ML20080B092 | 30 September 1994 | Evaluation of Util Response to Suppl 1 to NRC Bulletin 90-01, for Plant | |
ML20073S648 | 10 June 1994 | Technical Evaluation:Core Thermal Limit Protection Function Setpoint Methodology for Seabrook Station YAEC-1854P for Yankee Atomic Electric Co | Anticipated operational occurrence |
ML20091H875 | 17 December 1991 | Final Technical Evaluation Rept,Seabrook Station Unit 1 Station Blackout Evaluation | Safe Shutdown Battery sizing |
ML20006F035 | 30 November 1989 | Technical Evaluation Rept on First 10-yr Interval Inservice Insp Program Plan:Public Svc of New Hampshire,Seabrook Station,Unit 1. | Incorporated by reference Dissimilar Metal Weld |
ML20244A470 | 31 May 1989 | Rev 1 to Technical Evaluation Rept,Tmi Action--NUREG-0737 (II.D.1),Relief & Safety Valve Testing,Seabrook Nuclear Station - Units 1 & 2 | |
ML20235L981 | 30 June 1987 | Conformance to Generic Ltr 83-28,Item 2.2.1 - Equipment Classification for All Other Safety-Related Components: Seabrook 1 & 2, Informal Rept | |
ML20235L839 | 30 June 1987 | Conformance to Generic Ltr 83-28,Item 2.2.2 - Vendor Interface Programs for All Other Safety-Related Components: Seabrook Units 1 & 2, Final Informal Rept | |
ML20206B245 | 31 March 1987 | a Review of the Seabrook Station Probabilistic Safety Assessment.Containment Failure Modes and Radiological Source Terms | Safe Shutdown Probabilistic Risk Assessment Earthquake |
ML20212P934 | 3 March 1987 | Technical Evaluation of EPZ Sensitivity Study for Seabrook, Technical Rept | Boric Acid Probabilistic Risk Assessment Finite Element Analysis |
ML20207B676 | 5 December 1986 | Draft Technical Evaluation of Emergency Planning Zone Sensitivity Study for Seabrook | Boric Acid Packing leak Probabilistic Risk Assessment Finite Element Analysis |
ML20211K510 | 30 November 1986 | Input for Ser,Mcguire Nuclear Station Units 1 & 2,Millstone Nuclear Power Station Unit 3,Seabrook Station Units 1 & 2, VC Summer Nuclear Station,Vogtle Electric...Reactor Trip Sys Reliability,Item 4.5.2 of Generic Ltr 83-28 | |
ML20212Q169 | 27 August 1986 | NRC Region I Insp 50-443/86-27 Review of Seabrook,Unit 1, Tech Specs, Technical Review Report of Onsite Activities Conducted on 860505-16 | Safe Shutdown Boric Acid Ultimate heat sink Stroke time Offsite Circuit |
ML20214H060 | 31 May 1986 | Conformance to Reg Guide 1.97,Seabrook Station,Units 1 & 2, Technical Evaluation Rept for May 1986 | Boric Acid Fuel cladding |
ML20214G128 | 18 March 1986 | Review of PRA for Seabrook Nuclear Power Plant, Monthly Highlights for Feb 1986 | Probabilistic Risk Assessment |
ML20140E047 | 28 February 1986 | Review of Seabrook Station Probabilistic Safety Assessment: Containment Failure Modes & Radiological Source Terms | Safe Shutdown Probabilistic Risk Assessment Earthquake |
ML20199E007 | 28 February 1986 | Sqrt Visit Rept | Shutdown Margin Safe Shutdown Earthquake Earthquake |
ML20199D999 | 28 February 1986 | Audit of Pump & Valve Operability Assurance Program for Seabrook Generating Station Unit 1 | Ultimate heat sink Hydrostatic |
ML20214G123 | 20 February 1986 | Review of PRA for Seabrook Nuclear Power Plant, Monthly Highlights for Jan 1986 | Probabilistic Risk Assessment |
ML20214G079 | 20 January 1986 | Review of PRA for Seabrook Nuclear Power Plant, Monthly Highlights for Dec 1985 | Probabilistic Risk Assessment |
ML20214G068 | 18 December 1985 | Review of PRA for Seabrook Nuclear Power Plant, Monthly Highlights for Nov 1985 | Probabilistic Risk Assessment |
ML20210K645 | 30 November 1985 | PRA Insights | Safe Shutdown Mission time Tornado Missile Internal Flooding Probabilistic Risk Assessment Earthquake Turbine Missile Fatality |
ML20214G065 | 21 November 1985 | Review of PRA for Seabrook Nuclear Power Plant, Monthly Highlights for Oct 1985 | Probabilistic Risk Assessment |
ML20214F766 | 18 October 1985 | Review of PRA for Seabrook Nuclear Power Plant, Monthly Progress Rept for Sept 1985 | Probabilistic Risk Assessment |
ML20214F755 | 20 September 1985 | Review of PRA for Seabrook Nuclear Power Plant, Monthly Highlights for Aug 1985 | |
ML20211D226 | 26 August 1985 | Review of Seabrook PRA, Monthly Mgt Ltr 15 for Jul 1985 | Safe Shutdown Ultimate heat sink Safe Shutdown Earthquake Probabilistic Risk Assessment Operating Basis Earthquake Tornado Generated Missile Earthquake Weak link |
ML20211D208 | 9 August 1985 | Review of Seabrook PRA, Monthly Mgt Ltr 14 for June 1985 | Probabilistic Risk Assessment |
ML20214G204 | 31 July 1985 | Review of PRA for Seabrook Nuclear Power Plant, Monthly Highlights for Jul 1985.Related Info,Including Transmittal of Vouchers for Svcs Rendered,Encl | Probabilistic Risk Assessment |
ML20214G192 | 30 June 1985 | Review of PRA for Seabrook Nuclear Power Plant, Monthly Highlights for June 1985 | Probabilistic Risk Assessment |
ML20211D198 | 27 June 1985 | Review of Seabrook PRA, Monthly Mgt Ltr 13 for May 1985 | Probabilistic Risk Assessment |
ML20206F182 | 6 June 1985 | Marked-up Analysis of Station Blackout Transient W/Reactor Coolant Pump Seal Leakage for Seabrook Nuclear Plant | Loop seal Fuel cladding |
ML20214G188 | 31 May 1985 | Review of PRA for Seabrook Nuclear Power Plant, Monthly Highlights for May 1985 | Probabilistic Risk Assessment |
ML20211D169 | 1 May 1985 | Review of Seabrook PRA, Monthly Mgt Ltr 11 for Mar 1985 | Probabilistic Risk Assessment |
ML20211D178 | 1 May 1985 | Review of Seabrook PRA, Monthly Mgt Ltr 12 for Apr 1985 | Probabilistic Risk Assessment |
ML20214G181 | 30 April 1985 | Review of PRA for Seabrook Nuclear Power Plant, Monthly Highlights for Apr 1985 | Probabilistic Risk Assessment |
ML20214G179 | 31 March 1985 | Review of PRA for Seabrook Nuclear Power Plant, Monthly Highlights for Mar 1985 | Probabilistic Risk Assessment |
ML20209E274 | 29 March 1985 | Review of Seabrook PRA, Monthly Mgt Ltr 10 for Feb 1985 | Probabilistic Risk Assessment |
ML20214G171 | 28 February 1985 | Review of PRA for Seabrook Nuclear Power Plant, Monthly Highlights for Feb 1985 | Probabilistic Risk Assessment |
ML20211D129 | 20 February 1985 | Review of Seabrook PRA, Monthly Mgt Ltr 9 for Jan 1985 | Probabilistic Risk Assessment |
ML20214G062 | 19 February 1985 | Review of PRA for Seabrook Nuclear Power Plant, Monthly Highlights for Jan 1985 | Probabilistic Risk Assessment |
ML20211D092 | 4 February 1985 | Review of Seabrook PRA, Monthly Mgt Ltr 8 for Dec 1984 | Probabilistic Risk Assessment |
ML20211E040 | 31 January 1985 | Preliminary Review & Evaluation of Seabrook Probabilistic Safety Study | Safe Shutdown Shutdown Margin Probabilistic Risk Assessment |
ML20211D068 | 25 January 1985 | Review of Seabrook PRA, Monthly Mgt Ltr 7 for Nov 1984 | Probabilistic Risk Assessment |
ML20214G057 | 18 January 1985 | Review of PRA for Seabrook Nuclear Power Plant, Monthly Highlights for Dec 1984 | Probabilistic Risk Assessment |
ML20214G041 | 17 December 1984 | Review of PRA for Seabrook Nuclear Power Plant, Monthly Highlights for Nov 1984 | Probabilistic Risk Assessment |
ML20113E569 | 12 December 1984 | Draft Review of Seabrook Station Probabilistic Safety Assessment | |
ML20211C904 | 19 November 1984 | Review of Seabrook PRA, Monthly Mgt Ltr 6 for Oct 1984 | Probabilistic Risk Assessment |
ML20214F817 | 16 November 1984 | Safety Evaluation of Core-Melt Accidents:CESSAR-FDA, Westinghouse Std Plant-FDA, Safety Evaluation of Core-Melt Accidents:Indian Point...& Zion-Operating Reactor & Review of PRA for Seabrook..., Monthly Repts for Oct 1984 | Probabilistic Risk Assessment |
ML20209D547 | 14 November 1984 | PRA Review & Recommended Approach for Completion of Project, Status Rept as of 841101 | Turbine Missile |
ML20214G148 | 19 October 1984 | Review of PRA for Seabrook Nuclear Power Plant, Monthly Highlights for Sept 1984 | Probabilistic Risk Assessment |
ML20209D479 | 15 October 1984 | Review of Seabrook PRA, Monthly Mgt Ltr 5 for Sept 1984 | Tornado Missile Probabilistic Risk Assessment |