|
---|
Category:Letter type:ND
MONTHYEARND-24-0103, Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests2024-04-26026 April 2024 Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests ND-24-0114, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-04-0101 April 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-24-0046, (Vegp), Unit 3, Condition Prohibited by Technical Specification Limiting Condition of Operation 3.1.6 Control Bank Overlap Limits Exceeded Due to Inadequate Procedure Guidance2024-03-18018 March 2024 (Vegp), Unit 3, Condition Prohibited by Technical Specification Limiting Condition of Operation 3.1.6 Control Bank Overlap Limits Exceeded Due to Inadequate Procedure Guidance ND-24-0059, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-03-0404 March 2024 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0693, Combined License (COL) License Condition 2.D.(4)(d) Completion of Initial Criticality and Low-Power Tests2024-02-15015 February 2024 Combined License (COL) License Condition 2.D.(4)(d) Completion of Initial Criticality and Low-Power Tests ND-23-0690, Combined License (COL) License Condition 2.D.(3)(e) Completion of Pre-Critical Tests2024-02-0808 February 2024 Combined License (COL) License Condition 2.D.(3)(e) Completion of Pre-Critical Tests ND-24-0019, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-02-0101 February 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0912, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-01-0202 January 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0881, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-12-0404 December 2023 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0817, (Vegp), Units 3 and 4 - Report of UFSAR Chapter 14 Changes to the Initial Test Program in Accordance with License Condition 2.D.(7)(a)2023-11-17017 November 2023 (Vegp), Units 3 and 4 - Report of UFSAR Chapter 14 Changes to the Initial Test Program in Accordance with License Condition 2.D.(7)(a) ND-23-0823, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-11-0303 November 2023 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0723, (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-10-0404 October 2023 (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0697, (Vegp), Unit 4, Submittal of Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-09-0505 September 2023 (Vegp), Unit 4, Submittal of Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0669, (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-08-0707 August 2023 (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0205, (Vegp), Unit 3 - Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests2023-07-28028 July 2023 (Vegp), Unit 3 - Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests ND-23-0607, ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13) ND-23-0618, Resubmittal of ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.07c.ii.a (Index Number 797)2023-07-20020 July 2023 Resubmittal of ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.07c.ii.a (Index Number 797) ND-23-0609, Notification of Completion of All ITAAC2023-07-20020 July 2023 Notification of Completion of All ITAAC ND-23-0608, ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72) ND-22-0796, ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.08 (Index Number 813)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.08 (Index Number 813) ND-23-0459, ITAAC Closure Notification on Completion of ITAAC 2.6.01.04d (Index Number 587)2023-07-19019 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.01.04d (Index Number 587) ND-23-0162, ITAAC Closure Notification on Completion of ITAAC 2.2.03.05a.i (Index Number 165)2023-07-19019 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.05a.i (Index Number 165) ND-23-0483, ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4) ND-23-0552, Southern Nuclear Operating Company, Vogtle Electric Generating Plant, Unit 4, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02c (Index Number 624)2023-07-18018 July 2023 Southern Nuclear Operating Company, Vogtle Electric Generating Plant, Unit 4, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02c (Index Number 624) ND-23-0439, ITAAC Closure Notification on Completion of ITAAC 2.2.05.07a.i (Index Number 265)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.05.07a.i (Index Number 265) ND-23-0575, ITAAC Closure Notification on Completion of ITAAC 2.6.01.04e (Index Number 588)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.01.04e (Index Number 588) ND-23-0610, ITAAC Closure Notification on Completion of ITAAC Item 2.6.03.04c (Index Number 603)2023-07-17017 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.6.03.04c (Index Number 603) ND-23-0586, ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159)2023-07-17017 July 2023 ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159) ND-23-0406, ITAAC Closure Notification on Completion of ITAAC Item 2.4.02.02b (Index Number 498)2023-07-16016 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.4.02.02b (Index Number 498) ND-23-0573, ITAAC Closure Notification on Completion of 2.4.02.02a (Index Number 497)2023-07-16016 July 2023 ITAAC Closure Notification on Completion of 2.4.02.02a (Index Number 497) ND-23-0476, ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355) ND-23-0499, ITAAC Closure Notification on Completion of ITAAC 2.7.01.14 (Index Number 700)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.7.01.14 (Index Number 700) ND-23-0606, ITAAC Closure Notification on Completion of ITAAC 2.5.04.02.i (Index Number 557)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.5.04.02.i (Index Number 557) ND-23-0601, ITAAC Closure Notification on Completion of ITAAC Item 2.7.05.02.i (Index Number 719)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.7.05.02.i (Index Number 719) ND-23-0594, ITAAC Closure Notification on Completion of ITAAC 2.6.05.02.ii (Index Number 629)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.05.02.ii (Index Number 629) ND-23-0446, ITAAC Closure Notification on Completion of ITAAC 2.2.04.12a.iii (Index Number 250)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.04.12a.iii (Index Number 250) ND-23-0603, ITAAC Closure Notification on Completion of ITAAC Item 3.5.00.06 (Index Number 831)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 3.5.00.06 (Index Number 831) ND-22-0816, ITAAC Closure Notification of Completion of ITAAC 2.1.02.05a (Index Number 19)2023-07-15015 July 2023 ITAAC Closure Notification of Completion of ITAAC 2.1.02.05a (Index Number 19) ND-23-0002, ITAAC Closure Notification on Completion of ITAAC 2.2.05.07c (Index Number 270)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.05.07c (Index Number 270) ND-23-0597, ITAAC Closure Notification on Completion of ITAAC 2.5.02.06a.ii (Index Number 530)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.5.02.06a.ii (Index Number 530) ND-23-0122, ITAAC Closure Notification on Completion of ITAAC C.2.6.09.08a (Index Number 668)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.08a (Index Number 668) ND-23-0121, ITAAC Closure Notification on Completion of ITAAC C.2.6.09.07 (Index Number 667)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.07 (Index Number 667) ND-23-0588, ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78) ND-23-0394, ITAAC Closure Notification on Completion of ITAAC 2.7.02.03a (Index Number 703)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.7.02.03a (Index Number 703) ND-23-0543, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02a (Index Number 622)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02a (Index Number 622) ND-23-0461, ITAAC Closure Notification on Completion of ITAAC 2.6.09.13a (Index Number 652)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.09.13a (Index Number 652) ND-23-0587, ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595) ND-22-0980, ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.06.i (Index Number 75)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.06.i (Index Number 75) ND-23-0111, ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646) ND-23-0581, ITAAC Closure Notification on Completion of ITAAC 2.2.04.02a (Index Number 220)2023-07-12012 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.04.02a (Index Number 220) 2024-04-26
[Table view] Category:Report
MONTHYEARML24297A6482024-10-23023 October 2024 5 to the Updated Final Safety Analysis Report, Technical Specification Bases Changes, Technical Requirements Manual Changes, Summary Report and Revised NRC Commitments Report ML23325A2022024-01-16016 January 2024 CFR Part 52 Construction Lessons-Learned Report NL-23-0926, Correction of Technical Specification Typographical Error2024-01-12012 January 2024 Correction of Technical Specification Typographical Error ML24004A2192024-01-0808 January 2024 Construction Reactor Oversight Process Performance Metric Report for Calendar Year 2023 ND-23-0025, Compliance with Order EA-12-0492023-08-21021 August 2023 Compliance with Order EA-12-049 ML22348A0932023-07-28028 July 2023 Finding That the Acceptance Criteria in the Combined License Are Met ML22348A0882023-07-25025 July 2023 VEGP Unit 4 - 103g - Basis Document ML23184A0472023-07-0303 July 2023 Dashboard Report 7-3-2023 ML23156A1882023-06-0505 June 2023 Construction Reactor Oversight Process Resources Report June 5, 2023 ML23121A0392023-05-0101 May 2023 Dashboard Report 5-1-2023 ML23003A0412023-01-0303 January 2023 Construction Reactor Oversight Process Resources Report January 3, 2023 ND-22-0817, Enclosures 1 and 2: Proposed Alternative Inspection Requirements for Steam Generator Nozzle to Reactor Coolant Pump Casing Welds and Alternative for Use of Code Case 648-2 for Inservice Inspection2022-11-0404 November 2022 Enclosures 1 and 2: Proposed Alternative Inspection Requirements for Steam Generator Nozzle to Reactor Coolant Pump Casing Welds and Alternative for Use of Code Case 648-2 for Inservice Inspection ND-22-0831, (Vegp), Units 3 and 4, Comments on AP1000 Standard Technical Specifications (STS) Draft NUREG-2194, Revision 12022-10-31031 October 2022 (Vegp), Units 3 and 4, Comments on AP1000 Standard Technical Specifications (STS) Draft NUREG-2194, Revision 1 ML22278A0382022-10-0505 October 2022 Dashboard Report 10-5-2022 ML22215A0962022-08-0303 August 2022 Construction Reactor Oversight Process Resources Report August 3, 2022 ML22214A0072022-08-0101 August 2022 Archives ML20290A2762022-08-0101 August 2022 10CFR52.103(g) Basis Document NL-22-0510, Plants Units 1 and 2, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20212022-07-14014 July 2022 Plants Units 1 and 2, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2021 ML22179A1462022-06-15015 June 2022 Tier 1, Revision 10, Updated Through 04/22/2022 ML22159A1712022-06-0808 June 2022 Construction Reactor Oversight Process Resources Report June 8, 2022 ML22131A0502022-05-11011 May 2022 Construction Reactor Oversight Process Resources Report May 11, 2022 ML22089A0412022-03-30030 March 2022 Construction Reactor Oversight Process Resources Report March 30 2022 ND-22-0003, Report of 10 CFR 50.59 Changes, Tests, and Experiments and 10 CFR 52 Appendix D Departure Report2022-01-0606 January 2022 Report of 10 CFR 50.59 Changes, Tests, and Experiments and 10 CFR 52 Appendix D Departure Report ND-21-1003, Request for Exemption: Applicability of 10 CFR 26.3. Scope, Until Initial Fuel Load - Supplement2021-11-12012 November 2021 Request for Exemption: Applicability of 10 CFR 26.3. Scope, Until Initial Fuel Load - Supplement ND-21-0991, Exemption Request: Applicability of 10 CFR 26.3, Scope, Until Initial Fuel Load2021-11-0505 November 2021 Exemption Request: Applicability of 10 CFR 26.3, Scope, Until Initial Fuel Load ML21280A3042021-10-0707 October 2021 Q 2020 Performance Summary ML21280A3052021-10-0707 October 2021 Q/2020 Performance Summary ML21277A0762021-10-0404 October 2021 Vog 4 Dashboard 10-4-2021 ND-21-0848, Enclosure - Unit 4 Operator Candidates Requesting Credit for Unit 3 Written Examination and Operating Test (Revised)2021-10-0101 October 2021 Enclosure - Unit 4 Operator Candidates Requesting Credit for Unit 3 Written Examination and Operating Test (Revised) IR 05000424/20210052021-08-25025 August 2021 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 1 and 2 (Report 05000424/2021005 and 05000425/2021005) ND-21-0603, Electrical Construction and Measuring & Test Equipment Control2021-06-25025 June 2021 Electrical Construction and Measuring & Test Equipment Control ML21179A0972021-06-15015 June 2021 to Tier 1 ML21132A0482021-05-12012 May 2021 Construction Reactor Oversight Process Resources Report May 2021 ML21118A1162021-04-28028 April 2021 Emergency Response Data System (ERDS) Data Point Library for Vogtle Unit 3 ND-21-0342, Emergency Response Data System (ERDS) Data Point Library for Vogtie Unit 42021-04-28028 April 2021 Emergency Response Data System (ERDS) Data Point Library for Vogtie Unit 4 ML21090A2092021-03-31031 March 2021 Construction Reactor Oversight Process Resources Report March 2021 ML21040A1672021-02-0909 February 2021 (Vegp), Units 3 and 4, Revision to Westinghouse Non-Proprietary Technical Description of the Flaw Tolerance Evaluation Conducted on the Subject Weldolet Branch Connections ML20358A1822020-12-31031 December 2020 LTR-SDA-20-096-NP, Revision 1, Flaw Tolerance Evaluation to Assess Lack of Inspection Coverage of AP1000 14 X 4 Stainless Steel Weldolets to Pipe Welds ML20343A0672020-12-0202 December 2020 Dashboard Report 12-2-2020 ML20314A0492020-11-0909 November 2020 Construction Reactor Oversight Process Resources November 2020 ND-20-1220, Report of Changes Incorporated Into Revision 6 to the Security Plan, Training and Qualification Plan, and Safeguards Contingencv Plan2020-10-21021 October 2020 Report of Changes Incorporated Into Revision 6 to the Security Plan, Training and Qualification Plan, and Safeguards Contingencv Plan ML20287A1862020-10-13013 October 2020 Construction Reactor Oversight Process Resources October 2020 ML20274A2582020-09-10010 September 2020 Wp on Uswc for AP1000_Revised, Reactor Oversight Process Whitepaper - Modification of the Description of Unplanned Scrams with Complications Performance Indicator to Reflect AP1000 Design ML20191A3832020-08-14014 August 2020 Transition to Reactor Oversight Process for Vogtle Electric Generating Plant, Units 3 and 4 ND-20-0907, Revision to Proposed Alternative Requirements for Preservice Inspection Acceptance of Volumetric Examinations, in Accordance with 10 CFR 50.551(z)(1),(VEGP 3&4-PSI/ISI-ALT-14R1)2020-07-28028 July 2020 Revision to Proposed Alternative Requirements for Preservice Inspection Acceptance of Volumetric Examinations, in Accordance with 10 CFR 50.551(z)(1),(VEGP 3&4-PSI/ISI-ALT-14R1) ND-20-0561, Submittal of Turbine Maintenance and Inspection Program in Accordance with Updated Final Safety Analysis Report2020-07-10010 July 2020 Submittal of Turbine Maintenance and Inspection Program in Accordance with Updated Final Safety Analysis Report ML20189A4292020-07-0707 July 2020 Construction Reactor Oversight Process Resources July 2020 ML20136A4562020-04-30030 April 2020 Updated Flex Plan Nuclear Regulatory Commission Order EA-12-049 Strategies for Beyond Design Basis External Events NL-19-0832, EPRI Technical Report 3002014590, Technical Bases for Inspection Requirements for PWR Steam Generator Feedwater and Main Steam Nozzle-to-Shell Welds and Nozzle Inside Radius Sections.2019-12-31031 December 2019 EPRI Technical Report 3002014590, Technical Bases for Inspection Requirements for PWR Steam Generator Feedwater and Main Steam Nozzle-to-Shell Welds and Nozzle Inside Radius Sections. ML19284B3722019-11-15015 November 2019 Attachment - VEGP U3 Amendment 166 (LAR-19-008) 2024-10-23
[Table view] Category:Technical
MONTHYEARML24297A6482024-10-23023 October 2024 5 to the Updated Final Safety Analysis Report, Technical Specification Bases Changes, Technical Requirements Manual Changes, Summary Report and Revised NRC Commitments Report ML23325A2022024-01-16016 January 2024 CFR Part 52 Construction Lessons-Learned Report ML24004A2192024-01-0808 January 2024 Construction Reactor Oversight Process Performance Metric Report for Calendar Year 2023 ND-23-0025, Compliance with Order EA-12-0492023-08-21021 August 2023 Compliance with Order EA-12-049 ML22348A0882023-07-25025 July 2023 VEGP Unit 4 - 103g - Basis Document ML23156A1882023-06-0505 June 2023 Construction Reactor Oversight Process Resources Report June 5, 2023 ML23121A0392023-05-0101 May 2023 Dashboard Report 5-1-2023 ML23003A0412023-01-0303 January 2023 Construction Reactor Oversight Process Resources Report January 3, 2023 ND-22-0817, Enclosures 1 and 2: Proposed Alternative Inspection Requirements for Steam Generator Nozzle to Reactor Coolant Pump Casing Welds and Alternative for Use of Code Case 648-2 for Inservice Inspection2022-11-0404 November 2022 Enclosures 1 and 2: Proposed Alternative Inspection Requirements for Steam Generator Nozzle to Reactor Coolant Pump Casing Welds and Alternative for Use of Code Case 648-2 for Inservice Inspection ML22278A0382022-10-0505 October 2022 Dashboard Report 10-5-2022 ML20290A2762022-08-0101 August 2022 10CFR52.103(g) Basis Document NL-22-0510, Plants Units 1 and 2, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20212022-07-14014 July 2022 Plants Units 1 and 2, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2021 ML22179A1462022-06-15015 June 2022 Tier 1, Revision 10, Updated Through 04/22/2022 ML22159A1712022-06-0808 June 2022 Construction Reactor Oversight Process Resources Report June 8, 2022 ML22089A0412022-03-30030 March 2022 Construction Reactor Oversight Process Resources Report March 30 2022 ND-22-0003, Report of 10 CFR 50.59 Changes, Tests, and Experiments and 10 CFR 52 Appendix D Departure Report2022-01-0606 January 2022 Report of 10 CFR 50.59 Changes, Tests, and Experiments and 10 CFR 52 Appendix D Departure Report ND-21-0848, Enclosure - Unit 4 Operator Candidates Requesting Credit for Unit 3 Written Examination and Operating Test (Revised)2021-10-0101 October 2021 Enclosure - Unit 4 Operator Candidates Requesting Credit for Unit 3 Written Examination and Operating Test (Revised) ML21179A0972021-06-15015 June 2021 to Tier 1 ML21132A0482021-05-12012 May 2021 Construction Reactor Oversight Process Resources Report May 2021 ND-21-0342, Emergency Response Data System (ERDS) Data Point Library for Vogtie Unit 42021-04-28028 April 2021 Emergency Response Data System (ERDS) Data Point Library for Vogtie Unit 4 ML21118A1162021-04-28028 April 2021 Emergency Response Data System (ERDS) Data Point Library for Vogtle Unit 3 ML21090A2092021-03-31031 March 2021 Construction Reactor Oversight Process Resources Report March 2021 ML21040A1672021-02-0909 February 2021 (Vegp), Units 3 and 4, Revision to Westinghouse Non-Proprietary Technical Description of the Flaw Tolerance Evaluation Conducted on the Subject Weldolet Branch Connections ML20358A1822020-12-31031 December 2020 LTR-SDA-20-096-NP, Revision 1, Flaw Tolerance Evaluation to Assess Lack of Inspection Coverage of AP1000 14 X 4 Stainless Steel Weldolets to Pipe Welds ND-20-1220, Report of Changes Incorporated Into Revision 6 to the Security Plan, Training and Qualification Plan, and Safeguards Contingencv Plan2020-10-21021 October 2020 Report of Changes Incorporated Into Revision 6 to the Security Plan, Training and Qualification Plan, and Safeguards Contingencv Plan ML20274A2582020-09-10010 September 2020 Wp on Uswc for AP1000_Revised, Reactor Oversight Process Whitepaper - Modification of the Description of Unplanned Scrams with Complications Performance Indicator to Reflect AP1000 Design ND-20-0561, Submittal of Turbine Maintenance and Inspection Program in Accordance with Updated Final Safety Analysis Report2020-07-10010 July 2020 Submittal of Turbine Maintenance and Inspection Program in Accordance with Updated Final Safety Analysis Report ML20189A4292020-07-0707 July 2020 Construction Reactor Oversight Process Resources July 2020 ML20136A4562020-04-30030 April 2020 Updated Flex Plan Nuclear Regulatory Commission Order EA-12-049 Strategies for Beyond Design Basis External Events NL-19-0832, EPRI Technical Report 3002014590, Technical Bases for Inspection Requirements for PWR Steam Generator Feedwater and Main Steam Nozzle-to-Shell Welds and Nozzle Inside Radius Sections.2019-12-31031 December 2019 EPRI Technical Report 3002014590, Technical Bases for Inspection Requirements for PWR Steam Generator Feedwater and Main Steam Nozzle-to-Shell Welds and Nozzle Inside Radius Sections. NL-19-0674, Proposed Alternative to Use ASME Code Case N-831-1, Ultrasonic Examination in Lieu of Radiography for Welds in Ferritic or Austenitic Pipe Section XI, Division 12019-09-30030 September 2019 Proposed Alternative to Use ASME Code Case N-831-1, Ultrasonic Examination in Lieu of Radiography for Welds in Ferritic or Austenitic Pipe Section XI, Division 1 ND-19-0356, Pressurized Thermal Shock (PTS) Evaluation2019-04-10010 April 2019 Pressurized Thermal Shock (PTS) Evaluation ND-19-0665, (VEGP) Units 3 and 4 - WCAP-15927-NP, Design Process for AP1000 Common Q Safety Systems, Revision 7 (Public Version)2019-03-21021 March 2019 (VEGP) Units 3 and 4 - WCAP-15927-NP, Design Process for AP1000 Common Q Safety Systems, Revision 7 (Public Version) ML19038A4632019-02-0707 February 2019 Construction Reactor Oversight Process Resources ML18275A0402018-10-31031 October 2018 Technical Evaluation Report: Use of BADGER and Narwhal to Compute Strainer Failure Probability - Vogtle Units 1 and 2 Nuclear Power Plant NL-18-0684, Fukushima Near-Term Task Force Recommendation 2.1: Seismic Supplemental Information Regarding NEI 12-06. Appendix H. Revision 4. H.4.5 Path 5 Mitigating Strategies Assessment (MSA) Report2018-06-25025 June 2018 Fukushima Near-Term Task Force Recommendation 2.1: Seismic Supplemental Information Regarding NEI 12-06. Appendix H. Revision 4. H.4.5 Path 5 Mitigating Strategies Assessment (MSA) Report NL-14-0639, Revision 5 Pressure and Temperature Limits Report and Unit 2 Revision 5 Pressure and Temperature Limits Report2014-04-22022 April 2014 Revision 5 Pressure and Temperature Limits Report and Unit 2 Revision 5 Pressure and Temperature Limits Report NL-14-0344, Seismic Hazard and Screening Report for CEUS Sites2014-03-31031 March 2014 Seismic Hazard and Screening Report for CEUS Sites ML14043A4762014-02-24024 February 2014 Staff Assessment of the Seismic Walkdown Report Supporting Implementation of Near- Term Task Force Recommendation 2.3 Related to the Fukushima DAI-ICHI Nuclear Power Plant Accident ML14006A2012014-01-0303 January 2014 Mega-Tech Services, LLC Technical Evaluation Report Regarding the Overall Integrated Plan for Vogtle Electric Generating Plant, Units 1 and 2, TAC Nos.: MF0714 and MF0715 ML13211A2622013-07-25025 July 2013 SNCV061-RPT-02, Ver. 2.0, Vogtle Unit 2 Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic. Part 7 of 14 NL-13-1236, SNCV061-RPT-02, Ver. 2.0, Vogtle Unit 2 Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic. Part 14 of 142013-07-25025 July 2013 SNCV061-RPT-02, Ver. 2.0, Vogtle Unit 2 Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic. Part 14 of 14 NL-13-1236, SNCV061-RPT-02, Ver. 2.0, Vogtle Unit 2 Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic. Part 13 of 142013-07-25025 July 2013 SNCV061-RPT-02, Ver. 2.0, Vogtle Unit 2 Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic. Part 13 of 14 NL-13-1236, SNCV061-RPT-02, Ver. 2.0, Vogtle Unit 2 Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic. Part 11 of 142013-07-25025 July 2013 SNCV061-RPT-02, Ver. 2.0, Vogtle Unit 2 Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic. Part 11 of 14 NL-13-1236, SNCV061-RPT-02, Ver. 2.0, Vogtle Unit 2 Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic. Part 12 of 142013-07-25025 July 2013 SNCV061-RPT-02, Ver. 2.0, Vogtle Unit 2 Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic. Part 12 of 14 NL-13-1236, SNCV061-RPT-02, Ver. 2.0, Vogtle Unit 2 Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic. Part 10 of 142013-07-25025 July 2013 SNCV061-RPT-02, Ver. 2.0, Vogtle Unit 2 Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic. Part 10 of 14 NL-13-1236, SNCV061-RPT-02, Ver. 2.0, Vogtle Unit 2 Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic. Part 9 of 142013-07-25025 July 2013 SNCV061-RPT-02, Ver. 2.0, Vogtle Unit 2 Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic. Part 9 of 14 ML13211A2432013-07-25025 July 2013 SNCV061-RPT-02, Ver. 2.0, Vogtle Unit 2 Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic. Part 9 of 14 NL-13-1236, SNCV061-RPT-02, Ver. 2.0, Vogtle Unit 2 Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic. Part 6 of 142013-07-25025 July 2013 SNCV061-RPT-02, Ver. 2.0, Vogtle Unit 2 Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic. Part 6 of 14 ML13211A2592013-07-25025 July 2013 SNCV061-RPT-02, Ver. 2.0, Vogtle Unit 2 Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic. Part 4 of 14 2024-10-23
[Table view] |
Text
B. H. Whitley Southern Nuclear
.A Southern Nuclear Director Regulatory Affairs Operating Company, Inc.
3535 Colonnade Parkway Birmingham. AL 35243 Tel 205.992.7079 April10, 2019 Docket Nos.: 52-025 ND-19-0356 52-026 10 CFR 52.97(c)
U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Mr. Frederick D. Brown Director, Office of New Reactors Document Control Desk Washington, DC 20555-001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Units 3 and 4 Pressurized Thermal Shock (PTS) Evaluation Ladies and Gentlemen:
In accordance with combined operating license (COL) condition 2.D(12)(g)5 of the Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Combined Licenses, Numbers NPF-91 and NPF-92, respectively, Southern Nuclear Operating Company (SNC) is submitting a copy of the VEGP Units 3 and 4 Pressurized Thermal Shock (PTS) Evaluation.
This letter contains no regulatory commitments. This letter has been reviewed and confirmed to contain no security-related information. Should you have any questions, please contact Mr. Corey Thomas at (205) 992-5221.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 1Oth day of April 2019.
Respectfully submitted, SOUTHERN NUCLEAR OPERATING COMPANY Brian H. Whitley Director, Regulatory Affairs Southern Nuclear Operating Company : Vogtle Electric Generating Pfant Units 3 and 4 Pressurized Thermal Shock (PTS)
Evaluation
U.S. Nuclear Regulatory Commission ND-19-0356 Page 2 of 3 cc:
Southern Nuclear Operating Company / Georgia Power Company Mr. S. E. Kuczynski (w/o enclosure)
Mr. D. G. Bost (w/o enclosure)
Mr. M. D. Meier (w/o enclosure)
Mr. D. H. Jones (w/o enclosure)
Mr. J. B. Klecha Mr. G. Chick Mr. D. L. McKinney (w/o enclosure)
Mr. T. W. Yelverton (w/o enclosure)
Mr. B. H. Whitley Ms. C. A. Gayheart Mr. C. R. Pierce Ms. A. G. Aughtman Mr. D. L. Fulton Mr. M. J. Yox Mr. C. T. Defnall Mr. J. Tupik Mr. W. A. Sparkman Ms. A. C. Chamberlain Mr. S. Leighty Mr. E. Riffle Ms. K. Roberts Mr. J. Haswell Mr. J. Andrews Document Services RTYPE: VND.LI.L00 File AR.01.02.06 Nuclear Regulatory Commission Mr. W. Jones (w/o enclosure)
Ms. J. Dixon-Herrity Mr. C. Patel Ms. J. M. Heisserer Mr. B. Kemker Mr. G. Khouri Ms. S. Temple Mr. F. Brown Mr. C. J. Even Mr. A. Lerch Mr. S. Walker State of Georgia Mr. R. Dunn Oglethorpe Power Corporation Mr. M. W. Price Ms. A. Whaley
U.S. Nuclear Regulatory Commission ND-19-0356 Page 3 of 3 Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Dalton Utilities Mr. T. Bundros Westinghouse Electric Company, LLC Mr. L. Oriani (w/o enclosure)
Mr. T. Rubenstein (w/o enclosure)
Mr. M. Corletti Mr. M. L. Clyde Mr. D. Hawkins Mr. J. Coward Other Mr. S. W. Kline, Bechtel Power Corporation Ms. L. A. Matis, Tetra Tech NUS, Inc.
Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, Inc.
Mr. S. Roetger, Georgia Public Service Commission Ms. S. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. S. Blanton, Balch Bingham NDDocumentinBox@duke-energy.com, Duke Energy Mr. S. Franzone, Florida Power & Light
Southern Nuclear Operating Company ND-19-0356 Enclosure 1 Vogtle Electric Generating Plant Units 3 and 4 Pressurized Thermal Shock (PTS) Evaluation (This enclosure consists of 7 pages, including this cover page.)
ND-19-0356 Pressurized Thermal Shock (PTS) Evaluation The purpose of this enclosure is to document the required Vogtle Units 3 and 4 reactor vessel (RV) integrity pressurized thermal shock (PTS) compliance with 10 CFR 50.61 [1] and the Vogtle Units 3 and 4 UFSAR (plant-specific DCD) [2] using the measured as-built material properties from the Certified Material Test Reports (CMTRs). This evaluation fulfills Southern Nuclear Operating Company (SNC) combined operating license (COL) Commitment 2.D(12)(g)5. There have been no changes between the approved DCD Rev. 19 document and the current UFSAR Subsections 5.3.3.1 and Tables 5.3-1 and 5.3-3 that would impact the original COL commitment.
The PTS reference temperatures (RTPTS) calculated with the Vogtle Units 3 and 4 actual RV chemical and mechanical properties from the CMTRs are below the RTPTS screening criteria values of 270F for plates, forgings, and longitudinal welds, and 300F for circumferential welds at 56 EFPY. This satisfies 10 CFR 50.61 [1] and the UFSAR [2]. A comparison of the plant specific RTPTS values to the screening limits is provided in Table 1. Tables 5 and 6 contain the RTPTS calculations for each of the beltline materials for the Vogtle Units 3 and 4 at 56 effective full power years (EFPY).
The scope of this assessment includes the beltline material for Vogtle Units 3 and 4. The beltline materials are those that will receive a fluence greater than 1017 n/cm2 (E > 1.0 MeV) during the 40-year licensed operating period. For the AP1000 units, the beltline materials include:
Upper Shell (US) Forging, Lower Shell (LS) Forging, Transition Ring (TR), and the welds connecting these components The initial RTNDT values and best-estimate Cu and Ni weight % values for the RV beltline materials are provided in Table 2 for Vogtle Unit 3 and in Table 3 for Vogtle Unit 4.
The neutron fluence values used to calculate the RTPTS are provided in Table 4. These fluence values represent the projected fluence at 56 EFPY for Vogtle Units 3 and 4 at clad/base metal interface for RV beltline materials, and are taken from APP-RXS-M3C-026 [3]. The use of 56 EFPY fluence values is conservative compared to a 40-year life, and the 54 EFPY term defined in Table 5.3-3 of the UFSAR [2] for the 60-year design life.
Table 1 Comparison of Plant Specific RTPTS with the Bounding RTPTS Values RTPTS
(°F)
Material 10 CFR 50.61 [1]
Vogtle Unit 3 Vogtle Unit 4
[Table 5] [Table 6]
UFSAR [2]
Upper Shell (US) 29 23 < 270 Lower Shell (LS) 39 19 < 270 Transition Ring (TR) 13 23 < 270 US-to LS-Circumferential
-18 -18 < 300 (Circ.) Weld LS-to-TR Circ. Weld -13 -13 < 300 2 of 7
ND-19-0356 Pressurized Thermal Shock (PTS) Evaluation Table 2 Material Properties for the Vogtle Unit 3 Reactor Vessel Beltline Materials(a)
Fracture Chemical Composition(b) Toughness Properties Material Description Initial Cu Ni RTNDT(c)
Wt. % Wt. %
(°F)
US Forging 08W172-1-1 0.03 0.76 -20 LS Forging 09W4-1-1 0.03 0.76 -20 Transition Ring 08D1090-1-1 0.03 0.75 -40 US-to-LS Circumferential Weld US-40N (Heat # GZ005499727) with PF-H55SN Flux 0.02 0.02 -70 (Lot # 0KGY610)
LS-to-TR Circ. Weld US-40N (Heat #
GZ005499727) with PF-H55SN Flux 0.02 0.02 -70 (Lot # 0KGY610)
Notes for Table 2:
(a) All values were obtained from CMTRs.
(b) The best-estimate chemical composition values listed here are the maximum of the materials product analyses as documented in the CMTRs.
(c) All initial RTNDT values are based on measured data.
Table 3 Material Properties for the Vogtle Unit 4 Reactor Vessel Beltline Materials(a)
Fracture Chemical Composition(b) Toughness Properties Material Description Initial Cu Ni RTNDT(c)
Wt. % Wt. %
(°F)
US Forging F09173 010 0.04 0.83 -40 LS Forging F09174 010 0.03 0.84 -40 Transition Ring F09175 010 0.03 0.78 -30 US-to-LS Circumferential Weld US-40N (Heat # GZ005499727) with PF-H55SN Flux 0.02 0.02 -70 (Lot # 0KGY610)
LS-to-TR Circ. Weld US-40N (Heat #
GZ005499727) with PF-H55SN Flux 0.02 0.02 -70 (Lot # 0KGY610)
Notes for Table 3:
(a) All values were obtained from CMTRs.
(b) The best-estimate chemical composition values listed here are the maximum of the materials product analyses as documented in the CMTRs.
(c) All initial RTNDT values are based on measured data.
3 of 7
ND-19-0356 Pressurized Thermal Shock (PTS) Evaluation Table 4 Vogtle Units 3 and 4 Calculated Pressure Vessel Clad/Base Metal Interface Fast Neutron Fluence Fluence, n/cm2 (E > 1.0 MeV)
Reactor Vessel Material 56 EFPY(a)
US Forging(b) 2.24 x 1019 LS Forging 7.32 x 1019 Transition Ring(c) 3.54 x 1019 US-to-LS Circ. Weld 2.24 x 1019 LS-to-TR Circ. Weld 3.54 x 1019 Notes for Table 4:
(a) All fluence values are taken from APP-RXS-M3C-026, Revision 1 [3].
(b) US Forging fluence value is conservatively deemed equivalent to the US-to LS-Circ. Weld fluence value.
(c) Transition Ring fluence value is conservatively deemed equivalent to the LS-to-TR Circ. Weld fluence value.
4 of 7
ND-19-0356 Pressurized Thermal Shock (PTS) Evaluation Table 5 Calculation of the Vogtle Unit 3 RTPTS Values for 56 EFPY Fluence(b)
CF(a) RTNDT(U)(d) RTNDT(e) U(d) (f) Margin(g) RTPTS(h)
Reactor Vessel Material (x1019 n/cm2, FF(c)
(F) (F) (F) (°F) (°F) (F) (F)
E > 1.0 MeV)
US Forging 08W172-1-1 20 2.24 1.2184 -20 24.4 0 12.2 24.4 29 LS Forging 09W4-1-1 20 7.32 1.4700 -20 29.4 0 14.7 29.4 39 Transition Ring 08D1090-1-1 20 3.54 1.3292 -40 26.6 0 13.3 26.6 13 US-to-LS Circ. Weld US-40N (Heat # GZ005499727) with 21.5 2.24 1.2184 -70 26.2 0 13.1 26.2 -18 PF-H55SN Flux (Lot # 0KGY610)
LS-to-TR Circ. Weld US-40N (Heat # GZ005499727) with 21.5 3.54 1.3292 -70 28.6 0 14.3 28.6 -13 PF-H55SN Flux (Lot # 0KGY610)
Notes for Table 5:
(a) Values determined using the chemical compositions from Table 2 of this letter in conjunction with Tables 1 and 2 of 10 CFR 50.61 [1].
(b) Taken from Table 4 of this letter.
(c) FF = fluence factor = f(0.28 - 0.1 log (f)); per 10 CFR 50.61 [1].
(d) Initial RTNDT values are taken from Table 2 of this letter. All initial RTNDT values are based on material-specific measured data; therefore, U = 0°F consistent with WCAP-14040-A [4].
(e) RTNDT = CF
(f) Per 10 CFR 50.61 [1], = 17°F for the base metal and = 28°F for the weld metal; however, need not exceed 0.5*RTNDT.
(g) Margin 2 ; per 10 CFR 50.61 [1].
(h) RTPTS values calculated in accordance with 10 CFR 50.61 [1].
5 of 7
ND-19-0356 Pressurized Thermal Shock (PTS) Evaluation Table 6 Calculation of the Vogtle Unit 4 RTPTS Values for 56 EFPY Fluence(b)
CF(a) RTNDT(U)(d) RTNDT(e) U(d) (f) Margin(g) RTPTS(h)
Reactor Vessel Material (x1019 n/cm2, FF(c)
(F) (F) (F) (°F) (°F) (F) (F)
E > 1.0 MeV)
US Forging F09173 010 26 2.24 1.2184 -40 31.7 0 15.8 31.7 23 LS Forging F09174 010 20 7.32 1.4700 -40 29.4 0 14.7 29.4 19 Transition Ring F09175 010 20 3.54 1.3292 -30 26.6 0 13.3 26.6 23 US-to-LS Circ. Weld US-40N (Heat # GZ005499727) with 21.5 2.24 1.2184 -70 26.2 0 13.1 26.2 -18 PF-H55SN Flux (Lot # 0KGY610)
LS-to-TR Circ. Weld US-40N (Heat # GZ005499727) with 21.5 3.54 1.3292 -70 28.6 0 14.3 28.6 -13 PF-H55SN Flux (Lot # 0KGY610)
Notes for Table 6:
(a) Values determined using the chemical compositions from Table 3 of this letter in conjunction with Tables 1 and 2 of 10 CFR 50.61 [1].
(b) Taken from Table 4 of this letter.
(c) FF = fluence factor = f(0.28 - 0.1 log (f)); per 10 CFR 50.61 [1].
(d) Initial RTNDT values are taken from Table 3 of this letter. All. Initial RTNDT values are based on material-specific measured data; therefore U = 0°F consistent with WCAP-14040-A [4].
(e) RTNDT = CF
(f) Per 10 CFR 50.61 [1], = 17°F for the base metal and =28°F for the weld metal; however, need not exceed 0.5*RTNDT.
(g) Margin 2 ; per 10 CFR 50.61 [1].
(h) RTPTS values calculated in accordance with 10 CFR 50.61 [1].
6 of 7
ND-19-0356 Pressurized Thermal Shock (PTS) Evaluation References
- 1. 10 CFR 50.61, Fracture Toughness Requirements for Protection Against Pressurized Thermal Shock Events, Federal Register, Volume 60, No. 243, dated December 19, 1995, effective January 18, 1996.
- 2. Vogtle Units 3 and 4 Updated Final Safety Analysis Report.
- 3. APP-RXS-M3C-026, AP1000 Neutron Fast Fluence, DPA, and Heating Rate Evaluation -
Long-Term Power Distribution, Revision 1, April 2012.
- 4. WCAP-14040-A, Methodology Used to Develop Cold Overpressure Mitigating System Setpoints and RCS Heatup and Cooldown Limit Curves, Revision 4, May 2004.
7 of 7