ML100710113 | 10 March 2010 | Whipple V NRC/ADM/DC | Task Order No. 002 Under Delivery Order No. NRC-03-10-070 | Acceptance Review |
ML100710114 | 10 March 2010 | Whipple V NRC/ADM/DC | Task Order No. 002 Under Delivery Order No. NRC-03-10-070 | Acceptance Review |
ML101320187 | 18 May 2010 | Kimberly Green License Renewal Projects Branch 2 | Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application | RAI |
ML101380614 | 24 May 2010 | Kimberly Green License Renewal Projects Branch 2 | Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Scoping and Screening Methodology | RAI |
ML101540419 | 14 June 2010 | Ferrer N License Renewal Projects Branch 2 | Letter Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Aging Management Programs | RAI |
ML101620187 | 21 June 2010 | Ferrer N License Renewal Projects Branch 2 | Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Aging Management Programs | RAI |
ML101690130 | 29 June 2010 | Ferrer N License Renewal Projects Branch 2 | Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Aging Management Programs | RAI |
ML101760104 | 6 July 2010 | Ferrer N License Renewal Projects Branch 2 | Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application | RAI |
ML101760243 | 14 July 2010 | Ferrer N License Renewal Projects Branch 2 | RAI Related to the Review of the DCPP LRA - Aging Management Programs | RAI |
ML101830131 | 15 July 2010 | Ferrer N License Renewal Projects Branch 2 | Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Scoping and Screening and Aging Management Review | RAI |
ML101890832 | 16 July 2010 | Ferrer N License Renewal Projects Branch 2 | Audit Report Regarding the Diablo Canyon Nuclear Power Plant License Renewal Application Scoping and Screening Methodology | Other |
ML101870088 | 19 July 2010 | Ferrer N License Renewal Projects Branch 2 | Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Aging Management Programs | RAI |
ML101830144 | 20 July 2010 | Ferrer N License Renewal Projects Branch 2 | RAI Related to the Review of the DCPP LRA - Aging Management Programs and Aging Management Review | RAI |
ML101880255 | 20 July 2010 | Ferrer N License Renewal Projects Branch 2 | RAI Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Reactor Vessel Internals | RAI |
ML101900470 | 20 July 2010 | Ferrer N License Renewal Projects Branch 2 | Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 & 2, LRA (Tac Nos. ME2896, and ME2897) - Scoping and Screening | RAI |
ML101880735 | 22 July 2010 | Ferrer N License Renewal Projects Branch 2 | Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application - Aging Management Review and Aging Management Programs | RAI |
ML101890021 | 22 July 2010 | Ferrer N License Renewal Projects Branch 2 | Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application - Aging Management Review and Time Limited Aging Analysis | RAI |
ML102000488 | 3 August 2010 | Ferrer N License Renewal Projects Branch 2 | Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Aging Management Review and Aging Management Programs | RAI |
ML102040251 | 9 August 2010 | Ferrer N License Renewal Projects Branch 2 | RAI Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Scoping and Screening and Aging Management Review | RAI |
ML101690321 | 11 August 2010 | Ferrer N License Renewal Projects Branch 2 | Audit Report for Plant Aging Management Programs for DCPP, Units 1 and 2 | Other |
ML101960644 | 13 August 2010 | David Wrona License Renewal Projects Branch 2 | Safety Project Manager Change for the License Renewal Project for Diablo Canyon Nuclear Power Plant (TAC ME2896 and ME2897) | Other |
ML102170524 | 25 August 2010 | Ferrer N License Renewal Projects Branch 2 | Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Metal Fatigue | RAI |
ML102010700 | 26 August 2010 | Ferrer N License Renewal Projects Branch 2 | Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Time Limited Aging Analyses and Aging Management Programs | RAI |
ML102240277 | 26 August 2010 | Ferrer N License Renewal Projects Branch 2 | Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC ME2896 and ME2897) - Aging Management Programs | RAI |
ML102290542 | 30 August 2010 | Ferrer N License Renewal Projects Branch 2 | Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Aging Management Review and Time Limited Aging Analyses | RAI |
ML102360749 | 1 September 2010 | Ferrer N License Renewal Projects Branch 2 | Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Aging Management Programs | RAI |
ML102430027 | 13 September 2010 | Ferrer N License Renewal Projects Branch 2 | Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. Me 2869 and ME2897) - Scoping and Screening | RAI |
ML102520278 | 17 September 2010 | Ferrer N License Renewal Projects Branch 2 | RAI Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Scoping and Screening | RAI |
ML102460050 | 17 September 2010 | Ferrer N License Renewal Projects Branch 2 | RAI Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 & ME2897) Aging Management Programs | RAI |
ML102510297 | 23 September 2010 | Ferrer N License Renewal Projects Branch 2 | RAI Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Time Limited Aging Analyses | RAI |
ML102460151 | 28 September 2010 | Ferrer N License Renewal Projects Branch 2 | Summary of Telephone Conference Call Held on 9/2/10 Between Us NRC and Pacific Gas and Electric Company Concerning the Response to RAIs Related to the Diablo Canyon Nuclear Power Plant Units 1 and 2 LRA | RAI |
ML102520264 | 29 September 2010 | Ferrer N License Renewal Projects Branch 2 | Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application - Aging Management Review | RAI |
ML102660541 | 30 September 2010 | Ferrer N License Renewal Projects Branch 1 | Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Fire Protection | RAI |
ML102980689 | 2 November 2010 | Ferrer N License Renewal Projects Branch 2 | Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Time Limited Aging Analysis | RAI |
ML102930630 | 3 November 2010 | Ferrer N License Renewal Projects Branch 2 | Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application - Aging Management Programs | RAI |
ML103481013 | 20 December 2010 | Ferrer N License Renewal Projects Branch 1 | Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Aging Management Program and Time Limited Aging Analysis | RAI |
ML103410434 | 20 December 2010 | Ferrer N License Renewal Projects Branch 2 | Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC ME2896 and ME2897) - Time Limited Aging Analysis | RAI |
ML103490417 | 10 January 2011 | Ferrer N License Renewal Projects Branch 2 | 12/1/10 Summary of Telephone Conference Call Held Btw the USNRC and Pacific Gas and Electric Company Concerning Draft Request for Additional Information Related to the Diablo Canyon Nuclear Power Plant, Units 1 and 2, LRA | Draft RAI |
ML103560321 | 10 January 2011 | Ferrer N License Renewal Projects Branch 2 | 12/8/10 Summary of Telephone Conference Call Held Btw the USNRC and Pacific Gas and Electric Company Concerning Requests for Additional Information Response Related to the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Ap | RAI |
ML103430623 | 11 January 2011 | Ferrer N License Renewal Projects Branch 2 | Summary of Telephone Conference Call Held Between NRC and PG&E Concerning Request for Additional Information Related Tot the Diablo Canyon Nuclear Power Plant, Units 1 and 2, LRA (TAC Nos. ME2896 & ME2897) | RAI |
ML103550680 | 11 January 2011 | Ferrer N License Renewal Projects Branch 2 | 12/9/10 Summary of Telephone Conference Call Held Between NRC and PG&E Concerning Requests for Additional Information Response Related to the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 & M | RAI |
ML110100588 | 25 January 2011 | Ferrer N License Renewal Projects Branch 2 | Summary of Telephone Conference Call Held on December 16, 2010, Between the NRC and Pacific Gas and Electric Company Concerning RAI Related to the Diablo Canyon Nuclear Power Plant, Units 1 and 2, LRA | RAI |
ML110110261 | 25 January 2011 | Ferrer N License Renewal Projects Branch 2 | Summary of Telephone Conference Call Held on 12/22/2010, Between the NRC and Pacific Gas and Electric Company Concerning Requests for Additional Information Related to the Diablo Canyon Nuclear Power Plant, Units 1 and 2, LRA (TAC Nos. ME28 | RAI |
ML110120418 | 7 February 2011 | Ferrer N License Renewal Projects Branch 2 | Summary of Telephone Conference Call Held with NRC and PG&E Concerning Requests for Additional Information Response Related to the Diablo Canyon Nuclear Power Plant, Units 1 and 2, LRA (TAC Nos. ME2896 & ME2897) | RAI |
ML110140008 | 7 February 2011 | Ferrer N License Renewal Projects Branch 2 | 01/04/11 Summary of Telephone Conference Call Held Between the NRC and PG&E Company Concerning Requests for Additional Information Related to the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 | RAI |
ML110410528 | 14 February 2011 | Ferrer N Meaburn G License Renewal Projects Branch 2 | Summary of Telephone Conference Call Held on 1/19/11 Between the USNRC and PG&E Concerning Open Items Related to the Diablo Canyon Nuclear Power Plant, Units 1 and 2, Safety Evaluation Report | Approval |
ML110460718 | 18 February 2011 | Ferrer N License Renewal Projects Branch 2 | January 25, 2011, Summary of Telephone Conference Call Held Between NRC and PG&E Concerning Open Items Related to the Diablo Canyon Nuclear Power Plant, Units 1 and 2, SER (TAC Nos. ME2896 & 2897) | Other |
ML110590749 | 17 March 2011 | Ferrer N License Renewal Projects Branch 2 | Summary of Telephone Conference Calls Held on February 2 and 4, 2011, Btw the USNRC and Pacific Gas and Electric Company Concerning RAIs Related to the Diablo Canyon Nuclear Power Plant, Units 1 and 2, LRA | RAI |
ML110840459 | 11 April 2011 | Ferrer N License Renewal Projects Branch 2 | Summary of Telephone Conference Calls Held on 2/28/11 and 3/17/11 Btw the USNRC and Pacific Gas and Electric Company Concerning RAIs Related to the Diablo Canyon Nuclear Power Plant, Units 1 and 2, LRA | RAI |
ML15037A540 | 24 February 2015 | Brian Wittick License Renewal Projects Branch 2 | Project Manager Change for the License Renewal of Diablo Canyon Power Plant, Units 1 and 2, (TAC Nos. MF4019 and MF4020) | Other |