Similar Documents at Fermi |
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217N4261999-10-25025 October 1999 Forwards Amend 17 to License DPR-9 & Safety Evaluation. Amend Revises TS by Deleting SR D.3.c,which Required Weekly Observation of Nitrogen Cover Gas Pressure within Sodium Storage Tanks Located in Sodium Building NRC-99-0085, Forwards Rev 15 to Fermi 2 Security Personnel Training & Qualification Plan, IAW 10CFR50.54(p)(2).Without Encl1999-10-22022 October 1999 Forwards Rev 15 to Fermi 2 Security Personnel Training & Qualification Plan, IAW 10CFR50.54(p)(2).Without Encl NRC-99-0094, Forwards Safeguards Event Rept 99-S01-00 for Reportable Event That Occurred on 990922.Commitments Made by Util Listed1999-10-22022 October 1999 Forwards Safeguards Event Rept 99-S01-00 for Reportable Event That Occurred on 990922.Commitments Made by Util Listed ML20217P1661999-10-21021 October 1999 Forwards Insp Rept 50-341/99-17 on 990927-1005.No Violations Noted ML20217M0771999-10-19019 October 1999 Confirms Discussion Between GL Shear,M Mitchell,E Kosky, D Williams,B Rumins,D Harmon & W Rutenberg in Public Meeting on 990923.Purpose of Meeting Was to Discuss Current Status RP Program at Enrico Fermi 2 ML20217N9231999-10-15015 October 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 40 ML20217E5671999-10-14014 October 1999 First Partial Response to FOIA Request for Documents.Records in App a Already Available in Pdr.App B Records Encl & Being Released in Entirety NRC-99-0087, Responds to NRC Re Violations Noted in Insp Rept 50-341/99-10.Licensee Contests Subject Violation,Due to Listed Reasons1999-10-12012 October 1999 Responds to NRC Re Violations Noted in Insp Rept 50-341/99-10.Licensee Contests Subject Violation,Due to Listed Reasons NRC-99-0083, Submits Requested Response to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal1999-10-0707 October 1999 Submits Requested Response to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal ML20217D5331999-10-0707 October 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 39 ML20217F5931999-10-0707 October 1999 Forwards Insp Rept 50-341/99-11 on 990724-0908.Two Violations Re Failure to Follow Procedures While Sampling Standby Liquid Control Tank & Wear Dosimetry Properly Being Treated as Noncited Violations ML20217B8261999-10-0404 October 1999 Forwards Summary of Decommissioning Insp Plan for Fy 2000. Plan Will Be Updated Annually & May Be Revised at Any Time Based Upon Future Insp Findings,Events & Resource Availability ML20212J8121999-10-0101 October 1999 Discusses Plant,Unit 2 Completion of Licensing Action for GL 98-01 & Suppl 1, Y2K Readiness of Computer Sys at Npps. Ack Efforts That Licensee Have Completed to Date in Preparing Plant for Y2K Transition ML20212K8881999-09-30030 September 1999 Refers to 990928 Meeting Conducted at Fermi Unit 2 to Discuss Initiatives in Risk Area & to Establish Dialog Between SRAs & PSA Staff ML20217A3261999-09-30030 September 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 38 NRC-99-0091, Forwards NRC Form 536,in Response to NRC Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Examinations1999-09-27027 September 1999 Forwards NRC Form 536,in Response to NRC Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Examinations ML20212J8331999-09-27027 September 1999 Responds to Licensee 990924 Request That NRC Exercise Discretion Not to Enforce Compliance with Actions Required in TS 3/4.6.1.8.Ltr Documents 990923 Telcon with Util in Which NRC Orally Issued NOED ML20216G9791999-09-24024 September 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 37 NRC-99-0092, Documents Util Request for Enforcement Discretion with Respect to Requirements of TS 3/4.6.1.8 Re Drywell & Suppression Chamber Purge Sys1999-09-24024 September 1999 Documents Util Request for Enforcement Discretion with Respect to Requirements of TS 3/4.6.1.8 Re Drywell & Suppression Chamber Purge Sys ML20216H3561999-09-23023 September 1999 Informs That During 990914 Telcon,L Sanders & M Bielby Made Arrangements with NRC to Inspect Licensed Operator Requalification Program at Fermi Nuclear Station for Week of 991129 Which Coincides with Util Regularly Scheduled Exam ML20216H4541999-09-23023 September 1999 Informs That During 990914 Telcon L Sanders & M Bielby Made Arrangements for Administration of Licensing Exams at Fermi Nuclear Station for Week of Jan 31,2000.NRC Will Make Exam Validation Visit to Facility During Week of Jan 10,2000 ML20212F3241999-09-20020 September 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 36 NRC-99-0081, Submits Eight Relief Requests Associated with Containment Inservice Exam Program for Fermi 2 Plant,Per Provisions of 10CFR50.55a(g)(5)(iv).Requested Relief Does Not Adversely Affect Health & Safety of Public1999-09-17017 September 1999 Submits Eight Relief Requests Associated with Containment Inservice Exam Program for Fermi 2 Plant,Per Provisions of 10CFR50.55a(g)(5)(iv).Requested Relief Does Not Adversely Affect Health & Safety of Public ML20217A9421999-09-0909 September 1999 Informs That NRC Plan to Conduct Addl Resident Insps Beyond Core Insp Program Over Next 6 Months to Assess Improvements in Areas of Procedural Compliance & Quality of Work. Historical Listing of Plant Issues Encl NRC-99-0079, Forwards Rev 15 to Fermi 2 ITS Submittal,Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev1999-09-0808 September 1999 Forwards Rev 15 to Fermi 2 ITS Submittal,Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev ML20211Q0991999-09-0303 September 1999 Forwards Rev 35 to Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section) NRC-99-0090, Forwards Proprietary Operator License Renewal Application, NRC Forms 398 & 396 for SW Burt,License SOP-30199-3. Proprietary Encls Withheld1999-09-0303 September 1999 Forwards Proprietary Operator License Renewal Application, NRC Forms 398 & 396 for SW Burt,License SOP-30199-3. Proprietary Encls Withheld NRC-99-0066, Forwards semi-annual fitness-for-duty Rept for Fermi 2 for Period of 990101-0630,IAW 10CFR26.71(d)1999-08-30030 August 1999 Forwards semi-annual fitness-for-duty Rept for Fermi 2 for Period of 990101-0630,IAW 10CFR26.71(d) ML20211G4951999-08-24024 August 1999 Forwards Rev 34 to Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section) NRC-99-0055, Forwards Rev 5 to Inservice Testing Program for Pumps & Valves for Fermi 2 Second 10-Year Interval, Per Provisions of 10CFR50.55a(f)(5)(iv).Rev Includes Four Pump Relief Requests & Ten Valve Relief Requests Requiring NRC Approval1999-08-19019 August 1999 Forwards Rev 5 to Inservice Testing Program for Pumps & Valves for Fermi 2 Second 10-Year Interval, Per Provisions of 10CFR50.55a(f)(5)(iv).Rev Includes Four Pump Relief Requests & Ten Valve Relief Requests Requiring NRC Approval IR 05000341/19990131999-08-19019 August 1999 Discusses Insp Rept 50-341/99-13 & OI Rept 3-98-039 Conducted Into Potential Misconduct of Operator Formerly Employed by De.Nrc Determined That Violation of NRC Regulations Occurred.Synopsis of IO Rept Encl NRC-99-0056, Forwards Rev 2,change 0 to ISI-Nondestructive Exam (ISI-NDE) Program (Plan) for Piping,Components & Integral Attachments, for Second ten-year Interval of Fermi 2 Plant Operation1999-08-19019 August 1999 Forwards Rev 2,change 0 to ISI-Nondestructive Exam (ISI-NDE) Program (Plan) for Piping,Components & Integral Attachments, for Second ten-year Interval of Fermi 2 Plant Operation ML20211C0521999-08-17017 August 1999 Forwards Tables for Sections 3.6 & 3.7 of Draft Safety Evaluation of Proposed Conversion of Current TS to Improved Standard TS NRC-99-0089, Forwards Rev 13 to Fermi 2 ITS Submittal Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev1999-08-17017 August 1999 Forwards Rev 13 to Fermi 2 ITS Submittal Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev ML20217E6181999-08-13013 August 1999 FOIA Request for Documents Re Implementing Regulations in 10CFR & Requesting That Region III Task Interface Agreement (TIA) Related to Fermi 2 Plant Be Made Available IR 05000341/19990011999-08-10010 August 1999 Forwards Insp Rept 50-341/99-01 on 990619-0723 & Nov. Violation of Concern Because Operators Did Not Understand License Requirements & Placed Plant in Configuration Where EDG 11 Was Removed from Service IR 05000341/19990121999-08-0606 August 1999 Forwards Insp Rept 50-341/99-12 on 990712-0716.No Violations Noted.Insp Focused on Implementation of Plant Chemistry & Radiological Environ Monitoring Programs & Operation of post-accident Sampling Sys ML20211C4761999-08-0606 August 1999 Forwards Draft Safety Evaluation Re Proposed Conversion of Current TS to Improved Standard TS NRC-99-0057, Forwards Rev 12 to ITS 980403 Submittal,Providing Update to Submittal for ITS Section 3.3,including Changes Associated with NRC Review of Rev 6 ITS1999-08-0404 August 1999 Forwards Rev 12 to ITS 980403 Submittal,Providing Update to Submittal for ITS Section 3.3,including Changes Associated with NRC Review of Rev 6 ITS ML20210N5451999-08-0303 August 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 33 NRC-99-0077, Forwards Rev 11 to Fermi ITS Submittal,Dtd 980403,providing Update to Submittal for ITS Sections 3.5,3.6 & 3.8.Update Includes Changes Associated with NRC Review of Util Transmittals of Revs 5,5a & 7 to ITS1999-07-26026 July 1999 Forwards Rev 11 to Fermi ITS Submittal,Dtd 980403,providing Update to Submittal for ITS Sections 3.5,3.6 & 3.8.Update Includes Changes Associated with NRC Review of Util Transmittals of Revs 5,5a & 7 to ITS ML20210J2121999-07-23023 July 1999 Discusses NRC OI Investigation Rept 3-98-039 Completed on 990524 & Forwards Notice of Violation NRC-99-0053, Forwards Rev 14 to Fermi 2 Security Personnel Training & Qualification Plan, Per 10CFR50.54(p)(2).Changes Do Not Decrease Effectiveness of Plan.Summary of Changes Also Encl1999-07-15015 July 1999 Forwards Rev 14 to Fermi 2 Security Personnel Training & Qualification Plan, Per 10CFR50.54(p)(2).Changes Do Not Decrease Effectiveness of Plan.Summary of Changes Also Encl ML20209H7211999-07-14014 July 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 32 NRC-99-0054, Forwards Rev 10 to Fermi 2 ITS Submittal, , Providing Update to Submittal for ITS Section 3.4,RCS.Update Includes Changes Associated with NRC Review of Util Transmittal of Rev 4 to ITS Submittal1999-07-13013 July 1999 Forwards Rev 10 to Fermi 2 ITS Submittal, , Providing Update to Submittal for ITS Section 3.4,RCS.Update Includes Changes Associated with NRC Review of Util Transmittal of Rev 4 to ITS Submittal ML20209F6571999-07-12012 July 1999 Forwards Insp Rept 50-341/99-09 on 990516-0618.No Violations Noted.Weak Procedural Guidance,Communications Issues & Configuration Control Weaknessess Were Evident NRC-99-0052, Forwards Rev 9 to Fermi 2 ITS Submittal,Dtd 980403. Attachment 1 Contains Brief Abstract of Changes Included in Rev.Attachment 2 Contains Revised Pages for Submittal Along with Rev Instructions1999-07-0707 July 1999 Forwards Rev 9 to Fermi 2 ITS Submittal,Dtd 980403. Attachment 1 Contains Brief Abstract of Changes Included in Rev.Attachment 2 Contains Revised Pages for Submittal Along with Rev Instructions ML20196J5511999-07-0202 July 1999 Discusses GL 92-01,Rev 1,Supp 1, Rv Integrity, Issued by NRC on 950519 & DE Responses & 980729 for Fermi 2.Informs That Staff Revised Info in Rvid & Released Info as Rvid Version 2 as Result of Review of Responses ML20209C6141999-07-0101 July 1999 Rev 31 to Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section) NRC-99-0076, Forwards Rev 8 to ITS Submittal to Provide Update to ITS Submittal for ITS Section 3.7.Brief Abstract of Changes Included1999-06-30030 June 1999 Forwards Rev 8 to ITS Submittal to Provide Update to ITS Submittal for ITS Section 3.7.Brief Abstract of Changes Included 1999-09-09
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARNRC-99-0094, Forwards Safeguards Event Rept 99-S01-00 for Reportable Event That Occurred on 990922.Commitments Made by Util Listed1999-10-22022 October 1999 Forwards Safeguards Event Rept 99-S01-00 for Reportable Event That Occurred on 990922.Commitments Made by Util Listed NRC-99-0085, Forwards Rev 15 to Fermi 2 Security Personnel Training & Qualification Plan, IAW 10CFR50.54(p)(2).Without Encl1999-10-22022 October 1999 Forwards Rev 15 to Fermi 2 Security Personnel Training & Qualification Plan, IAW 10CFR50.54(p)(2).Without Encl ML20217N9231999-10-15015 October 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 40 NRC-99-0087, Responds to NRC Re Violations Noted in Insp Rept 50-341/99-10.Licensee Contests Subject Violation,Due to Listed Reasons1999-10-12012 October 1999 Responds to NRC Re Violations Noted in Insp Rept 50-341/99-10.Licensee Contests Subject Violation,Due to Listed Reasons NRC-99-0083, Submits Requested Response to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal1999-10-0707 October 1999 Submits Requested Response to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal ML20217D5331999-10-0707 October 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 39 ML20217A3261999-09-30030 September 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 38 NRC-99-0091, Forwards NRC Form 536,in Response to NRC Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Examinations1999-09-27027 September 1999 Forwards NRC Form 536,in Response to NRC Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Examinations ML20216G9791999-09-24024 September 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 37 NRC-99-0092, Documents Util Request for Enforcement Discretion with Respect to Requirements of TS 3/4.6.1.8 Re Drywell & Suppression Chamber Purge Sys1999-09-24024 September 1999 Documents Util Request for Enforcement Discretion with Respect to Requirements of TS 3/4.6.1.8 Re Drywell & Suppression Chamber Purge Sys ML20212F3241999-09-20020 September 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 36 NRC-99-0081, Submits Eight Relief Requests Associated with Containment Inservice Exam Program for Fermi 2 Plant,Per Provisions of 10CFR50.55a(g)(5)(iv).Requested Relief Does Not Adversely Affect Health & Safety of Public1999-09-17017 September 1999 Submits Eight Relief Requests Associated with Containment Inservice Exam Program for Fermi 2 Plant,Per Provisions of 10CFR50.55a(g)(5)(iv).Requested Relief Does Not Adversely Affect Health & Safety of Public NRC-99-0079, Forwards Rev 15 to Fermi 2 ITS Submittal,Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev1999-09-0808 September 1999 Forwards Rev 15 to Fermi 2 ITS Submittal,Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev NRC-99-0090, Forwards Proprietary Operator License Renewal Application, NRC Forms 398 & 396 for SW Burt,License SOP-30199-3. Proprietary Encls Withheld1999-09-0303 September 1999 Forwards Proprietary Operator License Renewal Application, NRC Forms 398 & 396 for SW Burt,License SOP-30199-3. Proprietary Encls Withheld ML20211Q0991999-09-0303 September 1999 Forwards Rev 35 to Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section) NRC-99-0066, Forwards semi-annual fitness-for-duty Rept for Fermi 2 for Period of 990101-0630,IAW 10CFR26.71(d)1999-08-30030 August 1999 Forwards semi-annual fitness-for-duty Rept for Fermi 2 for Period of 990101-0630,IAW 10CFR26.71(d) ML20211G4951999-08-24024 August 1999 Forwards Rev 34 to Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section) NRC-99-0056, Forwards Rev 2,change 0 to ISI-Nondestructive Exam (ISI-NDE) Program (Plan) for Piping,Components & Integral Attachments, for Second ten-year Interval of Fermi 2 Plant Operation1999-08-19019 August 1999 Forwards Rev 2,change 0 to ISI-Nondestructive Exam (ISI-NDE) Program (Plan) for Piping,Components & Integral Attachments, for Second ten-year Interval of Fermi 2 Plant Operation NRC-99-0055, Forwards Rev 5 to Inservice Testing Program for Pumps & Valves for Fermi 2 Second 10-Year Interval, Per Provisions of 10CFR50.55a(f)(5)(iv).Rev Includes Four Pump Relief Requests & Ten Valve Relief Requests Requiring NRC Approval1999-08-19019 August 1999 Forwards Rev 5 to Inservice Testing Program for Pumps & Valves for Fermi 2 Second 10-Year Interval, Per Provisions of 10CFR50.55a(f)(5)(iv).Rev Includes Four Pump Relief Requests & Ten Valve Relief Requests Requiring NRC Approval NRC-99-0089, Forwards Rev 13 to Fermi 2 ITS Submittal Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev1999-08-17017 August 1999 Forwards Rev 13 to Fermi 2 ITS Submittal Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev ML20217E6181999-08-13013 August 1999 FOIA Request for Documents Re Implementing Regulations in 10CFR & Requesting That Region III Task Interface Agreement (TIA) Related to Fermi 2 Plant Be Made Available NRC-99-0057, Forwards Rev 12 to ITS 980403 Submittal,Providing Update to Submittal for ITS Section 3.3,including Changes Associated with NRC Review of Rev 6 ITS1999-08-0404 August 1999 Forwards Rev 12 to ITS 980403 Submittal,Providing Update to Submittal for ITS Section 3.3,including Changes Associated with NRC Review of Rev 6 ITS ML20210N5451999-08-0303 August 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 33 NRC-99-0077, Forwards Rev 11 to Fermi ITS Submittal,Dtd 980403,providing Update to Submittal for ITS Sections 3.5,3.6 & 3.8.Update Includes Changes Associated with NRC Review of Util Transmittals of Revs 5,5a & 7 to ITS1999-07-26026 July 1999 Forwards Rev 11 to Fermi ITS Submittal,Dtd 980403,providing Update to Submittal for ITS Sections 3.5,3.6 & 3.8.Update Includes Changes Associated with NRC Review of Util Transmittals of Revs 5,5a & 7 to ITS NRC-99-0053, Forwards Rev 14 to Fermi 2 Security Personnel Training & Qualification Plan, Per 10CFR50.54(p)(2).Changes Do Not Decrease Effectiveness of Plan.Summary of Changes Also Encl1999-07-15015 July 1999 Forwards Rev 14 to Fermi 2 Security Personnel Training & Qualification Plan, Per 10CFR50.54(p)(2).Changes Do Not Decrease Effectiveness of Plan.Summary of Changes Also Encl ML20209H7211999-07-14014 July 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 32 NRC-99-0054, Forwards Rev 10 to Fermi 2 ITS Submittal, , Providing Update to Submittal for ITS Section 3.4,RCS.Update Includes Changes Associated with NRC Review of Util Transmittal of Rev 4 to ITS Submittal1999-07-13013 July 1999 Forwards Rev 10 to Fermi 2 ITS Submittal, , Providing Update to Submittal for ITS Section 3.4,RCS.Update Includes Changes Associated with NRC Review of Util Transmittal of Rev 4 to ITS Submittal NRC-99-0052, Forwards Rev 9 to Fermi 2 ITS Submittal,Dtd 980403. Attachment 1 Contains Brief Abstract of Changes Included in Rev.Attachment 2 Contains Revised Pages for Submittal Along with Rev Instructions1999-07-0707 July 1999 Forwards Rev 9 to Fermi 2 ITS Submittal,Dtd 980403. Attachment 1 Contains Brief Abstract of Changes Included in Rev.Attachment 2 Contains Revised Pages for Submittal Along with Rev Instructions ML20209C6141999-07-0101 July 1999 Rev 31 to Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section) NRC-99-0049, Submits Response to NRC GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Npps. Disclosure Encl1999-06-30030 June 1999 Submits Response to NRC GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Npps. Disclosure Encl NRC-99-0076, Forwards Rev 8 to ITS Submittal to Provide Update to ITS Submittal for ITS Section 3.7.Brief Abstract of Changes Included1999-06-30030 June 1999 Forwards Rev 8 to ITS Submittal to Provide Update to ITS Submittal for ITS Section 3.7.Brief Abstract of Changes Included ML20209C1081999-06-29029 June 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 30 NRC-99-0050, Forwards Rev 7 to ITS Submittal of 980403,to Provide Remaining Responses to NRC RAIs Re ITS Sections 3.5 & 3.8. Revision Instructions Included1999-06-24024 June 1999 Forwards Rev 7 to ITS Submittal of 980403,to Provide Remaining Responses to NRC RAIs Re ITS Sections 3.5 & 3.8. Revision Instructions Included NRC-99-0075, Forwards Operator License Renewal Application,Nrc Forms 398 & 396 for CR Effan,License SOP-30186-3.Encl Withheld1999-06-22022 June 1999 Forwards Operator License Renewal Application,Nrc Forms 398 & 396 for CR Effan,License SOP-30186-3.Encl Withheld ML20212J3861999-06-18018 June 1999 Forwards Rev 29 to Approved UFSAR LCR That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section) NRC-99-0047, Responds to NRC 990513 RAI Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design- Basis Accident Conditions. Revised Design Calculation DC-5957, GL 96-06 Calculations, Encl1999-06-0909 June 1999 Responds to NRC 990513 RAI Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design- Basis Accident Conditions. Revised Design Calculation DC-5957, GL 96-06 Calculations, Encl ML20195G2001999-06-0808 June 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy & Approved TRM Lcrs (Sorted by Section), Rev 28 ML20195E7391999-06-0303 June 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy & Approved TRM Lcrs (Sorted by Section), Rev 27 NRC-99-0046, Forwards Rev 6 to Fermi 2 ITS Submittal ,to Provide Remaining Responses to NRC RAI Re ITS Section 3.3, & Update ITS Submittal to Reflect Responses.Brief Abstract of Changes Contained in Attachment 11999-06-0202 June 1999 Forwards Rev 6 to Fermi 2 ITS Submittal ,to Provide Remaining Responses to NRC RAI Re ITS Section 3.3, & Update ITS Submittal to Reflect Responses.Brief Abstract of Changes Contained in Attachment 1 ML20207D9631999-05-26026 May 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy & Approved TRM Lcrs (Sorted by Section) ML20195B3381999-05-19019 May 1999 Forwards Rev 25 to Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy & Approved TRM Lcrs (Sorted by Section) NRC-99-0040, Requests NRC Approval of Revs to Weld Tables of Encl Relief Requests RR-A21,rev 1 & RR-A22,rev 1.Revs Do Not Impact Basis for Original Requests for Relief Because There Is No Change to Technical Basis or Proposed Alternative1999-05-14014 May 1999 Requests NRC Approval of Revs to Weld Tables of Encl Relief Requests RR-A21,rev 1 & RR-A22,rev 1.Revs Do Not Impact Basis for Original Requests for Relief Because There Is No Change to Technical Basis or Proposed Alternative NRC-99-0039, Requests Relief from ASME Section XI Requirement to Examine Essentially 100% of Selected Category B-J Pipe Welds,Per 10CFR50.55a(g)(5)(iii).Relief Request RR-A23,encl1999-05-14014 May 1999 Requests Relief from ASME Section XI Requirement to Examine Essentially 100% of Selected Category B-J Pipe Welds,Per 10CFR50.55a(g)(5)(iii).Relief Request RR-A23,encl NRC-99-0041, Requests Relief from ASME Section XI Requirements to Examine Essentially 100% of Accessible Category B-D Nozzle Welds,Per 10CFR50.55a(g)(5)(iii).Rev 1 to Relief Request RR-A6,encl1999-05-14014 May 1999 Requests Relief from ASME Section XI Requirements to Examine Essentially 100% of Accessible Category B-D Nozzle Welds,Per 10CFR50.55a(g)(5)(iii).Rev 1 to Relief Request RR-A6,encl NRC-99-0038, Requests Relief from ASME Section XI 1980 Requirement to Examine Essentially 100% If Category B-A RPV Shell Weld Lengths,Per 10CFR50.55a(g)(5)(iii)1999-05-14014 May 1999 Requests Relief from ASME Section XI 1980 Requirement to Examine Essentially 100% If Category B-A RPV Shell Weld Lengths,Per 10CFR50.55a(g)(5)(iii) NRC-99-0045, Forwards Rev 5a to Fermi 980403 Submittal,Converting TS to Its.Encl Rev Provides Remaining Responses to NRC RAIs Re ITS Section 3.6 Contained in NRC 990211 Rai.Brief Abstract of Changes & Responses to Rai,Encl1999-05-0707 May 1999 Forwards Rev 5a to Fermi 980403 Submittal,Converting TS to Its.Encl Rev Provides Remaining Responses to NRC RAIs Re ITS Section 3.6 Contained in NRC 990211 Rai.Brief Abstract of Changes & Responses to Rai,Encl NRC-99-0044, Forwards Rev 5 to ITS to Provide Responses to RAI Re ITS Section 3.6 (Except ITS Section 3.6.1.3) Contained in & Update in ITS Submittal to Reflect Responses1999-04-30030 April 1999 Forwards Rev 5 to ITS to Provide Responses to RAI Re ITS Section 3.6 (Except ITS Section 3.6.1.3) Contained in & Update in ITS Submittal to Reflect Responses NRC-99-0059, Provides Notification Required by 10CFR50.82(a)(7) of Changes to Fermi 1 Decommissioning Cost Estimate1999-04-29029 April 1999 Provides Notification Required by 10CFR50.82(a)(7) of Changes to Fermi 1 Decommissioning Cost Estimate ML20206E2941999-04-28028 April 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy & Approved TRM Lcrs (Sorted by Section), Rev 24 NRC-99-0037, Forwards Rev 9 to Fermi 2 Ufsar,Per 10CFR50.71(e) & 10CFR50.4(b)(6).Summary of Changes to QA Program & Vol 1 of Technical Requirements Manual,Encl1999-04-26026 April 1999 Forwards Rev 9 to Fermi 2 Ufsar,Per 10CFR50.71(e) & 10CFR50.4(b)(6).Summary of Changes to QA Program & Vol 1 of Technical Requirements Manual,Encl 1999-09-08
[Table view] |
Text
- - _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
USINie$7se lj,,
T Detroit r.-
'99' Edison !EEF## ^usuet '2 NRC-91-0094
% ~opere,ms e U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D. C. 20555
Reference:
- 1) Fermi 2 NRC Docket No. 50-341 NRC License No. NPF-43
- 2) Notice of Violation, NRC Inspection Report No. 50-341/91002, dated July 11, 1991
Subject:
Response to the Notice of Violation 91-002 Attached is the response to the Nctice of Violation 91-002 contained in Reference 2. These violations occurred or were discovered during a special-NRC team inspection of the Fermi 2 modification implementation process.
Detroit Edison is pleased the inspection cor.cluded that the modification process at Fermi was adequate and that individual aspects of the process were good. However, the detracting minor documentation errors, the occasional performance of work steps nonsequentially and the instances of failing to follow proper radiological controls are of concern to Detroit Edison and are areas that company personnel concur need increased attention. The feedback provided by the inspection will provide a basis for continued improvement at Fermi 2.
If there are any questions relating to this response, please contact Terry Riley, Supervisor, Compliance and Special Projects, at (313) l' t
586-1684 or Patricia Anthony, Senior Compliance Engineer, at (313)
! 586-1617.
1 i Sincerely, V IkY cc: A. B. Davis R. W. DeFayette J. F. Stang S. Stasek Region III
~8 wn n8 n PDR ADOCK 03000341
/@ h I
- O PDR
Attachment to' August 12, 1991 NRC-91-0094 Page 1 Statement of Violation 91-002-01 In the Notice of Violation contained in Reference 2, it states:
"10 CFR 50, Appendix B, Criterion V, requires that activities affecting quality be prescribed by documented instructions, procedures, and drawings, and those activities be accomplished in accordance with those instructions, procedures, and drawings.
Instructions, procedures, or drawings shall include appropriate quantitative or qualitative acceptance criteria for determining that important activities have been satisfacterily accomplished.
Fermi Management Directive. FHD CT1, Revision 1, " Calibration, Testing, and Surveillance," Section 4.5 312, an instruction requires, in part, that the calibration, test or surveillance procedure provide a sequence of operations, including inspections, functional checks, and measurements, as applicable, and the acceptance criteria and the means by which the response is to be observed for each.
Under " Definitions" of Appendix A. Revision 3, to the Fermi Management Policy and Directives Manual, acceptance criteria is defined as a limit or limits placed on the variation permitted in the characteristics of an item expressed in definitive engineering terms such as dimensional tolerances, chemical composition limits, density and size of defects, temperature ranges, item limits, operating parameters, and other similar characteristics.
Contrary to the above, surveillance procedures for the reactor protection system electrical protection assembly calibration / functional tests, 42.610.02 (Division 1) and 42.610.04 (Division II) did not include appropriate quantitative or qualitative acceptance criteria for the EPA breakers in that the undervoltage time delay limits were not acceptance criteria."
Reason for the Violation:
Procedures are developed using the Fermi 2 Writers Guide. The
-existing definition of acceptance criteria at that time in this
-document did not cover all values / settings required to support component and/or system operability, only values / settings specifically listed as line items in the Technical Specifications.
Since the undervoltage time delay limits were not line items in the Technical Specifications, they were designated as " acceptable limits" which did not have to be met in order for the EPA breakers to be considered operable. This was consistent with the guidance provided in the Fermi 2 Writers Guide at that time.
l l
i Attachment to August 12, 1991 NRC-91-0094 Page 2 Corrective Actions Being Taken and Results Achieved:
Procedures 42.610.02 and 42.610.04 have been placed in suspense so they cannot be used. Revisions to these procedures are being prepared to properly identify the time delay limits as acceptance criteria.
The precedure revisions will be approved by August. 16, 1991.
All procedures which use the term " acceptable limits" have been identified. These procedures are being reviewed to determine if any of these acceptable limits should actually be acceptance criteria.
The review is expected to be complete by the cr.d cf Septc.eber,1991, Appropriate procedure revisions, if any are needed, will be generated. Initial reviews indicate that the problem with the EPA undervoltage relay time delays was an isolated incident.
Corrective Actions to be Taken to Prevent Recurrence:
The Fermi 2 Writers Guide is being revised to define acceptance criteria in plant technical surveillance procedures as the performance limits necessary to meet the Technical Specification requirements.
This revision will be completed by August 16, 1991. Once this is completed, the guide will be issued as required reading to personnel responsible for developing procedures.
The NRC's notice of violation and Detroit Edison's response will be distributed to Maintenance, Operations, Technical Engineering and Nuclear. Engineering personnel for required reading in August 1991.
Date When Full Coggliance Will Be Achieved:
Detroit Edison is presently in full compliance and the corrective actions will ensure that Fermi 2 remains in compliance.
I I
)
Attachaent to August 12, 1991 NRC-91-0094 Page 3 Statement of Violation 91-002-02 In the Notice of Violation contained in Reference 2, it states:
" Technical Specification 6.8.1 requires that written procedures shall be established, implemented and maintained covering the applicable procedures recommended in Appendix A of Regulatory Guide 1 33, Revision 2, February 1978.
Appendix A of Regulatory Guide 1.33, Revision 2, February 1978, Scction 9, recommends proce* men for performing maintenance.
Procedure NPP-MA1-04 , Revision 7, " Conduct of Haintenance",
Section 5,2 3 requires that actual work instructions be included on the work request planning form. Instructions are to be followed sequentially unless as indicated within the body of the instructions.
Contrary to the above, on numerous occasions (work requests 0030900322, 010c890814, 011c890814, 005C890814, 020D900724, 0090901129, 010D901129, 008D901129, 007D901129, 010D901112) maintenance work instructions were not followed sequentially and this was not indicated in the body of work instructions."
Reason for the Violation:
A review of this issue has . led to the conclusion that this violation is attributable to personnel error. Several factors which contributed to this violation were identified.
First, procedure NPP-MA1-04 was determined to be overly restrictive as it relates to the performance sequence of steps in work packages.
This allowed no flexibility for the supervisors and craft who are capable of informed and responsible decisions in this area. Second, there was a lack of personnel attention to detail in regards to the requirements of NPP-MA1-04. Finally, there was a lack of '
comprehension / full understanding of the significance of proper documentation of work performed.
As was confirmed in Reference 2, there was no safety significance or impact on component operability as a result of these-decisions. -
Therefore, this level of performance was inappropriately accepted.
Corrective Actions Being Taken and Results Achieved:
A comprehensive review of the work packages completed in the month of April, 1991 has been performed by the Maintenance Department. The purpose of this review was to identify and correct any discrepancies in the documentation. The Quality Assurance organization is performing a surveillance of this review and it is expected to be completed at the end of August 1991.
Attachment to August 12, 1991 NRC-91-0094 Page 4 After the concern with attention to detail in work package documentation was identified during the outage, the subject was discussed in meetings with senior management. The appropriato expectations were conveyed down the line organization to the craftsmen and first line supervisors in a variety of meetings.
Corrective Actions Taken to Prevent Recurrence:
Detroit Edison's Quality Assurance organization is implementing increased inspections to provide specific feedback to the nuclear organization regarding work package performance and documentation.
This information is used in continuing briefings to improve the standards of performance in this area. Inspections will continue to monitor site performance in this area for work performed after April, 1991. This is an ongoing activity !n which the frequency and depth of review will be modified based upon the inspection results and trends. '
Maintenance management is providing formal presentations to personnel to communicate expectations in the areas of work package documentation, procedural compliance and related topics. These meetings will be held by August 15, 1991.
Procedure NPP-MA1-04 is being revised to provide supervisory discretion in the performance sequence of steps within work packages.
This revision is expected to be approved by the end of August 1991.
In the interim, th? planning and work groups have been instructed to include a statement allowing non-sequential performance of steps in the work packages, if appropriate.
The NRC's violation and this response will be in the required reading issued to Operations, Maintenance and Technical Engineering personnel in August, 1991.
Date When Full Compliance Will Be Achieved:
Detroit Edison is presently in full compliance. The actions described previously in this section will ensure that full compliance is maintained.
i I
i
, _ - _ _ - _ _ - - - _ - _ ~ _ - - . _ - - _ _ - - - - - - _ - - . - - -
Attachment to August 12, 1991 NRC-91-0094 Page 5 Statement of Violation 91-002-03 In the Notice of Violation contained in Reference 2, it states:
" Technical Specification 6.8.1 requires that written procedures shall be established, implemented, and maintained covering the applicable procedures recommended in Appendix A of Regulatory Guide 1.33, Revision 2, February 1978.
Appendix A of Regulatory Guide 133, Revision 2, February 1978, Sectior, 7 recommended proccJures for control of radioactivity (for limiting materials released to the environment and limiting personnel exposure),
- a. Procedure F1P-RC1-01, Revision 2, Accessing and Working in Radiologically Controlled Areas", Section 5.1.1 required written instructions on appropriate radiation work permits (RWP) always be followed.
RWP No. 91-1155. Special Instruction 2.A. required on May 1, 1991, that coveralls be worn for entry into the contaminated work area for EDP 08321, on the second floor of the Turbine Building.
Contrary to the above, on May 1, 1991, a contractor wolder, while working inside a contaminated area controlled by RWP 91-1155, improperly wore radiation protection coveralls in that the coveralls were unzipped while in the contaminated area to use a pen. This is an example of a violation.
- b. Procedure FIP-RC1-01, Revision 2, " Accessing and Working In Radiologically Controlled Areas", Section 5.1.1 required that written instructions on appropriate RWPs always be followed. J RWP 91-1155, Special Instruction 7, required that a whole body frisk be performed at the nearest frisker location immediately upon exiting the contaminated work area for EDP 08321.
Contrary to the_above, on May 1, 1991, a contractor carpenter failed to perform a whole body frisk at the nearest frisker location immediately upon exiting the contaminated area for EDP 08321. This is an example or a violation.
- c. Procedure FIP-RC1-01, Revision 2, " Accessing and Working In Radiologically Controlled Areas", Section 5.1.1 required that radiological postings never be-violated.
Contrary to the above, on May 2, 1991, a contractor violated a
- radiological costing by climbing above a contamination boundary area posting affixed to a ladder on the south side of the drywell, in the Reactor Building. This is an example of a violation.
Attachsent to August 12, 1991 NRC-91-0094 Page 6
- d. Procedure F1P-RCI-01, Revision 2, " Accessing and Working In Radiologically Controlled Areas", Section 5.1.1 required that written instructions on appropriate RWPs always be followed.
RWP 91-1151, Special instruction 4, required that workers bag all tools and equipment or have radiation protection personnel survey items prior to removal from the contaminated work areas for EDP 11300.
Contrary to the above, on May 6, 1991, contractor Vers passed tools and equipment through piping penetrat on P-17171 on the first floor of the Turbine Building steam tunnel (a contaminated work area for EDP 11300) to the second floor of the steam tunnel (a radiologically clean area) without bagging ot performing surveys of the tools and equipment. This is ar.
example of a violation."
Reason for the Violation:
The four violation examples noted by the NRC have similar causes. The primary reason for these violations 13 personnel error. Several factors contributed to these errors, as follows: (1) lack of personnel accountability for and personal ownership of Radiation Protection responsibilities; (2) ineffective implementation of administrative and procedural controla; (3) lack of attention to detail in implementing existing and adequate Radiation Protection policies and practices and (4) inade:guate contractor controls .
The four examples noted all involved personnel errors committed by contractors. Decru't WimWs review of the current rhdiation protection program requirements at F6ral 2 indicates that current l
policies, practices and procedures are sufficient to have precluded i
the occurrence of these events., Tnis is based on the following:
(1) Violation 91-002-03a: As noted in tne vlolation stat ment, EIP-RC1-01 requires that written instructions on appropriate RWPs
[.
always be followed. RWP oi-1155 required that coveralls be worn
! inside the affected contaminated area for EDP 8321. All radiation workers are trained in proper techniques for donning and wearing anti-contamination clott g, A practical demonstration is required to qualify. The contract individual involved showed a disregard for these requirements.
(2) Violat. ion 91-002-03b: As noted in the violation statement, FIP-RC1-01 requires that written instructions on appropriate RWPs i
always be followed. RWP 91-1155 required whole body frisks at the nearest frisker upon exiting the contaminated area. All radiation workers are trained on RWP compliance and frisking requirements.
A practical demonstration of frisking techniques is required to qualify as a radiation worker. The contract individual involved showed a disregard for these requirements.
Attachment to
+
August 12, 1991 NRC-91-0094 Page 7 (3) Violation 91-002-03c: As noted in the violation statement, FIP-RC1-01 requires that radiological postings never be violated.
All site personnel are trained on the requirements of radiological postings. Discussion with the area Radiatico Protection Technician assigned indicated the worker was directed not to cross the boundary during a pre-job briefing. The contract worker involved demonstrated a disregard for these requirements.
(4) Violation 91-002-03d: As noted in the violation statement, FIP-RC1-01 rc eu M that written instructions on appropriate RWPs always'be followed. RWP 91-1151 required that personnel involved bag tools / equipment or perform radiation surveys prior to removal from the contaminated areas for EDP 11300. All radiation workers are instructed and tested on the correct method for removal of tools / equipment from contaminated areas. The contract workers involved demonstrated a general failure to observe the appropriate radiological requirements.
Ultimately, the responsibility and accountability for inplementation of appropriate radiological controls rests with the individual (s) involved in the work activity. Initiatives are underway to improve Fermi 2 performance in this area as described below.
Corrective Actions Taken and Results Achieved:
For each exarnle violation noted by the NRC, the following remedial actions werr 2 ken:
(1) Violation 91-002-03a - The contractor involved was released from Employment at fermi 2.
(2) Violation 91-002-03b - The contract worker involved was not immediately identified due to the time lag prior to notification of site Radiation Protection personnel and the Modifications Supervisor. Later, the contractor was identified and released by the Modifications Supervisor. Radiation Protection technicians were briefed on the concern and the contract ALARA Coordinator discussed the incident witn other contract persor.nel.
. (3) Violation 91-002-03c - Although a Radiation Protection technician was notified of the NRC inspector's concern, the technician stated that the contract worker did not violate the posting while he observed the work and it was not clear to him that a previous violation had occurred. No further remedial action was taken for this instance.
(4) Violation 91-002-03d - Site Radiation Protection personnel were notified of this-incident and proceeded to survey the area and the tools placed.in the area. A posted area was established by Radiation Protection. Radiation Protection technicians were briefed on this event and instructed to be alert to similar circumstances which could develop on other jobs. The contract
g Attachment to August 12, 1991 NRC-91-0094 Page 8 ALARA Coordinator briefed modifications personnel on this event.
'the contract workers involved were released from employment at Fermi 2. No recurrence of this problem was identified during the outage. RadWorker training has been reviewed and determined to ;
adequately cover passing material in/out of contaminated areas.
Corrective Action to be Taken to Prevent Recurrence:
Deviation Event Report (DER) , .,617 was written to address these violations. This DER addr; es further corrective actions being taken to prever.t recurrence of tht.a violations of radiation protection program requirements and procedures.
Current radiation protection requirements are adequate to preclude these violations. All personnel who work at Fermi 2 are, however, individually responsible for their actions in this regard. Attention )
to detail during the performance of all jobs involving radiological conditions is essential to successful implementation of these !
requirements.
The following actions are being/will be taken to address the root causes of these violations:
o Contracts for off-site assistance will more clearly emphasize that Fermi 2 radiological protect, ion program, policies and procedures must be followed at all times by contract personnel during the performance of their contract duties. Appropriate disciplinary actions, up to and including personnel release from the job site, will be taken in the event these requirements are violated.
During contract negotiations, continued emphasis will be placed on individual ownership, responsibility and accountability during the performance of required tasks. Pre-job briefings will also continue to focus on these and other matters specific to radiological controls, o Onsite meetings will be held between Radiation Protection management, department heads and other key supervisory personnel to discuss the importance of proper implementation of radiological controls. These meetings will emphasice previous problems experienced, individual job responsibilities, accountability for personnel actions and supervisory controls. This action will be-completed by the end of 1991.
o When radiation protection implementation problems are encountered, accountability meetings will be held with the individual (s) involved, their supervision, the Plant Manager and the Radiation Protection manager (RPM). Actions will be critiqued and appropriate lessons learned will be disseminated, as needed.
o A special radiological assessment will be conducted regarding the understanding of individual responsibility to up-hold and follow radiological practices, assess implementation problems experienced by site workers and to determine the effectiveness of corrective
Attach ent to August 12, 1991 NRC-91-0094 Page 9 actions taken or underway to improve performance. A report on this assessment will be issued onsite by March 31, 1992. This will allow sufficient time to review results of meetings with supervision and identify any additional corrective actions to be implemented.
o A discussion of the above incidents, the NRC Notice of Violatior, and this response will be included in site radiation worker training. Training for site radiation workers will be completed during the current requalification cycle, which is scheduled to end in SeptemLer, 1992, contractors will be trained when hired, o Managemenu initiatives are underway to rely less on the use of contractors for futu,e outages.
Date When Full Compliance Will S3 Achieved:
The requireuents of Technical Specification 6.8.1, our commitment to Appendix A of Regulatory Guide 133, Revision 2, and existing site radiat19n protection programs, practices ano procedures are already fully complied with by Fermi 2. The incidents identified in this violecien involved personnel errors and/or failures to implement these receirements. The corrective actions identified above should result in improvements in effective implementation of these controls.
1 i
t 1
- . - - .