Letter Sequence Acceptance Review |
---|
|
|
MONTHYEARRA-20-0334, Relief Request to Utilize an Alternative Acceptance Criteria for Code Case N-853, - PWR Class 1 Primary Piping Alloy 600 Full Penetration Branch Connection Weld Metal Buildup for Material Susceptible to Primary2021-05-0404 May 2021 Relief Request to Utilize an Alternative Acceptance Criteria for Code Case N-853, - PWR Class 1 Primary Piping Alloy 600 Full Penetration Branch Connection Weld Metal Buildup for Material Susceptible to Primary Project stage: Request ML21138A0102021-05-18018 May 2021 NRR E-mail Capture - Oconee Nuclear Station, Units 1, 2, and 3 - Acceptance of Requested Licensing Action Use of Alternative Acceptance Criteria for Code Case N-853 Project stage: Acceptance Review ML21217A1912021-08-0505 August 2021 Request for Additional Information Alternative Request (RA-20-0334) Regarding Use of an Alternative to the ASME Code Case N-853 Acceptance Criteria Project stage: RAI RA-21-0242, Response to Request for Additional Information, Regarding Relief Request to Utilize an Alternative Acceptance Criteria for Code Case N-853, PWR Class 1 Primary Piping Alloy 600 Full Penetration Branch Connection2021-08-31031 August 2021 Response to Request for Additional Information, Regarding Relief Request to Utilize an Alternative Acceptance Criteria for Code Case N-853, PWR Class 1 Primary Piping Alloy 600 Full Penetration Branch Connection Project stage: Response to RAI ML21274A0682021-10-0101 October 2021 Request for Additional Information Alternative Request (RA-20-0334) Regarding Use of an Alternative to the ASME Code Case N-853 Acceptance Criteria Project stage: RAI RA-21-0270, Response to Second Request for Additional Information (RAI) Regarding Relief Request to Utilize an Alternative Acceptance Criteria for Code Case N-8532021-10-28028 October 2021 Response to Second Request for Additional Information (RAI) Regarding Relief Request to Utilize an Alternative Acceptance Criteria for Code Case N-853 Project stage: Request ML21348A5452021-12-14014 December 2021 December 13, 2021, Clarification Call Summary Use of an Alternative to the ASME Code Case N-853 Acceptance Criteria Project stage: Approval ML22020A2622022-01-20020 January 2022 Memorandum (Notice Regarding Issuance of Decision) Project stage: Request RA-22-0025, Supplemental Information for Relief Request to Utilize an Alternative Acceptance Criteria for Code Case, PWR Class 1 Primary Piping Alloy 600 Full Penetration Branch Connection Weld Metal Buildup for Material2022-01-20020 January 2022 Supplemental Information for Relief Request to Utilize an Alternative Acceptance Criteria for Code Case, PWR Class 1 Primary Piping Alloy 600 Full Penetration Branch Connection Weld Metal Buildup for Material Project stage: Supplement ML22028A3652022-02-0707 February 2022 Authorization and Safety Evaluation for Alternative Acceptance Criteria for Code Case N-853 Project stage: Approval 2021-05-04
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24257A0212024-09-11011 September 2024 Document Request for Oconee Nuclear Station - Radiation Protection Inspection - Inspection Report 2024-04 ML24234A2972024-08-21021 August 2024 August 21, 2024 - Oconee Nuclear Station, Units 1, 2, and 3 - Acceptance of Requested Licensing Action License Amendment Request to Revise Technical Specification 3.7.7 ML24211A0872024-07-27027 July 2024 EN 57079 Paragon Energy Solutions Final - No Active Links ML24197A2292024-07-15015 July 2024 Email from Mark Yoo (NRC) to Steve Snider (Duke) - Oconee SLRA - RAI - 2024 Annual Update ML24190A0462024-07-0505 July 2024 Notification of Inspection and Request for Information ML24179A1292024-06-24024 June 2024 Acceptance Review for LAR to Revise TS to Adopt TSTF-234-A, Revision 1 ML24143A1322024-05-22022 May 2024 May 22, 2024, Verbal Authorization for Duke Energy Request to Use a Provision of a Later Edition and Addenda of the ASME Boiler and Pressure Vessel Code, Section XI (RA-24-0152) (EPID L- 2024-LLR-0034) ML24127A0892024-05-0202 May 2024 57079-EN57079-1 - Redline Strikethrough e-mail Re Part 21 Interim Notification of Potential Defect with Schneider Electric Medium Voltage Vr Type Circuit Breaker ML24108A0792024-04-16016 April 2024 EN 57079 Paragon Energy Solutions Email Forwarding Part 21 Interim Report Re Potential Defect with Schneider Electric Medium Voltage Vr Type Circuit Breaker Part Number V5D4133Y000 ML24086A3772024-03-26026 March 2024 Request for Additional Information License Amendment Request to Revise Technical Specification 5.5.2 ML24036A1442024-02-27027 February 2024 NRC to Fws, NRC Request for Concurrence with Endangered Species Act Determinations for Oconee Nuclear Station, Units 1, 2, and 3, Proposed Subsequent License Renewal in Oconee County, South Carolina (Consultation Code: 2023-0054989) ML24054A0492024-02-21021 February 2024 Notification of Oconee Nuclear Station FEI Inspection and Information Request-Email ML23349A0272023-12-15015 December 2023 – Acceptance of Requested Licensing Action License Amendment Request to Revise Technical Specification 5.5.2 ML23284A3322023-10-11011 October 2023 Request for Additional Information Alternative Request (RA-22-0174) (L-2022-LLR-0060) ML23270B8362023-09-26026 September 2023 Code Case N-752 Audit September 26, 2023, E-mail Providing Additional Information Regarding the Use of Owners Requirements and Engineering Judgment in Lieu of Code and Standards ML23267A0032023-09-21021 September 2023 RP Inspection Document Request ML23269A0412023-08-22022 August 2023 Code Case N-752 Audit; August 22, 2023, E-mail Providing Additional Information Regarding Design and Quality Program Requirements ML23172A0132023-06-20020 June 2023 Duke Fleet - Correction to June 2, 2023, Request for Additional Information Proposed License Amendment Request to Revise Restrictive Surveillance Requirement Frequencies ML23153A1892023-06-0202 June 2023 Duke Fleet - Request for Additional Information Proposed License Amendment Request to Revise Restrictive Surveillance Requirement Frequencies ML23151A3482023-05-30030 May 2023 Duke Fleet - Request for Additional Information Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) ML23144A0862023-05-24024 May 2023 Acceptance of Requested Licensing Action Proposed Relief Request (RA-23-0018) to Use ASME Code Case 853 ML23142A2732023-05-22022 May 2023 Duke Fleet - Request for Additional Information Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) ML23125A1452023-05-0505 May 2023 Change in Estimated Review Schedule and Level of Effort for Proposed Alternative to Use Code Case N-752 ML23124A1212023-05-0404 May 2023 Acceptance of Requested Licensing Action Duke Fleet Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) ML23095A0052023-04-0404 April 2023 002 Radiation Safety Baseline Inspection Information Request ML23086C0362023-03-27027 March 2023 Request for Additional Information Steam Generator Tube Inspection Report (03R31) ML23073A2282023-03-13013 March 2023 Duke Fleet- Adoption of TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements - Acceptance Review ML23058A0562023-02-27027 February 2023 Acceptance of Amendment to Revise Surveillance Frequencies for RCS Pressure Isolation Valve Operational Leakage Testing and Reactor Trip System Instrumentation ML23048A1512023-02-16016 February 2023 Acceptance Review - Proposed Alternative for Steam Generator Welds (L-2023-LLR-0003) ML23038A1832023-02-0707 February 2023 Request for Additional Information Alternative Request (RA-22-0174) to Use ASME Code Case N-752 ML23031A1552023-01-17017 January 2023 1/17/2023 Email from John Moses, Deputy Director, Division of Rulemaking, Environmental, and Financial Support, to Diane Curran, Counsel to Beyond Nuclear and the Sierra Club, Request for Extension of Scoping Comment Period for Oconee EIS ML22294A0812022-10-21021 October 2022 Nrc/Duke Steam Generator Inspection Call for November 8, 2022 NRC-2100-2022, EN 55999 Valcor Coil Shell Assemblies Final Notification (004)2022-09-12012 September 2022 EN 55999 Valcor Coil Shell Assemblies Final Notification (004) ML22251A2902022-09-0808 September 2022 Request for Additional Information Additional Mode Change Limitations Applicable to the Adoption of Technical Specifications Tasks Force Traveler (TSTF) No. 359, Revision 9 ML22235A6552022-08-23023 August 2022 Acceptance of Requested Licensing Action Proposed Alternative to Use ASME Code Case N-752 NRC 2110-2022, EN 55999 - Valcor Engineering Corporation (009)2022-07-18018 July 2022 EN 55999 - Valcor Engineering Corporation (009) ML22234A1262022-07-0808 July 2022 Email from NRC to Duke - Feedback on Trp 76 RAI Responses - July 8, 2022 ML22234A1272022-06-14014 June 2022 Email from NRC to Duke - Feedback on Trp 76 RAI Responses - June 14, 2022 ML22154A2142022-06-0101 June 2022 Email from NRC (Angela Wu) to Duke (Paul Guill) - Oconee SLRA - 2nd Round RAI B2.1.7-4b ML22157A0012022-06-0101 June 2022 Email from NRC (Angela Wu) to Duke (Paul Guill) - Oconee SLRA - Additional NRC Comments on RAI 4.6.1-1a ML22124A2052022-05-0404 May 2022 Summary of May 4, 2022, Clarification Call with Duke Energy Carolinas, LLC, Application to Revise TS 3.7.7, Low Pressure Service Water (LPSW) System ML22124A1612022-05-0303 May 2022 Email from Angela Wu (NRC) to Steve Snider (Duke) - Oconee SLRA - 2nd Round RAI B2.1.7-4a ML22122A0192022-04-28028 April 2022 Email from Angela Wu (NRC) to Steve Snider (Duke) - Oconee SLRA - 2nd Round RAI B2.1.9-2a ML22122A1322022-04-27027 April 2022 Email from Angela Wu (NRC) to Steve Snider (Duke) - Oconee SLRA - 2nd Round Requests for Additional Information (FE 3.5.2.2.2.6 - Irradiation Structural) ML22115A1412022-04-25025 April 2022 NRR E-mail Capture - Duke Common EOF Relocation - Request for Addition Information ML22130A0112022-04-25025 April 2022 Email: Oconee SLRA - RAI 4.6.1-1a - NRC Staff Comments ML22112A1892022-04-22022 April 2022 Acceptance Review for Additional Mode Change Limitations Applicable to the Adoption of TSTF- 359, Revision 9 ML22113A0082022-04-20020 April 2022 Email from Marieliz Johnson (NRC) to Steve Snider (Duke) - Oconee SLRA - Request for Additional Information 3.1.2-1 ML22112A0072022-04-20020 April 2022 Email from Marieliz Johnson (NRC) to Steve Snider (Duke) - Oconee SLRA - Request for Confirmation of Information 3.5.2.2.2.6-L ML22088A0452022-03-28028 March 2022 Radiation Safety Baseline Inspection Initial Information Request Inspection Report 2022002 2024-09-11
[Table view] |
Text
From: Stone, Zackary Sent: Tuesday, May 18, 2021 6:40 AM To: Zaremba, Arthur H.
Cc: Vaughan, Jordan L; Williams, Shawn; Stone, Zackary
Subject:
Oconee Nuclear Station, Units 1, 2, and 3 - Acceptance of Requested Licensing Action RE: Use of Alternative Acceptance Criteria for Code Case N-853 (EPID L-2021-LLR-0032)
Mr. Zaremba, By [[letter::RA-20-0334, Relief Request to Utilize an Alternative Acceptance Criteria for Code Case N-853, - PWR Class 1 Primary Piping Alloy 600 Full Penetration Branch Connection Weld Metal Buildup for Material Susceptible to Primary|letter dated May 4, 2021]] (Agencywide Documents Access and Management System Accession No. ML21124A170), Duke Energy Carolinas, LLC, (the licensee) submitted an alternative request for Oconee Nuclear Station, Units 1, 2, and 3. The licensee is requesting use of acceptance criteria of American Society of Mechanical Engineers (ASME) Code,Section XI, IWB-3514 in lieu of Section III, NB-5330 to disposition fabrication flaws detected during ultrasonic testing (UT) of the weld-pad installed in accordance with ASME Code Case N-853, PWR Class 1 Primary Piping Alloy 600 Full Penetration Branch Connection Weld Metal Buildup for Material Susceptible to Primary Water Stress Corrosion Cracking,Section XI, Division 1.
The licensee submitted the request pursuant to 10 CFR Section 50.55a(z)(1), which requires the applicant to demonstrate that the proposed alternative would provide an acceptable level of quality and safety.
The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this proposed alternative. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to begin its detailed technical review. The acceptance review is also intended to identify whether the request has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to begin its detailed technical review and make an independent assessment regarding the acceptability of the proposed request in terms of regulatory requirements and the protection of public health and safety and the environment.
Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified in despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staffs detailed technical review by separate correspondence.
Based on the information provided in your submittal, the NRC staff has estimated that this proposed request will take approximately 110 hours0.00127 days <br />0.0306 hours <br />1.818783e-4 weeks <br />4.1855e-5 months <br /> to complete. The NRC staff expects to compete this review by your requested date of April 2022. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes along with the new estimates, will be communicated during the routine interactions with the assigned project manager.
These estimates are based on the NRC staffs initial review of the application and they can change due to several factors including requests for additional information, and unanticipated
addition of scope to the review. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.
If you have any questions, please contact Shawn Williams at (301) 415-1009 or Shawn.Williams@nrc.gov.
Shawn Williams, Senior Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-269, 50-270, 50-287 cc: Listserv
Hearing Identifier: NRR_DRMA Email Number: 1194 Mail Envelope Properties (BLAPR09MB635476DD58E3AC58131A57DFE12C9)
Subject:
Oconee Nuclear Station, Units 1, 2, and 3 - Acceptance of Requested Licensing Action RE: Use of Alternative Acceptance Criteria for Code Case N-853 (EPID L-2021-LLR-0032)
Sent Date: 5/18/2021 6:39:32 AM Received Date: 5/18/2021 6:39:36 AM From: Stone, Zackary Created By: Zackary.Stone@nrc.gov Recipients:
"Vaughan, Jordan L" <Jordan.Vaughan@duke-energy.com>
Tracking Status: None "Williams, Shawn" <Shawn.Williams@nrc.gov>
Tracking Status: None "Stone, Zackary" <Zackary.Stone@nrc.gov>
Tracking Status: None "Zaremba, Arthur H." <Arthur.Zaremba@duke-energy.com>
Tracking Status: None Post Office: BLAPR09MB6354.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 3671 5/18/2021 6:39:36 AM Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: