SNRC-1484, Suppl 11 to Startup Rept for May-Aug 1988

From kanterella
Jump to navigation Jump to search
Suppl 11 to Startup Rept for May-Aug 1988
ML20151N238
Person / Time
Site: Shoreham File:Long Island Lighting Company icon.png
Issue date: 08/03/1988
From: Leonard J, Scalice J, Steiger W
LONG ISLAND LIGHTING CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
SNRC-1484, NUDOCS 8808080152
Download: ML20151N238 (15)


Text

- _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _

P

$3 Il LONG ISLAND LIGHTING COMPANY Shoreham Nuclear Power Station Supplement No. 11 to the STARTUP REPORT for the period May 1, 1988 to August 1, 1988 Approved: J/d/ / h 8/8/M' J.pfSfelice'[ ' /Date Assistant Plarft Manage'.-

Approved: M, f'-3-88 W. E. Steiger/ V Date Plant Manager svo80SO152 880803 2 PDR ADOCK 0500

[ _ _ _ - - - - - - - - -

\

1 ,

TABLE OF CONTENTS l l 1.0 Overviaw 2.0 Chronology of Events 3.0 Startup Activities Performed / Test Results 4.0 License Conditions l

l 1

1.0 OVERVIEW This Startup Report Supplement has been written-by the Long 1 Island Lighting Company (LILCO) for submittal to the l Nuclear Regulatory Commission in compliance with Shoreham Huclear Power Station Technical Specifications, paragraphs l 6.9.1.1 through 6.9.1.3, and Regulatory Guide _l.16, l Revision 4, section C.l.a.

Technical Specifications and Regulatory Guide 1.16 require that a summary report of plant startup and pove.r escalation testing be submitted within 9 months following initial l 1

criticality. Shoreham Nuclear Power Station (SNPS) achieved initial criticality on February 15, 1985, and LILCO submitted a Startup Report on November 15, 1985. The i scope-of that Startup Report included fuel load and initial criticality under the .001% power license, NPF-19, and low power testing conducted und'er the 5% power license, NPF-36.

Since SNPS has not completed its startup test program or commenced commercial power operation, additional Supple-ments are required on a periodic basis. This Supplement covers the period from May 1, 1988 to August 1,-1988.

Shoreham was shutdown from June 1987 to August 1988. The major work in progress during this reporting period involved activities associeted with portions of the Colt diesel tie-in modification.

l

)

1 1

e 2.0 CHRONOLOGY OF EVENTS December 7, 1984 Received low power license .001%

December 17, 1984 Sources loaded in cere.

December 21, 1984 Fuel loading commenced.

January 4, 1985 Partial core shutdown margin test.

January 19, 1985 Fuel loading completed.

January 25, 1985 CRD open vessel testing completed. <

. February 15, 1985 Initial critical and shutdown margin test.

February 17, 1985 Completed open vessel testing. .

June 4, 1985 CRD open vessel retest' completed.

July 3, 1985 5% low power license received.

July 7, 1985 Reactor critical sequence-B. Test condition Heatup.

July 7, 1985 Heatup to 250 F System expansion performed.

IRM performance completed July 8, 1985 Heatup to 325 F performed.

APRM calibration.

July 9, 1985 SRV functional test performed (STP-26).

July 11, 1985 150 psig plateau reached.

System expansion DW entry.

RCIC testing. I HPCI system testing. l I

July 14, 1985 Reactor scram #1 on Rx level. I July 17, 1985 APRM calibration at 150 psig. i HPCI testing. l System expansion testing.  !

RBCLCW performance testing.  ;

July 18, 1985 Reactor Shutdown for RPV level instrumentation work.

July 23, 1985 Reactor critical.

July 26, 1985 Reactor shutdown for RPV level instrumentation work.

l l

i '

1 CHRONOLOGY OF EVENTS - (continued),

July 29, 1985 Reactor critical.

July 31, 1985 Reactor pressure to 150 psig.

HPCI c.ystem testing.

August 1, 1985 350 psig plateau.

Drywell radiation survey.

System expansion drywell inspection, system e> pansion data.

August 3, 1985 600 psig plateau.

System expansion.

RBCLCW performance.

CPD testing.

August 5, 1985 800 psig plateau.

System expansion.

CRD testing.

August 7, 1985 Rated pressure plateau.

System expansion testing.

HPCI testing.

RCIC testing.

CRD testing.

RBCLCW testing.

Water level testing.

Process computer STP-13 testing.

Chemical and radiochemical testing.

Radiation measurements.

LPRM testing.

August 23, 1985 Reactcr pressure reduced to 150 psig.

HPCI testing.

RCIC testing.

August 24, 1985 Reactor shutdown after' initial.heatup.

August 30, 1985 Reactor critical sequence A.

August 31, 1985 Scram #2 on loss of instrument air.

September 3, 1985 Reactor critigal sequence A. Second heatup to 150 F.

September 4, 1985 Heatup to 250 - 150 psig.

System expansion testing.

September 6, 1985 Reactor pressure 350 psig.

System expansion testing.

September 6, 1985 Reactor scram #3 due to surveillance on level instrument.

1 l

CHRONOLOGY OF' EVENTS - (continued)

September 7,.1935 Reactor pressure 600 psig.

System expansion testing.

CRD testing.

September 8, 1985 Unusual event.due t> reactor level indication problem.

September 10, 1985 Reactor shutdown for repair of reactor problem.-

September 11, 1985.

~

Reactor critical and heatup to investigate level problem.

September'12, 1985 Reactor scram f4 on low water. level indication. Actual level did not change. Level instrument problem investigated.

September 18, 1985 Reactor critical sequence A.

September 21, 1985 Reactor pressure 800 psig.

System expansion testing.

CRD testing.

RPV level problem fixed.

September 21, 1985 Rated pressure reached.

System expansion testing.

Second heatup.

RCIC testing.

HPCI testing.

MSIV testing.

Water level testing.

CRD testing.

RWCU testing.

Radiation testing.

Chemistry testing.

September 27, 1985 Reactor shutdown.

Hanger placed on B reference leg.

Miscellaneous maintenance.

October 3, 1985 Reactor critical sequence A. Third heatup to rated pressure.

System expansion testing.

October 4, 1985 RCIC vessel injection at rated pressure.

System expansion testing.

RWCU system testing.

MSR relief valve testing.

CHRONOLOGY OF EVENTS - (continued)

October 6, 1985 Initial turbino. generator roll to rated speed.

October 8, 1985 End of heatup testing.

Begin source replacement outage.

April 18, 1986 Reactor Mode Switch to Startup for generator synchronization and completion of Test Condition Heatup.

April 24, 1986 Loose Parts Monitor System testing.

Reactor Mode Switch to Shutdown due l to condenser leakage problem. l August 3, 1986 Mode Switch to startup for 5% retest program.  ;

August 4, 1986 Reactor critical, sequence A.

August 7, 1986 RCIC check valve cycling test, 150 psig plateau.

F?CI tuning and flow demonstration ST to CST) 150 psig plateau.

dystem expansion data, reactor building secondary walkdowns, 150 psig plateau.

August 8, 1986 RBCLCW performance test, normal and blowdown mode, 150 psig plateau.

August 10, 1986 RBCLCW performance test, normal and blowdown mode, 600 psig plateau.

August 11, 1986 Reactor cooldown to investigate /

repair a wide range transmitter.

Unusual Event declared.

August 13, 1986 Reactor water level measurements, rated plateau.

System expansion data, reactor building secondary walkdowns, rated plateau.

Radiochemistry water chemistry sampling data, rated plateau.

. , . l CHRONOLOGY OF EVENTS - (continued) j August 14, 1986 _ Scrami timing of' sequence A rods.

l System expansion balance of plant walkdown: steam tunnel and turbine building.

Reactor cooldown for maintenance l work in the drywell and sequence exchange.

August 15, 1986 Commenced reactor heatup in the B-2 sequence, reactor critical.

Drywell entry at rated conditions for system expansion data.

Feedwater low flow controller testing.

Scram timing of sequence B rods.

August 16, 1986 Commenced main turbine startup prerequisites.

HPCI tuning at rated conditions (CST to CST).

RBCLCW performance test at rated pressure plateau.

August 17, 1986 Main turbine roll.

Reactor building service water performance test.  ;

August 18, 1986 RWCU blowdown and normal mode tests.

I Reactor shutdown due to hurricane '

warnings.

August 20, 1986 Reactor startup - heatup to rated pressure plateau.

System expansion balance of plant walkdown at rated pressure plateau. i August 21, 1986 RCIC tuning to the reactor vessel at rated pressure platehu.

RWCU bottom head drain flow calibration.

CHRONOLOGY OF EVENTS --(continued)-

August 22, 1986 CRD flow controller tune-up.

RCIC instrumentation piping vibration test.

August 23, 1986 HPCI tuning at rated (CST to' CST).

-Reactor cooldown to 150 psig plateau.

Feedwater low flow controller tuning in auto during cooldown.

August 24, 1986 RCIC Vessel Injection and Stability Demonstration at 150 psig.

Heatup to rated pressure.

Feedwater low flow controller in manual during heatup.

HPCI tuning at rated conditions (CST to CST).

August 25, 1986 Main turbine roll and excitation checks.

August 26, 1986 Main turbine generator synchronization to the grid and 24 hr...run.

August 27, 1986 Turbine generator off grid.

RCIC cold quickstart il (vessel injection).

RCIC transient vibration test.

Process computer TIP hot alignment.

August 28, 1986 HPCI tuning at rated pressure plateau.

Reactor cooldown to 150 psig plateau.

HPCI quickstart (CST to CST) and stability demonstration at 150 psig.

Reactor heatup to rated pressure  !

plateau. l HPCI hot alignment verification. l l

l 1

. l CHRONOLOGY OF EVENTS - (continued)

August 29, 1986 CRD flow controller tuning.

August 30, 1986 RCIC cold quickstart #2 (vessel injection).

RCIC transient vibration test.

Loose parts monitoring data collection during RCIC vessel injection.

2 actor cooldown and shutdown.

May 22, 1987 Reactor critical.

May 26, 1987 ADS valve 18-month surveillance May 27, 1987 APRM calibration.

May 29, 1987 RCIC rated flow ~ surveillance.

HPCI rated flow surveillance and controller output limiter adjustment.

May 31, 1987 RCIC functional and stability demonstration from Remote Shutdown Panel.

June 1, 1987 Power reduction due to system load demand.

June 4, 1987 Generator synchronized for 8-hour run.

June 5, 1987 HPCI endurance run.

June 6, 1987 Reactor shutdown and cooldown.

3.0 STARTUP ACTIVITIES PERFORMED / TEST RESULTS The plant has been shutdown during the entire period-covered by this Supplement. There are no new results to report.

i 4.0 LICENSE CONDITIONS Technical Specifications require that the Startup Report )

discuss the license conditions which affect plant startup and power escalation testing. The specific license conditions are delineated in paragraph 2.C of the Shoreham l Operating License (NPF-36 of July 3, 1985). Each condition l is summarized and its status, as it applies to the ,

completed nortion of the test program, is provided below. l

4.1 Condition

The maximum core thermal power shall not exceed 5% rated core thermal power.

Status: During the period covered by this Supplement, the reactor did not exceed 5%

rated core thermal power.

4.2 Condition

The plant shall be operated in accordance with the Technical Specifications and the Environmental Protection Plan.

Status: The Low Power Test Program has been conducted in accordance with Technical Specifications and the Environmental Protection Plan. Any deviation from these documents is required to be reported to the NRC via a Licensee Event Report (LER) .

4.3 Condition

The plant shall maintain the fire protection program as described in the Fire Hazards Analysis Report and in'the USAR.

Status: The plant has adhered to the provisions of the Fire Protection Program. Non-compliances shall be the subject of a Licensee Event Report.

4.4 Condition

Changes to the initial test program shall be reported in one month.

Status: All changes to the test program as described in Chapter-14 of the USAR will be reported per the license condition.

4.5 Condition

The initial inservice inspection shall be developed and implemented before the first refueling outage.

Status: This condition is not affected by the Low Power Test Program. Development of the inservice inspection program is in progress.

l

4.6 Condition

Within thirty (30) days after plant startup following the first refueling outage, the licensee shall comply with items 1, 2, and 3 of I.E. Bulletin No.

l 79-26, Revision 1, "Boron Loss From BWR l Control Blades", and submit a written response on item.3.

Status: This condition is not yet applicable.

l

4.7 Condition

The provisions of the NUREG-0737 actinn plan described in the SER,-Supplement 1 and 4, shall be followed.

4.7.1 Status

The qualifications of the required seven backup STA's have been submitted to the Commission, all have been approved.

4.7.2 Status

The requirement to mark control room indicators with operating limits and with trip and alarm setpoint values is not yet implemented. The requirements of the provision remain under review and'shall be imple-mented prior to the completion of the startup test program.

4.7.3 Status:- We will revise our core damage pro-cedures (EPIP l-11 and EPIP 1-14) prior to startup from the first re-fueling outage, to include estimates of fuel overheating and the use of other plant parameters.in the assessment of core damage. This item is being tracked by Region I as 50-322/85-04-19.

4.7.4 Status

The modifications required to imple-ment the emergency response capa-bilities, as require by Attachment 1 to the license, are in progress.

4.8 Condition

Prior to November 30, 1985, all electrical equipment shall be qualified.

Status: Station modifications to environmentally

~

qualify the required electrical equipment are complete. j 1

4.9 Condition

The remote shutdown system shall be l improved prior to the first startup  !

following the first refueling outage.

Status: The modifications will be implemented as required.

I

. i l

4.10 Condition: The RHR system may not be operated in the cteam condensing mode except under emergency conditions.

Status: The station procedures have been modified to preclude the steam condensing mode of operation except as a last resort when all other methods of core and containment cooling have failed.

4.11 Condition: Two containment isolation barriers in series will be installed by the end of the first refueling outage.

Status: Modifications to satisfy this condition will be completed by the end of the first refueling outage.

4.12 Condition: The provisions of Attachment 3 to the license shall be satisfied as they apply to the TDI diesel generators.

Status: Station procedures and maintenance schedules have been modified to include the required TDI diesel generator tests and inspections.

4.13 Condition: The results of the independent design review shall be incorporated prior to exceeding 5 percent power.

Status: The requirements of this condition have been met.

4.14 Condition: a.) Prior to exceeding five percent power, radiation monitoring panels 1D11*PNL-117A, B and radiation monitoring pumps 1D11*P126, 134 shall be qualified.

b.) The invessel storage racks shall be qualified prior to use.

Status: a.) The required qualification for the l radiation monitoring equipment has been completed, l b.) The invessel storage racks have been administratively prohibited from use.

l 4.15 Condition: The plant shall have on-shift advisors as I required by Attachment 2 of the license. j 1 l l

Status: The plant currently has sufficient i

! numbers of qualified on-shift advisors to I satisfy this condition.

l 1

1 1

i a

4.16 Condition: The Emergency Core Cooling Systems performance shall be reanalyzed for the second cycle and beyond, utilizing models

.that account for burnup gas pressure and local oxidation and which are approved by the NRC.

Status: This condition will be completed by the required date.

4.17 Condition: The licensee shall implement the response to Generic Letter 83-28 on schedule.

Status: All provisions stipulated in SNRC-1013, 1116, 1184, and 1217 are complete except for the provision that requires the Safety Parameter Display System (SPDS) to be operable prior to the first restart after the-first refueling.

l l

l i

l

3 aus. .

i l

su ma m mar- -

[/Eg@

LONG ISLAND LIGHTING COM PANY SHOREHAM NUCLEAR POWER STATION P.O. 00X 618, NORTH COUNTRY RO AD e WADING RIVER, N.Y.11792 JOHN D. LEONARD, JR.

VICE PPE$l0 ENT . NUCLE AR OPER ATIONS SNRC-1484 AUG 03 M U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Supplement No, 11 to the Startup Test Report Shoreham Nuclear Power Station Docket No. 50-322 Gentlemen:

Attached is Supplement No. 11 to the Startup Test Report, prepared by the Long Island Lighting Company in compliance with Shoreham Nuclear Power Station's Technical Specifications paragraphs 6.9.1.1 through 6.9.1.3 and Regulatory Guide 1.16, Revision 4, Section C l.a.

This report covers the period from May 1, 1988 to August 1, 1988.

Shoreham has been shutdown since June 1987. No startup activi-ties were performed during this reporting period. We have, how-ever, been working on various other activities and those which required a major effort are identified in this report.

If there are any questions, please contact thic office.

Very truly yours, J. D. Leonard, Jr.

Vice President - Nuclear Operations TD:ck Attachment cc: S. Brown i l

W. Russell F. Crescenzo