Category:Letter type:PNP
MONTHYEARPNP 2023-030, License Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations2023-12-14014 December 2023 License Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations PNP 2023-035, Withdrawal of License Amendment Request - Revise License Condition to Eliminate Cyber Security Plan Requirements2023-12-12012 December 2023 Withdrawal of License Amendment Request - Revise License Condition to Eliminate Cyber Security Plan Requirements PNP 2023-028, Application for Order Consenting to Transfer of Control of License and Approving Conforming License Amendments2023-12-0606 December 2023 Application for Order Consenting to Transfer of Control of License and Approving Conforming License Amendments PNP 2023-026, Pre-Submittal Meeting Presentation - Palisades Nuclear Plant License Transfer Application to Support Resumption of Power Operations2023-09-28028 September 2023 Pre-Submittal Meeting Presentation - Palisades Nuclear Plant License Transfer Application to Support Resumption of Power Operations PNP 2023-025, Request for Exemption from Certain Termination of License Requirements of 10 CFR 50.822023-09-28028 September 2023 Request for Exemption from Certain Termination of License Requirements of 10 CFR 50.82 PNP 2023-023, Special Report High Range Noble Gas Monitor Inoperable2023-08-0909 August 2023 Special Report High Range Noble Gas Monitor Inoperable PNP 2023-018, 2022 Annual Non-Radiological Environmental Operating Report2023-04-25025 April 2023 2022 Annual Non-Radiological Environmental Operating Report PNP 2023-007, and Big Rock Point, 2022 Annual Radioactive Effluent Release and Waste Disposal Reports2023-04-19019 April 2023 and Big Rock Point, 2022 Annual Radioactive Effluent Release and Waste Disposal Reports PNP 2023-008, 2022 Radiological Environmental Operating Report2023-04-18018 April 2023 2022 Radiological Environmental Operating Report PNP 2023-002, 6 to Updated Final Safety Analysis Report2023-03-31031 March 2023 6 to Updated Final Safety Analysis Report PNP 2023-006, Report of Changes to Security Plan, Revision 202023-03-29029 March 2023 Report of Changes to Security Plan, Revision 20 PNP 2023-012, Presentation on Regulatory Path to Reauthorize Power Operations2023-03-16016 March 2023 Presentation on Regulatory Path to Reauthorize Power Operations PNP 2023-001, Regulatory Path to Reauthorize Power Operations2023-03-13013 March 2023 Regulatory Path to Reauthorize Power Operations PNP 2023-004, Report of Changes to Palisades Nuclear Plant Technical Specification Bases2023-03-0808 March 2023 Report of Changes to Palisades Nuclear Plant Technical Specification Bases PNP 2023-005, Response to Palisades Nuclear Plant - Request for Additional Information Related to the Post-Shutdown Decommissioning Activities Report2023-03-0101 March 2023 Response to Palisades Nuclear Plant - Request for Additional Information Related to the Post-Shutdown Decommissioning Activities Report PNP 2022-037, Report of Changes to Security Plan, Revision 192022-12-14014 December 2022 Report of Changes to Security Plan, Revision 19 PNP 2022-036, Response to Request for Additional Information Regarding License Amendment Request for Proposed Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme2022-11-0808 November 2022 Response to Request for Additional Information Regarding License Amendment Request for Proposed Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme PNP 2022-035, International - Notification of Commitment Cancellations for Remaining Activities Related to Beyond-Design-Basis Seismic Hazard Reevaluations2022-11-0202 November 2022 International - Notification of Commitment Cancellations for Remaining Activities Related to Beyond-Design-Basis Seismic Hazard Reevaluations PNP 2022-026, Request for Exemption from 10 CFR 50.54(w)(1) Concerning Onsite Property Damage Insurance2022-10-26026 October 2022 Request for Exemption from 10 CFR 50.54(w)(1) Concerning Onsite Property Damage Insurance PNP 2022-024, Request for Exemption from 10 CFR 140.11(a)(4) Concerning Primary and Secondary Liability Insurance2022-10-26026 October 2022 Request for Exemption from 10 CFR 140.11(a)(4) Concerning Primary and Secondary Liability Insurance PNP 2022-031, License Amendment Request, Revise License Condition to Eliminate Cyber Security Plan Requirements2022-09-14014 September 2022 License Amendment Request, Revise License Condition to Eliminate Cyber Security Plan Requirements PNP 2022-025, Report of Changes to Palisades Nuclear Plant Security Plan, Revision 182022-09-12012 September 2022 Report of Changes to Palisades Nuclear Plant Security Plan, Revision 18 PNP 2022-032, 2022 Evacuation Time Estimate Report2022-09-0707 September 2022 2022 Evacuation Time Estimate Report PNP 2022-023, Report of Changes to Palisades Nuclear Plant Security Plan, Revision 172022-08-15015 August 2022 Report of Changes to Palisades Nuclear Plant Security Plan, Revision 17 PNP 2022-014, Report of Changes to Palisades Nuclear Plant Site Emergency Plan, Revision 342022-07-13013 July 2022 Report of Changes to Palisades Nuclear Plant Site Emergency Plan, Revision 34 PNP 2022-016, License Amendment Request: Proposed Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme2022-07-12012 July 2022 License Amendment Request: Proposed Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme PNP 2022-017, Request for Exemptions from Certain Emergency Planning Requirements of 10 CFR 50.47(b); 10 CFR 50.47(c)(2); and 10 CFR Part 50, Appendix E2022-07-11011 July 2022 Request for Exemptions from Certain Emergency Planning Requirements of 10 CFR 50.47(b); 10 CFR 50.47(c)(2); and 10 CFR Part 50, Appendix E PNP 2022-019, & Big Rock Point - Notification of Expected Date of Transfer of Ownership of Nuclear Plants to Holtec Palisades, LLC; and Notification of Receipt of All Required Regulatory Approvals2022-06-24024 June 2022 & Big Rock Point - Notification of Expected Date of Transfer of Ownership of Nuclear Plants to Holtec Palisades, LLC; and Notification of Receipt of All Required Regulatory Approvals PNP 2022-011, Termination of the Emergency Response Data System (Eros) Link2022-06-13013 June 2022 Termination of the Emergency Response Data System (Eros) Link PNP 2022-010, Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel2022-06-13013 June 2022 Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel PNP 2022-004, 2021 Radiological Environmental Operating Report2022-05-12012 May 2022 2021 Radiological Environmental Operating Report PNP 2022-003, and Big Pock Point Plant - 2021 Annual Radioactive Effluent Release and Waste Disposal Report2022-04-25025 April 2022 and Big Pock Point Plant - 2021 Annual Radioactive Effluent Release and Waste Disposal Report PNP 2022-007, 2021 Annual Non-Radiological Environmental Operating Report2022-04-21021 April 2022 2021 Annual Non-Radiological Environmental Operating Report PNP 2022-012, Response to Request for Additional Information Regarding License Amendment Request to Revise Facility Operating License and Technical Specifications for a Permanently Defueled Condition2022-04-21021 April 2022 Response to Request for Additional Information Regarding License Amendment Request to Revise Facility Operating License and Technical Specifications for a Permanently Defueled Condition PNP 2022-002, Annual Report of Changes in Emergency Core Cooling System Models2022-03-24024 March 2022 Annual Report of Changes in Emergency Core Cooling System Models PNP 2021-012, Report of Changes, Tests and Experiments, and Summary of Commitment Changes2021-10-0707 October 2021 Report of Changes, Tests and Experiments, and Summary of Commitment Changes PNP 2021-029, Pre-Notice of Disbursement from Decommissioning Trust2021-09-0202 September 2021 Pre-Notice of Disbursement from Decommissioning Trust PNP 2021-013, Request for Rescission of Interim Compensatory Measure from Order EA-02-0262021-07-21021 July 2021 Request for Rescission of Interim Compensatory Measure from Order EA-02-026 PNP 2021-020, Request for Partial Exemption from Record Retention Requirements in 10 CFR 50.122021-06-15015 June 2021 Request for Partial Exemption from Record Retention Requirements in 10 CFR 50.12 PNP 2021-005, License Amendment Request to Revise Renewed Facility Operating License and Technical Specifications for Permanently Defueled Condition2021-06-0101 June 2021 License Amendment Request to Revise Renewed Facility Operating License and Technical Specifications for Permanently Defueled Condition PNP 2021-026, Pre-Notice of Disbursement from Decommissioning Trust2021-05-27027 May 2021 Pre-Notice of Disbursement from Decommissioning Trust PNP 2021-016, 2020 Radiological Environmental Operating Report2021-05-12012 May 2021 2020 Radiological Environmental Operating Report PNP 2021-022, 2020 Annual Non-Radiological Environmental Operating Report2021-04-27027 April 2021 2020 Annual Non-Radiological Environmental Operating Report PNP 2021-015, and Big Rock Point, Submittal of 2020 Annual Radioactive Effluent Release and Waste Disposal Report2021-04-21021 April 2021 and Big Rock Point, Submittal of 2020 Annual Radioactive Effluent Release and Waste Disposal Report PNP 2021-017, Schedule Change to Open Phase Condition Detection Implementation2021-04-0101 April 2021 Schedule Change to Open Phase Condition Detection Implementation PNP 2021-003, 2020 Steam Generator Tube Inspection Report2021-03-25025 March 2021 2020 Steam Generator Tube Inspection Report PNP 2021-010, Annual Report of Changes in Emergency Core Cooling System Models2021-03-19019 March 2021 Annual Report of Changes in Emergency Core Cooling System Models PNP 2021-004, Report - Changes to Palisades Nuclear Plant Technical Specifications Bases2021-03-10010 March 2021 Report - Changes to Palisades Nuclear Plant Technical Specifications Bases PNP 2021-006, Pre-Notice of Disbursement from Decommissioning Trust2021-03-0808 March 2021 Pre-Notice of Disbursement from Decommissioning Trust PNP 2021-001, ASME Section XI 90-Day Owner'S Activity Report2021-01-12012 January 2021 ASME Section XI 90-Day Owner'S Activity Report 2023-09-28
[Table view] Category:Report
MONTHYEARPNP 2023-025, Request for Exemption from Certain Termination of License Requirements of 10 CFR 50.822023-09-28028 September 2023 Request for Exemption from Certain Termination of License Requirements of 10 CFR 50.82 ML23087A0392023-05-0202 May 2023 PSDAR Comment Resolution PNP 2023-001, Regulatory Path to Reauthorize Power Operations2023-03-13013 March 2023 Regulatory Path to Reauthorize Power Operations CNRO-2021-00023, Entergy Operations, Inc. - Supplement to CNRO-2021-00002, Basis for Concluding the Terms of Confirmatory Order EA-17-132/EA-17-153 Are Complete, Element L2021-10-0606 October 2021 Entergy Operations, Inc. - Supplement to CNRO-2021-00002, Basis for Concluding the Terms of Confirmatory Order EA-17-132/EA-17-153 Are Complete, Element L PNP 2020-039, 10 CFR 71.95 Report Involving 3-608 Cask2020-11-20020 November 2020 10 CFR 71.95 Report Involving 3-608 Cask ML20272A1662020-09-30030 September 2020 Attachment 3 - Framatome Document No. ANP-3876, Revision 1Q1NP, Response to NRC Request for Additional Information of Palisades Relief Request Number RR 5-8, Repair of Reactor Pressure Vessel Head Penetration, Inservice Inspection Program, ML20267A3912020-09-22022 September 2020 Attachment 4, Framatome Document No. 51-9292503-002, Palisades CEDM Nozzle Idtb Repair - Life Assessment Summary PNP 2019-001, Request for Deferral of Actions Related to a Beyond-Design-Basis External Seismic Event2019-03-20020 March 2019 Request for Deferral of Actions Related to a Beyond-Design-Basis External Seismic Event ML18354B1332019-01-17017 January 2019 Staff Assessment of Flood Focused Evaluation ML18330A1432018-11-26026 November 2018 Relief Request Number RR 5-7, Proposed Alternative to ASME Section Xi Code Requirements for Repair of Reactor Pressure Vessel Head Penetrations ML18330A1462018-11-24024 November 2018 Framatome, Document No. 51-9292503, Palisades CRDM & Ici Nozzle Idtb Repair - Life Assessment Summary ML18270A3232018-09-27027 September 2018 Attachment 2: Probabilistic Risk Assessment Technical Adequacy PNP 2018-036, Revised Mitigating Strategies Assessment for Flooding Pursuant to 10 CFR 50.54(f) Request for Information Regarding Recommendation 2.1: Flooding of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident2018-09-25025 September 2018 Revised Mitigating Strategies Assessment for Flooding Pursuant to 10 CFR 50.54(f) Request for Information Regarding Recommendation 2.1: Flooding of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident PNP 2018-041, Focused Evaluation Pursuant to 10 CFR 50.54(f) Request for Information Regarding Recommendation 2.1: Flooding of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident2018-09-25025 September 2018 Focused Evaluation Pursuant to 10 CFR 50.54(f) Request for Information Regarding Recommendation 2.1: Flooding of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident PNP 2016-066, Special Report for Inoperability of High Range Noble Gas Monitor2016-12-20020 December 2016 Special Report for Inoperability of High Range Noble Gas Monitor PNP 2016-042, Annual Status Notification in Response to Confirmatory Order, EA-14-0132016-06-16016 June 2016 Annual Status Notification in Response to Confirmatory Order, EA-14-013 ML16048A3442016-02-10010 February 2016 Annual Fatigue Reporting Form 2015 ML15351A3522015-12-16016 December 2015 Attachment 1, Compliance with Order EA-12-049 ML15351A3532015-12-16016 December 2015 Attachment 2, Order EA-12-049 Compliance Elements Summary ML15351A3542015-12-16016 December 2015 Attachment 3, Audit Open Item Responses ML15351A3552015-12-16016 December 2015 Attachment 4, Interim Staff Evaluation Open Item and Confirmation Item Responses ML15351A3622015-12-16016 December 2015 Attachment 6, System Operating Procedure 23, Plant Heating System, Attachment 14, Actions When Outside Temperatures Are Less than 20 Degrees Fahrenheit. ML15351A3602015-12-16016 December 2015 Attachment 5, Final Integrated Plan PNP 2015-066, Submittal of Report on the 8-120B Cask2015-08-20020 August 2015 Submittal of Report on the 8-120B Cask PNP 2015-058, Technical Specification Required Report2015-08-0404 August 2015 Technical Specification Required Report PNP 2015-037, Appendix a, Computer Files Listing, File No. 1200895.306, Revision 12015-05-22022 May 2015 Appendix a, Computer Files Listing, File No. 1200895.306, Revision 1 ML15147A6192015-05-22022 May 2015 Enclosure 2, Corrected Documentation for Relief Request Number RR 4-18 ML15147A6182015-05-22022 May 2015 Appendix a, Computer File Listing, File No. 1400669.323, Revision 0 ML15147A6172015-05-22022 May 2015 Enclosure 1, Relief Request Number RR 4-21 Proposed Alternative, in Accordance with 10 CFR 50.55a(z)(2), Hardship Without a Compensating Increase in Level of Quality and Safety PNP 2015-018, Areva, Inc., 51-9226987-000, Palisades Nuclear Plant Flooding Hazard Re-Evaluation Report.2015-02-25025 February 2015 Areva, Inc., 51-9226987-000, Palisades Nuclear Plant Flooding Hazard Re-Evaluation Report. PNP 2014-108, Expedited Seismic Evaluation Process Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima.2014-12-18018 December 2014 Expedited Seismic Evaluation Process Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima. PNP 2014-051, Response to May 1, 2014 Request for Additional Information for License Amendment Request to Revise Emergency Response Organization Staff Augmentation Response Times2014-07-16016 July 2014 Response to May 1, 2014 Request for Additional Information for License Amendment Request to Revise Emergency Response Organization Staff Augmentation Response Times PNP 2014-038, Special Report for Inoperability of High Range Noble Gas Monitor2014-04-14014 April 2014 Special Report for Inoperability of High Range Noble Gas Monitor PNP 2014-033, Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from The.2014-03-31031 March 2014 Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from The. ML13365A2642014-02-10010 February 2014 Interim Staff Evaluation Regarding Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) ML14030A2072014-02-0606 February 2014 Mega-Tech Services, LLC, Technical Evaluation Report Regarding the Overall Integrated Plan for Palisades Nuclear Plant, TAC No.: MF0768 PNP 2013-072, Report of Changes, Tests and Experiments and Summary of Commitment Changes2013-10-14014 October 2013 Report of Changes, Tests and Experiments and Summary of Commitment Changes PNP 2013-063, Unsatisfactory Laboratory Testing Report2013-09-18018 September 2013 Unsatisfactory Laboratory Testing Report ML13242A1592013-08-29029 August 2013 Addendum to the Results of Independent Samples Collected by the NRC at Palisades Nuclear Plant Storm Drain Outfall ML13295A4502013-07-31031 July 2013 WCAP-15353-Supplement 2-NP, Rev. 0, Palisades Reactor Pressure Vessel Fluence Evaluation. PNP 2013-046, Updated Palisades Nuclear Plant Reactor Vessel Fluence Evaluation2013-06-25025 June 2013 Updated Palisades Nuclear Plant Reactor Vessel Fluence Evaluation PNP 2013-027, National Pollutant Discharge Elimination System (NPDES) Permit Renewal Application2013-04-10010 April 2013 National Pollutant Discharge Elimination System (NPDES) Permit Renewal Application ML14316A2082013-02-28028 February 2013 Attachment 5 - Westinghouse WCAP-17651-NP, Revision 0, Palisades Nuclear Power Plant Reactor Vessel Equivalent Margins Analysis ML13295A4512013-02-28028 February 2013 WCAP-17651-NP, Rev. 0, Palisades Nuclear Power Plant Reactor Vessel Equivalent Margins Analysis. ML13038A4402013-02-0707 February 2013 BADGER Test Campaign at Palisades Nuclear Plant ML13295A4492013-01-31031 January 2013 WCAP-17403-NP, Rev. 1, Palisades Nuclear Power Plant Extended Beltline Reactor Vessel Integrity Evaluation. ML14316A1992013-01-31031 January 2013 Attachment 3 - Westinghouse WCAP-17403-NP, Revision 1, Palisades Nuclear Power Plant Extended Beltline Reactor Vessel Integrity Evaluation ML12334A0962012-11-27027 November 2012 PLP-RPT-12-00141, Rev. 0, Palisades Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Part 1 of 3 PNP 2012-101, Flooding Walkdown Report - Response to NRC Request for Information Pursuant to 10CFR50.54(f) the Flooding Aspects of Recommendation 2.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident2012-11-27027 November 2012 Flooding Walkdown Report - Response to NRC Request for Information Pursuant to 10CFR50.54(f) the Flooding Aspects of Recommendation 2.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident ML12334A0972012-11-27027 November 2012 PLP-RPT-12-0041, Rev. 0, Palisades Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Part 2 of 3 2023-09-28
[Table view] Category:Miscellaneous
MONTHYEARML23087A0392023-05-0202 May 2023 PSDAR Comment Resolution PNP 2023-001, Regulatory Path to Reauthorize Power Operations2023-03-13013 March 2023 Regulatory Path to Reauthorize Power Operations CNRO-2021-00023, Entergy Operations, Inc. - Supplement to CNRO-2021-00002, Basis for Concluding the Terms of Confirmatory Order EA-17-132/EA-17-153 Are Complete, Element L2021-10-0606 October 2021 Entergy Operations, Inc. - Supplement to CNRO-2021-00002, Basis for Concluding the Terms of Confirmatory Order EA-17-132/EA-17-153 Are Complete, Element L PNP 2019-001, Request for Deferral of Actions Related to a Beyond-Design-Basis External Seismic Event2019-03-20020 March 2019 Request for Deferral of Actions Related to a Beyond-Design-Basis External Seismic Event ML18354B1332019-01-17017 January 2019 Staff Assessment of Flood Focused Evaluation PNP 2016-066, Special Report for Inoperability of High Range Noble Gas Monitor2016-12-20020 December 2016 Special Report for Inoperability of High Range Noble Gas Monitor PNP 2016-042, Annual Status Notification in Response to Confirmatory Order, EA-14-0132016-06-16016 June 2016 Annual Status Notification in Response to Confirmatory Order, EA-14-013 ML16048A3442016-02-10010 February 2016 Annual Fatigue Reporting Form 2015 ML15351A3542015-12-16016 December 2015 Attachment 3, Audit Open Item Responses ML15351A3622015-12-16016 December 2015 Attachment 6, System Operating Procedure 23, Plant Heating System, Attachment 14, Actions When Outside Temperatures Are Less than 20 Degrees Fahrenheit. ML15351A3602015-12-16016 December 2015 Attachment 5, Final Integrated Plan ML15351A3552015-12-16016 December 2015 Attachment 4, Interim Staff Evaluation Open Item and Confirmation Item Responses ML15351A3522015-12-16016 December 2015 Attachment 1, Compliance with Order EA-12-049 ML15351A3532015-12-16016 December 2015 Attachment 2, Order EA-12-049 Compliance Elements Summary PNP 2015-066, Submittal of Report on the 8-120B Cask2015-08-20020 August 2015 Submittal of Report on the 8-120B Cask ML15147A6192015-05-22022 May 2015 Enclosure 2, Corrected Documentation for Relief Request Number RR 4-18 ML15147A6182015-05-22022 May 2015 Appendix a, Computer File Listing, File No. 1400669.323, Revision 0 ML15147A6172015-05-22022 May 2015 Enclosure 1, Relief Request Number RR 4-21 Proposed Alternative, in Accordance with 10 CFR 50.55a(z)(2), Hardship Without a Compensating Increase in Level of Quality and Safety PNP 2015-037, Appendix a, Computer Files Listing, File No. 1200895.306, Revision 12015-05-22022 May 2015 Appendix a, Computer Files Listing, File No. 1200895.306, Revision 1 PNP 2014-033, Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from The.2014-03-31031 March 2014 Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from The. PNP 2013-072, Report of Changes, Tests and Experiments and Summary of Commitment Changes2013-10-14014 October 2013 Report of Changes, Tests and Experiments and Summary of Commitment Changes PNP 2013-063, Unsatisfactory Laboratory Testing Report2013-09-18018 September 2013 Unsatisfactory Laboratory Testing Report PNP 2013-046, Updated Palisades Nuclear Plant Reactor Vessel Fluence Evaluation2013-06-25025 June 2013 Updated Palisades Nuclear Plant Reactor Vessel Fluence Evaluation PNP 2013-027, National Pollutant Discharge Elimination System (NPDES) Permit Renewal Application2013-04-10010 April 2013 National Pollutant Discharge Elimination System (NPDES) Permit Renewal Application PNP 2012-101, Flooding Walkdown Report - Response to NRC Request for Information Pursuant to 10CFR50.54(f) the Flooding Aspects of Recommendation 2.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident2012-11-27027 November 2012 Flooding Walkdown Report - Response to NRC Request for Information Pursuant to 10CFR50.54(f) the Flooding Aspects of Recommendation 2.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident ML12334A0962012-11-27027 November 2012 PLP-RPT-12-00141, Rev. 0, Palisades Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Part 1 of 3 ML12334A0972012-11-27027 November 2012 PLP-RPT-12-0041, Rev. 0, Palisades Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Part 2 of 3 PNP 2012-102, PLP-RPT-12-0041, Rev. 0, Palisades Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Part 3 of 32012-11-27027 November 2012 PLP-RPT-12-0041, Rev. 0, Palisades Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Part 3 of 3 PNP 2012-094, 2012 Steam Generator Tube Inspection Report2012-11-0101 November 2012 2012 Steam Generator Tube Inspection Report PNP 2012-059, 60-Day Reports Per Bulletin 2004-01 and CAL No NRR-07-023 Pressurizer Inspection Results for the 2012 Refueling Outage2012-07-11011 July 2012 60-Day Reports Per Bulletin 2004-01 and CAL No NRR-07-023 Pressurizer Inspection Results for the 2012 Refueling Outage IR 05000255/20110192012-02-14014 February 2012 Final Significance Determination of Yellow and White Findings with Assessment Followup and Notice of Violation NRC Inspection Report Nos. 05000255-11-019 and 05000255-11-020 Palisades Nuclear Plant ML12023A1872012-01-17017 January 2012 EA-PSA-SDP-D11-2-11-07, Rev. 2, SDP Assessment of DC Panel D11-2 Fault, Cover Through Appendix a ML12023A1882012-01-17017 January 2012 EA-PSA-SDP-D11-2-11-07, Rev. 2, SDP Assessment of DC Panel D11-2 Fault, Appendix B Through End ML12006A0712012-01-0505 January 2012 SDP Assessment of DC Panel D-11-2 Fault Palisades ML1134205122011-12-19019 December 2011 Review of the 2010 Steam Generator Tube Inspections During Refueling Outage 21 ML12006A0722011-10-17017 October 2011 Plant Trip During D-11-2 Maintenance Root Cause ML1128705702011-10-14014 October 2011 Report of Changes, Tests and Experiments and Summary of Commitment Changes ML12006A0672011-09-28028 September 2011 SDP Assessment of Service Water Pump P-7C Coupling Failures Part 3 ML1031603372010-11-0909 November 2010 Unsatisfactory Laboratory Testing Report ML1012704392010-05-0505 May 2010 Y020100187 - List of Historical Leaks and Spills at U.S. Commercial Nuclear Power Plants ML1020301642010-04-28028 April 2010 E-Mail. from Dotson to Cassidy, GZA 2007 Report ML0929505252009-10-22022 October 2009 Generator Tube Inspection Report ML0928903362009-10-15015 October 2009 Report of Facility Changes, Tests and Experiments and Summary of Commitment Changes ML0901402872008-07-16016 July 2008 E-mail from Ellegood to M. Chawla Et Al. Palisades SFP Racks with Attachment: Report on Resolution of Outstanding Concerns on Spent Fuel Pit Rack Localized Swelling Palisades Nuclear Plant ML0810000792008-04-0808 April 2008 Request for Enforcement Discretion - Technical Specification 3.8.1 Required Actions F.1 and F.2 ML0717802162007-06-19019 June 2007 Revised Steam Generator Tube Integrity Assessment from the 2006 Refueling Outage ML0719400912006-09-15015 September 2006 Request for Relief from ASME Section Xl Code Requirements for Repair of Pressurizer Nozzle Penetrations (Non-Proprietary) ML0619803382006-07-20020 July 2006 Review of the 2004 Steam Generator Tube Inspection Reports ML0617301112006-06-21021 June 2006 Day Report Per First Revised Order EA-03-009 ML0608203512006-03-20020 March 2006 License Amendment Request: Removal of TSP from Palisades Containment 2023-05-02
[Table view] |
Text
~Entergy Entergy Nuclear Operations, Inc.
Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043 Tel 269 764 2000 Jeffery A. Hardy Director, Regulatory Assurance and Performance Improvement PNP 2016-042 June 16, 2016 EA-14-013 Mr. Kenneth O'Brien U. S. Nuclear Regulatory Commission Director, Division of Reactor Safety 2443 Warrenville Road Lisle, IL 60532
Subject:
Entergy Nuclear Operations, Inc. Annual Status Notification in Response to Confirmatory Order, EA-14-013 Palisades Nuclear Plant Docket 50-255 License No. DPR-20
Reference:
Confirmatory Order Related to NRC Report No. 0500025512014406 and 01 Report 3-2013-018; Palisades Nuclear Plant, dated July 21,2014 (ML14203A082)
Dear Mr. O'Brien:
On July 21, 2014, the Nuclear Regulatory Commission (NRC) issued the referenced Confirmatory Order to Entergy Nuclear Operations, Inc (ENO). The Confirmatory Order requires ENO to submit written notifications to the NRC on the status of each item in the Confirmatory Order at intervals of six months, one year and annually thereafter until the terms of the Confirmatory Order are completed.
The purpose of this letter is to provide an annual status notification pursuant to Section V, Item F.1, of the Confirmatory Order. The attachment delineates progress made in implementing the requirements of the Confirmatory Order.
This letter contains no new commitments and no revisions to existing commitments.
Sincerely, 9h~t7 JAH/tad
Attachment:
Entergy Nuclear Operations, Inc. Annual Status Notification in Response to Confirmatory Order, EA-14-013 cc: Document Control Desk, USNRC Administrator, Region III, USNRC Project Manager, Palisades, USNRC Resident Inspector, Palisades, USNRC
Entergy Nuclear Operations, Inc. Annual Status Notification in Response to Confirmatory Order, EA-14-013 Confirmatory Order Item St atus Comments A. Verification of Training Credentials for both Staff and Management:
A.l: Complete Each Entergy site Security Conduct fleet-wide review of qualifications of each duty position in security to ensure Manager validated the that the qualifications for each position are clear and verifiable by all parties (security qualifications for each officers, security supervisors, and security manager). The initial review and applicable position are clear and procedure revisions shall be completed by November 30, 2014. verifiable by all parties A.2: Complete Revised EN-NS-221, Verify and modify, if necessary, the applicable security procedure to ensure that both ((Security Department assignor and assignee validate qualifications before the assignee performs a duty Standards and position. This shall be completed by November 30, 2014. Expectations" revision 6 A.3: Complete Training has been Following completion of A.l and A.2, training will be conducted on the changes. This conducted for all active shall be completed by June 30, 2015. security personnel. For inactive personnel, e.g.,
medical leave, etc., training will be conducted upon resumption of active duty.
B. Strengthen Safety Culture:
B.l: In-progress Quarterly meetings have Through June 30, 2016, the Palisades Security Manager shall meet quarterly (during the been held with each calendar quarter, allowing for one month grace period) with each security team: (a) to security team.
reinforce the importance of a healthy SCWE and management's intolerance for retaliation, and (b) to discuss security concerns and issue resolution .
B.2: In-progress Security Top 10 issues and Through June 30, 2016, Palisades' security management shall maintain and update a resolutions are maintained I I
"Security Top 10 Issues" board to reflect, among other things, the expected issues and communicated on a I resolution dates. routine basis. I I
I Page 1 of 3
Entergy Nuclear Operations, Inc., Annual Status Notification in Response to Confirmatory Order, EA-14-013 Confirmatory Order Item St atus Comments B.3: Complete The third and final monthly Discuss the safety culture aspects of the event with Palisades Nuclear Plant staff, tailgate meeting material including long-term contract staff, in three monthly tailgate meetings. The tailgate was distributed on meetings shall include employee rights, licensee expectations with respect to raising November 6,2014.
issues, methods to raise issues, and the right to contact the NRC. The tailgate meetings will be completed by December 31, 2014.
B.4: Complete EN-U-102 Revision 24, Revise procedure EN-U-I02 to ensure that the Condition Review Group (CRG) chair Section 5.4[6](d)(1) considers whether the person assigned is sufficiently independent. This applies to condition reports that have challenges to a decision or a resolution that is highly The "read and sign" training dependent on a single individual. A "read and sign" will be provided to each Entergy to CRG chairs is completed.
(fleet-wide) CRG chair to inform them of the procedure revision. The procedure will be revised by November 30, 2014, and the "read and sign" training will be completed by January 31, 2015.
B.5: Complete Case study sessions were Conduct a case study for supervisors and above throughout the Entergy fleet that conducted by June 30, highlights safety culture aspects of the event: questioning attitude, proceeding in the 2015.
face of uncertainty, procedure compliance, and responsiveness to employee concerns.
The case study will be developed and conducted by June 30, 2015.
C. Recognition by the Reactor Community:
C.l: Complete NRC reviewed presentation Entergy Fleet Director of Nuclear Security shall make a presentation to an industry prior to presentation at NEI security working group on this event. The licensee will provide the NRC an opportun ity Security Working Group to review the presentation. The presentation shall be accomplished by December 31, meeting on November 5, ,
2014. 2014 C.2: Complete Presented at the winter Entergy shall make a related presentation at a broad industry meeting aimed at an meeting of the National audience beyond the security organizations and covering all four NRC regions. It is Association of Employee acceptable to make the presentation at mUltiple meetings, if deemed necessary to reach Concerns Professiona ls the desired audience. The presentations ~a!Lb~accomplished by June 30, 2015. (ECP), Februar'l}~-25, 2015 Page 2 of 3
Entergy Nuclear Operations, Inc., Annual Status Notification in Response to Confirmatory Order, EA-14-013 Confirmatory Order Item Status Comments D. Setting Standards for Security Senior Management:
Entergy shall revise procedure EN-FAP-HR-006 to include specific requirements for Complete EN-FAP-HR-006 revision 1 I Security Manager selection and development. This shall be accomplished by December issued on December 23, I I
31,2014. 2014 E. Effectiveness Review:
Entergy shall arrange for an independent effectiveness review of the actions discussed in In-progress Independent effectiveness sections A and B. The review will be conducted no earlier than one year, but less than . review started June 13, two years, from the issuance date of the Confirmatory Order. 2016 F. Notification of NRC When Actions Are Completed:
F.1: On target The one year status Unless otherwise specified, Entergy will submit written notification by letter to the NRC notification was completed staff, specifically, the Director, Division of Reactor Safety, 2443 Warrenville Road, Lisle, on June 19, 2015 IL, 60532, at intervals of six months, one year, and annually thereafter until the terms of the Confirmatory Order are completed, providing a status of each item in the Confirmatory Order.
F.2: On target Upon completion of all terms of the Confirmatory Order, Entergy will provide the NRC with a letter discussing its basis for concluding that the Order has been satisfied.
Page 3 of 3