NRC 2016-0014, Use of NEI 12-06, Revision 2, Diverse and Flexible Coping Strategies (FLEX) Implementation Guide

From kanterella
Jump to navigation Jump to search

Use of NEI 12-06, Revision 2, Diverse and Flexible Coping Strategies (FLEX) Implementation Guide
ML16098A306
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 04/07/2016
From: Mccartney E
Point Beach
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
EA-12-049, NEI 12-06, Rev. 2, NRC 2016-0014
Download: ML16098A306 (2)


Text

NEXTeraM ENERGY~

~

April? , 2016 NRC 2016-0014 10 CFR 50.54(f)

U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington , DC 20555-0001 Point Beach Nuclear Plant, Units 1 and 2 Docket 50-266 and 50-301 Renewed License Nos. DPR-24 and DPR-27 NextEra Energy Point Beach, LLC, Use of NEI 12-06, Revision 2, Diverse and Flexible Coping Strategies (FLEX) Implementation Guide

References:

(1) NextEra Energy Point Beach, LLC's Notification of Full Compliance with Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events and Submittal of Final Integrated Plan , dated December 16, 2015 (ML15350A085)

(2) JLD-ISG-2012-01 , Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, Revision 1, January 22, 2016 (ML15357A163)

(3) Federal Register Notice Announcing Issuance of JLD-ISG-2012-01, Revision 1, dated February 29, 2016 (81 FR 10283) (ML15365A514)

(4) NEI 12-06, Diverse and Flexible Coping Strategies (FLEX) Implementation Guide, Revision 2, December 2015 (ML16005A625)

By letter dated December 16, 2015 (Reference 1), NextEra Energy Point Beach, LLC (NextEra),

provided notification of full compliance with Order EA- 12-049 and submitted a Final Integrated Plan . NextEra's submittal indicates Point Beach Nuclear Power Plant utilized the guidance in NEI 12-06, Diverse and Flexible Coping Strategies (FLEX) Implementation Guide. NEI 12-06, Revision 0, was utilized in preparing and implementing the FLEX strategies. Subsequently, JLD-ISG-2012-01, Revision 1 (References 2 and 3), endorsed use of NEI 12-06, Revision 2 (Reference 4) .

This letter is providing documentation of NextEra's intent to use NEI 12-06, Revision 2, to complete mitigating strategies assessments (NEI 12-06, Revision 2, Appendices G and H) and as a guide for FLEX strategies. NextEra does not intend at this time to revise the existing strategy for use of spent fuel pool spray, as described in NEI 12-06, Revision 0.

Use of NEI 12-06, Revision 2, does not change the information provided in NextEra's Final Integrated Plan (FIP), therefore a new FIP submittal will not be made.

NextEra Energy Point Beach, LLC, 6610 Nuclear Road, Two Rivers, WI 54241

Document Control Desk Page 2 This letter contains no new regulatory commitments.

If you have any questions please contact Mr. Bryan Woyak, Licensing Manager, at 920/755-7599.

Very truly yours, NextEra Energy Point Beach, LLC Eric McCartney Site Vice President cc: Director, Office of Nuclear Reactor Regulation Administrator, Region Ill, USNRC Resident Inspector, Point Beach Nuclear Plant, USNRC Project Manager, Point Beach Nuclear Plant, USNRC J. Paige, Project Manager, Japan Lessons-Learned Division

NEXTeraM ENERGY~

~

April? , 2016 NRC 2016-0014 10 CFR 50.54(f)

U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington , DC 20555-0001 Point Beach Nuclear Plant, Units 1 and 2 Docket 50-266 and 50-301 Renewed License Nos. DPR-24 and DPR-27 NextEra Energy Point Beach, LLC, Use of NEI 12-06, Revision 2, Diverse and Flexible Coping Strategies (FLEX) Implementation Guide

References:

(1) NextEra Energy Point Beach, LLC's Notification of Full Compliance with Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events and Submittal of Final Integrated Plan , dated December 16, 2015 (ML15350A085)

(2) JLD-ISG-2012-01 , Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, Revision 1, January 22, 2016 (ML15357A163)

(3) Federal Register Notice Announcing Issuance of JLD-ISG-2012-01, Revision 1, dated February 29, 2016 (81 FR 10283) (ML15365A514)

(4) NEI 12-06, Diverse and Flexible Coping Strategies (FLEX) Implementation Guide, Revision 2, December 2015 (ML16005A625)

By letter dated December 16, 2015 (Reference 1), NextEra Energy Point Beach, LLC (NextEra),

provided notification of full compliance with Order EA- 12-049 and submitted a Final Integrated Plan . NextEra's submittal indicates Point Beach Nuclear Power Plant utilized the guidance in NEI 12-06, Diverse and Flexible Coping Strategies (FLEX) Implementation Guide. NEI 12-06, Revision 0, was utilized in preparing and implementing the FLEX strategies. Subsequently, JLD-ISG-2012-01, Revision 1 (References 2 and 3), endorsed use of NEI 12-06, Revision 2 (Reference 4) .

This letter is providing documentation of NextEra's intent to use NEI 12-06, Revision 2, to complete mitigating strategies assessments (NEI 12-06, Revision 2, Appendices G and H) and as a guide for FLEX strategies. NextEra does not intend at this time to revise the existing strategy for use of spent fuel pool spray, as described in NEI 12-06, Revision 0.

Use of NEI 12-06, Revision 2, does not change the information provided in NextEra's Final Integrated Plan (FIP), therefore a new FIP submittal will not be made.

NextEra Energy Point Beach, LLC, 6610 Nuclear Road, Two Rivers, WI 54241

Document Control Desk Page 2 This letter contains no new regulatory commitments.

If you have any questions please contact Mr. Bryan Woyak, Licensing Manager, at 920/755-7599.

Very truly yours, NextEra Energy Point Beach, LLC Eric McCartney Site Vice President cc: Director, Office of Nuclear Reactor Regulation Administrator, Region Ill, USNRC Resident Inspector, Point Beach Nuclear Plant, USNRC Project Manager, Point Beach Nuclear Plant, USNRC J. Paige, Project Manager, Japan Lessons-Learned Division

Text

NEXTeraM ENERGY~

~

April? , 2016 NRC 2016-0014 10 CFR 50.54(f)

U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington , DC 20555-0001 Point Beach Nuclear Plant, Units 1 and 2 Docket 50-266 and 50-301 Renewed License Nos. DPR-24 and DPR-27 NextEra Energy Point Beach, LLC, Use of NEI 12-06, Revision 2, Diverse and Flexible Coping Strategies (FLEX) Implementation Guide

References:

(1) NextEra Energy Point Beach, LLC's Notification of Full Compliance with Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events and Submittal of Final Integrated Plan , dated December 16, 2015 (ML15350A085)

(2) JLD-ISG-2012-01 , Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, Revision 1, January 22, 2016 (ML15357A163)

(3) Federal Register Notice Announcing Issuance of JLD-ISG-2012-01, Revision 1, dated February 29, 2016 (81 FR 10283) (ML15365A514)

(4) NEI 12-06, Diverse and Flexible Coping Strategies (FLEX) Implementation Guide, Revision 2, December 2015 (ML16005A625)

By letter dated December 16, 2015 (Reference 1), NextEra Energy Point Beach, LLC (NextEra),

provided notification of full compliance with Order EA- 12-049 and submitted a Final Integrated Plan . NextEra's submittal indicates Point Beach Nuclear Power Plant utilized the guidance in NEI 12-06, Diverse and Flexible Coping Strategies (FLEX) Implementation Guide. NEI 12-06, Revision 0, was utilized in preparing and implementing the FLEX strategies. Subsequently, JLD-ISG-2012-01, Revision 1 (References 2 and 3), endorsed use of NEI 12-06, Revision 2 (Reference 4) .

This letter is providing documentation of NextEra's intent to use NEI 12-06, Revision 2, to complete mitigating strategies assessments (NEI 12-06, Revision 2, Appendices G and H) and as a guide for FLEX strategies. NextEra does not intend at this time to revise the existing strategy for use of spent fuel pool spray, as described in NEI 12-06, Revision 0.

Use of NEI 12-06, Revision 2, does not change the information provided in NextEra's Final Integrated Plan (FIP), therefore a new FIP submittal will not be made.

NextEra Energy Point Beach, LLC, 6610 Nuclear Road, Two Rivers, WI 54241

Document Control Desk Page 2 This letter contains no new regulatory commitments.

If you have any questions please contact Mr. Bryan Woyak, Licensing Manager, at 920/755-7599.

Very truly yours, NextEra Energy Point Beach, LLC Eric McCartney Site Vice President cc: Director, Office of Nuclear Reactor Regulation Administrator, Region Ill, USNRC Resident Inspector, Point Beach Nuclear Plant, USNRC Project Manager, Point Beach Nuclear Plant, USNRC J. Paige, Project Manager, Japan Lessons-Learned Division

NEXTeraM ENERGY~

~

April? , 2016 NRC 2016-0014 10 CFR 50.54(f)

U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington , DC 20555-0001 Point Beach Nuclear Plant, Units 1 and 2 Docket 50-266 and 50-301 Renewed License Nos. DPR-24 and DPR-27 NextEra Energy Point Beach, LLC, Use of NEI 12-06, Revision 2, Diverse and Flexible Coping Strategies (FLEX) Implementation Guide

References:

(1) NextEra Energy Point Beach, LLC's Notification of Full Compliance with Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events and Submittal of Final Integrated Plan , dated December 16, 2015 (ML15350A085)

(2) JLD-ISG-2012-01 , Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, Revision 1, January 22, 2016 (ML15357A163)

(3) Federal Register Notice Announcing Issuance of JLD-ISG-2012-01, Revision 1, dated February 29, 2016 (81 FR 10283) (ML15365A514)

(4) NEI 12-06, Diverse and Flexible Coping Strategies (FLEX) Implementation Guide, Revision 2, December 2015 (ML16005A625)

By letter dated December 16, 2015 (Reference 1), NextEra Energy Point Beach, LLC (NextEra),

provided notification of full compliance with Order EA- 12-049 and submitted a Final Integrated Plan . NextEra's submittal indicates Point Beach Nuclear Power Plant utilized the guidance in NEI 12-06, Diverse and Flexible Coping Strategies (FLEX) Implementation Guide. NEI 12-06, Revision 0, was utilized in preparing and implementing the FLEX strategies. Subsequently, JLD-ISG-2012-01, Revision 1 (References 2 and 3), endorsed use of NEI 12-06, Revision 2 (Reference 4) .

This letter is providing documentation of NextEra's intent to use NEI 12-06, Revision 2, to complete mitigating strategies assessments (NEI 12-06, Revision 2, Appendices G and H) and as a guide for FLEX strategies. NextEra does not intend at this time to revise the existing strategy for use of spent fuel pool spray, as described in NEI 12-06, Revision 0.

Use of NEI 12-06, Revision 2, does not change the information provided in NextEra's Final Integrated Plan (FIP), therefore a new FIP submittal will not be made.

NextEra Energy Point Beach, LLC, 6610 Nuclear Road, Two Rivers, WI 54241

Document Control Desk Page 2 This letter contains no new regulatory commitments.

If you have any questions please contact Mr. Bryan Woyak, Licensing Manager, at 920/755-7599.

Very truly yours, NextEra Energy Point Beach, LLC Eric McCartney Site Vice President cc: Director, Office of Nuclear Reactor Regulation Administrator, Region Ill, USNRC Resident Inspector, Point Beach Nuclear Plant, USNRC Project Manager, Point Beach Nuclear Plant, USNRC J. Paige, Project Manager, Japan Lessons-Learned Division