ML23312A088

From kanterella
Jump to navigation Jump to search

Acceptance of Request to Revise Alternatives 1-RR-5-10 and 2-RR-5-10
ML23312A088
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 11/08/2023
From: Ballard B
Plant Licensing Branch III
To: Kivi J, Mark Miller
Northern States Power Co
Kuntz R
References
EPID L-2023-LLR-0052
Download: ML23312A088 (1)


Text

From: Brent Ballard To: Miller, Michael A; Kivi, Jeffrey L Cc: Jeff Whited

Subject:

Prairie Island Nuclear Generating Plant - Acceptance of Request to Revise Alternatives 1-RR-5-10 and 2-RR-5-10 (EPID L-2023-LLR-0052)

Date: Wednesday, November 8, 2023 9:34:00 AM Good morning, By letter dated October 3, 2023 (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML23276B462), Northern States Power Company, a Minnesota corporation (NSPM, the licensee), doing business as Xcel Energy, submitted an alternative request pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Section 50.55a(z)(1), Acceptable level of quality and safety, for Prairie Island Nuclear Generating Plant. Specifically, the alternative request revises previously authorized alternatives 1-RR-5-10 and 2-RR-5-10 to correct an error in the weld fluence value for the nozzle to shell circumferential weld, and incorporates new information from test results of surveillance capsules withdrawn from the Unit 1 and Unit 2 reactor vessels. The licensees original request and the NRC staffs authorization are available in ADAMS at ML19164A166 and ML19282A541, respectively. The time period applicable for the use of the requested alternative is until December 20, 2034.

The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed request in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staffs detailed technical review by separate correspondence.

Based on the information provided in your submittal, the NRC staff has estimated that this request will take approximately 125 hours0.00145 days <br />0.0347 hours <br />2.066799e-4 weeks <br />4.75625e-5 months <br /> to complete. The NRC staff expects to complete this review by April 4, 2024. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during routine interactions with the assigned project manager.

These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, and unanticipated addition of

scope to the review. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.

If you have any questions, please contact me at 301-415-0680 or by e-mail.

Thank you, Brent Brent Ballard Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission 301-415-0680