ND-22-0151, ITAAC Closure Notification on Completion of ITAAC 2.2.02.06b (Index Number 133)

From kanterella
(Redirected from ML22059B068)
Jump to navigation Jump to search

ITAAC Closure Notification on Completion of ITAAC 2.2.02.06b (Index Number 133)
ML22059B068
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 02/28/2022
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
ND-22-0151
Download: ML22059B068 (7)


Text

Michael J. Yox 7825 River Road

.. Southern Nuclear Regu latory Affairs Waynesboro, GA 30830 Vogtle 3 & 4 706-848-6459 tel FEB 2 8 2022 Docket No.: 52-025 ND-22-0151 10 CFR 52.99(c)(1)

U.S. Nuclear Regulatory Commission Document Control Desk Washington , DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 ITAAC Closure Notification on Completion of ITAAC 2.2.02.06b [Index Number 133)

Ladies and Gentlemen:

In accordance with 10 CFR 52.99(c)(1 ), the purpose of this letter is to notify the Nuclear Regulatory Commission (NRG) of the completion of Vogtle Electric Generating Plant (VEGP) Unit 3 Inspections, Tests , Analyses, and Acceptance Criteria (ITAAC) Item 2.2.02.06b [Index 133). This ITAAC confirms that the Class 1E Passive Containment Cooling System (PCS) components identified in Combined License (COL) Table 2.2.2-1 are powered from their respective Class 1E division. The closure process for this ITAAC is based on the guidance described in NEI 08-01, "Industry Guideline for the ITAAC Closure Process under 10 CFR Part 52," which was endorsed by the NRG in Regulatory Guide 1.215.

This letter contains no new NRG regulatory commitments. Southern Nuclear Operating Company (SNC) requests NRG staff confirmation of this determination and publication of the required notice in the Federal Register per 10 CFR 52.99.

If there are any questions, please contact Kelli Roberts at 706-848-6991.

Respectfully submitted, Michael J. Yox Regulatory Affairs Director Vogtle 3 & 4

Enclosure:

Vogtle Electric Generating Plant (VEGP) Unit 3 Completion of ITAAC 2.2.02.06b [Index Number 133)

MJY/MSV/sfr

U.S. Nuclear Regulatory Commission ND-22-0151 Page 2 of 3 To:

Southern Nuclear Operating Company/ Georgia Power Company Mr. Peter P. Sena Ill Mr. D. L. McKinney Mr. H. Nieh Mr. G. Chick Mr. S. Stimac Mr. P. Martino Mr. J.B. Williams Mr. M. J. Yox Mr. A. S. Parton Ms. K. A. Roberts Ms. J.M. Coleman Mr. C. T. Defnall Mr. C. E. Morrow Mr. K. J. Drudy Mr. J. M. Fisher Mr. R. L. Beilke Mr. S. Leighty Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 Nuclear Regulatory Commission Ms. M. Bailey Mr. M. King Mr. G. Bowman Ms. A. Veil Mr. C. P. Patel Mr. G. J. Khouri Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert Mr. C. Welch Mr. J. Gaslevic Mr. 0. Lopez-Santiago Mr. G. Armstrong Mr. M. Webb Mr. T. Fredette Mr. C. Santos Mr. B. Davis Mr. J. Vasquez Mr. J. Eargle Mr. T. Fanelli Ms. K. Mccurry Mr. J. Parent Mr. B. Griman Mr. V. Hall

U.S. Nuclear Regulatory Commission ND-22-0151 Page 3 of 3 Oglethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Dalton Utilities Mr. T. Bundros Westinghouse Electric Company, LLC Dr. L. Oriani Mr. D. C. Durham Mr. M. M. Corletti Mr. Z. S. Harper Mr. J. L. Coward Other Mr. S. W. Kline , Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr. , Ph.D., GOS Associates, Inc.

Mr. S. Roetger, Georgia Public Service Commission Mr. R. L. Trokey, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. S. Blanton , Balch Bingham

U.S. Nuclear Regulatory Commission ND-22-0151 Enclosure Page 1 of 4 Southern Nuclear Operating Company ND-22-0151 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 3 Completion of ITAAC 2.2.02.06b [Index Number 133]

U.S. Nuclear Regulatory Commission ND-22-0151 Enclosure Page 2 of 4 IT AAC Statement Design Commitment 6.b) The Class 1E components identified in Table 2.2.2-1 are powered from their respective Class 1E division.

Inspections/Tests/Analyses Testing will be performed by providing a simulated test signal in each Class 1E division.

Acceptance Criteria A simulated test signal exists at the Class 1E components identified in Table 2.2.2-1 when the assigned Class 1E division is provided the test signal.

ITAAC Determination Basis Testing was performed on the Class 1E components identified in the VEGP Unit 3 COL Appendix C Table 2.2.2-1 (Attachment A) to demonstrate they are powered from their respective Class 1E division. This ITAAC performs testing on the components identified in Table 2.2.2-1 by providing a simulated test signal in each Class 1E division.

Class 1E power verification testing of the Protection and Safety Monitoring System (PMS) cabinets, associated with the equipment identified in Attachment A, was verified through the applicable portions of ITAAC 2.5.02.05a testing (Reference 1) and confirms the PMS cabinets are powered from their respective Class 1E division. SV3-PCS-ITR-800133 (Reference 2) documents completion of power verification activities from the PMS cabinets and the Class 1E power distribution panels/motor control centers to the components identified in Attachment A.

Reference 2 first verified that power supply cables/wiring are installed and terminated from the applicable PMS cabinet and Class 1E power distribution panel/motor control center to the respective component identified in Attachment A using approved construction drawings and cable/wiring termination documentation. Reference 2 then confirmed, via cable/wiring termination inspection documentation, that continuity testing was performed on each of the installed cables/wiring to confirm current flow within the installed cable/wiring . The combination of cable/wiring installation and termination verification, with the installed cable/wiring continuity testing, confirmed that the components identified in Appendix A are powered from their respective Class 1E division.

SV3-PCS-ITR-800133 (Reference 2) confirmed that a simulated test signal exists at the Class 1E components identified in Table 2.2.2-1 when the assigned Class 1E division is provided the test signal.

References 1 and 2 are available for NRC inspection as part of Unit 3 ITAAC Completion Package (Reference 3).

U.S. Nuclear Regulatory Commission ND-22-0151 Enclosure Page 3 of 4 ITAAC Finding Review In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company (SNC) performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAAC findings associated with this ITAAC.

The ITAAC completion review is documented in the Vogtle Unit 3 ITAAC Completion Package for ITAAC 2.2.02.06b (Reference 3) and is available for NRC inspection .

ITAAC Completion Statement Based on the above information , SNC hereby notifies the NRC that ITAAC 2.2.02 .06b was performed for VEGP Unit 3 and that the prescribed acceptance criteria were met.

Systems, structures, and components verified as part of this ITAAC are being maintained in their as-designed , ITAAC compliant condition in accordance with approved plant programs and procedures.

References (available for NRC inspection)

1. SV3-PMS-ITR-800527-1 Rev. 0, "Unit 3 Protection & Safety Monitoring (PMS) System Equipment by Assigned Class 1E Division: ITAAC 2.5.02.05a"
2. SV3-PCS-ITR-800133 Rev0 "Unit 3 Passive Containment Cooling System (PCS) Class 1E Equipment Signaled: ITAAC 2.2.02.06b"
3. 2.2.02 .06b-U3-CP-Rev0, ITAAC Completion Package

U.S. Nuclear Regulatory Commission ND-22-0151 Enclosure Page 4 of 4 Attachment A COL Appendix C Table 2.2.2-1 Component Name* Tag No.*

PCCWST Isolation Valve PCS-PL-V001A PCCWST Isolation Valve PCS-PL-V001 B PCCWST Isolation Valve MOV PCS-PL-V001 C PCCWST Isolation Block MOV PCS-PL-V002A PCCWST Isolation Block MOV PCS-PL-V002B PCCWST Isolation Block MOV PCS-PL-V002C PCS Water Delivery Flow Sensor PCS-001 PCS Water Delivery Flow Sensor PCS-002 PCS Water Delivery Flow Sensor PCS-003 PCS Water Delivery Flow Sensor PCS-004 Containment Pressure Sensor PCS-005 Containment Pressure Sensor PCS-006 Containment Pressure Sensor PCS-007 Containment Pressure Sensor PCS-008 PCCWST Water Level Sensor PCS-010 PCCWST Water Level Sensor PCS-011 High-range Containment Pressure Sensor PCS-012 High-range Containment Pressure Sensor PCS-013 High-range Containment Pressure Sensor PCS-014

  • Excerpted from COL Appendix C Table 2.2.2-1