Semantic search

Jump to navigation Jump to search
 Issue dateTitleTopic
IR 05000293/19990058 October 1999Insp Rept 50-293/99-05 on 990726-0905.Violations Noted.Major Areas Inspected:Operations,Engineering,Maint & Plant SupportHigh Radiation Area
Probabilistic Risk Assessment
Condition Adverse to Quality
Battery sizing
IR 05000271/19990117 October 1999Insp Rept 50-271/99-11 on 990809-27.No Violations Noted. Major Areas Inspected:Maint & EngineeringUnanalyzed Condition
Temporary Modification
Operability Determination
Operability Assessment
PNO-I-99-043, on 990916,Hurricane Floyd Was Approaching Ccnpp,Sgs,Hcgs & Ocnpp.Hurricane Was Centered at Latitude 36.0 North & Longitude 76.6 West & Moving north-northeast at Approx 25 Mph.Plants Remain at Power16 September 1999PNO-I-99-043:on 990916,Hurricane Floyd Was Approaching Ccnpp,Sgs,Hcgs & Ocnpp.Hurricane Was Centered at Latitude 36.0 North & Longitude 76.6 West & Moving north-northeast at Approx 25 Mph.Plants Remain at Power
IR 05000245/199900814 September 1999Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant SupportFitness for Duty
High Radiation Area
Grab sample
Enforcement Discretion
Temporary Modification
Locked High Radiation Area
Missed surveillance
Foreign Material Exclusion
Operability Determination
Fire Watch
Grace period
Operability Assessment
IR 05000271/199900613 September 1999Insp Rept 50-271/99-06 on 990621-0801.Noncited Violation Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant SupportHigh Radiation Area
Temporary Modification
IR 05000293/199900427 August 1999Insp Rept 50-293/99-04 on 990610-0725.Non-cited Violations Noted.Major Areas Inspected:Aspects of Licensee Operations, Engineering,Maint & Plant SupportStroke time
Temporary Modification
IR 05000423/199900727 August 1999Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing ProblemsBoric Acid
Temporary Modification
Operability Determination
ML20211H08919 August 1999Notice of Violation from Insp on 990628-0811.Violation Noted:Periodic Assessment Conducted for Period of November 1996 Through May 1998 Did Not Adequately Evaluate Maint Activities as Listed
IR 05000271/199901219 August 1999Insp Rept 50-271/99-12 on 990628-0811.Violation Noted.Major Areas Inspected:Maint Rule Periodic Evaluation Required by 10CFR50.65(a)(3)Probabilistic Risk Assessment
Maintenance Rule Program
IR 05000029/19990024 August 1999Insp Rept 50-029/99-02 on 990411-0714.One Violation Noted & Being Treated as Ncv.Major Areas Inspected:Safe Operation of Sf Pool,Radiological Controls,Organization & Mgt Controls & Auditing & C/As for Decommissioning ActivitiesHigh Radiation Area
IR 05000271/199900526 July 1999Insp Rept 50-271/99-05 on 990510-0620.Noncited Violations Identified.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant SupportSafe Shutdown
Offsite Dose Calculation Manual
Probabilistic Risk Assessment
Foreign Material Exclusion
Scram Discharge Volume
Annual Radiological Environmental Operating Report
IR 05000336/199900619 July 1999Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant SupportHigh Radiation Area
Non-Destructive Examination
Nondestructive Examination
Temporary Modification
Foreign Material Exclusion
Operability Determination
Maintenance Rule Program
Liquid penetrant
Through-Wall Leak
Downpower
ML20209G2339 July 1999Insp Rept 50-293/99-03 on 990419-0609.Violations Noted & Being Treated as non-cited Violations.Major Areas Inspected: Operations,Maint,Engineering & Plant Support.Response to Main Transformer Fire by Fire Brigade Members Was GoodFitness for Duty
High Radiation Area
Temporary Modification
Locked High Radiation Area
Condition Adverse to Quality
Job Performance Measure
Foreign Material Exclusion
Continuous fire watch
Scaffolding
PNO-I-99-030, on 990630,licensee Notified NRC Region I That Shipping Container Loaded with Internally Contaminated Vacuum Cleaning Device,Used at Maine Yankee for Asbestos Removal,Was Damaged.No Radioactive Matl Was Released30 June 1999PNO-I-99-030:on 990630,licensee Notified NRC Region I That Shipping Container Loaded with Internally Contaminated Vacuum Cleaning Device,Used at Maine Yankee for Asbestos Removal,Was Damaged.No Radioactive Matl Was Released
IR 05000271/199900314 June 1999Insp Rept 50-271/99-03 on 990329-0509.Non-cited Violations Noted.Major Areas Inspected:Operations,Engineering, Maintenance,Plant Support & Review of Maint Rule Program ImplementationTime of Discovery
Probabilistic Risk Assessment
Missed surveillance
Foreign Material Exclusion
Maintenance Rule Program
Grace period
IR 05000336/199821910 June 1999Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation
IR 05000309/19990017 June 1999Insp Rept 50-309/99-01 on 990214-0513.No Violations Noted. Major Areas Inspected:Aspects of Licensee Operations,Maint, Engineering & Plant SupportGrab sample
Offsite Dose Calculation Manual
Foreign Material Exclusion
IR 05000245/19990054 June 1999Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1
IR 05000271/19990044 June 1999Insp Rept 50-271/99-04 on 990426-28.No Violations Noted. Major Areas Inspected:Performance of Emergency Response OrganizationGrace period
ML20207G1213 June 1999Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant SupportSafe Shutdown
Unanalyzed Condition
Boric Acid
High winds
Shutdown Margin
Offsite Dose Calculation Manual
Enforcement Discretion
Coatings
Reserve Station Service Transformer
Operating Basis Earthquake
Temporary Modification
Emergency Lighting
Missed surveillance
Foreign Material Exclusion
Annual Radiological Environmental Operating Report
Process Control Program
Operability Determination
Battery sizing
Earthquake
Downpower
PNO-I-99-026A, on 990518,main Transformer Was Damaged During Testing of Replacement Bushing While Unit Was in Refueling Outage.Current Refueling Outage Was Originally Scheduled to Be Completed on 990607,with Return to Full Power Operation1 June 1999PNO-I-99-026A:on 990518,main Transformer Was Damaged During Testing of Replacement Bushing While Unit Was in Refueling Outage.Current Refueling Outage Was Originally Scheduled to Be Completed on 990607,with Return to Full Power Operation
IR 05000271/199930228 May 1999NRC Operator Licensing Exam Rept 50-271/99-302(including Completed & Graded Tests) for Tests Administered on 990510-11Safe Shutdown
Half scram
Squib
Job Performance Measure
Scram Discharge Volume
Fuel cladding
Failure to Scram
ML20207F15225 May 1999Notice of Violation from Investigation Rept 1-94-021 on 940506-960329.Violation Noted:Between 740831-910407,licensee Made Changes to Facility Described in Safety Analysis Rept for Refueling Core Offloads Without Performing Evaluation
ML20196K26224 May 1999EN-99-020:on 980525,notice of Violation & Exercise of Enforcement Discretion Will Be Issued to Licensee.Action Based on Severity Level III Problem Consisting of Four Individual Violations Involving Refueling OutageEnforcement Discretion
PNO-I-99-026, on 990518,fire Occurred at Pilgrim Station in Main Electrical Transformer.Licensee Requested off-site Firefighting Assistance.Resident Inspector Responded to Site Upon Notification of Event.Licensee Issued Press Release19 May 1999PNO-I-99-026:on 990518,fire Occurred at Pilgrim Station in Main Electrical Transformer.Licensee Requested off-site Firefighting Assistance.Resident Inspector Responded to Site Upon Notification of Event.Licensee Issued Press Release
IR 05000293/199900217 May 1999Insp Rept 50-293/99-02 on 990308-0418.Two Level 4 Violations Occurred & Being Treated as Ncv.Major Areas Inspected: Operations,Maint,Engineering & Plant SupportLocked High Radiation Area
Power change
PNO-I-99-022, on 990509,Millstone Unit 2 Established Reactor Criticality.Nrc Staff Providing Augmented Insp Coverage of Restart Activities,Including round-the-clock Observations of Licensee Activities During Key Operational Evolutions11 May 1999PNO-I-99-022:on 990509,Millstone Unit 2 Established Reactor Criticality.Nrc Staff Providing Augmented Insp Coverage of Restart Activities,Including round-the-clock Observations of Licensee Activities During Key Operational Evolutions
IR 05000336/199900310 May 1999Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire ProtectionHot Short
Safe Shutdown
Boric Acid
Fire Barrier
Reserve Station Service Transformer
Operator Manual Action
Emergency Lighting
Job Performance Measure
Exemption Request
Fuel cladding
Fire Protection Program
IR 05000271/19990026 May 1999Insp Rept 50-271/99-02 on 990215-0328.Non-cited Violations Noted.Major Areas Inspected:Operations,Engineering, Maintenance & Plant SupportLoop seal
Foreign Material Exclusion
Operability Determination
Scaffolding
IR 05000029/19990015 May 1999Insp Rept 50-029/99-01 on 990101-0411.No Violations Noted. Major Areas Inspected:Cold Weather Preparations for Spent Fuel Pool,Radiological Controls & self-assessment & Auditing & Corrective Actions for Decommissioning ActivitiesSafe Shutdown
High Radiation Area
Offsite Dose Calculation Manual
ML20206F46030 April 1999Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working HoursReactor Vessel Water Level
Commercial Grade Dedication
Probabilistic Risk Assessment
Temporary Modification
Foreign Material Exclusion
Maintenance Rule Program
Power Operated Valves
Fire Watch
Scaffolding
IR 05000293/199900120 April 1999Insp Rept 50-293/99-01 on 990125-0307.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support.Also Included Routine Core Insp of Security Program During Period of 990301-05Grab sample
Fire Watch
Scaffolding
PNO-I-99-016, on 990406,operators Initiated Plant Cooldown from Normal Operating Pressure & Temp in Mode 3,hot Standby. Cooldown Was Necessary to Minimize Further Degradation of Bonnet Pressure Seal for Valve 2-SI-652 & to Repair Valve7 April 1999PNO-I-99-016:on 990406,operators Initiated Plant Cooldown from Normal Operating Pressure & Temp in Mode 3,hot Standby. Cooldown Was Necessary to Minimize Further Degradation of Bonnet Pressure Seal for Valve 2-SI-652 & to Repair ValveTime of Discovery
ML20205M7356 April 1999Notice of Violation from Investigation in Case Numbers 1-96-002 & 1-97-007.Violation Noted:Licensee Discriminated Against Supervisor in Performance Engineering Group at Plant Due to Involvement in Protected Activities
ML20205M7206 April 1999Notice of Violation from NRC OI Case 1-96-002 & Conclusions of Millstone Independent Review Team.Violation Noted. E Debarba,Deliberately Discriminated Against Supervisor in Performance Engineering Group at Millstone Station
IR 05000245/19990022 April 1999Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support
IR 05000272/19990011 April 1999Insp Repts 50-272/99-01 & 50-311/99-01 on 990117-0307.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant SupportSafe Shutdown
High Radiation Area
Fire Barrier
Condition Adverse to Quality
Maintenance Rule Program
Biofouling
Unidentified leakage
IR 05000336/199900129 March 1999Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing ProblemsTemporary Modification
Operability Determination
IR 05000309/199800526 March 1999Insp Rept 50-309/98-05 on 981101-990213.Violations Noted & Being Treated as non-cited Violations.Major Areas Inspected: Licensee Operations,Engineering & Plant SupportOffsite Dose Calculation Manual
Foreign Material Exclusion
Operability Determination
Fire Watch
IR 05000271/199900116 March 1999Insp Rept 50-271/99-01 on 990104-0214.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support Re Security ProceduresSafe Shutdown
Unanalyzed Condition
High Radiation Area
Stroke time
Locked High Radiation Area
Foreign Material Exclusion
Operability Determination
Deep Dose Equivalent
Biofouling
ML20205J09412 March 1999Rept of Review of Millstone Units 1,2 & 3:Allegations of Discrimination in NRC Ofc of Investigations Cases 1-96-002, 1-96-007,1-97-007 & Associated Lessons LearnedEnforcement Discretion
ML20207M1139 March 1999Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $88,000.Violation Noted:Employment of Two Contractor Employees Terminated in Aug 1997,in Part Because Individuals Raised Concerns Re MOV Program Manual
ML20205G6169 March 1999EN-99-010:on 990309,notice of Proposed Imposition of Civil Penalty in Amount of $88,000 Issued to Licensee.Action Based Upon Severity Level II Problem Involving Discrimination Against Two Contractor Employees at Millstone MOV Dept
IR 05000245/19980061 March 1999Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant SupportBoric Acid
Offsite Dose Calculation Manual
Enforcement Discretion
Temporary Modification
Foreign Material Exclusion
PNO-I-99-006, on 990128,operators Inadvertently Reduced Spent Fuel Pool Water Level by Two Inches When Purification of Spent Fuel Pool Water Initiated.Operators Held Shift Briefing to Discuss Realigning Purification Sys29 January 1999PNO-I-99-006:on 990128,operators Inadvertently Reduced Spent Fuel Pool Water Level by Two Inches When Purification of Spent Fuel Pool Water Initiated.Operators Held Shift Briefing to Discuss Realigning Purification Sys
ML20202G27828 January 1999Insp Rept 50-271/98-14 on 981122-990104.No Violations Noted. Major Areas Inspected:Operations,Maint & EngineeringTime of Discovery
Probabilistic Risk Assessment
Foreign Material Exclusion
Scram Discharge Volume
Maintenance Rule Program
IR 05000245/199821722 January 1999Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ
PNO-I-99-004, on 990115,carbon Dioxide Was Inadvertently Discharged Into Unit 3 Cable Spreading Room,Containing Electrical Wiring.Ambulance Reported to Site as Precautionary Measure.Licensee Assembled Event Review20 January 1999PNO-I-99-004:on 990115,carbon Dioxide Was Inadvertently Discharged Into Unit 3 Cable Spreading Room,Containing Electrical Wiring.Ambulance Reported to Site as Precautionary Measure.Licensee Assembled Event Review
IR 05000336/19980057 January 1999Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant SupportSafe Shutdown
Shutdown Margin
Fire Barrier
Stroke time
Enforcement Discretion
Coatings
Temporary Modification
Missed surveillance
Job Performance Measure
Fire Protection Program
Grace period
Downpower
ML20199C6387 January 1999Notice of Violation from Insp on 981006-1123.Violation Noted:On or Before 981120,conduit 9-15,in Fire Area A-24,not Sealed & Tested in Accordance with Astme E-119,fire Endurance TestFire Barrier
Fire Protection Program