Updated Inspection Plan for Shearon Harris Nuclear Power Plant Unit 1 Report 05000400/2025005
ML25237A053
Person / Time
Site: Harris 
Issue date: 08/26/2025
From: Matthew Fannon
NRC/RGN-II/DORS/PB2
To: Joseph C
Duke Energy Progress
References
IR 2025005
Download: ML25237A053 (5)


Text

SUBJECT:

UPDATED INSPECTION PLAN FOR SHEARON HARRIS NUCLEAR POWER PLANT, UNIT 1 REPORT 05000400/2025005

Dear Carolyne Joseph:

The enclosed inspection plan lists the inspections scheduled through June 30, 2027, for the Shearon Harris Nuclear Power Plant. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. As discussed in SECY-25-0045, Recommendations for Revising the Reactor Oversight Process, dated June 5, 2025 (ML25042A278), the NRC determined that a broad, comprehensive review of the ROP is necessary to reflect improvements in industry performance and advancements in technology. The outcome of the comprehensive review and recommendations to revise the ROP baseline inspection program, when approved by the NRC Commission, will require a revision to this inspection plan. The NRC will contact you as soon as possible to discuss any revisions after the new baseline inspection program is implemented.

This letter and its enclosure will be made available for public inspection and copying at ADAMS Public Documents l NRC.gov and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

August 26, 2025 Please contact me at 404-997-4547 with any questions you have regarding this letter.

Sincerely, Matthew S. Fannon, Chief Projects Branch 2 Division of Operating Reactor Safety Docket No.: 05000400 License No.: NPF-63 Enclosure:

Shearon Harris Inspection/Activity Plan (09/01/2025 - 06/30/2027)

cc w/ encl: Distribution via LISTSERV Signed by Fannon, Matthew on 08/26/25

ML25237A053 X

SUNSI Review X

Non-Sensitive

Sensitive X

Publicly Available

Non-Publicly Available OFFICE RII/DORS RII/DORS NAME A. Wilson M. Fannon DATE 8/26/2025 8/26/2025

Site Inspection Activity Plan

Harris 09/01/2025 - 06/30/2027 Unit Start End Activity CAC Title Staff Count FOCUSED ENGINEERING INSPECTION (CGD)

1 9/22/2025 9/26/2025 IP 71111.21N.03 001808 Commercial Grade Dedication RP OCCUPATIONAL RAD SAFETY AND TRANSPORTATION BASELINE INSPECTION

1 10/6/2025 10/10/2025 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls

10/6/2025 10/10/2025 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation

10/6/2025 10/10/2025 IP 71151 000746 Performance Indicator Verification UNIT 1 IN-SERVICE INSPECTION

1 10/13/2025 10/17/2025 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

HARRIS REQUAL INSPECTION

1 12/14/2025 12/20/2025 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance FOCUSED ENGINEERING INSPECTION (AGE-RELATED)

1 3/23/2026 3/27/2026 IP 71111.21N.04 001832 Age-Related Degradation

4/6/2026 4/10/2026 IP 71111.21N.04 001832 Age-Related Degradation SECURITY BASELINE INSPECTION

1 4/13/2026 4/16/2026 IP 71130.02 000734 Access Control

4/13/2026 4/16/2026 IP 71130.05 000737 Protective Strategy Evaluation

4/13/2026 4/16/2026 IP 71130.09 001656 Security Plan Changes

4/13/2026 4/16/2026 IP 71151 001338 Performance Indicator Verification EMERGENCY PREPAREDNESS PROGRAM INSPECTION

1 4/27/2026 5/1/2026 IP 71114.02 000717 Alert and Notification System Testing

4/27/2026 5/1/2026 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System

4/27/2026 5/1/2026 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes

4/27/2026 5/1/2026 IP 71114.05 000720 Maintenance of Emergency Preparedness

4/27/2026 5/1/2026 IP 71151 001397 Performance Indicator Verification

Site Inspection Activity Plan

RP OCCUPATIONAL AND PUBLIC RAD SAFETY BASELINE INSPECTION

6/22/2026 6/26/2026 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls

6/22/2026 6/26/2026 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment

6/22/2026 6/26/2026 IP 71124.07 000731 Radiological Environmental Monitoring Program

6/22/2026 6/26/2026 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation

6/22/2026 6/26/2026 IP 71151 000746 Performance Indicator Verification PROBLEM IDENTIFICATION AND RESOLUTION

1 8/17/2026 8/21/2026 IP 71152B 000747 Problem Identification and Resolution

8/31/2026 9/4/2026 IP 71152B 000747 Problem Identification and Resolution HARRIS INITIAL LICENSE EXAM

1 11/1/2026 11/7/2026 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)

12/6/2026 12/19/2026 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)

FORCE-ON-FORCE PLANNING AND EXERCISE WEEKS - HAR

1 2/1/2027 2/5/2027 IP 71130.03 000735 Contingency Response - Force-On-Force Testing

3/1/2027 3/5/2027 IP 71130.03 000735 Contingency Response - Force-On-Force Testing UNIT 1 IN-SERVICE INSPECTION +SG

1 4/26/2027 5/7/2027 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

EMERGENCY PREPAREDNESS EXERCISE INSPECTION

1 4/26/2027 4/30/2027 IP 71114.01 000716 Exercise Evaluation

4/26/2027 4/30/2027 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes

4/26/2027 4/30/2027 IP 71151 001397 Performance Indicator Verification SECURITY BASELINE INSPECTION - HAR

1 5/24/2027 5/27/2027 IP 71130.02 000734 Access Control

5/24/2027 5/27/2027 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance

5/24/2027 5/27/2027 IP 71130.09 001656 Security Plan Changes

5/24/2027 5/27/2027 IP 71151 001338 Performance Indicator Verification