Significant Hazards Evaluation and Environmental Considerations for Farley Risk Informed Technical Specifications Response to Request for Additional Information
ML19137A343
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 05/17/2019
From: Gayheart C
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NL-19-0623
Download: ML19137A343 (1)


Text

~ Southern Nuclear Regulatory Affairs 3535 Colonnade Parkway Birmingham, AL 35243 205 992 5000 tel 205 992 7795 fax MAY 1 7 2019 Docket Nos.: 50-348 NL-19-0623 50-364 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Joseph M. Farley Nuclear Plant Units 1 & 2 Significant Hazards Evaluation and Environmental Considerations for Farley Risk Informed Technical Specifications Response to Request for Additional Information Ladies and Gentlemen:

By letter dated July 27, 2018, Southern Nuclear Operating Company (SNC) submitted a license amendment request (LAR) for the Joseph M. Farley Nuclear Plant Unit 1 and Unit 2 facility operating license (FOL) and technical specifications (TS). By letter dated May 3, 2019, SNC responded to Nuclear Regulatory Commission (NRC) requests for additional information (RAis). This RAI response included some modifications to the proposed FOL and TS markups from those provided in the LAR. The purpose of this letter is to inform the NRC that the RAI response letter (including the revised markups and supplemental request) does not alter the conclusions of either the No Significant Hazards Consideration response nor the Environmental Considerations response provided in the LAR.

This letter contains no NRC commitments. If you have any questions, please contact Jamie Coleman at 205.992.6611.

I d~clare under penalty of perjury that the foregoing is true and correct. Executed on the

~day of May 2019.

Respectfully submitted, Cheryl a~ a Director, egulatory Affairs Southern Nuclear Operating Company CAG/PDB/CBG cc: Regional Administrator, Region II NRR Project Manager- Farley Senior Resident Inspector- Farley Director, Alabama Office of Radiation Control RTYPE: CFA04.054