ML23325A202 | 16 January 2024 | CFR Part 52 Construction Lessons-Learned Report | |
NL-23-0926, Correction of Technical Specification Typographical Error | 12 January 2024 | Correction of Technical Specification Typographical Error | |
ML24004A219 | 8 January 2024 | Construction Reactor Oversight Process Performance Metric Report for Calendar Year 2023 | |
ND-23-0025, Compliance with Order EA-12-049 | 21 August 2023 | Compliance with Order EA-12-049 | Safe Shutdown High winds Ultimate heat sink Tornado Missile Safe Shutdown Earthquake Post Accident Monitoring Emergency Lighting FLEX Fukushima Dai-Ichi Spent Fuel Pool Instrumentation Severe Accident Management Guideline Frazil ice Earthquake GOTHIC |
ML22348A093 | 28 July 2023 | Finding That the Acceptance Criteria in the Combined License Are Met | |
ML22348A088 | 25 July 2023 | VEGP Unit 4 - 103g - Basis Document | Fitness for Duty Fire Barrier Significance Determination Process Exemption Request Flow Induced Vibration |
ML23184A047 | 3 July 2023 | Dashboard Report 7-3-2023 | |
ML23156A188 | 5 June 2023 | Construction Reactor Oversight Process Resources Report June 5, 2023 | |
ML23121A039 | 1 May 2023 | Dashboard Report 5-1-2023 | |
ML23003A041 | 3 January 2023 | Construction Reactor Oversight Process Resources Report January 3, 2023 | |
ND-22-0817, Enclosures 1 and 2: Proposed Alternative Inspection Requirements for Steam Generator Nozzle to Reactor Coolant Pump Casing Welds and Alternative for Use of Code Case 648-2 for Inservice Inspection | 4 November 2022 | Enclosures 1 and 2: Proposed Alternative Inspection Requirements for Steam Generator Nozzle to Reactor Coolant Pump Casing Welds and Alternative for Use of Code Case 648-2 for Inservice Inspection | Hydrostatic Nondestructive Examination Incorporated by reference Finite Element Analysis EVT-1 Liquid penetrant Dissimilar Metal Weld DM weld |
ND-22-0831, (Vegp), Units 3 and 4, Comments on AP1000 Standard Technical Specifications (STS) Draft NUREG-2194, Revision 1 | 31 October 2022 | (Vegp), Units 3 and 4, Comments on AP1000 Standard Technical Specifications (STS) Draft NUREG-2194, Revision 1 | Shutdown Margin Probabilistic Risk Assessment Squib |
ML22278A038 | 5 October 2022 | Dashboard Report 10-5-2022 | |
ML22215A096 | 3 August 2022 | Construction Reactor Oversight Process Resources Report August 3, 2022 | |
ML22214A007 | 1 August 2022 | Archives | Fitness for Duty Coatings Nondestructive Examination Squib Condition Adverse to Quality Significance Determination Process Liquid penetrant |
ML20290A276 | 1 August 2022 | 10CFR52.103(g) Basis Document | Fitness for Duty Significance Determination Process Exemption Request Preliminary White Finding |
NL-22-0510, Plants Units 1 and 2, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2021 | 14 July 2022 | Plants Units 1 and 2, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2021 | |
ML22179A146 | 15 June 2022 | Tier 1, Revision 10, Updated Through 04/22/2022 | Safe Shutdown Boric Acid Loop seal Non-Destructive Examination Fire Barrier Anticipated operational occurrence Tornado Missile Safe Shutdown Earthquake Hydrostatic Probabilistic Risk Assessment Coatings Nondestructive Examination Squib Emergency Lighting Incorporated by reference Tornado Generated Missile Earthquake Pressure Boundary Leakage Pressure boundary leak Flow Induced Vibration |
ML22159A171 | 8 June 2022 | Construction Reactor Oversight Process Resources Report June 8, 2022 | |
ML22131A050 | 11 May 2022 | Construction Reactor Oversight Process Resources Report May 11, 2022 | |
ML22089A041 | 30 March 2022 | Construction Reactor Oversight Process Resources Report March 30 2022 | |
ND-22-0003, Report of 10 CFR 50.59 Changes, Tests, and Experiments and 10 CFR 52 Appendix D Departure Report | 6 January 2022 | Report of 10 CFR 50.59 Changes, Tests, and Experiments and 10 CFR 52 Appendix D Departure Report | Temporary Modification Exemption Request |
ND-21-1003, Request for Exemption: Applicability of 10 CFR 26.3. Scope, Until Initial Fuel Load - Supplement | 12 November 2021 | Request for Exemption: Applicability of 10 CFR 26.3. Scope, Until Initial Fuel Load - Supplement | Condition Adverse to Quality Exemption Request Fuel cladding |
ND-21-0991, Exemption Request: Applicability of 10 CFR 26.3, Scope, Until Initial Fuel Load | 5 November 2021 | Exemption Request: Applicability of 10 CFR 26.3, Scope, Until Initial Fuel Load | Condition Adverse to Quality Exemption Request Fuel cladding |
ML21280A304 | 7 October 2021 | Q 2020 Performance Summary | Condition Adverse to Quality Significance Determination Process |
ML21280A305 | 7 October 2021 | Q/2020 Performance Summary | |
ML21277A076 | 4 October 2021 | Vog 4 Dashboard 10-4-2021 | |
ND-21-0848, Enclosure - Unit 4 Operator Candidates Requesting Credit for Unit 3 Written Examination and Operating Test (Revised) | 1 October 2021 | Enclosure - Unit 4 Operator Candidates Requesting Credit for Unit 3 Written Examination and Operating Test (Revised) | |
IR 05000424/2021005 | 25 August 2021 | Updated Inspection Plan for Vogtle Electric Generating Plant, Units 1 and 2 (Report 05000424/2021005 and 05000425/2021005) | Fitness for Duty Cyber Security Exemption Request COVID-19 |
ND-21-0603, Electrical Construction and Measuring & Test Equipment Control | 25 June 2021 | Electrical Construction and Measuring & Test Equipment Control | |
ML21179A097 | 15 June 2021 | to Tier 1 | Safe Shutdown Boric Acid Loop seal Non-Destructive Examination Fire Barrier Anticipated operational occurrence Tornado Missile Safe Shutdown Earthquake Hydrostatic Probabilistic Risk Assessment Coatings Nondestructive Examination Squib Emergency Lighting Incorporated by reference Tornado Generated Missile Earthquake Pressure Boundary Leakage Pressure boundary leak Flow Induced Vibration |
ML21132A048 | 12 May 2021 | Construction Reactor Oversight Process Resources Report May 2021 | |
ML21118A116 | 28 April 2021 | Emergency Response Data System (ERDS) Data Point Library for Vogtle Unit 3 | Boric Acid |
ND-21-0342, Emergency Response Data System (ERDS) Data Point Library for Vogtie Unit 4 | 28 April 2021 | Emergency Response Data System (ERDS) Data Point Library for Vogtie Unit 4 | Boric Acid |
ML21090A209 | 31 March 2021 | Construction Reactor Oversight Process Resources Report March 2021 | |
ML21040A167 | 9 February 2021 | (Vegp), Units 3 and 4, Revision to Westinghouse Non-Proprietary Technical Description of the Flaw Tolerance Evaluation Conducted on the Subject Weldolet Branch Connections | Nondestructive Examination |
ML20358A182 | 31 December 2020 | LTR-SDA-20-096-NP, Revision 1, Flaw Tolerance Evaluation to Assess Lack of Inspection Coverage of AP1000 14 X 4 Stainless Steel Weldolets to Pipe Welds | Nondestructive Examination |
ML20343A067 | 2 December 2020 | Dashboard Report 12-2-2020 | |
ML20314A049 | 9 November 2020 | Construction Reactor Oversight Process Resources November 2020 | |
ND-20-1220, Report of Changes Incorporated Into Revision 6 to the Security Plan, Training and Qualification Plan, and Safeguards Contingencv Plan | 21 October 2020 | Report of Changes Incorporated Into Revision 6 to the Security Plan, Training and Qualification Plan, and Safeguards Contingencv Plan | Incorporated by reference |
ML20287A186 | 13 October 2020 | Construction Reactor Oversight Process Resources October 2020 | |
ML20274A258 | 10 September 2020 | Wp on Uswc for AP1000_Revised, Reactor Oversight Process Whitepaper - Modification of the Description of Unplanned Scrams with Complications Performance Indicator to Reflect AP1000 Design | Fuel cladding |
ML20191A383 | 14 August 2020 | Transition to Reactor Oversight Process for Vogtle Electric Generating Plant, Units 3 and 4 | Enforcement Discretion Probabilistic Risk Assessment Incorporated by reference Significance Determination Process Grace period Power change |
ND-20-0907, Revision to Proposed Alternative Requirements for Preservice Inspection Acceptance of Volumetric Examinations, in Accordance with 10 CFR 50.551(z)(1),(VEGP 3&4-PSI/ISI-ALT-14R1) | 28 July 2020 | Revision to Proposed Alternative Requirements for Preservice Inspection Acceptance of Volumetric Examinations, in Accordance with 10 CFR 50.551(z)(1),(VEGP 3&4-PSI/ISI-ALT-14R1) | Non-Destructive Examination Hydrostatic Nondestructive Examination |
ND-20-0561, Submittal of Turbine Maintenance and Inspection Program in Accordance with Updated Final Safety Analysis Report | 10 July 2020 | Submittal of Turbine Maintenance and Inspection Program in Accordance with Updated Final Safety Analysis Report | Nondestructive Examination |
ML20189A429 | 7 July 2020 | Construction Reactor Oversight Process Resources July 2020 | |
ML20136A456 | 30 April 2020 | Updated Flex Plan Nuclear Regulatory Commission Order EA-12-049 Strategies for Beyond Design Basis External Events | Safe Shutdown High winds Ultimate heat sink Tornado Missile Safe Shutdown Earthquake Post Accident Monitoring Emergency Lighting FLEX Fukushima Dai-Ichi Spent Fuel Pool Instrumentation Severe Accident Management Guideline Frazil ice Earthquake GOTHIC |
NL-19-0832, EPRI Technical Report 3002014590, Technical Bases for Inspection Requirements for PWR Steam Generator Feedwater and Main Steam Nozzle-to-Shell Welds and Nozzle Inside Radius Sections. | 31 December 2019 | EPRI Technical Report 3002014590, Technical Bases for Inspection Requirements for PWR Steam Generator Feedwater and Main Steam Nozzle-to-Shell Welds and Nozzle Inside Radius Sections. | Hydrostatic Nondestructive Examination VT-2 Finite Element Analysis Exemption Request Through-Wall Leak Scaffolding |
ML19284B372 | 15 November 2019 | Attachment - VEGP U3 Amendment 166 (LAR-19-008) | Fire Protection Program |
NL-19-0674, Proposed Alternative to Use ASME Code Case N-831-1, Ultrasonic Examination in Lieu of Radiography for Welds in Ferritic or Austenitic Pipe Section XI, Division 1 | 30 September 2019 | Proposed Alternative to Use ASME Code Case N-831-1, Ultrasonic Examination in Lieu of Radiography for Welds in Ferritic or Austenitic Pipe Section XI, Division 1 | Nondestructive Examination Dissimilar Metal Weld |