ND-23-0609, Notification of Completion of All ITAAC
Letter Sequence Request | |
---|---|
EPID:L-2023-LLA-0123, ITAAC Closure Verification Evaluation Form (Vef) for ITAAC Number 2.1.02.08e (Index No. 40) for Vogtle Unit 4 Combined License (VOG4) (Open) | |
Initiation
Administration Questions
| |
MONTHYEARND-22-0830, ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.1 0.ii (Index Number 816)2022-10-26026 October 2022
[Table View]ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.1 0.ii (Index Number 816) Project stage: Request ND-22-0689, ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.i (Index Number 53)2022-11-0303 November 2022 ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.i (Index Number 53) Project stage: Request ND-22-0862, ITAAC Closure Notification on Completion of ITAAC Item C.2.5.04.04a (Index Number 561)2022-11-0808 November 2022 ITAAC Closure Notification on Completion of ITAAC Item C.2.5.04.04a (Index Number 561) Project stage: Request ND-22-0730, ITAAC Closure Notification on Completion of ITAAC 2.3.03.02 (Index Number 319)2022-11-10010 November 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.03.02 (Index Number 319) Project stage: Request ND-22-0657, ITAAC Closure Notification on Completion of ITAAC 2.3.14.04 (Index Number 480)2022-11-17017 November 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.14.04 (Index Number 480) Project stage: Request ND-22-0898, ITAAC Closure Notification on Completion of 3.2.00.04 (Index Number 751)2022-11-18018 November 2022 ITAAC Closure Notification on Completion of 3.2.00.04 (Index Number 751) Project stage: Request ND-22-0714, ITAAC Closure Notification on Completion of ITAAC 2.3.08.02.iii (Index Number 4171)2022-11-22022 November 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.08.02.iii (Index Number 4171) Project stage: Request ND-22-0711, ITAAC Closure Notification on Completion of ITAAC 3.3.00.01 (Index Number 759)2022-11-23023 November 2022 ITAAC Closure Notification on Completion of ITAAC 3.3.00.01 (Index Number 759) Project stage: Request ML22332A5372022-11-28028 November 2022 Draft LAR 23-001 for 12-8-22 Public Meeting ND-22-0821, ITAAC Closure Notification on Completion of ITAAC 3.3.00.13 (Index Number 819)2022-11-29029 November 2022 ITAAC Closure Notification on Completion of ITAAC 3.3.00.13 (Index Number 819) Project stage: Request ML22334A0752022-12-0101 December 2022 Update to Targeted Inspections, Tests, Analysis, and Acceptance Criteria for Vogtle Electric Generating Plant Unit 4 Project stage: Request ND-22-0920, ITAAC Closure Notification on Completion of ITAAC 2.7.01 .02a (Index Number 678)2022-12-0707 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.7.01 .02a (Index Number 678) Project stage: Request ND-22-0899, ITAAC Closure Notification on Completion of ITAAC 2.2.03.12a.i (Index Number 214)2022-12-15015 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.2.03.12a.i (Index Number 214) Project stage: Request ND-22-0656, ITAAC Closure Notification on Completion of ITAAC 2.3.05.03b.iii (Index Number 348)2022-12-15015 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.05.03b.iii (Index Number 348) Project stage: Request ND-22-0600, ITAAC Closure Notification on Completion of ITAAC 2.3.02.05.i (Index Number 291)2022-12-16016 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.02.05.i (Index Number 291) Project stage: Request ND-22-0747, ITAAC Closure Notification on Completion of ITAAC 2.1 .02.08d.ii (Index Number 33)2022-12-21021 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.1 .02.08d.ii (Index Number 33) Project stage: Request ND-22-0967, Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.c (Index Number 802)2022-12-22022 December 2022 Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.c (Index Number 802) Project stage: Request ND-22-0964, Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.a (Index Number 800)2022-12-22022 December 2022 Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.a (Index Number 800) Project stage: Request ND-22-0965, Resubmittal of Notice of Uncompleted IT Aac 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.b (Index Number 801)2022-12-22022 December 2022 Resubmittal of Notice of Uncompleted IT Aac 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.b (Index Number 801) Project stage: Request ND-22-0895, ITAAC Closure Notification on Completion of ITAAC 2.2.01.01 (Index Number 90)2022-12-28028 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.2.01.01 (Index Number 90) Project stage: Request ML22349A2142023-01-0303 January 2023 Summary of December 8, 2022, Public Meeting with Southern Nuclear Operating Company Project stage: Request ND-23-1001, ITAAC Closure Notification on Completion of ITAAC 2.7.01.05.i (Index Number 684)2023-01-0505 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.7.01.05.i (Index Number 684) Project stage: Request ND-22-0848, ITAAC Closure Notification on Completion of ITAAC 2.3.02.14 (Index Number 317)2023-01-10010 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.02.14 (Index Number 317) Project stage: Request ND-22-0869, ITAAC Closure Notification on Completion of Item 2.3.13.05.i (Index Number 462)2023-01-12012 January 2023 ITAAC Closure Notification on Completion of Item 2.3.13.05.i (Index Number 462) Project stage: Request ND-23-0030, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.d (Index Number 763)2023-01-13013 January 2023 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.d (Index Number 763) Project stage: Request ND-23-0026, ITAAC Closure Notification on Completion of ITAAC 2.2.03.12a.iv (Index Number 216)2023-01-13013 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.12a.iv (Index Number 216) Project stage: Request ND-23-0029, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.c (Index Number 762)2023-01-13013 January 2023 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.c (Index Number 762) Project stage: Request ND-22-0649, ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.iv (Index Number 56)2023-01-13013 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.iv (Index Number 56) Project stage: Request ND-22-0893, ITAAC Closure Notification on Completion of ITAAC 2.1.02.01 (Index Number 12)2023-01-16016 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.01 (Index Number 12) Project stage: Request ND-22-0700, ITAAC Closure Notification on Completion of Item 2.2.04.12a.i (Index Number 248)2023-01-20020 January 2023 ITAAC Closure Notification on Completion of Item 2.2.04.12a.i (Index Number 248) Project stage: Request ND-22-0521, ITAAC Closure Notification on Completion of ITAAC 2.2.03.08c.i.03 (Index Number 179)2023-01-20020 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.08c.i.03 (Index Number 179) Project stage: Request ND-22-0585, ITAAC Closure Notification on Completion of 2.2.02.11a.i (Index Number 154)2023-01-23023 January 2023 ITAAC Closure Notification on Completion of 2.2.02.11a.i (Index Number 154) Project stage: Request ND-23-0041, ITAAC Closure Notification on Completion of ITAAC 2.2.04.01 (Index Number 219)2023-01-26026 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.04.01 (Index Number 219) Project stage: Request ND-23-0078, ITAAC Closure Notification on Completion of ITAAC 2.2.02.06b (Index Number 133)2023-01-27027 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.02.06b (Index Number 133) Project stage: Request ND-22-0739, ITAAC Closure Notification on Completion of ITAAC 2.3.08.02.i (Index Number 415)2023-01-31031 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.08.02.i (Index Number 415) Project stage: Request ND-22-0876, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02h 9Index Number 776)2023-01-31031 January 2023 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02h 9Index Number 776) Project stage: Request ND-23-0079, ITAAC Closure Notification on Completion of ITAAC 2.3.02.02a (Index Number 285)2023-02-0202 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.02.02a (Index Number 285) Project stage: Request ND-23-0039, ITAAC Closure Notification on Completion of ITAAC 2.2.03.08c.ii (Index Number 181)2023-02-0303 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.08c.ii (Index Number 181) Project stage: Request ND-23-0043, ITAAC Closure Notification on Completion of ITAAC 2.1.02.08d.i (Index Number 32)2023-02-0303 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.08d.i (Index Number 32) Project stage: Request ND-22-0670, ITAAC Closure Notification on Completion of 2.4.06.02 (Index Number 504)2023-02-0707 February 2023 ITAAC Closure Notification on Completion of 2.4.06.02 (Index Number 504) Project stage: Request ND-22-0733, ITAAC Closure Notification on Completion of ITAAC 2.3.05.03c.ii (Index Number 350)2023-02-10010 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.05.03c.ii (Index Number 350) Project stage: Request ND-23-0130, ITAAC Closure Notification on Completion of ITAAC 2.3.07.07c (Index Number 408)2023-02-10010 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.07.07c (Index Number 408) Project stage: Request ND-22-0737, ITAAC Closure Notification on Completion of ITAAC 2.3.05.03d.ii (Index Number 352)2023-02-10010 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.05.03d.ii (Index Number 352) Project stage: Request ND-23-0124, ITAAC Closure Notification on Completion of ITAAC Item 2.3.10.12 (Index Number 879)2023-02-13013 February 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.3.10.12 (Index Number 879) Project stage: Request ND-23-0153, ITAAC Closure Notification on Completion of ITAAC 2.3.09.02a (Index Number 421)2023-02-16016 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.09.02a (Index Number 421) Project stage: Request ND-23-0141, ITAAC Closure Notification on Completion of ITAAC 2.3.04.05 (Index Number 332)2023-02-16016 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.04.05 (Index Number 332) Project stage: Request ND-23-0071, ITAAC Closure Notification on Completion of Item 2.2.05.05a.i (Index Number 259)2023-02-17017 February 2023 ITAAC Closure Notification on Completion of Item 2.2.05.05a.i (Index Number 259) Project stage: Request ND-23-0118, ITAAC Closure Notification on Completion of ITAAC 2.3.07.05.i (Index Number 396)2023-02-17017 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.07.05.i (Index Number 396) Project stage: Request ND-22-0919, ITAAC Closure Notification on Completion of ITAAC 3.3.00.07d.i (Index Number 799)2023-02-24024 February 2023 ITAAC Closure Notification on Completion of ITAAC 3.3.00.07d.i (Index Number 799) Project stage: Request ND-23-0159, ITAAC Closure Notification on Completion of ITAAC 2.6.03.05d.i (Index Number 613)2023-03-0101 March 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.03.05d.i (Index Number 613) Project stage: Request 2023-01-12 |
ML23201A266 | |
Person / Time | |
---|---|
Site: | Vogtle |
Issue date: | 07/20/2023 |
From: | Coleman J Southern Nuclear Operating Co |
To: | Office of Nuclear Reactor Regulation, Document Control Desk |
References | |
ND-23-0609 | |
Download: ML23201A266 (2) | |
Similar Documents at Vogtle | |
---|---|
Category:Letter type:ND
MONTHYEARND-24-0103, Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests2024-04-26026 April 2024
[Table view]Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests ND-24-0114, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-04-0101 April 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-24-0059, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-03-0404 March 2024 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0693, Combined License (COL) License Condition 2.D.(4)(d) Completion of Initial Criticality and Low-Power Tests2024-02-15015 February 2024 Combined License (COL) License Condition 2.D.(4)(d) Completion of Initial Criticality and Low-Power Tests ND-23-0690, Combined License (COL) License Condition 2.D.(3)(e) Completion of Pre-Critical Tests2024-02-0808 February 2024 Combined License (COL) License Condition 2.D.(3)(e) Completion of Pre-Critical Tests ND-24-0019, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-02-0101 February 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0912, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-01-0202 January 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0881, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-12-0404 December 2023 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0817, Report of UFSAR Chapter 14 Changes to the Initial Test Program in Accordance with License Condition 2.D.(7)(a)2023-11-17017 November 2023 Report of UFSAR Chapter 14 Changes to the Initial Test Program in Accordance with License Condition 2.D.(7)(a) ND-23-0823, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-11-0303 November 2023 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0723, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-10-0404 October 2023 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0697, Submittal of Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-09-0505 September 2023 Submittal of Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0669, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-08-0707 August 2023 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0205, Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests2023-07-28028 July 2023 Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests ND-23-0618, Resubmittal of ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.07c.ii.a (Index Number 797)2023-07-20020 July 2023 Resubmittal of ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.07c.ii.a (Index Number 797) ND-23-0609, Notification of Completion of All ITAAC2023-07-20020 July 2023 Notification of Completion of All ITAAC ND-23-0608, ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72) ND-23-0607, ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13) ND-22-0796, ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.08 (Index Number 813)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.08 (Index Number 813) ND-23-0459, ITAAC Closure Notification on Completion of ITAAC 2.6.01.04d (Index Number 587)2023-07-19019 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.01.04d (Index Number 587) ND-23-0162, ITAAC Closure Notification on Completion of ITAAC 2.2.03.05a.i (Index Number 165)2023-07-19019 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.05a.i (Index Number 165) ND-23-0575, ITAAC Closure Notification on Completion of ITAAC 2.6.01.04e (Index Number 588)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.01.04e (Index Number 588) ND-23-0439, ITAAC Closure Notification on Completion of ITAAC 2.2.05.07a.i (Index Number 265)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.05.07a.i (Index Number 265) ND-23-0552, Southern Nuclear Operating Company, Vogtle Electric Generating Plant, Unit 4, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02c (Index Number 624)2023-07-18018 July 2023 Southern Nuclear Operating Company, Vogtle Electric Generating Plant, Unit 4, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02c (Index Number 624) ND-23-0483, ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4) ND-23-0586, ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159)2023-07-17017 July 2023 ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159) ND-23-0610, ITAAC Closure Notification on Completion of ITAAC Item 2.6.03.04c (Index Number 603)2023-07-17017 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.6.03.04c (Index Number 603) ND-23-0573, ITAAC Closure Notification on Completion of 2.4.02.02a (Index Number 497)2023-07-16016 July 2023 ITAAC Closure Notification on Completion of 2.4.02.02a (Index Number 497) ND-23-0406, ITAAC Closure Notification on Completion of ITAAC Item 2.4.02.02b (Index Number 498)2023-07-16016 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.4.02.02b (Index Number 498) ND-23-0601, ITAAC Closure Notification on Completion of ITAAC Item 2.7.05.02.i (Index Number 719)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.7.05.02.i (Index Number 719) ND-22-0816, ITAAC Closure Notification of Completion of ITAAC 2.1.02.05a (Index Number 19)2023-07-15015 July 2023 ITAAC Closure Notification of Completion of ITAAC 2.1.02.05a (Index Number 19) ND-23-0603, ITAAC Closure Notification on Completion of ITAAC Item 3.5.00.06 (Index Number 831)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 3.5.00.06 (Index Number 831) ND-23-0446, ITAAC Closure Notification on Completion of ITAAC 2.2.04.12a.iii (Index Number 250)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.04.12a.iii (Index Number 250) ND-23-0594, ITAAC Closure Notification on Completion of ITAAC 2.6.05.02.ii (Index Number 629)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.05.02.ii (Index Number 629) ND-23-0606, ITAAC Closure Notification on Completion of ITAAC 2.5.04.02.i (Index Number 557)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.5.04.02.i (Index Number 557) ND-23-0499, ITAAC Closure Notification on Completion of ITAAC 2.7.01.14 (Index Number 700)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.7.01.14 (Index Number 700) ND-23-0476, ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355) ND-23-0588, ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78) ND-23-0002, ITAAC Closure Notification on Completion of ITAAC 2.2.05.07c (Index Number 270)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.05.07c (Index Number 270) ND-23-0597, ITAAC Closure Notification on Completion of ITAAC 2.5.02.06a.ii (Index Number 530)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.5.02.06a.ii (Index Number 530) ND-23-0121, ITAAC Closure Notification on Completion of ITAAC C.2.6.09.07 (Index Number 667)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.07 (Index Number 667) ND-23-0122, ITAAC Closure Notification on Completion of ITAAC C.2.6.09.08a (Index Number 668)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.08a (Index Number 668) ND-23-0543, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02a (Index Number 622)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02a (Index Number 622) ND-23-0394, ITAAC Closure Notification on Completion of ITAAC 2.7.02.03a (Index Number 703)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.7.02.03a (Index Number 703) ND-23-0461, ITAAC Closure Notification on Completion of ITAAC 2.6.09.13a (Index Number 652)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.09.13a (Index Number 652) ND-22-0980, ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.06.i (Index Number 75)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.06.i (Index Number 75) ND-23-0111, ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646) ND-23-0587, ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595) ND-23-0589, ITAAC Closure Notification on Completion of ITAAC 2.6.03.04a (Index Number 601)2023-07-12012 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.03.04a (Index Number 601) ND-23-0581, ITAAC Closure Notification on Completion of ITAAC 2.2.04.02a (Index Number 220)2023-07-12012 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.04.02a (Index Number 220) 2024-04-26 |
Text
Jamie M. Coleman Regulatory Affairs Director Vogtle 3 & 4 7825 River Road Waynesboro, GA 30830 706-848-6926 tel July 20, 2023 Docket No.: 52-026 ND-23-0609 10 CFR 52.99(c)(4)
U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Andrea D. Veil Director, Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 4 Notification of Completion of All ITAAC Ladies and Gentlemen:
Pursuant to 10 CFR 52.99(c)(4), and in accordance with Vogtle Electric Generating Plant (VEGP)
Unit 4 Combined License (COL) NPF-92 condition 2.D.(2)(d), Southern Nuclear Operating Company (SNC) hereby notifies the NRC that all of the inspections, tests, analyses and acceptance criteria (ITAAC) in VEGP Unit 4 COL Appendix C have been successfully completed and are being maintained.
ITAAC Closure Notifications have been submitted to the NRC for each ITAAC in VEGP Unit 4 COL Appendix C in accordance with 10 CFR 52.99(c)(1). All of the ITAAC Closure Notifications are substantiated by ITAAC Completion packages, which include the documentation (tests, reports, completed procedures, completed analyses, etc.) that support the ITAAC determination bases. The ITAAC completion packages are available for NRC inspection at the plant site.
SNC is not aware of any condition that warrants submittal of an ITAAC Post-Closure Notification (IPCN) under 10 CFR 52.99(c)(2) for which an IPCN has not been submitted and hereby affirms the completion of all ITAAC prescribed in the combined license for VEGP Unit 4. On this basis, SNC requests that NRC staff make a finding that the acceptance criteria in the combined license are met (10 CFR 52.103(g)).
If there are any questions, please contact Kelli Roberts at 706-848-6991.
Respectfully submitted, Jamie M. Coleman Regulatory Affairs Director Vogtle 3 & 4 JMC/CEM/sfr
U.S. Nuclear Regulatory Commission ND-23-0609 Page 2 of 2 cc:
Regional Administrator, Region ll Director, Office of Nuclear Reactor Regulation (NRR)
Director, Vogtle Project Office NRR Senior Resident Inspector - Vogtle 3 & 4