NRR E-mail Capture - Prairie Island Nuclear Generating Plant, Units 1 and 2 - Acceptance of Requested Licensing Action Request to Adopt TSTF-277
ML22167A045
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 06/16/2022
From: Robert Kuntz
NRC/NRR/DORL/LPL3
To: Kivi J
Northern States Power Company, Minnesota
References
L-2022-LLA-0084
Download: ML22167A045 (3)


Text

From: Kuntz, Robert Sent: Thursday, June 16, 2022 8:52 AM To: Kivi, Jeffrey L.

Cc: Scott, Sara

Subject:

Prairie Island Nuclear Generating Plant, Units 1 and 2 - Acceptance of Requested Licensing Action Re: Request to Adopt TSTF-277 (EPID L-2022-LLA-0084)

Mr. Kivi, By letter dated June 7, 2022 (Agencywide Documents Access and Management System (ADAMS) Accession Number ML22158A090), Northern States Power Company, a Minnesota corporation (NSPM), doing business as Xcel Energy, submitted a license amendment for Prairie Island Nuclear Generating Plant, Units 1 and 2 to adopt Technical Specification Task Force (TSTF) Traveler TSF-577, Revised Frequencies for Steam Generator Tube Inspections. The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

Based on the information provided in your submittal the NRC staff has estimated that this licensing request will take approximately 40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> to complete. The NRC staff expects to complete this review in approximately 6 months, which is December 16, 2022. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.

These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities.

If you have any questions, please contact me.

Robert F. Kuntz, Senior Project Manager Plant Licensing Branch 3 Division of Operating Reactor Licensing

Office of Nuclear Reactor Regulation Hearing Identifier: NRR_DRMA Email Number: 1676 Mail Envelope Properties (SA9PR09MB4640FE40F5E451E5D9BECF3699AC9)

Subject:

Prairie Island Nuclear Generating Plant, Units 1 and 2 - Acceptance of Requested Licensing Action Re: Request to Adopt TSTF-277 (EPID L-2022-LLA-0084)

Sent Date: 6/16/2022 8:52:17 AM Received Date: 6/16/2022 8:52:00 AM From: Kuntz, Robert Created By: Robert.Kuntz@nrc.gov Recipients:

"Scott, Sara" <sara.scott@xcelenergy.com>

Tracking Status: None "Kivi, Jeffrey L." <jeffrey.l.kivi@xcelenergy.com>

Tracking Status: None Post Office: SA9PR09MB4640.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 2868 6/16/2022 8:52:00 AM Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: