of OLs or CPsfor nuclear power reactors.All byproduct, source, andand special nuclear materiallicensees.All holders of operatinglicenses or constructionpermits for boiling-waterreactors (BWRs).All holders of OLs or CPsfor test and researchreactors.All nuclear fuel cyclelicensees.All holders of OLs or CPsfor nuclear power reactors.All holders of OLs or CPsfor nuclear power reactors.OL = Operating LicenseCP = Construction Permit
MJFarber 07/ /93 C/DRP:RIII


IN 93-84October 14, 1993 This information notice requires no specific action or written response. Ifyou have any questions about the information in this notice, please contactone of the technical contacts listed below or the appropriate Office ofNuclear Reactor Regulation (NRR) project manager.Original signed bYBrian K. GrimefBrian K. Grimes, DirectorDivision of Operating Reactor SupportOffice of Nuclear Reactor RegulationTechnical contacts:Steve(815)DuPont, RIII458-2852Martin Farber, RIII(708) 790-5774Chu-Yu Liang, NRR(301) 504-2878Attachments:1. Simplified Braidwood Seal Water Injectionand Leakoff Flow Diagram2. Excerpt from Westinghouse TechnicalBulletin, NSD-TB-93-01-RO, "RevisedProcedures for RCP Shutdown with No. ISeal Leakage Outside Operating Limits"3. List of Recently Issued NRC Information Notices*SEE PREVIOUS CONCURRENCEOFFNAMEDATE*OGCB:DORSPCWen07/26/93*SRXB:DSSACYLiang07/26/93*SRI:DRP:RIIISGDuPont07/26/93*TECH EDMMejac07/27/93*SC/DRP:RIIIMJFarber07/29/93*D/DSSAACThadani09/23/93*C/DRP:RIIIBClayton07/29/93*C/OGCB:DORSGHMarcus09/28/93*SC/SRXB:DSSAMACaruso08/05-93.4:;tes10// r 93*C/SRXB:DSSARCJones08/09/93DOCUMENT NAME: 93-84.IN
BClayton 07/ /93 C/SRXB:DSSA


IN 93-xxOctober xx, 1993 This information notice requires no specific action or written response. Ifyou have any questions about the information in this notice, please contactone of the technical contacts listed below or the appropriate Office ofNuclear Reactor Regulation (NRR) project manager.Brian K. Grimes, DirectorDivision of Operating Reactor SupportOffice of Nuclear Reactor RegulationTechnical contacts:Steve DuPont, RIII(815) 458-2852Martin Farber, RIII(708) 790-5774Chu-Yu Liang, NRR(301) 504-2878Attachments:1. Simplified Braidwood Seal Water Injection and Leakoff Flow Diagram2. Excerpt from Westinghouse Technical Bulletin, NSD-TB-93-01-RO, "RevisedProcedures for RCP Shutdown with No. 1 Seal Leakage Outside OperatingLimits"3. List of Recently Issued NRC Information Notices*SEE PREVIOUS CONCURRENCEOFFNAMEDATE*OGCB:DORSPCWen07/26/93*SRXB:DSSACYLiang07/26/93*SRI:DRP:RIIISGDuPont07/26/93*TECH EDMMejac07/27/93*SC/DRP:RIIIMJFarber07/29/93*C/DRP:RIIIBClayton07/29/93*SC/SRXB:DSSAMACaruso08/05/93*C/SRXB:DSSARCJones08/09/93*D/DSSAACThadani09/23/93DOCUMENT NAME:C/OGCB:DOi,_ D/DORS PcEYGHMarcu$s& !:' BKGrimesng P4it P (so-.-qI),MAMWRCPSEAL.We 0fFnfS T HE 049 /9o o3eevat lro1hE NftC 41TA03rA* THS g*Sr*qWSC _ %,A _ } U. .O ' 0a* W S~--.W""i r. MOFbV4' ( H& S5ef ) vvia %;nfgnri& dr i tw LWI44n44t et-K'%$ U -te pnvi.d %e ,W Tec6-,.p^ MoTtwcdL. ?et hk~
RCJones 07/ /93 D/DSSA ACThadani 07/ /93 C/OGCB:DORS
IN 93-xxSeptember xx, 1993 This information notice requires no specific action or written response. Ifyou have any questions about the information in this notice, please contactone of the technical contacts listed below or the appropriate Office ofNuclear Reactor Regulation (NRR) project manager.Brian K. Grimes, DirectorDivision of Operating ReactorSupportOffice of Nuclear Reactor RegulationTechnical contacts:Steve DuPont, RIII(815) 458-2852Martin Farber, RIII(708) 790-5774Chu-Yu Liang, NRR(301) 504-2878Attachments:1. Simplified Braidwood Seal Water Injection and Leakoff Flow Diagram2. Excerpt from Westinghouse Technical Bulletin, NSD-TB-93-01-RO, 'RevisedProcedures for RCP Shutdown with No. 1 Seal Leakage Outside OperatingLimits'3. List of Recently Issued NRC Information Notices*SEE PREVIOUS CONCURRENCEOFFNAMEDATE*OGCB:DORSPCWen07/26/93*SRXB:DSSACYLiang07/26/93*SRI:DRP:RIIISGDuPont07/26/93*TECH EDMMejac07/27/93*SC/DRP:RIIIMJFarber07/29/ AFD/DSS ai' _ACThadani09/2_/93DOCUMENT NAME:*C/DRP:RIIIBClayton07/29/93C/OGCB:DORSGHMarcus09/ /93WRCPSEAL.WEN*SC/SRXB:DSSAMACaruso08/05/93*C/SRXB:DSSARCJones08/09/93D/DORSBKGrimes09/ /93 Brian K. Grimes, DirectorDivision of Operating Reactor SupportOffice of Nuclear Reactor RegulationTechnical contacts:Steve DuPont, RIII(815) 458-2852Martin Farber, RIII(708) 790-5774Chu-Yu Liang, NRR(301) 504-2878Attachments:1. Simplified Braidwood Seal Water Injection and Leakoff Flow Diagram2. Excerpt from Westinghouse Technical Bulletin, NSD-TB-93-01-RO, 'RevisedProcedures for RCP Shutdown with No. 1 Seal Leakage Outside OperatingLimits"3. List of Recently Issued NRC Information Notices*SEE PREVIOUS CONCURRENCEOFF *OGCB:DORS *SRXB:DSSANAME PCWen CYLiangDATE 07/26/93 O7/26/93STW RD I :I I C/R J.:RIIIMJFarber 4 BClayton07ial/93 J 07/< /93we 74FCoo .7,6/93D/DSSA C/OGCB:DORSACThadani GHMarcus07/ /93 07/ /93*SRI:DRP:RIIISGDuPont07/26/93,JSRXB:DSSAC ones?/ /93*TECH EDMMejac07/27/93SC/SRXB:DSSALMACaruso `y rr/4r/93 / rD/DORSBKGrimes07/ /93
\s-/Martin Farber, RIII(708) 790-5774Chu-Yu Liang, NRR(301) 504-2878Attachments:1. Braidwood Seal Water Injection and Leakoff Flow Diagram..r-2. Excerpt from Westinghouse Technical Bulletin, NSD-TB-93-01-RO, "RevisedProcedures for RCP Shutdown with No. 1 Seal Leakage Outside OperatingLimits"3. -List-ef Recently IssueFd4RC-4nf-4fmation.-Not-ies-.-OFFNAMEDATEOCB:DORSPCWen07/a6/93SRXB L SA S I RIIICYLiang _ SGDuPont MR-07/;xb/93 V~ 07/Vb/93 T1-e'A.@TECH EDMMejac *Mi 07/1.7/93SC/SRXB:DSSAMACaruso07/ /93SC/DRP:RIIIMJFarber07/ /93C/DRP:RIIIBClayton07/ /93C/SRXB:DSSARCJones07/ /93D/DSSAACThadani07/ /93C/OGCB:DORSGHMarcus07/ /93D/DORSBKGrimes07/ /93! .


}}
GHMarcus 07/ /93 D/DORS BKGrimes 07/ /93! .}}


{{Information notice-Nav}}
{{Information notice-Nav}}

Revision as of 13:55, 31 August 2018

Determination of Westinghouse Reactor Coolant Pump Seal Failure
ML031070307
Person / Time
Site: Beaver Valley, Millstone, Hatch, Monticello, Calvert Cliffs, Dresden, Davis Besse, Peach Bottom, Browns Ferry, Salem, Oconee, Mcguire, Nine Mile Point, Palisades, Palo Verde, Perry, Indian Point, Fermi, Kewaunee, Catawba, Harris, Wolf Creek, Saint Lucie, Point Beach, Oyster Creek, Watts Bar, Hope Creek, Grand Gulf, Cooper, Sequoyah, Byron, Pilgrim, Arkansas Nuclear, Three Mile Island, Braidwood, Susquehanna, Summer, Prairie Island, Columbia, Seabrook, Brunswick, Surry, Limerick, North Anna, Turkey Point, River Bend, Vermont Yankee, Crystal River, Haddam Neck, Ginna, Diablo Canyon, Callaway, Vogtle, Waterford, Duane Arnold, Farley, Robinson, Clinton, South Texas, San Onofre, Cook, Comanche Peak, Yankee Rowe, Maine Yankee, Quad Cities, Humboldt Bay, La Crosse, Big Rock Point, Rancho Seco, Zion, Midland, Bellefonte, Fort Calhoun, FitzPatrick, McGuire, LaSalle, Fort Saint Vrain, Shoreham, Satsop, Trojan, Atlantic Nuclear Power Plant  Entergy icon.png
Issue date: 10/20/1993
From: Grimes B K
Office of Nuclear Reactor Regulation
To:
References
IN-93-084, NUDOCS 9310140192
Download: ML031070307 (16)


UNITED STATES NUCLEAR'REGULATORY

COMMISSION

OFFICE OF NUCLEAR REACTOR REGULATION

WASHINGTON, D.C. 20555 October 20, 1993 NRC INFORMATION

NOTICE 93-84: DETERMINATION

OF WESTINGHOUSE

REACTOR COOLANT PUMP SEAL FAILURE

Addressees

All holders of operating

licenses or construction

permits for pressurized

water reactors (PWRs).PurDose The U.S. Nuclear Regulatory

Commission (NRC) is'issuing

this information

notice to alert addressees

to a potential

problem that could result from the use of Westinghouse-designed

reactor coolant pump (RCP) shutdown procedures

for pumps whose No. 1 seals have failed. It is expected that recipients

will review the information

for applicability

to their facilities

and consider actions, as appropriate, to avoid similar problems.

However, suggestions

contained

in this information

notice are not NRC requirements;

therefore, no specific action or written response is required.Background

Westinghouse

supplied the Braidwood

Station RCPs, incorporating

a three-stage

seal series arrangement

to limit coolant flow up the pump shaft. The No. 1 seal, the main seal of the pump, is a controlled-leakage, film riding face seal. The No. 2 and No. 3 seals are rubbing face seals. During normal operation, an injection

flow of nominally

30.3 liters [8 gallons] per minute enters the pump below the No. 1 seal (see Attachment

1). Here the flow splits. A portion (approximately

18.9 liters [5 gallons] per minute) flows down through the thermal barrier heat exchanger

and enters the reactor coolant system. In this manner, the primary coolant is prevented

from entering the radial bearing and seal section of the pump unit. The remainder

(11.4 liters[3 gallons] per minute) (controlled

leakage) passes through the pump radial bearing and enters the No. 1 seal. Above the No. 1 seal, most of the flow leaves the pump through the No. 1 seal leakoff line and returns to the chemical and volume control system. Minor flow passes through the No. 2 seal and its leakoff line to the reactor coolant drain tank. A back flush injection

of 0.8 liters [0.21 gallons] per hour from a head tank flows into the No. 3 seal between its "double dam" seal area. At this point, half of the flow passes through one side of the seal and out the No. 2 seal leakoff line while the remaining

flow passes through the other side and out the No. 3 seal leakoff line. This arrangement

ensures essentially

zero leakage of reactor coolant from the pump.9310140192 o W q 3.O3;Afe4% ;IivftC

IN 93-84 Octoer 20, 1993 During normal operation, the No. 1 seal is subject to full reactor coolant system pressure.

When the injection

flow passes through the No. 1 seal, it produces a pressure drop of approximately

15.41 MPa [2235 psi]. The No. 2 seal has the capability

to withstand

full operating

pressure, and its major function is to act as a backup in case the No. 1 seal fails. If the No. 1 seal fails, leakage through the No. 2 seal increases.

The No. 2 seal high leak flow alarm actuates at 3.8 liters [1 gallon] per minute.Description

of Circumstances

In the middle of 1992, while developing

shutdown procedures

for the RCPs at the Braidwood

Station, Commonwealth

Edison Company (the licensee)

found that its abnormal operating

procedure

contained

inadequate

instructions

for responding

to a failure of the RCP No. 1 seal. On a high RCP No. 1 seal leakoff condition, the abnormal operating

procedure

directed the operating personnel

to check the condition

of the No. 2 seal. If the No. 2 seal was acting as the primary pressure boundary on the basis of leakage of at least 3.8 liters [1 gallon] per minute from the No. 2 seal, the procedure

required that the RCP be shut down. If the condition

of the No. 2 seal was normal, the procedure

required no further action and gave no further guidance.Discussions

with Westinghouse

indicated

that the condition

of the No. 2 seal might not be a sufficient

indication

of the operability

of the No. 1 seal.Discussion

The inadequacies

in the operating

procedure

stem from the limitations

of the instrumentation

used to monitor the leakage. The relevant No. 1 seal instrumentation

limits maximum readings to 22.7 liters [6 gallons] per minute.Although the No. 2 seal high leak flow alarm was set at 3.8 liters [1 gallon]per minute, very high No. 1 seal leak rates, more than 113.6 liters (30 gallons] per minute, are needed for the No. 2 seal to reach this flow rate. Thus, the No. 1 seal could have substantial

leakage (e.g., 22.7-113.6 liters (6-30 gallons] per minute) even though the No. 2 seal high leak flow alarm was not actuated.

In the mean time, the RCP seal system might be severely damaged if loss of injection

were to occur or the No. 1 seal leak rates were more than 30.3 liters [8 gallons] per minute. Therefore, monitoring

for high No. 2 seal leakage is not a reliable method of determining

whether the No. 1 seal has failed.After finding that the condition

of the No. 2 seal might not indicate the operability

of the No. 1 seal, Westinghouse

provided guidance for the Braidwood

Station that significantly

enhances operator ability to determine

if immediate

shutdown of an RCP is required or if a more orderly shutdown can be conducted.

Westinghouse

completed

a safety evaluation

and issued Technical Bulletin, NSD-TB-93-01-RO, "Revised Procedures

for RCP Shutdown with No. 1 Seal Leakage Outside Operating

Limits," dated March 30, 1993, to other PWRs that might be affected.

An excerpt from this document is attached to this information

notice (see Attachment

2).

IN 93-84 October 14, 1993 This information

notice requires no specific action or written response.

If you have any questions

about the information

in this notice, please contact one of the technical

contacts listed below or the appropriate

Office of Nuclear Reactor Regulation (NRR) project manager.Brian K. Grimes, Director Division of Operating

Reactor Support Office of Nuclear Reactor Regulation

Technical

contacts:

Steve DuPont, RIII (815) 458-2852 Martin Farber, RIII (708) 790-5774 Chu-Yu Liang, NRR (301) 504-2878 Attachments:

1. Simplified

Braidwood

Seal Water Injection and Leakoff Flow Diagram 2. Excerpt from Westinghouse

Technical Bulletin, NSD-TB-93-01-RO, "Revised Procedures

for RCP Shutdown with No. 1 Seal Leakage Outside Operating

Limits" 3. List of Recently Issued NRC Information

Notices

2=."I 'I'TO SEAL WATER HAT EXCHANGER CO IrRo.D my LEVEL IN STAOPIPE TO REGENERATIWE1 HEAT EXCHANGER DR DRAIN IIMP go 0 Zrt aq ct (D j xD O m 00 MS 0 t I-'.II-h' LAl -NIN sAN ThERL ARRHER HEAT EXCHANGERF"U.t,&ID w SIMPLIFIED

BRAIDWOOD

SEAL WATER INJECTION

AND LEAKOFF FLOW DIAGRAM

I>Attachment

2 IN 93-84 October 20 1993 Page 1 of I Nuclear Services Division Westinghouse

Technical

Bulletin An advisory notice of a recent technical

development

pertining

to th- irts.ation

or operation

of Wastghous&suppi*d

Nudr Plant equipment.

Recipients

shouSd evaluate the Information

and recomnM aIRonl, and initite action wh-r aomopriabt.

P.O. SOX 35, Pltttxzu PA 15o Subject REVISED PROCEDURES

FOR ROP SHUTDOWN WITH NO.'.FAl I FAKA(LF OUTSIDE OPERATING

UMITS.o NSD-TB- 93-01-RO System(s)

REACTOR COOLANT SYSTEM Date 03r3/9 PLant ALL WESTINGHOUSE

REACTOR COOLANT PUMPS WITH lr SO(s) 125 CONTROLLED

LEAKAGE SEALS (See Aftacivelt

B)References

_- -- C , .nA~. cten Is Safety Related Yes 0 Page 1 Of 8 h M L) rilv Vl..I Vr-ij' 1 Q %- W I E2o m e t adgq No O1

BACKGROUND

Years of Westinghouse

RCP operating

experience

has demonstrated

that complete failure of the No. 1 seal is a rare occurrence.

A complete failure is defined as excessive

No. 1 seal leakage in conjunction

with pump bearing/seal

inlet and/or No. 1 leakoff temperatures

approaching

or exceeding

the maximum limits. Current operating

procedures

for failed No. 1 seals direct that the No. I seal leakoff be isolated within 5 minutes and RCP shutdown witlin 30 minutes. These procedures

are specified

in the RCP instruction

books or addenda to the books.After a review of current operating

procedures

and actual operating

experiences

with high and low leaking No. 1 seals, it was concluded

ftht distinct procedures

could specify steps for both emergency

and orderly RCP shutdowns.

The two iems that follow have been incorporated

into the revised procedures

in this technical

bulletin.

As used within this bulletin, the term 'emergefly

m refers to a condition

that is related only to RCP operation

and in no way pertains to emergency

conditions

for plant operation

as defined in a plant hnal Safety Analysis Report (FSAR).I) A damaged No. 1 seal may produce debris or leak at a high enough rate to exceed the injection

rate and introduce

unfiltered, high temperature

reactor coolant into the seals. In the presence of debris. the ability of the No. 2 seal to survive and function as a backup for the No. 1 seal is more favorable

under static conditions.

Thus, it is preferred

to have pump shutdown precede No. 1 seal leakoff isolation.

AJol" W omutfi. Flequd. may be Obhuned fron @fe 0rawc Teb hoffl 412- 963-5634 or (W) 29-5634 Appmvi.T. W. Dunn, Manager, Fied Service & RCP Engineerng

L J. Haper Ener Systes Saes Suport'q7- -t-. N R. F pleiter. mwnA~e CR 4 -& Seal Engineain at tr* gwonmul)Of

corame in W"t "Pon or -an wy reqpo-"kdy

1b "ik&ym dafiQ$ ~iC flf umastamtom

am of mooh irdofflol.

Attachment

2 IN 93-84 October 20, 1993 NSD-TB-93-01-RO 2) High No. 1 seal leakage (> 6.0 9pm) or low No. 1 seal leakage (< 0.8 gpen) can occur while no other RCP parameter

limits are approached

or violated.

In these cases. pump shutdowns

within several hours are within the capabilities

of the RCPs and are more conducive

to orderly plant shutdowns.

The following

new procedures

are provided to address each of four conditions

that irncate No. 1 seal flow outside of the operating

limits (0.8-6.0 gpm). The first three conditiors

address high No. I seal leakage and the fourth condition

addresses

low leakage. Each condition

with its respective

procedure

is specified

below and is summarized

in Attachment

A.PROCEDURES

The following

procedures

supersede

those in the RCP instruction

books or addenda to the books relative to: 1) RCP emergency

operation

and shutdown procedures

for high or low No. 1 seal leakage. Apply the Conditions

1 through 4 procedures

that follow.2) RCP emergency

operation

and shutdown procedure

for No. 2 and No. 3 seals. Apply the procedure

for shutdown specified

under Condition

1 below. The No. 2 and No. 3 seal parameters

tat indicate emergency

operation

remain the same as specified

in the RCP instruction

books.Definitions:

No. 1 seal leakoff indication:

Flowmeter

readout of No. 1 seal leak rate No. 2 seal leakoff indication:

Flowmeter

readout or estimate of No. 2 seal leak rate Total No. 1 Seal Flow: Sum of No. 1 and No. 2 seal leakoff indications

Immediate

Shutdown:

RCP shutdown and isolation

of No. 1 seal leakoff within 5 minutes Orderly Shutdown:

RCP shutdown within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> of higtow No. 1 seal leakoff flow indication

NOTE; A manual plant trip must precede an "Emergency

or 'Ordery RCP shutdown.

This will prevent an automatic

plant tip on a low flows signal which represents

an unnecessary

challenge

to installed

safety systems.

Attachment

2 IN 93-84 October 20, 1993 NSD-TB-93-011-RO If no alternative

Westinghouse

direction

has been provided to address a specfic RCP seal performance

condition

at a plant, the following

are the recommended

shutdown procedures

for No. 1 seal leak rates outside the operating

limits (08-6.0 gpm).Condition

1: a) No. 1 sea leakoff indication

> 6.0 gpcn.b) Increasing

pump beanngfseal

inlet temnperature.

and/or increasing

No. I seal leakoff temperature.

Procedure:

1)Shut down the RCP immediately.

2) Isolate the No. 1 seal leakoff after the RCP has come to a complete stop.3) Monitor component

cooling water (CCW) to ensure adequate flow and manually override automatic

isotation

as required. (Local boiling in the thermal barrier of the affected pump may cause isolation

of the CCW system.)4) Do not restart the pump until the cause of the seal malfunction

has been determined

and corrected.

Condition

2;a)No. I seal leakoff indication

> 6.0 gpm.andfor Total No. 1 seal flow > 6.0 gpm and < 8.0 gpm.b) Ppump bearing/seal

inlet temperature

is not increasing.

c) No. 1 seal leakoff temPerature (if equipped)

is not increasing.

Procedure:

1)Prepare for an orderly pump shutdown to take effect within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> of exceeding

6.0 gpm No. I seal flow. Ensure that seal injection

flow rate is 9 gpm or greater to the affected RCR

Attachment

2 IN 93-84 October 20, 1993 NSD-TB-93-o -RO 2) Continue to monitor the No. 1 seal for further degradation

durng the orderly shutdown.

If the total No. 1 seal flow exceeds 8.0 gpm or temperatures

begn to increase, proceed with immediate

shutdown in accordance

with the Condition

3 procedure.

Otherwise, proceed with the orderly shutdown.3) Secure the pump within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> of exceeding

a No. 1 seal eamkof indication

or total No. 1 seal flow of 6.0 gpn.4) Moritor component

cooing waler (CCOW to ensure adequate flow and manually override as required. (Local boiling in the thermal banier of the affected pump may cause isolaton of the CCW system.)5) No. I seal leakoff may be isolated at the discretion

of operations

to mitigate inventory

loss and to assure that seal injection

flow exceeds total No. 1 seal flow on the affected pump.6) Do not restart the pump until the cause of the seal malfunction

has been determined

and corrected.

Condition

3: a) Total No. 1 seal flow x 8.0 gpm.Procedure:

1) Shut down the RCP immediately.

2) Isolate the No. 1 seal leakoff after the RCP has come to a complete stop.3) Monitor component

cooling water (CCW) to ensure adequate flow and rnanaly override automatic

Isolation

as required. (Local boiling in the thermal banier of the affected pump may cause isolation

of the CCW system.)4) .Do not restart the pump until the cause of the seal malfunction

has been determined

and corected.Condition

4: a) No. I seal leakoff indication

c 0.8 gpm.b) Zero (or negligible)

No. 2 seal leak rate such that total No. 1 seal flow < 0.8 gprn.c) Pump bearingfseal

inlet temperature

and No. 1 seal leakoff temperature (if equipped)

are stable (i.e.. not coninuously

increasing)

and within limits.

Attachient

2 IN 93-84 October 20, 1993 NSD-TB-93"01-RO Procedure:

1) Prepare for an orderly pump shutdown to take effect within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> of violating

the rninimum 0.8 No. 1 seal leak rate Knit 2) Continue to monitor the No. 1 seal for further degradation

duing the orderly shutdown.

If the bw No. 1 sa lealkge reverses to high leakage (> 6.0 gpim) or temperatures

start to increase, proceed with immeciate shutdown in accordance

with the Condcion 1 procedure.

Otherwise, proceed with the orderly shutdown.3) Secure the pump within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> of violasts the rnirnmum 0.8 No. 1 seal leak rate limit.4) Do not restart the pump until the cause of the seal malfunction

has been determined

and corrected.

ATTACHMENT

A No. 1 Leakotf No. 2 Leakoft Total Pump Bearing/Seal

Condition

Indication

Indication

No. 1 Seal Flow Inlet and/or RCP Shutdown No. 1 Leakoff Temp.1 > 6.0 gpm > 6.0 gpm Increasing

Immediate (wilhin 5 minutes)2 > 6.0 gpm > 6.0 and < 8.0 gpm Stable Orderly (within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />)3 > 8.0 gpm Stable or Immediate increasing (within 5 minutes)4 < 0.8 gpm zero < 0.8 gpm Stable Orderly (or negligible) (within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />)Note: Total No. 1 seal flow a No. 1 leakoff plus No. 2 leakoff indications

(0 0 q4 0 oz 3 IF wo I'd Pz n MD 0 a% ID 0 0'-P-a (J.%D rt*r1-U) 0 i2w~,r

Attachment

3 IN 93-84 October 20, 1993 LIST OF RECENTLY ISSUED NRC INFORMATION

NOTICES Information

Date of Notice No. Subject Issuance Issued to 93-83 Potential

Loss of Spent Fuel Pool Cooling Following

A Loss of Coolant Accident (LOCA)10/07/93 All holders for boiling (BWRs).of OLs or CPs water reactors 93-82 93-81 93-80 93-79 93-78 93-77 93-76 93-75 Recent Fuel and Core Performance

Problems in Operating

Reactors Implementation

of Engineering

Expertise on Shift Implementation

of the Revised 10 CFR Part 20 Core Shroud Cracking at Beltline Region Welds in Boiling-Water

Reactors Inoperable

Safety Systems At A Non-Power

Reactor Human Errors that Result in Inadvertent

Transfers of Special Nuclear Material at Fuel Cycle Facilities

Inadequate

Control of Paint and Cleaners for Safety-Related

Equipment Spurious Tripping of Low-Voltage

Power Circuit Breakers with GE'RMS-9 Digital Trip Units 10/12/93 10/12/93 10/08/93 09/30/93 10/04/93 10/04/93 09/21/93 09/17/93 All holders of OLs or CPs for nuclear power reactors and all NRC-approved

fuel suppliers.

All holders of OLs or CPs for nuclear power reactors.All byproduct, source, and and special nuclear material licensees.

All holders of operating licenses or construction

permits for boiling-water

reactors (BWRs).All holders of OLs or CPs for test and research reactors.All nuclear fuel cycle licensees.

All holders of OLs or CPs for nuclear power reactors.All holders of OLs or CPs for nuclear power reactors.OL = Operating

License CP = Construction

Permit

IN 93-84 October 14, 1993 This information

notice requires no specific action or written response.

If you have any questions

about the information

in this notice, please contact one of the technical

contacts listed below or the appropriate

Office of Nuclear Reactor Regulation (NRR) project manager.Original signed bY Brian K. Grimef Brian K. Grimes, Director Division of Operating

Reactor Support Office of Nuclear Reactor Regulation

Technical

contacts: Steve (815)DuPont, RIII 458-2852 Martin Farber, RIII (708) 790-5774 Chu-Yu Liang, NRR (301) 504-2878 Attachments:

1. Simplified

Braidwood

Seal Water Injection and Leakoff Flow Diagram 2. Excerpt from Westinghouse

Technical Bulletin, NSD-TB-93-01-RO, "Revised Procedures

for RCP Shutdown with No. I Seal Leakage Outside Operating

Limits" 3. List of Recently Issued NRC Information

Notices*SEE PREVIOUS CONCURRENCE

OFF NAME DATE*OGCB:DORS

PCWen 07/26/93*SRXB:DSSA

CYLiang 07/26/93*SRI:DRP:RIII

SGDuPont 07/26/93*TECH ED MMejac 07/27/93*SC/DRP:RIII

MJFarber 07/29/93*D/DSSA ACThadani 09/23/93*C/DRP:RIII

BClayton 07/29/93*C/OGCB:DORS

GHMarcus 09/28/93*SC/SRXB:DSSA

MACaruso 08/05-93.4:;tes 10// r 93*C/SRXB:DSSA

RCJones 08/09/93 DOCUMENT NAME: 93-84.IN

IN 93-xx October xx, 1993 This information

notice requires no specific action or written response.

If you have any questions

about the information

in this notice, please contact one of the technical

contacts listed below or the appropriate

Office of Nuclear Reactor Regulation (NRR) project manager.Brian K. Grimes, Director Division of Operating

Reactor Support Office of Nuclear Reactor Regulation

Technical

contacts: Steve DuPont, RIII (815) 458-2852 Martin Farber, RIII (708) 790-5774 Chu-Yu Liang, NRR (301) 504-2878 Attachments:

1. Simplified

Braidwood

Seal Water Injection

and Leakoff Flow Diagram 2. Excerpt from Westinghouse

Technical

Bulletin, NSD-TB-93-01-RO, "Revised Procedures

for RCP Shutdown with No. 1 Seal Leakage Outside Operating Limits" 3. List of Recently Issued NRC Information

Notices*SEE PREVIOUS CONCURRENCE

OFF NAME DATE*OGCB:DORS

PCWen 07/26/93*SRXB:DSSA

CYLiang 07/26/93*SRI:DRP:RIII

SGDuPont 07/26/93*TECH ED MMejac 07/27/93*SC/DRP:RIII

MJFarber 07/29/93*C/DRP:RIII

BClayton 07/29/93*SC/SRXB:DSSA

MACaruso 08/05/93*C/SRXB:DSSA

RCJones 08/09/93*D/DSSA ACThadani 09/23/93 DOCUMENT NAME: C/OGCB:DOi,_

D/DORS PcEY GHMarcu$s&

!:' BKGrimesng

P4it P (so-.-qI),MAM

WRCPSEAL.We

0fFnfS T HE 049 /9o o3eevat lro 1hE NftC 41TA03rA*

THS g*Sr*qWS C _ %,A _ } U. .O ' 0a* W S~--.W""i r. MOFbV4' ( H& S5ef ) vvia %;nfgnri&

dr i tw LWI44n44t

et-K'%$ U -te pnvi.d %e ,W Tec6-,.p^

MoTtwcdL.

?et hk~

IN 93-xx September

xx, 1993 This information

notice requires no specific action or written response.

If you have any questions

about the information

in this notice, please contact one of the technical

contacts listed below or the appropriate

Office of Nuclear Reactor Regulation (NRR) project manager.Brian K. Grimes, Director Division of Operating

Reactor Support Office of Nuclear Reactor Regulation

Technical

contacts: Steve DuPont, RIII (815) 458-2852 Martin Farber, RIII (708) 790-5774 Chu-Yu Liang, NRR (301) 504-2878 Attachments:

1. Simplified

Braidwood

Seal Water Injection

and Leakoff Flow Diagram 2. Excerpt from Westinghouse

Technical

Bulletin, NSD-TB-93-01-RO, 'Revised Procedures

for RCP Shutdown with No. 1 Seal Leakage Outside Operating Limits'3. List of Recently Issued NRC Information

Notices*SEE PREVIOUS CONCURRENCE

OFF NAME DATE*OGCB:DORS

PCWen 07/26/93*SRXB:DSSA

CYLiang 07/26/93*SRI:DRP:RIII

SGDuPont 07/26/93*TECH ED MMejac 07/27/93*SC/DRP:RIII

MJFarber 07/29/ AF D/DSS ai' _ACThadani 09/2_/93 DOCUMENT NAME:*C/DRP:RIII

BClayton 07/29/93 C/OGCB:DORS

GHMarcus 09/ /93 WRCPSEAL.WEN

  • SC/SRXB:DSSA

MACaruso 08/05/93*C/SRXB:DSSA

RCJones 08/09/93 D/DORS BKGrimes 09/ /93 Brian K. Grimes, Director Division of Operating

Reactor Support Office of Nuclear Reactor Regulation

Technical

contacts: Steve DuPont, RIII (815) 458-2852 Martin Farber, RIII (708) 790-5774 Chu-Yu Liang, NRR (301) 504-2878 Attachments:

1. Simplified

Braidwood

Seal Water Injection

and Leakoff Flow Diagram 2. Excerpt from Westinghouse

Technical

Bulletin, NSD-TB-93-01-RO, 'Revised Procedures

for RCP Shutdown with No. 1 Seal Leakage Outside Operating Limits" 3. List of Recently Issued NRC Information

Notices*SEE PREVIOUS CONCURRENCE

OFF *OGCB:DORS

  • SRXB:DSSA

NAME PCWen CYLiang DATE 07/26/93 O7/26/93 STW RD I :I I C/R J.:RIII MJFarber 4 BClayton 07ial/93 J 07/< /93 we 74FCoo .7,6/93 D/DSSA C/OGCB:DORS

ACThadani

GHMarcus 07/ /93 07/ /93*SRI:DRP:RIII

SGDuPont 07/26/93 ,JSRXB:DSSA

C ones?/ /93*TECH ED MMejac 07/27/93 SC/SRXB:DSSAL

MACaruso `y r r/4r/93 / r D/DORS BKGrimes 07/ /93

\s-/Martin Farber, RIII (708) 790-5774 Chu-Yu Liang, NRR (301) 504-2878 Attachments:

1. Braidwood

Seal Water Injection

and Leakoff Flow Diagram..r-

2. Excerpt from Westinghouse

Technical

Bulletin, NSD-TB-93-01-RO, "Revised Procedures

for RCP Shutdown with No. 1 Seal Leakage Outside Operating Limits" 3. -List-ef Recently IssueFd4RC-4nf-4fmation.-Not-ies-.-

OFF NAME DATE OCB:DORS PCWen 07/a6/93 SRXB L SA S I RIII CYLiang _ SGDuPont MR-07/;xb/93 V~ 07/Vb/93 T1-e'A.@TECH ED MMejac *M i 07/1.7/93 SC/SRXB:DSSA

MACaruso 07/ /93 SC/DRP:RIII

MJFarber 07/ /93 C/DRP:RIII

BClayton 07/ /93 C/SRXB:DSSA

RCJones 07/ /93 D/DSSA ACThadani 07/ /93 C/OGCB:DORS

GHMarcus 07/ /93 D/DORS BKGrimes 07/ /93! .