ML23122A302 | 20 July 2023 | Issuance of Amendments Technical Specifications 2.1.1 and 4.2.1 to Allow a Previously Irradiated Accident Tolerant Fuel Lead Test Assembly to Be Further Irradiated in Unit No. 2 | Anticipated operational occurrence |
ML22095A270 | 12 May 2022 | Issuance of Amendment Nos. 227, 227, 229, 229, and 245, Respectively, Regarding Adoption of TSTF 273, Safety Function Determination Program Clarifications | Ultimate heat sink |
ML22090A086 | 29 April 2022 | Amendments to Adopt TSTF-541,Rev.2,Add Exceptions to Surveillance Requirements for Valves,Dampers Locked in Actuated Position | Safe Shutdown Water Inventory Control Cyber Security Surveillance Frequency Control Program Safeguards Contingency Plan Recently irradiated fuel Fire Protection Program |
RS-22-049, Constellation Energy Generation, LLC, Supplemental Information to Correct Typographical Errors in Constellation'S Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for | 4 April 2022 | Constellation Energy Generation, LLC, Supplemental Information to Correct Typographical Errors in Constellation'S Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for V | |
ML21347A038 | 13 January 2022 | Issuance of Amendments to Revise Reactor Coolant Leakage Requirements | Packing leak Cyber Security Pressure and Temperature Limits Report Surveillance Frequency Control Program Process Control Program Safeguards Contingency Plan Pressure Boundary Leakage Fire Protection Program Unidentified leakage |
JAFP-21-0089, Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position | 27 September 2021 | Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position | Safe Shutdown Reactor Vessel Water Level Ultimate heat sink Stroke time Water Inventory Control Surveillance Frequency Control Program Operability Determination Control of Heavy Loads Fuel cladding Recently irradiated fuel Scaffolding |
ML21060B281 | 2 April 2021 | Issuance of Amendments Nos. 221, 221, 224, and 224 Regarding Technical Specifications 3.8.1, AC Sources-Operating | Safe Shutdown Stroke time Anticipated operational occurrence Surveillance Frequency Control Program Nonconservative Technical Specifications |
ML21013A005 | 4 February 2021 | Issuance of Amendments to Adopt Technical Specifications Task Traveler TSTF-568, Revise Applicability of BWR/4 TS 3.6.2.5 and TS 3.6.3.2 | Cyber Security Surveillance Frequency Control Program Safeguards Contingency Plan Fire Protection Program |
ML20317A001 | 28 December 2020 | Non-Proprietary, Issuance of Amendment Nos. 219, 219, 223, and 223, Revise Loss-of-Coolant Accident Methodology in TS 5.6.5, Core Operating Limits Report (COLR) | Coatings |
ML21008A405 | 17 December 2020 | Byron/Braidwood Stations - Revision 18 to Updated Final Safety Analysis Report, Chapter 16, Technical Specifications | Incorporated by reference |
ML20246G865 | 21 September 2020 | Issuance of Amendment Nos. 222 and 222 One-Time Extension of Unit No. 2 Steam Generator Inspections (COVID-19) | Pandemic Coronavirus COVID-19 |
ML20167A007 | 11 September 2020 | R. E. Ginna - Issuance of Amendment Nos. 216, 216, 220, 220, and 143 - Adoption of TSTF-567, Rev. 1, Add Containment Sump Technical Specifications to Address GSI-191 Issues | Surveillance Frequency Control Program Fire Protection Program |
ML20086M288 | 2 April 2020 | Correction of Amendments Nos. for Amendments Revising Instrument Testing and Calibration Definitions | Surveillance Frequency Control Program |
RS-19-115, Supplement to Application to Revise Braidwood Station and Byron Station Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b | 20 December 2019 | Supplement to Application to Revise Braidwood Station and Byron Station Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b | |
ML19190A081 | 28 August 2019 | Issuance of Amendments Regarding Limiting Condition of Operation for Inoperability of Snubbers | Probabilistic Risk Assessment Large early release frequency Earthquake |
RS-19-018, Supplement to Application to Revise Technical Specifications to Adopt Risk Informed Completion Times | 14 February 2019 | Supplement to Application to Revise Technical Specifications to Adopt Risk Informed Completion Times | Safe Shutdown High Radiation Area Ultimate heat sink Probabilistic Risk Assessment Surveillance Frequency Control Program Power Operated Valves Power change |
RS-18-102, License Amendment Request for a One-Time Extension to Technical Specification 3.8.1, AC Sources-Operating, Required Action A.2 | 10 August 2018 | License Amendment Request for a One-Time Extension to Technical Specification 3.8.1, AC Sources-Operating, Required Action A.2 | Hot Short Safe Shutdown High winds Ultimate heat sink Mission time Anticipated operational occurrence Tornado Missile Internal Flooding Probabilistic Risk Assessment Multiple Spurious Operation Qualified Offsite Circuit FLEX Fukushima Dai-Ichi Tornado Missile Protection Large early release frequency TORMIS Earthquake Offsite Circuit |
ML18067A181 | 4 June 2018 | Correction to Technical Specification Amendment Identification Format | Time of Discovery Shutdown Margin High Radiation Area Hydrostatic Nondestructive Examination Surveillance Frequency Control Program Pressure Boundary Leakage Recently irradiated fuel Power change |
ML16180A251 | 1 August 2016 | Issuance of Amendments Regarding Use of Optimized Zirlo as Fuel Cladding Material | Shutdown Margin Anticipated operational occurrence Exemption Request Fuel cladding |
RS-16-034, License Amendment Request and 10 CFR 50.12 Exemption Request for the Use of Optimized Zirlo Fuel Rod Cladding | 23 February 2016 | License Amendment Request and 10 CFR 50.12 Exemption Request for the Use of Optimized Zirlo Fuel Rod Cladding | Shutdown Margin Exemption Request Fuel cladding |
ML15307A776 | 21 December 2015 | Braidwood - Issuance of Amendments Regarding Installation of New Low Degraded Voltage Relays and Timers on the 4.16 Kv Engineered Safety Features (ESF) Buses (CAC Nos. MF4051 - MF4054) | Safe Shutdown Surveillance Frequency Control Program |
ML15286A276 | 19 November 2015 | Technical Specifications | Time of Discovery Shutdown Margin Reactor Vessel Water Level High Radiation Area Ultimate heat sink Grab sample Offsite Dose Calculation Manual Post Accident Monitoring Hydrostatic Nondestructive Examination Pressure and Temperature Limits Report Surveillance Frequency Control Program Annual Radiological Environmental Operating Report Process Control Program Pressure Boundary Leakage Recently irradiated fuel Fire Protection Program Power change Unidentified leakage |
ML15232A441 | 28 October 2015 | Issuance of Amendments to Utilize WCAP-16143-P, Revision 1 Reactor Vessel Closure Head/Vessel Flange Requirements Evaluation for Byron/Braidwood Units 1 and 2, Dated October 2014 | Safe Shutdown Pressure and Temperature Limits Report Fire Protection Program |
ML15268A486 | 6 October 2015 | Correction of Amendments Adopting Technical Specification Task Force Traveler TSTF-523 (TAC Nos. MF4436-MF4446) | Surveillance Frequency Control Program |
ML15141A058 | 28 July 2015 | Issuance of Amendments Regarding Emergency Action Level Schemes (TAC Nos. MF4232-MF4251) | Fuel cladding |
ML14323A522 | 8 April 2015 | Issuance of Amendments Regarding the Emergency Plan Definition of Annual Training | |
RS-14-337, Units 1 & 2 - License Amendment Request for Diesel Generator Load Rejection Surveillance Requirement | 18 December 2014 | Units 1 & 2 - License Amendment Request for Diesel Generator Load Rejection Surveillance Requirement | Safe Shutdown Anticipated operational occurrence Surveillance Frequency Control Program Offsite Circuit |
ML14239A427 | 7 December 2014 | Issuance of Amendments to Clarify Technical Specification 3.3.1, Reactor Trip System Instrumentation, and TS 3.3.2, Engineered Safety Feature Actuation System Instrumentation | Safe Shutdown Fire Protection Program |
RS-14-285, License Amendment Request to Revise Technical Specifications 3.7.9, Ultimate Heat Sink(Uhs) | 24 November 2014 | License Amendment Request to Revise Technical Specifications 3.7.9, Ultimate Heat Sink(Uhs) | Unanalyzed Condition Ultimate heat sink Hydrostatic Surveillance Frequency Control Program Earthquake |
ML13311B481 | 21 July 2014 | Issuance of Amendments to Revise Technical Specifications Section 3.5.3 | Safe Shutdown Fire Protection Program |
ML14085A532 | 21 July 2014 | Issuance of Amendments Adoption of TSTF-522 Ventilation System Surveillance Requirements | Safe Shutdown Cyber Security Surveillance Frequency Control Program Safeguards Contingency Plan Fire Protection Program |
ML13281A000 | 7 February 2014 | Issuance of Amendments Regarding Measurement Uncertainty Recapture Power Uprate | Safe Shutdown Boric Acid Ultimate heat sink Anticipated operational occurrence Weld Overlay Internal Flooding Hydrostatic Coatings Aging Management Surveillance Frequency Control Program Time Critical Operator Action Battery sizing License Renewal Fuel cladding Recently irradiated fuel Fire Protection Program Flow Induced Vibration GOTHIC Power Uprate Stretch Power Uprate Measurement Uncertainty Recapture |
RS-13-137, Application to Revise Technical Specifications to Adopt TSTF-522, Revise Ventilation System Surveillance Requirements to Operate for 10 Hours Per Month, Using the Consolidated Line Item Improvement Process | 3 September 2013 | Application to Revise Technical Specifications to Adopt TSTF-522, Revise Ventilation System Surveillance Requirements to Operate for 10 Hours Per Month, Using the Consolidated Line Item Improvement Process | Surveillance Frequency Control Program Recently irradiated fuel |
RS-13-175, Bryon, Units 1 and 2, License Amendment Request to Revise Technical Specifications Section 3.7.2, Main Steam Isolation Valves (Msivs). | 21 August 2013 | Bryon, Units 1 and 2, License Amendment Request to Revise Technical Specifications Section 3.7.2, Main Steam Isolation Valves (Msivs). | Safe Shutdown Earthquake Earthquake |
RS-12-009, License Amendment Request - Diesel Generator Steady State Maximum Frequency and Adoption of Technical Specifications Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel | 1 May 2012 | License Amendment Request - Diesel Generator Steady State Maximum Frequency and Adoption of Technical Specifications Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel | Safe Shutdown Probabilistic Risk Assessment Surveillance Frequency Control Program Fuel cladding Offsite Circuit |
RS-12-028, Application to Revise Technical Specifications to Adopt TSTF-510, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection. | 22 March 2012 | Application to Revise Technical Specifications to Adopt TSTF-510, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection. | Non-Destructive Examination Nondestructive Examination |
RS-12-023, License Amendment Request to Revise Tech Specs Sections 5.5.9, Steam Generator (SG) Program, and TS 5.6.9, Steam Generator (SG) Tube Inspection Report, for Permanent Alternate Repair Criteria | 20 March 2012 | License Amendment Request to Revise Tech Specs Sections 5.5.9, Steam Generator (SG) Program, and TS 5.6.9, Steam Generator (SG) Tube Inspection Report, for Permanent Alternate Repair Criteria | Safe Shutdown Earthquake Nondestructive Examination |
RS-11-136, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications (TS) 3.3.1 | 2 September 2011 | Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications (TS) 3.3.1 | |
ML111790032 | 23 June 2011 | Request for License Amendment Regarding Measurement Uncertainty Recapture (Mur) Power Uprate, Attachment 2B, Markup of Proposed Operating License and Technical Specifications Pages | Safe Shutdown Recently irradiated fuel Fire Protection Program |
RS-11-070, Supplement to Information Supporting Request for License Amendment Regarding Ultimate Heat Sink | 4 May 2011 | Supplement to Information Supporting Request for License Amendment Regarding Ultimate Heat Sink | Safe Shutdown Ultimate heat sink Anticipated operational occurrence Surveillance Frequency Control Program |
RS-11-035, Additional Information Supporting Request for License Amendment Regarding Ultimate Heat Sink | 16 March 2011 | Additional Information Supporting Request for License Amendment Regarding Ultimate Heat Sink | Safe Shutdown Ultimate heat sink Anticipated operational occurrence |
ML110620148 | 10 March 2011 | Summary of Meeting with Exelon Generation Company, LLC to Discuss the Request for Additional Information Related to License Amendment Regarding the Ultimate Heat Sink | Ultimate heat sink |
ML103270435 | 21 December 2010 | Tech Spec Pages for Braidwood and Byron Amendment Large Break Loss-of-Coolant Accident Analysis Using Astrum | |
ML103270445 | 21 December 2010 | Tech Spec Pages for Braidwood and Byron Amendment Large Break Loss-of-Coolant Accident Analysis Using Astrum | |
RS-10-197, License Amendment Request to Revise Technical Specifications (TS) Sections 5.5.9, Steam Generator Program, and TS 5.6.9, Steam Generator Tube Inspection Report, for Temporary Alternate Repair Criteria | 14 December 2010 | License Amendment Request to Revise Technical Specifications (TS) Sections 5.5.9, Steam Generator Program, and TS 5.6.9, Steam Generator Tube Inspection Report, for Temporary Alternate Repair Criteria | Safe Shutdown Earthquake Nondestructive Examination Finite Element Analysis |
RS-10-184, Additional Information Supporting Request for License Amendment Regarding Ultimate Heat Sink | 8 November 2010 | Additional Information Supporting Request for License Amendment Regarding Ultimate Heat Sink | Ultimate heat sink |
RS-10-114, License Amendment Request Regarding Low Temperature Overpressure Protection and Loss of Decay Heat Removal | 29 June 2010 | License Amendment Request Regarding Low Temperature Overpressure Protection and Loss of Decay Heat Removal | |
RS-10-052, License Amendment Request for an Extension of the Inspection Interval for Reactor Coolant Pump Flywheels Using the Consolidated Line Item Improvement Process | 29 March 2010 | License Amendment Request for an Extension of the Inspection Interval for Reactor Coolant Pump Flywheels Using the Consolidated Line Item Improvement Process | Probabilistic Risk Assessment Incorporated by reference |
RS-10-020, Additional Information Supporting Request for License Amendment Regarding Ultimate Heat Sink | 25 January 2010 | Additional Information Supporting Request for License Amendment Regarding Ultimate Heat Sink | Ultimate heat sink |