MONTHYEARRNP-RA/21-0035, Duke Energy Progress, Inc - Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2021-02-18018 February 2021 Duke Energy Progress, Inc - Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report RNP-RA/20-0234, Independent Spent Fuel Storage Installation, Registration of Use of Spent Fuel Casks2020-07-23023 July 2020 Independent Spent Fuel Storage Installation, Registration of Use of Spent Fuel Casks RNP-RA/20-0199, Registration of Use of Spent Fuel Casks2020-06-25025 June 2020 Registration of Use of Spent Fuel Casks RNP-RA/18-0063, Request for Extension of Due Date for Seismic Probabilistic Risk Assessment Submittal2018-11-29029 November 2018 Request for Extension of Due Date for Seismic Probabilistic Risk Assessment Submittal RNP-RA/18-0060, Transmittal of Core Operating Limits Report2018-10-17017 October 2018 Transmittal of Core Operating Limits Report RNP-RA/18-0050, Response to Supplemental Request for Additional Information Regarding License Amendment Request Proposing to Add a Qualified Offsite Circuit to Technical Specification 3.8.1, AC Sources - Operating and the Use of Load Tap Change2018-08-0101 August 2018 Response to Supplemental Request for Additional Information Regarding License Amendment Request Proposing to Add a Qualified Offsite Circuit to Technical Specification 3.8.1, AC Sources - Operating and the Use of Load Tap Change RNP-RA/18-0044, Supplement to License Amendment Request Proposing to Add a Qualified Offsite Circuit to Technical Specification 3.8.1, AC Sources - Operating and the Use of Load Tap Changers in the Automatic Mode of Operation on the Startup Transform2018-07-11011 July 2018 Supplement to License Amendment Request Proposing to Add a Qualified Offsite Circuit to Technical Specification 3.8.1, AC Sources - Operating and the Use of Load Tap Changers in the Automatic Mode of Operation on the Startup Transformers RNP-RA/18-0039, Transmittal of Emergency Procedure Revisions and 10 CFR 50.54(q) Summary of Analysis2018-06-27027 June 2018 Transmittal of Emergency Procedure Revisions and 10 CFR 50.54(q) Summary of Analysis RNP-RA/18-0041, Independent Spent Fuel Storage Installation - Register as User for Cask2018-06-13013 June 2018 Independent Spent Fuel Storage Installation - Register as User for Cask RNP-RA/18-0036, Response to Request for Additional Information (RAI) Regarding Amendment Request Proposing to Add a Qualified Offsite Circuit to Technical Specification 3.8.1, AC Sources - Operating and the Use ...2018-05-16016 May 2018 Response to Request for Additional Information (RAI) Regarding Amendment Request Proposing to Add a Qualified Offsite Circuit to Technical Specification 3.8.1, AC Sources - Operating and the Use ... RNP-RA/18-0029, Submittal of 2017 Annual Radiological Environmental Operating Report2018-05-0808 May 2018 Submittal of 2017 Annual Radiological Environmental Operating Report RNP-RA/18-0031, (Hbrsep), Unit 2 - 2017 Annual Radioactive Effluent Release Report and Offsite Dose Calculation Manual, Revision 352018-04-23023 April 2018 (Hbrsep), Unit 2 - 2017 Annual Radioactive Effluent Release Report and Offsite Dose Calculation Manual, Revision 35 RNP-RA/18-0015, Application for Technical Specifications Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequently Requirements to a Licensee Controlled Program2018-04-16016 April 2018 Application for Technical Specifications Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequently Requirements to a Licensee Controlled Program RNP-RA/18-0024, Report of Changes Pursuant to 10 CFR 50.59(d)(2)2018-04-0202 April 2018 Report of Changes Pursuant to 10 CFR 50.59(d)(2) RNP-RA/18-0020, Notification of Change in Licensed Operator Status2018-02-20020 February 2018 Notification of Change in Licensed Operator Status RNP-RA/18-0003, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2018-01-23023 January 2018 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report RNP-RA/17-0085, Request for Additional Information Regarding Application to Revise Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles2018-01-0808 January 2018 Request for Additional Information Regarding Application to Revise Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles RNP-RA/17-0086, Transmittal of Emergency Procedure Revision and 10 CFR 50.54(q) Summary of Analyses2017-12-14014 December 2017 Transmittal of Emergency Procedure Revision and 10 CFR 50.54(q) Summary of Analyses RNP-RA/17-0081, Submittal of Change in Licensed Operators Medical Status2017-12-11011 December 2017 Submittal of Change in Licensed Operators Medical Status RNP-RA/17-0079, Operator License Renewal Application2017-12-0707 December 2017 Operator License Renewal Application RNP-RA/17-0071, Independent Spent Fuel Storage Installation (ISFSI) Registration for Use of General License Spent Fuel Casks2017-10-19019 October 2017 Independent Spent Fuel Storage Installation (ISFSI) Registration for Use of General License Spent Fuel Casks RNP-RA/17-0068, Response to NRC Request for Additional Information Related to License Amendment Request Regarding Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles2017-09-28028 September 2017 Response to NRC Request for Additional Information Related to License Amendment Request Regarding Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles RNP-RA/17-0037, License Amendment Request Proposing to Add a Qualified Offsite Circuit to Technical Specifications 3.8.1, AC Sources-Operating and the Use of Load Tap Changers in the Automatic Mode of Operation on the Startup Transformers2017-09-27027 September 2017 License Amendment Request Proposing to Add a Qualified Offsite Circuit to Technical Specifications 3.8.1, AC Sources-Operating and the Use of Load Tap Changers in the Automatic Mode of Operation on the Startup Transformers RNP-RA/17-0043, Relief Request (RR)-12 for Relief from Volumetric/Surface Examination Frequency Requirements of ASME Code Case N-729-42017-09-22022 September 2017 Relief Request (RR)-12 for Relief from Volumetric/Surface Examination Frequency Requirements of ASME Code Case N-729-4 RNP-RA/17-0065, Refueling Outage 30 Steam Generator Tube Inspection Report2017-09-18018 September 2017 Refueling Outage 30 Steam Generator Tube Inspection Report RNP-RA/17-0060, Notification of Change in Licensed Operator Status2017-08-10010 August 2017 Notification of Change in Licensed Operator Status RNP-RA/17-0058, Notification of Change in Licensed Operator Status2017-08-0303 August 2017 Notification of Change in Licensed Operator Status RNP-RA/17-0055, Transmittal of Core Operating Limits Report for Cycle 312017-07-26026 July 2017 Transmittal of Core Operating Limits Report for Cycle 31 RNP-RA/17-0042, Submittal of the PWROG-14048-P, Revision 1, to Satisfy the Regulatory Commitment Related to the Pressurized Water Reactor Internals Program Plan for Aging Management of Reactor Internals2017-06-29029 June 2017 Submittal of the PWROG-14048-P, Revision 1, to Satisfy the Regulatory Commitment Related to the Pressurized Water Reactor Internals Program Plan for Aging Management of Reactor Internals RNP-RA/17-0051, Submittal of Nine Day Inservice Inspection Summary Report2017-06-29029 June 2017 Submittal of Nine Day Inservice Inspection Summary Report RNP-RA/17-0041, Transmittal of Technical Specifications Bases Revisions2017-05-23023 May 2017 Transmittal of Technical Specifications Bases Revisions RNP-RA/17-0038, (Hbrsep), Unit No. 2 - 2016 Annual Radiological Environmental Operating Report2017-05-0909 May 2017 (Hbrsep), Unit No. 2 - 2016 Annual Radiological Environmental Operating Report RNP-RA/17-0034, Modification of Request for Technical Specification Change to Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles (MF9544)2017-05-0202 May 2017 Modification of Request for Technical Specification Change to Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles (MF9544) RNP-RA/17-0036, (Hbrsep), Unit No. 2 - 2016 Annual Radioactive Effluent Release Report and Offsite Dose Calculation Manual, Current Revision 342017-04-25025 April 2017 (Hbrsep), Unit No. 2 - 2016 Annual Radioactive Effluent Release Report and Offsite Dose Calculation Manual, Current Revision 34 RNP-RA/17-0031, Provides Additional Information Regarding License Amendment Request to Adopt Technical Specifications Task Force (TSTF) Traveler 522, Revision 02017-04-20020 April 2017 Provides Additional Information Regarding License Amendment Request to Adopt Technical Specifications Task Force (TSTF) Traveler 522, Revision 0 RNP-RA/17-0033, Flood Hazard Mitigating Strategies Assessment (MSA) Report Submittal2017-04-12012 April 2017 Flood Hazard Mitigating Strategies Assessment (MSA) Report Submittal RNP-RA/17-0014, Resubmittal of Request for Technical Specification Change to Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles2017-04-0303 April 2017 Resubmittal of Request for Technical Specification Change to Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles RNP-RA/17-0028, Submittal of Engineering Calculation in Support of a Request for Technical Specification Change to Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles2017-04-0303 April 2017 Submittal of Engineering Calculation in Support of a Request for Technical Specification Change to Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles RNP-RA/17-0021, Transmittal of Core Operating Limits Report2017-03-13013 March 2017 Transmittal of Core Operating Limits Report RNP-RA/17-0019, Supplemental Submittal to Correct Marked Up Technical Specifications (TS) Pages Transmitted with Application for Technical Specification Task Force (TSTF)-339, Relocate TS Parameters to the COLR Consistent with WCAP-14483, Revision 22017-03-0808 March 2017 Supplemental Submittal to Correct Marked Up Technical Specifications (TS) Pages Transmitted with Application for Technical Specification Task Force (TSTF)-339, Relocate TS Parameters to the COLR Consistent with WCAP-14483, Revision 2 RNP-RA/17-0015, Independent Spent Fuel Storage Installations - Letter Regarding Report of Changes Pursuant to 10 CFR 72.482017-02-22022 February 2017 Independent Spent Fuel Storage Installations - Letter Regarding Report of Changes Pursuant to 10 CFR 72.48 RNP-RA/17-0016, Independent Spent Fuel Storage Installation - Annual Radioactive Effluent Release Report2017-02-22022 February 2017 Independent Spent Fuel Storage Installation - Annual Radioactive Effluent Release Report RNP-RA/17-0015, H.B. Robinson Steam Electric Plant & ISFSIs - Report of Changes Pursuant to 10 CFR 72.482017-02-22022 February 2017 H.B. Robinson Steam Electric Plant & ISFSIs - Report of Changes Pursuant to 10 CFR 72.48 RNP-RA/16-0100, Response to Apparent Violation in NRC Inspection Report 05000261/2016404, EA-16-2272017-01-24024 January 2017 Response to Apparent Violation in NRC Inspection Report 05000261/2016404, EA-16-227 RNP-RA/16-0097, Transmittal Letter for Response to Inspection Report Temporary Instruction 2201/004, Inspection of Implementation of Interim Cyber Security Milestones 1-7, Inspection Report 05000261/20154052016-12-15015 December 2016 Transmittal Letter for Response to Inspection Report Temporary Instruction 2201/004, Inspection of Implementation of Interim Cyber Security Milestones 1-7, Inspection Report 05000261/2015405 RNP-RA/16-0089, Request for Withdrawal of License Amendment Request for Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles2016-11-10010 November 2016 Request for Withdrawal of License Amendment Request for Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles RNP-RA/16-0090, Notification of Rescheduled Date for 2017 Emergency Preparedness Graded Exercise2016-11-10010 November 2016 Notification of Rescheduled Date for 2017 Emergency Preparedness Graded Exercise RNP-RA/16-0087, Technical Specifications Section 5.6.6 Post Accident Monitoring Instrumentation Report for Inoperable High Range Containment Area Radiation Monitors2016-10-31031 October 2016 Technical Specifications Section 5.6.6 Post Accident Monitoring Instrumentation Report for Inoperable High Range Containment Area Radiation Monitors RNP-RA/16-0078, Technical Specifications Section 5.6.6, Post Accident Monitoring Instrumentation Report for Inoperable High Range Containment Area Radiation Monitors2016-10-0505 October 2016 Technical Specifications Section 5.6.6, Post Accident Monitoring Instrumentation Report for Inoperable High Range Containment Area Radiation Monitors RNP-RA/16-0079, Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Light Water Reactor Electric Generating Plants.2016-10-0505 October 2016 Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Light Water Reactor Electric Generating Plants. 2021-02-18
[Table view] Category:Technical Specifications
MONTHYEARML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 RA-23-0029, Technical Specifications Section 5.6.6 Post Accident Monitoring Instrumentation Report for Inoperable Containment Sump Water Level (Wide Range)2023-01-30030 January 2023 Technical Specifications Section 5.6.6 Post Accident Monitoring Instrumentation Report for Inoperable Containment Sump Water Level (Wide Range) ML22329A2982023-01-19019 January 2023 Issuance of Amendment No. 274 Regarding Revision of Technical Specification 3.8.1 Surveillance Requirement 3.8.1.16 ML22294A0922022-12-15015 December 2022 Issuance of Amendment No. 273 Regarding Adoption of TSTF-577, Revised Frequencies for Steam Generator Tube Inspections, Revision 1 ML22159A2952022-08-0303 August 2022 Issuance of Amendment No. 271 Regarding Correction to Non-Conservative Technical Specifications Figure 3.4.3-2, Pressure/Temperature Limit Cooldown Curves ML19158A3072019-08-15015 August 2019 Issuance of Amendment No. 265, Regarding Adoption of TSTF-425, Revision 3, Relocate Surveillance Frequencies to Licensee Control - RITSTF Initiative 5b RA-19-0308, Clean Technical Specifications Pages Regarding Application to Adopt TSTF-425, Revision 32019-07-16016 July 2019 Clean Technical Specifications Pages Regarding Application to Adopt TSTF-425, Revision 3 ML18200A0422018-08-16016 August 2018 Issuance of Amendment No. 260 Regarding Request to Revise Technical Specification Reactor Coolant System Pressure and Temperature Limits to Reflect 24-Month Fuel Cycles RA-17-0001, Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules2017-07-18018 July 2017 Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules ML17066A3742017-04-26026 April 2017 Issuance of Amendments Re. Application to Revise TSs to Adopt TSTF-427, Rev. 2, Using the Consolidated Line Item Improvement Process (CAC Nos. MF8039 Through MF8049) RNP-RA/17-0019, Supplemental Submittal to Correct Marked Up Technical Specifications (TS) Pages Transmitted with Application for Technical Specification Task Force (TSTF)-339, Relocate TS Parameters to the COLR Consistent with WCAP-14483, Revision 22017-03-0808 March 2017 Supplemental Submittal to Correct Marked Up Technical Specifications (TS) Pages Transmitted with Application for Technical Specification Task Force (TSTF)-339, Relocate TS Parameters to the COLR Consistent with WCAP-14483, Revision 2 RA-15-0042, Application to Revise Technical Specifications to Adopt Methodology Report DPC-NE-3008-P, Revision 0, Thermal-Hydraulic Models for Transient Analysis.2015-11-19019 November 2015 Application to Revise Technical Specifications to Adopt Methodology Report DPC-NE-3008-P, Revision 0, Thermal-Hydraulic Models for Transient Analysis. ML15222B1752015-09-0808 September 2015 Issuance of Amendment to Modify Technical Specification 3.8.1, Diesel Generator Testing Requirements RA-15-0031, Application to Revise Technical Specifications for Methodology Report DPC-NE-1008-P, Revision 0, Nuclear Design Methodology Using CASMO-5/Simulate-3 for Westinghouse Reactors.2015-08-19019 August 2015 Application to Revise Technical Specifications for Methodology Report DPC-NE-1008-P, Revision 0, Nuclear Design Methodology Using CASMO-5/Simulate-3 for Westinghouse Reactors. RNP-RA/15-0026, Technical Specifications (TS) Section 5.6.6, Post Accident Monitoring (PAM) Instrumentation Report, 14-Day Report for the Inoperability of Pressurizer Power Operated Relief Valves Position Indication2015-04-0101 April 2015 Technical Specifications (TS) Section 5.6.6, Post Accident Monitoring (PAM) Instrumentation Report, 14-Day Report for the Inoperability of Pressurizer Power Operated Relief Valves Position Indication RNP-RA/13-0117, License Amendment Request to Modify Technical Specification 3.3.1, Reactor Protection System (RPS) Instrumentation2014-02-10010 February 2014 License Amendment Request to Modify Technical Specification 3.3.1, Reactor Protection System (RPS) Instrumentation ML13198A3672013-08-29029 August 2013 Issuance of an Amendment to Revise the Steam Generator Program Inspection Frequencies and Tube Sample Selection and Application of Permanent Alternate Repair Criteria (H*) RNP-RA/13-0089, Supplemental Submittal to Correct TS Pages Re Request for Revision to Steam Generator Program Inspection Frequencies & Tube Sample Selection & Application of Permanent Alternate Repair Criteria2013-08-22022 August 2013 Supplemental Submittal to Correct TS Pages Re Request for Revision to Steam Generator Program Inspection Frequencies & Tube Sample Selection & Application of Permanent Alternate Repair Criteria RNP-RA/13-0002, License Amendment Request to Modify Technical Specification 3.1.7 to Delete the Monthly Rod Position Indication Surveillance Requirements2013-06-0707 June 2013 License Amendment Request to Modify Technical Specification 3.1.7 to Delete the Monthly Rod Position Indication Surveillance Requirements ML12339A0672012-12-18018 December 2012 Issuance of License Amendments Regarding Cyber Security RNP-RA/12-0057, License Amendment Request for Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection and Application of Permanent Alternate Repair Criteria (H*)2012-08-29029 August 2012 License Amendment Request for Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection and Application of Permanent Alternate Repair Criteria (H*) ML11342A1652011-12-29029 December 2011 Issuance of an Amendment on Technical Specifications Related to Use of Areva'S M5 Advanced Alloy in Fuel Cladding and Fuel Assembly Components RNP-RA/10-0096, Request for Technical Specifications Change Regarding Use of M5 Alloy Fuel2010-10-20020 October 2010 Request for Technical Specifications Change Regarding Use of M5 Alloy Fuel ML1008303302010-03-25025 March 2010 Issuance of Amendment Regarding Technical Specifications Changes Related to the Chemical and Volume Control System RNP-RA/10-0024, Request for Emergency Technical Specifications Change to Section 3.4.17, Chemical and Volume Control System (CVCS)2010-03-22022 March 2010 Request for Emergency Technical Specifications Change to Section 3.4.17, Chemical and Volume Control System (CVCS) RNP-RA/10-0001, Request for Technical Specification Changes to Section 3.3.2, Engineered Safety Feature, Actuation System (ESFAS) Instrumentation, and Section 3.3.6, Containment Ventilation Isolation Instrumentation2010-03-0505 March 2010 Request for Technical Specification Changes to Section 3.3.2, Engineered Safety Feature, Actuation System (ESFAS) Instrumentation, and Section 3.3.6, Containment Ventilation Isolation Instrumentation ML0936312122009-12-16016 December 2009 Request for Technical Specifications Change Regarding Steam Generator Alternate Repair Criteria RNP-RA/09-0024, Transmittal of Technical Specifications Bases Revisions2009-04-16016 April 2009 Transmittal of Technical Specifications Bases Revisions ML0813403232008-07-23023 July 2008 Issuance of Amendment Regarding the Incorporation of Technical Specification Task Force Standard Technical Specification Change Traveler, TSTF-448, Revision 3, Control Room Habitability. ML0815402792008-06-19019 June 2008 Tech Spec Pages for Amendment 218 Regarding Administrative Changes to the Operating License and Technical Specifications ML0803300542008-01-29029 January 2008 Tech Spec Pages for Amendment 217 to Make a One-time Change to Technical Specification (TS) 3.1.7 Rod Position Indication. ML0726102012007-09-19019 September 2007 Technical Specification, Correction to Technical Specification Page Issued with Amendment No. 215 Issued on June 15, 2007 ML0725706282007-09-18018 September 2007 Correction to Technical Specification Pages Issued with Amendment No. 216 Issued on July 16, 2007 RNP-RA/07-0095, Correction to Technical Specifications Page in Amendment 2162007-09-12012 September 2007 Correction to Technical Specifications Page in Amendment 216 ML0720102362007-07-16016 July 2007 Tech Spec Pages for Amendment 216 to Adopt Technical Specifications Task Force (TSTF) Standard TS Change Traveler, TSTF-447, Using the Consolidated Line Item Improvement Process ML0717202542007-06-15015 June 2007 Technical Specifications Changes Related to Containment Peak Pressure ML0709900232007-04-0404 April 2007 Technical Specifications, Changes Surveillance Requirement (SR) 3.5.2.6 RNP-RA/07-0032, Additional Information Pertaining to Proposed Technical Specifications Changes Regarding Steam Generator Tube Repair Criteria2007-03-22022 March 2007 Additional Information Pertaining to Proposed Technical Specifications Changes Regarding Steam Generator Tube Repair Criteria RNP-RA/07-0023, Response to NRC Request for Additional Information Pertaining to Proposed Technical Specifications Changes Regarding Steam Generator Tube Repair Criteria2007-03-13013 March 2007 Response to NRC Request for Additional Information Pertaining to Proposed Technical Specifications Changes Regarding Steam Generator Tube Repair Criteria ML0628404592006-10-0404 October 2006 Tech Spec Pages for Amendment 208 Regarding Emergency Diesel Generator or Automatic Trips Bypass TS 3.8.1 ML0627100222006-09-22022 September 2006 Technical Specification Amendment No. 210 - H.B. Robinson, Unit 2 - Issuance of Amendment and Partial Denial Reactor Protection System and Engineered Safety Feature Actuation System Instrumentation Tables ML0627005192006-09-20020 September 2006 Technical Specifications, Amendment, Methodology for Large Break Loss-of-Coolant Accident RNP-RA/06-0048, Request for Technical Specifications, Change Related to Containment Peak Pressure2006-07-17017 July 2006 Request for Technical Specifications, Change Related to Containment Peak Pressure ML0621900412006-07-11011 July 2006 Technical Specifications, Alternate Source Term for the loss-of-coolant RNP-RA/06-0046, Request for Technical Specifications Change to Section 3.5.2. Emergency Core Cooling System2006-06-0101 June 2006 Request for Technical Specifications Change to Section 3.5.2. Emergency Core Cooling System RNP-RA/06-0028, Request for Technical Specifications Change Regarding Steam Generator Tube Integrity Using the Consolidated Line Item Improvement Process2006-05-30030 May 2006 Request for Technical Specifications Change Regarding Steam Generator Tube Integrity Using the Consolidated Line Item Improvement Process ML0610805222006-04-11011 April 2006 H. B. Robinson, Unit 2 - Request for Technical Specification Change to Core Operating Limits Report References RNP-RA/06-0027, ANP-2512(NP), Loss of Forced Reactor Coolant Flow Analysis.2006-03-31031 March 2006 ANP-2512(NP), Loss of Forced Reactor Coolant Flow Analysis. ML0524205242005-08-25025 August 2005 Tech Spec Pages for Amendment 206 DC Sources - Operation and Shutdown RNP-RA/05-0062, Response to Request for Additional Information Regarding Technical Specifications Change Request to Section 3.8.4 DC Sources - Operating2005-07-13013 July 2005 Response to Request for Additional Information Regarding Technical Specifications Change Request to Section 3.8.4 DC Sources - Operating 2023-08-29
[Table view] |
Text
10 CFR 50.90 Progress Energy Serial: RNP-RA/07-0032 MAR, 22 2007 United States Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 DOCKET NO. 50-261/LICENSE NO. DPR-23 ADDITIONAL INFORMATION PERTAINING TO PROPOSED TECHNICAL SPECIFICATIONS CHANGES REGARDING STEAM GENERATOR TUBE REPAIR CRITERIA Ladies and Gentlemen:
In a letter dated January 19, 2007, Carolina Power and Light Company, also known as Progress Energy Carolinas, Inc. (PEC), requested NRC review and approval of changes to modify the Technical Specifications (TS) requirements related to steam generator tube alternate repair criteria for H. B. Robinson Steam Electric Plant (HBRSEP), Unit No. 2. An NRC request for additional information (RAI) pertaining to this amendment request was received by electronic mail transmission dated February 8, 2007. A response to that RAI was provided by letter dated March 13, 2007.
In telephone communications with the NRC staff reviewers for this proposed TS change, an apparent typographical error was noted in Table 7-11 a, Attachment II, of the March 13, 2007 letter. Specifically, the term "Hot Leg" should be changed to "Cold Leg" in that table, consistent with Table 7-12a.
Additionally, it was identified that the alternate repair criteria as proposed should be further clarified to state that it shall be applied as an alternative until the end of Operating Cycle 25, in lieu of stating that it may be applied. The proposed revision to TS page 5.0-13 is provided with this letter, which shows this clarification.
This clarification of the proposed TS requirement does not significantly alter the proposed requirements or associated technical justifications.
Attachment I provides an Affirmation in accordance with the provisions of 10 CFR 50.30(b).
Attachment II provides the revised edited TS page. Attachment III provides the revised TS page.
Progress Energy Carolinas. Inc.
Robinson Nuclear Plant 3581 West Entrance Road SC 29550 Hartsville,
United States Nuclear Regulatory Commission Serial: RNP-RA/07-0032 Page 2 of 2 In accordance with 10 CFR 50.91, a copy of this application is being provided to the State of South Carolina.
If you have any questions concerning this matter, please contact Mr. C. T. Baucom at (843) 857-1253.
Sincerely, Manager - Support Services - Nuclear JFL/cac Attachments: I. Affirmation II. Revised Edited Technical Specifications Page III. Revised Technical Specifications Page c: Mr. T. P. O'Kelley, Director, Bureau of Radiological Health (SC)
Mr. H. J. Porter, Director, Division of Radioactive Waste Management (SC)
Dr. W. D. Travers, NRC, Region II Ms. L. M. Regner, NRC, NRR Mr. C. P. Patel, NRC, NRR NRC Resident Inspector, HBRSEP Attorney General (SC)
United States Nuclear Regulatory Commission Attachment I to Serial: RNP-RA/07-0032 Page 1 of I AFFIRMATION The information contained in letter RNP-RA/07-0032 is true and correct to the best of my information, knowledge and belief; and the sources of my information are officers, employees, contractors, and agents of Carolina Power and Light Company, also known as Progress Energy Carolinas, Inc. I declare under penalty of perjury that the foregoing is true and correct.
Executed On:
T. D. Walt Vice President, HBRSEP, Unit No. 2
United States Nuclear Regulatory Commission Attachment II to Serial: RNP-RA/07-0032 2 pages (including this page)
H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 REVISED EDITED TECHNICAL SPECIFICATIONS PAGE
The following alternate tube repair criteria shall be applied as an alternative to the preceding criteria, until the end of Operating Cycle 25:
Flaws found in the portion of the tube below 17 inches from the top of the tubesheet do not require plugging. Tubes with flaws identified in the portion of the tube from the top of the tubesheet to 17 inches below the top of the tubesheet shall be plugged upon detection.
Prociranis Lao rianu d I S 5 ý5 5.5 Programs and Manuals-559 Steam Generator 1,SG) Proc-ran (continued)
- 2. Accident induced leakage performance criterion: The primary to secondary accident induced leakage rate for any design basis accident, other than a SG tube rupture, shall not exceed the leakage rate assumed in the accident analysis in terms of total leakage rate for all SGs and (until the en d leakage rate for an individual SG_ Leakage is not to of Operating exceed 75 gallons per day per SG.
Cycle 25 the required 3. The operational LEAKAGE performance criterion is specified in LCO 3.4.13, "RCS Operational LEAKAGE."
inspection length extend s c. Provisions for SG tube repair criteria. Tubes found by 17 inches bel ow inservice inspection to contain flaws with a depth equal to the top of th ie or exceeding the following criteria shall be plugged: 47% of tubesheet on the nominal tube wall thickness if the next inspection the tube hot interval of that tube is 12 months, and a 2% reduction in the leg side to I7 repair criteria for each 12 month period until the next inches below inspection of the tube.
the top of th ie d. Provisions for SG tube inspections. Periodic SG tube tubesheet on inspections shall be performed. The number and portions of the tube cold the tubes inspected and methods of inspection shall be leg side) performed with the objective of detecting flaws of any type (e-g. volumetric flaws. axial and circumferential cracks) that may be present along the length of the tube. from the tube-to-tubesheet weld at the tube inlet to the tube-to-tubesheet weld at the tube outlet* and that may satisfy the applicable tube repair criteria. The tube-to-tubesheet weld is not part of the tube. In addition to meeting the requirements of d.l. d.2. and d_3 below, the inspection scope. inspection methods, and inspection intervals shall be such as to ensure that SG tube integrity is maintained until the next SG inspection. An assessment of degradation shall be performed to determine the type and location of flaws to which the tubes may be susceptible and, based on this assessment. to determine which inspection methods need to be employed and at what locations-1P Inspect 100.. of the tubes in each SG during the first refueling outage following SG replacement.
- 2. Inspect 100% of the tubes at sequential periods of 120.
- 90. and. thereafter. 60 effective full power months- The first sequential period shall be considered to begin after the first inservice inspection of the SGs. In (continued)
HBRSEP Unit No. 2 5.0-13 Amendment No-
United States Nuclear Regulatory Commission Attachment III to Serial: RNP-RA/07-0032 2 pages (including this page)
H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 REVISED TECHNICAL SPECIFICATIONS PAGE
Programs and Manuals 55 5_5 Programs and Manual s 5.5_9 Steam Generator (SG) Program (continued)
- 2. Accident induced leakage performance criterion: The primary to secondary accident induced leakage rate for any design basis accident, other than a SG tube rupture, shall not exceed the leakage rate assumed in the accident analysis in terms of total leakage rate for all SGs and leakage rate for an individual 5G. Leakage is not to exceed 75 gallons per day per SG.
- 3. The operational LEAKAGE performance criterion is specified in LCO 3-4-13. "RCS Operational LEAKAGE-"
- c. Provisions for SG tube repair criteria. Tubes found by inservice inspection to contain flaws with a depth equal to or exceeding the following criteria shall be plugged: 47% of the nominal tube wall thickness if the next inspection interval of that tube is 12 months, and a 21 reduction in the repair criteria for each 12 month period until the next inspection of the tube.
The following alternate tube repair criteria shall be applied as an alternative to the preceding criteria, until the end of Operating Cycle 25:
Flaws found in the portion of the tube below 17 inches from the top of the tubesheet do not require plugging. Tubes with flaws identified in the portion of the tube from the top of the tubesheet to 17 inches below the top of the tubesheet shall be plugged upon detection.
- d. Provisions for SG tube inspections. Periodic SG tube inspections shall be performed. The number and portions of the tubes inspected and methods of inspection shall be performed with the objective of detecting flaws of any type (e.g., volumetric flaws. axial and circumferential cracks) that may be present along the length of the tube. from the tube-to-tubesheet weld at the tube inlet to the tube-to-tubesheet weld at the tube outlet (until the end of Operating Cycle 25 the required inspection length extends 17 inches below the top of the tubesheet on the tube hot leg side to 17 inches below the top of the tubesheet on the tube cold leg side). and that may satisfy the applicable tube repair criteria. The tube-to-tubesheet weld is not part of the tube.
in addition to meeting the requirements of d-l. d-2, and d-3 below, the inspection scope, inspection methods. and (continued)
HBRSEP Unit No- 2 5. 0-13 Amlendment No.