Tech Spec Pages for Amendment 217 to Make a One-time Change to Technical Specification (TS) 3.1.7 Rod Position Indication.
ML080330054
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 01/29/2008
From:
NRC/NRR/ADRO/DORL/LPLII-2
To:
Vaaler, Marlayna, NRO/DNRL 415-3178
Shared Package
ML080170047 List:
References
TAC MD7335
Download: ML080330054 (2)


Text

neutron sources for reactor startup, sealed sources for reactor instrumentation and radiation monitoring equipment calibration, and as fission detectors in amounts as required; D. Pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive, possess, and use in amounts as required any byproduct, source, or special nuclear material without restriction to chemical or physical form for sample analysis or instrument and equipment calibration or associated with radioactive apparatus or components; E. Pursuant to the Act and 10 CFR Parts 30 and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by operation of the facility.

3. This renewed license shall be deemed to contain and is subject to the conditions specified in the following Commission regulations: 10 CFR Part 20, Section 30.34 of 10 CFR Part 30, Section 40.41 of 10 CFR Part 40, Section 50.54 and 50.59 of 10 CFR Part 50, and Section 70.32 of 10 CFR Part 70; and is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:

A. -Maximum Power Level The licensee is authorized to operate the facility at a steady state reactor core power level not in excess of 2339 megawatts thermal.

B. Technical Specifications The Technical Specifications contained in Appendix A, as revised through

'Amendment No. 217 are hereby incorporated in the license.

The licensee shall operate the facility in accordance with the Technical Specifications.

(1) For Surveillance Requirements (SRs) that are new in Amendment 176 to Final Operating License DPR-23, the first performance is due at the end of the first surveillance interval that begins at implementation of Amendment 176. For SRs that existed prior to Amendment 176, including SRs with modified acceptance criteria and SRs whose frequency of performance is being extended, the first performance is due at the end of the first surveillance interval that begins on the date the Surveillance was last performed prior to implementation of Amendment 176.

Renewed Facility Operating License No. DPR-23 Amendment No. 217

Rod Position Indication 3.1.7 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME B. (continued) B.2 Reduce THERMAL POWER 8 hours0.333 days <br />0.0476 weeks <br />0.011 months <br /> to < 50% RTP.

C. One demand position C.1.1 Verify by Once per indicator per bank administrative means 8 hours0.333 days <br />0.0476 weeks <br />0.011 months <br /> inoperable for one or all ARPIs 'for the more banks.* affected banks are OPERABLE.

AND C.1.2 -------- NOTE ---------

Only required to be met for bank positions < 200 steps.

Verify the position Once per of each rod in the 8 hours0.333 days <br />0.0476 weeks <br />0.011 months <br /> affected bank(s) is within 7.5 inches of the average of the individual rod positions in the affected bank(s).

AND (continued)

  • During Cycle 25. the condition of two demand position indicators per bank inoperable for one or more banks is allowed with a required action to restore one demand position indicator per bank and a completion time of 4 hours0.167 days <br />0.0238 weeks <br />0.00548 months <br />.

HBRSEP Unit No. 2 .3.1-16 Amendment No. 217