RS-15-019, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)

From kanterella
Jump to navigation Jump to search

Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)
ML15058A529
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 02/27/2015
From: Kaegi G
Exelon Generation Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
EA-12-049, RS-15-019
Download: ML15058A529 (16)


Text

Exelon Generation, Order No. EA-12-049 RS-15-019 February 27, 2015 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Dresden Nuclear Power Station, Units 2 and 3 Renewed Facility Operating License Nos. DPR-19 and DPR-25 NRC Docket Nos. 50-237 and 50-249

Subject:

Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)

References:

1. NRC Order Number EA-12-049, "Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," dated March 12, 2012
2. NRC Interim Staff Guidance JLD-ISG-2012-01, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," Revision 0, dated August 29, 2012
3. NEI 12-06, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide,"

Revision 0, dated August 2012

4. Exelon Generation Company, LLC's Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated October 25, 2012
5. Exelon Generation Company, LLC Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated February 28, 2013 (RS-13-020)
6. Exelon Generation Company, LLC First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA 049), dated August 28, 2013 (RS-13-119)
7. Exelon Generation Company, LLC Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA 049), dated February 28, 2014 (RS-14-010)

U.S. Nuclear Regulatory Commission Integrated Plan Report to EA-12-049 February 27, 2015 Page 2

8. Exelon Generation Company, LLC Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA 049), dated August 28, 2014 (RS-14-208)
9. NRC letter to Exelon Generation Company, LLC, Dresden Nuclear Power Station, Units 2 and 3 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) (TAC Nos. MF1046 and MF1047), dated November 22, 2013 On March 12, 2012, the Nuclear Regulatory Commission ("NRC" or "Commission") issued an order (Reference 1) to Exelon Generation Company, LLC (EGG). Reference 1 was immediately effective and directs EGO to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a beyond-design-basis external event. Specific requirements are outlined in of Reference 1.

Reference 1 required submission of an initial status report 60 days following issuance of the final interim staff guidance (Reference 2) and an overall integrated plan pursuant to Section IV, Condition C. Reference 2 endorses industry guidance document NEI 12-06, Revision 0 (Reference 3) with clarifications and exceptions identified in Reference 2. Reference 4 provided the EGO initial status report regarding mitigation strategies. Reference 5 provided the Dresden Nuclear Power Station, Units 2 and 3 overall integrated plan.

Reference 1 requires submission of a status report at six-month intervals following submittal of the overall integrated plan. Reference 3 provides direction regarding the content of the status reports. References 6, 7, and 8 provided the first, second, and third six-month status reports, respectively, pursuant to Section IV, Condition C.2, of Reference 1 for Dresden Station. The purpose of this letter is to provide the fourth six-month status report pursuant to Section IV, Condition C.2, of Reference 1, that delineates progress made in implementing the requirements of Reference 1. The enclosed report provides an update of milestone accomplishments since the last status report, including any changes to the compliance method, schedule, or need for relief and the basis, if any. The enclosed report also addresses the NRC Interim Staff Evaluation Open and Confirmatory Items contained in Reference 9.

This letter contains no new regulatory commitments. If you have any questions regarding this report, please contact David P. Helker at 610-765-5525.

I declare under penalty of perjury that the foregoing is true and correct. Executed on the 27th day of February 2015.

Respectfully submitted, Glen T. Kaegi Director - Licensing & Regulatory Affairs Exelon Generation Company, LLC

U.S. Nuclear Regulatory Commission Integrated Plan Report to EA-12-049 February 27, 2015 Page 3

Enclosure:

1. Dresden Nuclear Power Station, Units 2 and 3 Fourth Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events cc: Director, Office of Nuclear Reactor Regulation NRC Regional Administrator - Region III NRC Senior Resident Inspector Dresden Nuclear Power Station, Units 2 and 3 NRC Project Manager, NRR Dresden Nuclear Power Station, Units 2 and 3 Ms. Jessica A. Kratchnnan, NRR/JLD/PMB, NRC Mr. Jack R. Davis, NRR/DPR/MSD, NRC Mr. Eric E. Bowman, NRR/DPR/MSD, NRC Mr. Jeremy S. Bowen, NRR/DPR/MSD/MSPB, NRC Mr. Robert L. Dennig, NRR/DSS/SCVB, NRC Mr. John P. Boska, NRR/JLD/JOMB, NRC Illinois Emergency Management Agency - Division of Nuclear Safety

Enclosure Dresden Nuclear Power Station, Units 2 and 3 Fourth Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (12 pages)

Dresden Nuclear Power Station. Units 2 and 3 Fourth Six Month Status Report for the Implementation of FLEX February 27, 2015 Enclosure Dresden Nuclear Power station, Units 2 and 3 Fourth Six Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events 1 Introduction Dresden Nuclear Power Station, Units 2 and 3 (Dresden) developed an Overall Integrated Plan (Reference I in Section 8), documenting the diverse and flexible strategies (FLEX), in response to Reference 2. This enclosure provides an update of milestone accomplishments since submittal of the Overall Integrated Plan, including any changes to the compliance method, schedule, or need for relief/relaxation and the basis, if any.

2 Milestone Accomplishments Modification development completed.

3 Milestone Schedule Status The following provides an update to Attachment 2 of the Overall Integrated Plan. It provides the activity status of each item, and whether the expected completion date has changed. The dates are planning dates subject to change as design and implementation details are developed.

Original Target Activity Status Revised Target Completion Date {Include date changes in Completion Date this column}

Submit 60 Day Status Report Complete Submit Overall Integrated Complete Implementation Plan Contract with RRC Complete Submit 6 month updates August 2013 Update 1 Complete February 2014 Update 2 Complete August 2014 Update 3 Complete February 2015 Update 4 Complete with this submittal Page 1 of 12

Dresden Nuclear Power Station, Units 2 and 3 Fourth Six Month Status Report for the Implementation of FLEX February 27, 2015 Original Target Activity Status Revised Target Completion Date {Include date changes in Completion Date this column)

August 2015 Update 5 Not started February 2016 Update 6 Not started August 2016 Update 7 Not started Submit Completion Report Unit 2 Unit 3 Modification Development Oct 2014 Sept 2015

  • Phase 1 modifications Complete Oct 2014 Sept 2015
  • Phase 2 modifications Complete Oct 2014 Sept 2015
  • Phase 3 modifications Complete Unit 2 Unit 3 Modification Implementation Nov 2015 Nov 2016
  • Phase 1 modifications None required Nov 2015 Nov 2016
  • Phase 2 modifications Started Nov 2015 Nov 2016
  • Phase 3 modifications Started Procedure development Nov 2015
  • Strategy procedures Started Nov 2015
  • Validate Strategy Note 1 Procedures (NEI 12-06, Sect. 11.4.3)

Nov 2015

  • Maintenance procedures Note 1 Jul 2015 Staffing analysis Note 1 Nov 2015 Storage Plan and construction Note 1 Nov 2015 FLEX equipment acquisition Started Nov 2015 Training completion Started Jul 2015 National SAFER Response Center (will be a standard date Operational from National SAFER Response Center)

Nov 2015 Unit 2 Implementation date Note 1 Nov 2016 Unit 3 Implementation date Note 1 Page 2 of 12

Dresden Nuclear Power Station, Units 2 and 3 Fourth Six Month Status Report for the Implementation of FLEX February 27, 2015 Note(s):

1. Exelon will update the status of ongoing and future milestones in the Integrated Plan for Dresden Nuclear Power Station during a scheduled six (6) month update. This update will include any changes to the milestone schedule as submitted in the February 28, 2014 Integrated Plan.

4 Changes to Compliance Method There are no changes to compliance methods since the last update.

5 Need for Relief/Relaxation and Basis for the Relief/Relaxation Dresden Nuclear Power Station expects to comply with the order implementation date and no relief/relaxation is required at this time.

Page 3 of 12

Dresden Nuclear Power Station, Units 2 and 3 Fourth Six Month Status Report for the Implementation of FLEX February 27, 2015 6 Open Items from Overall Integrated Plan and Draft Safety Evaluation The following tables provide a summary of the open items documented in the Overall Integrated Plan or the Draft Safety Evaluation (SE) and the status of each item.

Section Reference Overall Integrated Plan Open Item Status Sequence of Events The times to complete actions in the Events Not Started (page 5-6) Timeline are based on operating judgment, conceptual designs, and current supporting analyses. The final timeline will be time validated once detailed designs are completed and procedures developed.

Sequence of Events Analysis of deviations between Exelon's Completed. See August (page 5) engineering analyses and the analyses contained 2013 Update in BWROG Document NEDC-33771P, "GEH Evaluation of FLEX Implementation Guidelines and documentation of results on Att. 1B, "NSSS Significant Reference Analysis Deviation Table." Planned to be completed and submitted with August 2013 Six Month Update.

Sequence of Events Initial evaluations were used to determine the Completed. See August (page 8) fuel pool timelines. Formal calculations will be 2014 Update performed to validate this information during development of the spent fuel pool cooling strategy detailed design.

Deployment Strategy Transportation routes will be developed from See Interim Staff (pages 8-9) the equipment storage area to the FLEX staging Evaluation Confirmatory areas. An administrative program will be Item 3.1.2.2.A response.

developed to ensure pathways remain clear or compensatory actions will be implemented to ensure all strategies can be deployed during all modes of operation.

Identification of storage areas and creation of the administrative program are open items.

Programmatic Controls An administrative program for FLEX to Started (pages 9- establish responsibilities, and testing 8z,

10) maintenance requirements will be implemented.

Spent Fuel Pool Cooling Complete an evaluation of the spent fuel pool See Interim Staff Phase 2 area for steam and condensation. Evaluation Confirmatory Discussion (page 46) Item 3.2.2.A response.

Page 4 of 12

Dresden Nuclear Power Station, Units 2 and 3 Fourth Six Month Status Report for the Implementation of FLEX February 27, 2015 Section Reference Overall Integrated Plan Open Item Status Safety Functions Evaluate the habitability conditions for the See Interim Staff Support Phase 2 Main Control Room and develop a strategy to Evaluation Confirmatory Discussion (page 57) maintain habitability. Item 3.2.4.6.0 response.

Safety Functions Evaluate the habitability conditions for the See Interim Staff Support Phase 2 Auxiliary Electric Equipment Room (AEER) Evaluation Confirmatory Discussion (page 57) and develop a strategy to maintain habitability. Item 3.2.4.2.0 response.

Item Interim Staff Evaluation OPEN Item Status number 3.1.1.1.A Each section of the Integrated Plan Completed. See February 2014 Update describing storage protection from hazards makes reference to Section 11 rather than to the specific protection requirements described in NET 12-06 for the applicable hazard; that is Section 6.2.3.1 for floods, Section 7.3.1 for wind, etc. As a result, the specific guidelines for each hazard are not addressed.

3.1.2.2. B The Plan is silent regarding loss of Completed. See February 2014 Update normal access to the Ultimate Heat Sink (UHS) due to flood hazard conditions, the need to provide electrical power for sump pumps, and whether or not flood barriers will be utilized.

3.2.4.8.A Updated information provided by the Completed. See August 2014 Update licensee as part of the 6-month update states that they are proposing to install a prestaged generator to supply all FLEX related loads for both units simultaneously for Phase 2 mitigating strategies. This appears to be an alternative approach for satisfying the Mitigating Strategies order. Insufficient information has been provided by the licensee in order to determine whether this provides an equivalent level of protection as would be provided through conformance with NEI 12-06.

Page 5 of 12

Dresden Nuclear Power Station, Units 2 and 3 Fourth Six Month Status Report for the Implementation of FLEX February 27, 2015 Item Interim Staff Evaluation number CONFIRMATORY Item Status 3.1.1.2.A A postulated downstream dam failure Completed. See February 2014 Update from a seismic event is still being evaluated.

3.1.1.2.B Plans for strategies did not address Started whether electrical power would be required to move or deploy FLEX equipment (e.g. to open a door from a storage location.)

3.1.1.3.A Development of a reference source Started for obtaining necessary instrument readings in the event of seismic damage to electrical equipment as described in NEI 12-06, Section 5.3.3, consideration 1.

3.1.1.3.B Use of, or need for ac power to Completed. See February 2014 Update mitigate ground water intrusion was not addressed.

3.1.1.4.A Regarding off site resources, detailed Proposed Complete plans for local staging areas and All licensees, including Exelon Generation Company, transport of FLEX equipment to relying on SAFER and the National SAFER Response overcome hazards are to be provided Centers (NSRC), have executed contractual agreements in 6-month update. with Pooled Equipment Inventory Company (PEICo) which allows for the capabilities (considerations) in Section 12.2 of NE! 12-06. The NRC staff evaluated the NSRCs and the SAFER program, plans, and procedures against these 10 capabilities (considerations) from NE!

12-06, Section 12.2. The NRC audit results concluded that the NSRCs and the SAFER plans and procedures conform to the guidance described by the 10 capabilities (considerations) of NET 12-06, Section 12.2.

The NRC findings are documented in a letter from the NRC (Jack R. Davis) to the Nuclear Energy Institute (Joseph E. Pollock), Staff Assessment of National Safer Response Centers Established in Response to Order EA-12-049, dated September 26, 2014 (ML14265A107).

3.1.2.A Impact of persistence of flooding to Started staging of FLEX equipment not fully addressed.

3.1.2.2.A Administrative program and Started procedures for on-site FLEX equipment storage locations and transport routes not yet established.

Page 6 of 12

Dresden Nuclear Power Station, Units 2 and 3 Fourth Six Month Status Report for the Implementation of FLEX February 27, 2015 Item Interim Staff Evaluation number CONFIRMATORY Item Status 3.1.2.3.A Administrative program and Started procedures related to implementation of mitigation strategies not yet developed.

3.1.4.2.A Equipment to clear ice and snow from Completed. See February 2014 Update haul pathways is not identified in plan.

3.1.5.2.A Procedures to assure equipment can Not started be deployed in a high temperature context have not been developed.

Specifically, address high temperature effects on storage locations (e.g.

expansion of sheet metal, swollen seals, etc.)

3.1.5.3.A Procedures to address high Started temperature impacts on FLEX equipment not yet developed.

3.2.1.1.A Need benchmarks to demonstrate Completed. See August 2014 Update Modular Accident Analysis Program (MAAP) 4 is the appropriate code for simulation of ELAP.

3.2.1.1.B For MAAP4, collapsed level must Completed. See August 2014 Update remain above Top of Active Fuel and cool down rate must meet technical specifications.

3.2.1.1.0 MAAP4 use must be consistent with Completed. See August 2014 Update June 2013 position paper.

3.2.1.1.D In using MAAP4, the licensee must Completed. See August 2014 Update identify and justify the subset of key modeling parameters cited from Tables 4-1 through 4-6 of the "MAAP4 Application Guidance, Desktop Reference for Using MAAP4 Software, Revision 2" (Electric Power Research Institute Report 1 020236).

3.2.1.1.E The specific MAAP4 analysis case Completed. See August 2014 Update that was used to validate the timing of mitigating strategies in the integrated plan must be identified and should be available on the ePortal for NRC staff to view. Alternately, a comparable level of information may be included in the supplemental response.

Page 7 of 12

Dresden Nuclear Power Station, Units 2 and 3 Fourth Six Month Status Report for the Implementation of FLEX February 27, 2015 Item Interim Staff Evaluation number CONFIRMATORY Item Status 3.2.1.3.A Outstanding Confirmatory Items Not started regarding the use of the MAAP4 analysis may impact the sequence of events timeline. Any changes to the MAAP4 analysis results will need to be reviewed for impact on the sequence of events timeline. The licensee stated that the final timeline will be time validated once detailed designs are completed, procedures are developed, and the results will be provided in a future six (6) month update.

3.2.1.3.B Sequence of Events timing for Started compensatory actions to control temperature rise in the Main Control Room not resolved.

3.2.1.4.A Detailed engineering analyses to Started confirm the ability of FLEX pumps to provide required flow and head capacities are not complete.

3.2.1.4.B Analysis needs to be performed to Started validate that the plant modifications, selected equipment, and identified mitigating strategy can satisfy the safety function requirements of NET 12-06. To be provided in a future six (6) month update.

3.2.1.6.A Whether or not backup compressed Completed. See August 2014 Update air for valve actuation is required, is contingent on the MAAP4 analyses conclusions. The MAAP4 conclusions will determine if containment venting is necessary.

3.2.2.A Final analysis of fuel pool area for Started steam and condensation impacts regarding access is not complete.

3.2.3.A There are outstanding issues Completed. See Aug 2014 Update regarding the acceptability of the MAAP4 analysis. The potential for impact of MAAP4 results on the containment heat removal strategy needs to be reviewed.

Page 8 of 12

Dresden Nuclear Power Station, Units 2 and 3 Fourth Six Month Status Report for the Implementation of FLEX February 27, 2015 Item Interim Staff Evaluation number CONFIRMATORY Item Status 3.2.4.2.A A discussion is needed on the effects Not started of extreme low temperatures (i.e.,

temperatures below those assumed in the sizing calculation for each battery) on each battery's capability to perform its function for the duration of the ELAP event.

3.2.4.2.B Procedure will be developed to Started address controlling battery room hydrogen concentration.

3.2.4.2.0 Evaluations to address loss of Not started ventilation in the auxiliary equipment electric room and Battery Rooms are not complete.

3.2.4.2.D Insufficient information to address Not started impact on elevated temperatures in areas critical to mitigation strategies.

For example, initial temperatures assumed in the analyses is not clear, critical components in pump rooms are not identified, etc. Detailed design information is needed.

3.2.4.4.A Provisions for portable lighting for Not started area access not clear. More information required.

3.2.4.4.B Confirm upgrades to communication Started system that resulted from the licensee communications assessment.

ADAMS Accession Nos. ML12306A199 and ML13056A135.

3.2.4.6.A Surface pyrometer temperature Started readings are required in the torus area.

The licensee needs to address habitability and access to the torus area.

3.2.4.6.B Final GOTHIC analysis for the HPCI Started room temperature rise is not complete.

3.2.4.6.0 Habitability of the control room Started should consider temperature limits of NUMARC 87-00 and MIL-STD-1472C.

3.2.4.8.B Detailed designs will identify Not started comprehensive load lists to confirm conceptual load assumptions.

Page 9 of 12

Dresden Nuclear Power Station, Units 2 and 3 Fourth Six Month Status Report for the Implementation of FLEX February 27, 2015 Item Interim Staff Evaluation number CONFIRMATORY Item Status 3.2.4.8.0 Insufficient information provided Proposed complete.

regarding FLEX diesel generators and The FLEX diesel generator will not be connected to plant the plant Class 1 E diesel generators electrical systems during normal operation. During a isolation to prevent simultaneously FLEX event all power to the plant electrical system will supplying power to the same Class 1 be lost per FLEX assumptions. Connection of the FLEX E bus and regarding minimum bus diesel generator requires installation of a special device voltages during the use of FLEX to allow connection of temporary cables to the associated generators. plant electrical bus. Direction for installation of this device will be controlled by procedures initiated by entry into a FLEX event. Based on this the FLEX diesel generator will not be simultaneously providing power to the busses with the Class 1 E diesel generators.

3.2.4.9.A The licensee stated in its 6-month Proposed complete.

update that a modification has been A strategy to obtain fuel oil from Emergency Diesel proposed to allow transfer of fuel oil Generator main fuel oil storage tanks without a from the 2/3 Emergency Diesel modification was developed. A submersible pump Generator main fuel oil storage tank capable of being lowered directly into a main fuel oil to the area of the proposed FLEX storage tank was identified. A procedure is being diesel generators. Need to confirm developed to provide direction for use of the pump and that the modification is installed and methods to refuel FLEX equipment. Use of the supplies sufficient fuel. submersible pump allows greater flexibility in that fuel oil can be obtained from more than just the 2/3 Emergency Diesel Generator main fuel oil storage tank.

Off-site testing of the submersible pump confirms a minimum pumping capacity of 1.3 gpm (78 gph) for each submersible pump. At the present time the largest fueling need is the FLEX Diesel Generator which has a fuel burn rate of approximately 57 gph at full load. One submersible pump will meet this requirement with margin.

The fuel oil use evaluation for equipment requiring refueling in the current strategy identifies approximately 68 gallons per hour (56.7 gph FLEX generator, 7.6 gph pump in Ultimate Heat Sink, 4.5 gph all 6 small portable generators operating). This is within the capacity of 1 submersible fuel oil pump with margin.

Multiple pumps have been obtained for use. More than one pump can be in operation at a time which further increases available refueling rates for FLEX equipment.

There are 3 Emergency Diesel Generator main fuel oil storage tanks. Each has a Technical Specification minimum volume of 10,000 gallons. With an overall fuel consumption rate of 69 gph each storage tank would Page 10 of 12

Dresden Nuclear Power Station, Units 2 and 3 Fourth Six Month Status Report for the Implementation of FLEX February 27, 2015 Item Interim Staff Evaluation number CONFIRMATORY Item Status provide a minimum of 6 days fuel requirements. Within this time off-site support would be available to obtain additional fuel.

The above discussion describes the strategy during non-flood conditions.

Because the Dresden flood event is precipitation based there is time to prepare for the flood. During those preparations station personnel will install a standpipe on the 2/3 EDG Main Fuel Oil Tank vent line. The standpipe is designed such that additional sections can be added/removed as the flood waters rise and recede. The submersible pump described above will be lowered into the standpipe. A floating platform will provide a working location for personnel and equipment to support pumping fuel oil out of the 2/3 EDG fuel oil tank.

3.2.4.9.B Assessing and maintaining fuel oil Proposed complete.

quality for FLEX equipment use was As identified in the response to 3.2.4.9.A (above) the fuel not addressed. oil for FLEX equipment will be obtained from the safety related Emergency Diesel Main Fuel Oil Storage tanks.

The fuel quality of the tanks is maintained through existing station processes for purchasing safety related fuel oil.

3.2.4.10. Final analysis for battery operation Proposed Complete A with load shed not complete. Need EC 391973 Rev 0 was developed to evaluate proposed detailed load profile for all mitigating battery load shed to support FLEX events. The strategies and a detailed discussion of evaluation addressed both 125V and 250V battery loads that will be shed, how they will systems. The evaluation identified that with the load be shed, and what are the effects of shed the 125V and 250V batteries will maintain the shed. acceptable capacity for a minimum of 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />. This time supports the FLEX Strategy time line actions.

3.4.A Details not provided to demonstrate Started the minimum capabilities for offsite resources will be met per NEI 12-06 Section 12.2.

7 Potential Draft Safety Evaluation Impacts There are no potential impacts to the Draft Safety Evaluation identified at this time.

Page 11 of 12

Dresden Nuclear Power Station, Units 2 and 3 Fourth Six Month Status Report for the Implementation of FLEX February 27, 2015 8 References The following references support the updates to the Overall Integrated Plan described in this enclosure.

1. Dresden Nuclear Power Station's Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)," dated February 28, 2013 (subsequently revised Aug 28, 2013).
2. NRC Order Number EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," dated March 12, 2012.
3. Dresden Nuclear Power Station Updated Final Safety Analysis Report, Revision 9
4. Diverse and Flexible Coping Strategies (FLEX) Implementation Guide", NEI 12-06, Revision 0, August 2012
5. Dresden's First Six Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (August 2013)
6. Dresden's Second Six Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (February 2014)
7. Dresden's Third Six Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (August 2014)
8. Engineering Change 391973 Rev 000, Extend 125VDC and 250VDC Battery Coping Time with Load Shedding.

Page 12 of 12