ML22060A189

From kanterella
Jump to navigation Jump to search

Correction to TS Pg 3.6.6-4 During Issuance of Amendment Nos. 225 and 222
ML22060A189
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 03/15/2022
From: Stephanie Devlin-Gill
NRC/NRR/DORL/LPL2-1
To: Gayheart C
Southern Nuclear Operating Co
Devlin-Gill S (301) 415-5301
References
EPID L-2018-LLA-0210
Download: ML22060A189 (5)


Text

March 15, 2022 Ms. Cheryl A. Gayheart Regulatory Affairs Director Southern Nuclear Operating Co., Inc.

3535 Colonnade Parkway Birmingham, AL 35243

SUBJECT:

JOSEPH M. FARLEY NUCLEAR PLANT, UNITS 1 AND 2 - CORRECTION TO TECHNICAL SPECIFICATION PAGE 3.6.6-4 DURING ISSUANCE OF AMENDMENT NOS. 225 AND 222 (EPID L-2018-LLA-0210)

Dear Ms. Gayheart:

On August 23, 2019 (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML19175A243), the U.S. Nuclear Regulatory Commission (NRC) issued Amendment No. 225 to Renewed Facility Operating License (RFOL) No. NPF-2 and Amendment No. 222 to RFOL No. NPF-8 for the Joseph M. Farley Nuclear Plant (FNP),

Units 1 and 2, respectively, modifying of the Technical Specifications (TSs) to permit the use of Risk-Informed Completion Times in accordance with Topical Report Nuclear Energy Institute (NEI) 06-09, "Risk-Informed Technical Specifications Initiative 4b, Risk-Managed Technical Specifications (RMTS) Guidelines," Revision 0-A. The amendments also added a new program, the "Risk-Informed Completion Time Program," to TS Section 5.5, "Programs and Manuals."

Subsequent to the issuance of Amendment No. 225 to RFOL No. NPF-2 and Amendment No. 222 to RFOL No. NPF-8, by letter dated February 24, 2022 (ADAMS Accession No. ML22056A310), Southern Nuclear Operating Company (SNC, the licensee) identified that an administrative error was introduced on the updated TS page 3.6.6-4. The administrative error occurred during the submittal and processing of Amendment No. 225 to RFOL No. NPF-2 and Amendment No. 222 to RFOL No. NPF-8, respectively, and the error was that the Surveillance Requirement (SR) 3.6.6.9 on TS page 3.6.6-4 was inadvertently removed.

The NRC staff has determined that this error was administrative in nature and has corrected the errors. The corrections do not change any of the conclusions associated with the issuance of Amendment No. 225 to RFOL No. NPF-2 and Amendment No. 222 to RFOL No. NPF-8. The NRC staff has determined that this error does not affect the proposed finding that the amendments involve no significant hazards consideration published in the Federal Register on June 4, 2019 (84 FR 25840).

Consistent with NRC staff guidance dated January 16, 1997 (ADAMS Accession No. ML103260096), based on the NRCs policy established by SECY-96-238, these errors can be corrected by a letter to the licensee from the NRC staff.

C. Gayheart If you have any questions, please contact me at 301-415-5301, or via e-mail at Stephanie.Devlin-Gill@nrc.gov.

Sincerely,

/RA/

Stephanie Devlin-Gill, Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-348, 50-364

Enclosure:

1. Corrected Page for Amendment No. 225 to NPF-2 and Amendment No. 222 to NPF-8 Cc w/

Enclosure:

Listserv

ENCLOSURE 1 CORRECTED PAGE FOR AMENDMENT NO. 225 TO NPF-2 AND AMENDMENT NO. 222 TO NPF-8 SOUTHERN NUCLEAR OPERATING COMPANY, INC.

JOSEPH M. FARLEY NUCLEAR PLANT, UNITS 1 AND 2 DOCKET NOS. 50-348 AND 50-364

Containment Spray and Cooling Systems 3.6.6 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.6.6.2 Operate each required containment cooling train fan In accordance with unit for 15 minutes. the Surveillance Frequency Control Program SR 3.6.6.3 Verify each containment cooling train cooling water In accordance with flow rate is 1600 gpm. the Surveillance Frequency Control Program SR 3.6.6.4 Verify each containment spray pump's developed In accordance with head at the flow test point is greater than or equal to the INSERVICE the required developed head. TESTING PROGRAM SR 3.6.6.5 Verify each automatic containment spray valve in the In accordance with flow path that is not locked, sealed, or otherwise the Surveillance secured in position, actuates to the correct position Frequency Control on an actual or simulated actuation signal. Program SR 3.6.6.6 Verify each containment spray pump starts In accordance with automatically on an actual or simulated actuation the Surveillance signal. Frequency Control Program SR 3.6.6.7 Verify each containment cooling train starts In accordance with automatically on an actual or simulated actuation the Surveillance signal. Frequency Control Program SR 3.6.6.8 Verify each spray nozzle is unobstructed. In accordance with the Surveillance Frequency Control Program SR 3.6.6.9 Verify containment spray locations susceptible to gas In accordance with accumulation are sufficiently filled with water. the Surveillance Frequency Control Program Farley Units 1 and 2 3.6.6-4 Amendment No. 225 (Unit 1)

Amendment No. 222 (Unit 2)

C. Gayheart

SUBJECT:

JOSEPH M. FARLEY NUCLEAR PLANT, UNITS 1 AND 2 - CORRECTION TO TECHNICAL SPECIFICATION PAGE 3.6.6-4 DURING ISSUANCE OF AMENDMENT NOS. 225 AND 222 (EPID L-2018-LLA-0210) DATED MARCH 15, 2022 DISTRIBUTION:

PUBLIC LPL2-1 R/F RidsAcrs_MailCTR Resource RidsNrrDorlLpl2-1 Resource RidsNrrLAKGoldstein Resource RidsNrrPMFarley Resource RidsRgn2Mail Center Resource JLamb, NRR SWilliams, NRR ADAMS Accession No.: ML22060A189 OFFICE NRR/DORL/LPL2-1/PM NRR/DORL/LPL2-1/LA NRR/DORL/LPL2-1/BC NAME SDevlin-Gill KGoldstein MMarkley DATE 03/01/2022 03/01/2022 03/15/2022 OFFICE NRR/DORL/LPL2-1/PM NAME SDevlin-Gill DATE 03/15/2022