EPID - L-2018-LLA-0210, TSTF-500, TSTF-505, TSTF-412 (Approved, Closed) 27 July 2018 - 15 March 2022 | |
---|---|
Initiation
| |
From: | |
MONTHYEARNL-18-0039, License Amendment Request to Revise Technical Specifications to Implement NEI 06-09, Revision 0-A, Risk-Informed Technical Specifications Initiative 4b, Risk Managed Technical Specifications (Rmts) ...2018-07-27027 July 2018
[table view]Title: License Amendment Request to Revise Technical Specifications to Implement NEI 06-09, Revision 0-A, Risk-Informed Technical Specifications Initiative 4b, Risk Managed Technical Specifications (Rmts) ... ML18243A4062018-08-31031 August 2018 Title: Acceptance of Licensing Action Regarding Request to Revise Technical Specifications to Implement NEI 06-09, Revision 0-A, Risk-Informed Technical Specifications Initiative 4b ML18290B0942018-10-16016 October 2018 Title: October 16, 2018, Public Meeting Presentation Slides Related to July 27, 2018, License Amendment Request to Implement NEI 06-09, Revision 0-A, Risk-Informed Technical Specifications Initiative 4b. ML18306A3132018-11-0707 November 2018 Title: Summary of October 16, 2018, Meeting with Southern Nuclear Operating Company, Inc., to Discuss the Joseph M. Farley Unit 1 & 2, Electrical Distribution System as It Relates to the Risk-Informed Completion Times Amendment ML18338A0052019-01-0404 January 2019 Title: Regulatory Audit in Support of the License Amendment Request to Implement Risk-Informed Technical Specifications Initiative 4B ML19042A1082019-02-26026 February 2019 Title: Audit Summary in Support of the License Amendment Request to Implement Risk-Informed Technical Specifications Initiative 4B ML19072A0272019-03-12012 March 2019 Title: NRR E-mail Capture - Joseph M. Farley Nuclear Plant, Units 1 and 2 - Request to Revise Technical Specifications to Implement NEI 06-09, Revision 0-A, Risk-Informed Technical Specifications Initiative 4B NL-19-0221, Risk-Informed Technical Specifications Initiative 4b, Risk-Managed Technical Specifications, SNC Response to NRC Request for Additional Information (RAI)2019-05-0303 May 2019 Title: Risk-Informed Technical Specifications Initiative 4b, Risk-Managed Technical Specifications, SNC Response to NRC Request for Additional Information (RAI) NL-19-0623, Significant Hazards Evaluation and Environmental Considerations for Farley Risk Informed Technical Specifications Response to Request for Additional Information2019-05-17017 May 2019 Title: Significant Hazards Evaluation and Environmental Considerations for Farley Risk Informed Technical Specifications Response to Request for Additional Information NL-19-0771, Risk Informed Technical Specification Information Only Bases Changes2019-06-27027 June 2019 Title: Risk Informed Technical Specification Information Only Bases Changes ML19175A2432019-08-23023 August 2019 Title: Issuance of Amendments 225 and 222 Implementation of NEI 06-09, Risk-Informed Technical Specifications Initiative 4B, Risk-Managed Technical Specification (Rmts) Guidelines, Revision 0-A NL-22-0091, Correction of Technical Specification Typographical Omission2022-02-24024 February 2022 Title: Correction of Technical Specification Typographical Omission ML22060A1892022-03-15015 March 2022 Title: Correction to TS Pg 3.6.6-4 During Issuance of Amendment Nos. 225 and 222 2019-03-12 |