ND-21-0620, ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.07c.ii.b (Index Number 798)

From kanterella
(Redirected from ML22110A234)
Jump to navigation Jump to search

ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.07c.ii.b (Index Number 798)
ML22110A234
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 04/20/2022
From: Coleman J
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
ITAAC 3.3.00.07c.ii.b, ND-21-0620
Download: ML22110A234 (1)


Text

.>,,, Southern Nuclear Jamie M. Coleman Regu latory Affairs Director Vogtle 3 & 4 7825 River Road Waynesboro, GA 30830 706-848-6926 tel APR 2 0 2022 Docket No.: 52-025 ND-21-0620 10 CFR 52.99(c)(1)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.07c.ii.b [Index Number 7981 Ladies and Gentlemen:

In accordance with 10 CFR 52.99(c)(1 ), the purpose of this letter is to notify the Nuclear Regulatory Commission (NRC) of the completion of Vogtle Electric Generating Plant (VEGP) Unit 3 Inspections, Tests, Analyses , and Acceptance Criteria (ITAAC) Item 3.3.00.07c.ii.b [Index Number 798). This ITAAC confirms that fire barriers exist between fire areas identified in Table 3.3-3 inside the radiologically controlled area of the auxiliary building. The closure process for this ITAAC is based on the guidance described in Nuclear Energy Institute (NEI) 08-01, Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215.

This letter contains no new NRC regulatory commitments. Southern Nuclear Operating Company (SNC) requests NRC staff confirmation of this determination and publication of the required notice in the Federal Register per 10 CFR 52.99.

If there are any questions, please contact Kelli A. Roberts at 706-848-6991 .

Respectfully submitted,

~~

Jamie M. Coleman Regulatory Affairs Director Vogtle 3 & 4

Enclosure:

Vogtle Electric Generating Plant (VEGP) Unit 3 Completion of ITAAC Item 3.3.00.07c.ii.b [Index Number 798]

JMC/JFV/sfr

U.S . Nuclear Regulatory Commission ND-21-0620 Page 2 of 3 To:

Southern Nuclear Operating Company/ Georgia Power Company Mr. Peter P. Sena Ill Mr. D. L. McKinney Mr. H. Nieh Mr. G. Chick Mr. S. Stimac Mr. P. Martino Mr. J.B. Williams Mr. A. S. Parton Ms. K. A. Roberts Ms. J.M. Coleman Mr. C. T. Defnall Mr. C. E. Morrow Mr. K. J. Drudy Mr. J. M. Fisher Mr. R. L. Beilke Mr. S. Leighty Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.LI.L06 File AR .01 .02.06 Nuclear Regulatory Commission Ms. M. Bailey Mr. M. King Mr. G. Bowman Ms. A. Veil Mr. C. P. Patel Mr. G. J. Khouri Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert Mr. C. Welch Mr. J. Gaslevic Mr. 0. Lopez-Santiago Mr. G. Armstrong Mr. M. Webb Mr. T. Fredette Mr. C. Santos Mr. B. Davis Mr. J. Vasquez Mr. J. Eargle Ms. K. Mccurry Mr. J. Parent Mr. B. Griman Mr. V. Hall

U.S. Nuclear Regulatory Commission ND-21-0620 Page 3 of 3 Oglethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Dalton Utilities Mr. T. Bundros Westinghouse Electric Company, LLC Dr. L. Oriani Mr. D. C. Durham Mr. M. M. Corletti Mr. Z. S. Harper Ms. S.L. Zwack Other Mr. S. W. Kline, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr. , Ph.D. , GOS Associates, Inc.

Mr. S. Roetger, Georgia Public Service Commission Mr. R. L. Trokey, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. S. Blanton, Balch Bingham

U.S. Nuclear Regulatory Commission ND-21-0620 Enclosure Page 1 of 4 Southern Nuclear Operating Company ND-21-0620 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 3 Completion of ITAAC Item 3.3.00.07c.ii.b [Index Number 798]

U.S. Nuclear Regulatory Commission ND-21-0620 Enclosure Page 2 of 4 IT AAC Statement Design Commitment 7.c) Separation is maintained between Class 1E divisions in accordance with the fire areas as identified in Table 3.3-3.

Inspections, Tests, Analyses ii) Inspections of the as-built fire barriers between the fire areas identified in Table 3.3-3 will be conducted.

Acceptance Criteria ii.b) Results of the inspection will confirm that fire barriers exist between fire areas identified in Table 3.3-3 inside the radiologically controlled area of the auxiliary building.

ITAAC Determination Basis Multiple ITAAC are performed to demonstrate that separation is maintained between Class 1E divisions in accordance with the fire areas as identified in Table 3.3-3. The subject ITAAC requires inspections to be conducted of the as-built fire barriers between the fire areas identified in Table 3.3-3. The Class 1E divisions in Nuclear Island Fire Areas are described in Combined Operating License (COL) Appendix C Table 3.3-3 (Attachment A). The fire barriers between fire areas identified in Table 3.3-3 inside the radiologically controlled area of the auxiliary building are designed in accordance with APP-GW-E1-001 (Reference 1). Installation specifications provided to the constructor identify the fire barriers, consistent with the ITAAC commitment.

Fire barriers between the fire areas identified in the table were installed in accordance with design drawings, installation specifications issued for construction , and work package requirements. Completed fire barriers were inspected to ensure the fire barrier criteria in the installation specifications are satisfied . Inspections were performed in accordance with the Construction Quality Verification Program 26139-000-4MP-T81 C-N7101 (Reference 2). The completed inspection records document that satisfactory fire barriers exist between fire areas identified in the table inside the radiologically controlled area of the auxiliary building .

The Fire Barrier Inspection Report (Reference 3) identifies the inspection reports associated with the fire barrier inspections and confirmed that fire barriers exist between fire areas identified in Table 3.3-3 inside the radiologically controlled area of the auxiliary building.

The Fire Barrier Inspection Report is available for N RC inspection as part of the Unit 3 ITAAC Completion Package (Reference 4).

ITAAC Finding Review In accordance with plant procedures for ITAAC completion , Southern Nuclear Operating Company (SNC) performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAAC findings associated with this ITAAC. The ITAAC completion review is documented in the ITAAC Completion Package for ITAAC 3.3.00.0?c.ii.b (Reference 4) and is available for NRC review.

U.S. Nuclear Regulatory Commission ND-21-0620 Enclosure Page 3 of 4 ITAAC Completion Statement Based on the above information, SNC hereby notifies the NRC that ITAAC 3.3.00.0?c.ii.b was performed for VEGP Unit 3 and that the prescribed acceptance criteria were met. Systems, structures, and components verified as part of this ITAAC are being maintained in their as-designed, ITAAC compliant condition in accordance with approved plant programs and procedures.

References (available for NRC inspection)

1. APP-GW-E1-001 (SV3-GW-E1-001 ), Rev. 3 Electrical Systems Design Criteria
2. 26139-000-4MP-T81 C-N7101 RS, Construction Quality Verification Program
3. SV3-1200-ITR-800798 RO , Fire Barrier Inspection Report, Unit 3: ITAAC 3.3.00.0?c.ii.b (Aux Bldg Rad Area Fire Barriers) NRC Index Number 798
4. 3.3.00.07c.ii.b-U3-CP-Rev0, ITAAC Completion Package
5. NEI 08-01, "Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52"

U.S. Nuclear Regulatory Commission ND-21-0620 Enclosure Page 4 of 4 Attachment A Class 1E Divisions in Nuclear Island Fire Areas*

Fire Area Number Auxiliary Building Radiologically Controlled 1200 AF 01 1220 AF 02 Notes:

  • Excerpt from COL Appendix C Table 3.3-3