ML20246C823
| ML20246C823 | |
| Person / Time | |
|---|---|
| Site: | 05000000, Grand Gulf |
| Issue date: | 03/19/1982 |
| From: | Robert Lewis NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | Eisenhut D Office of Nuclear Reactor Regulation |
| Shared Package | |
| ML20246C819 | List: |
| References | |
| FOIA-89-226 NUDOCS 8908250144 | |
| Download: ML20246C823 (12) | |
Text
7-
\\
-.wmug
.i
,W Md 5 f' UfJits0 ST MET, w : LEAR RscutAToav ::t.:MissicN I y
.J ;r-I 4 - % *-
REGION 11 k "4d
[
- 01 viamEtT A ST. %.. Suit! Jico'
.....f s
anaur A. cronc e. :o:n3 y
~
MAR 191982 l
SSINS 50-416
..J MEMORANDUM FOR:
D. G. Eisenhut, Director, Division of Licensing, Office of i
Nuclear Reactor Regulation j
R. C. Lewis, Director, Division of Project and Resident Programs" FROM:
)
SUBJECT:
MISSISSIPPI POWER AND LIGHT COMPANY, GRAND GULF UNIT 1 In accordance with Inspection Procedure No. 94300B, the enclosures list tne remaining open items that require resolution before a finding of readiness for operation may be endorsed by NRC Region 11.
Remaining construction, testing, and I
inspection items identified in the enclosures nave been categorized by our -
i recommended mandatory completion milestones.
The licensee's. projected fuel loading date is April 23, 1982.
As of March 1, i
1982 construction was approximately 97 percent complete.
Region 11 considers the fuel load date to be optimistic by sp,eks.
(
f.C.
R. C.
ewis
Enclosures:
1.
Items, tg. be completed prior to Fuel ~ Loading 2.
Items to be completec prior to Initial Criticality 3.
Items to be completed prior to Exceeding 5% Rated Power 4.
Preoperational Testing Status and Operational Preparedness 5.
Status of Inspections Required by MC 2512 MC 2513, and 11C 2514 cc:
J. Taylor, DDRP B. Grimes DDEP E. Jordan, DDEQA L. Cobb, DDFFMS 4
D. Houston, LPH
\\
CORTACT:
A. K. Hardin 242-4182 1
8908250144 890816 PDR fDIA -
[g/n
- c f.
1
..,.,t.
- g*
l l
. Items to be' Completed Prior 'to Fuel Loading
- I.
The licensee will complete to the satisfaction of f RC Pegion '!I the following open items.
A.
Verify that battery capacity testing conducted at less than FSAR requirement of 125 percent is adequate (80-21-10).
I S.
Verify 'the effect of the vibration monitoring system not being
'3 operational during the instrument air preoperational test (Procedure 1P53PT01) as required by chapter 14 of the FSAR (81-13-01).
C.
Evaluate testing of the instrument air system (Procedure 1P53PT01) that did not conform to Regulatory Guide 1.80 (81-13-02).
D.
Resolve conflicts between wiring installations installed per the
.!", ", ^
schematic and the connection diagram (81-14-02) l II. The licensee will complete to the satisfaction of NRC Region !! the following Construction Deficiency Reports 10 CFR 50.55(e):
A.
Resolve' internal defects that affect operation of actuators used on Henry Pratt valves.
(80-72)
B.
Resolve environmental qualification of ASCO valves.
(81-14) 1 C.
Verify adequacy of Rockbestos series 100 coaxial cable above 230*F.
(81-46)
D.
Resolve settings on Bergen-Patterson hanger springs.
(81-47)
III. The licensee will complete to the satisfaction of NRC Region II the following preoperational/ acceptance testing:
A.
Sixty-three preoperational test must be completed and results evaluated.
(Twenty-nine are in progress and twenty have been completed.)
B.
Twenty-five acceptance tests must be ccmpleted and results evaluated.
(Ten are in progress and eight have been completed.)
C.
Five special tests nust be completed and results evaluated.
(* lone are in progress and four have been completed.)
__.m.___._.__.._______._______.__A____
A
--,w-h 4
aai wa- (ae.+ n.r, Sm i er 9.w.s&.)
E, fA4
% p y pa y,4 % Tm 6
he at% a aa~ prs f "/
W' A
R pr pe& 4ha ymde-a x&ub
.b A
~<47, p - pand y p
~e mwp, sued a<&%ak
-s~
m my u & a M - M cm da cas i n pw re.aust&' & y14 p
~r A2
~4uu 3, zr y rs m scs jutt y Y-6' J+y~p.swapm-iean~m/ "Mn, i i 1 e l l { I i x EE'%@,Q.{$0.Y!!UIMUfhMIj@E!N!W?%"'Z.S$E!!;?gM;R$,f?tigjgjgiyy;;g;p:.g e, ,a ..,c,;j,.7. e En' closure 4 Preoperational Testing Status and Operational Preparedness Hot functional' testing' is. complete. The. overall status-of the test program is sumarized below: In~ Completed & Accepted . Required Progress In Review-By PSRC PreoperatiobalTests Fuel. Load 63 29 20 7 j. 5% Power 9 0 1 0 Acceptance Tests Fuel Load 25 10 8 5 5% Power 19 6 6 1 Special Tests-Fuel Load 5 0 4 1-5% Power 4 0 'O O-i. I i S 0 ) i
- ~
1 h ENCLOSURE 5 STATUS OF INSPECTION REQUIRED BY MC 2512, 2513, AND 2514 All modules in the OIE Regional Office inspection program have been completed except as noted below: s 1 l 1 } $,
- f. [ + (
p
- ,7 e
ENCLOSURE 5 STATUS OF INSPECTION REQUIRED BY MC 2512, 2513,'AND 2514 'I.! a All modules in the OIE Regional 0ffice inspection program have been completed except as. noted below: Percent MC 2512 Complete j 35065B Procurement, Receiving and Storage 90-i 37051B Review of As-Builts 70 l 3705E3 On Site Design ~ Activities 50 50090B. Safety-Related Pipe Support and Restraint 10 Systems 510518 Electrical (Components & Systems) Review of 90 QA Implementing Procedures 63050B Containment Structural Integrity Test 60 73053B Preservice Inspection-Observation 90 I of Work and Work Activities Percent .fic 2513 Complete 803308 Environmental Protection - Preop 0 / Cod 811008 Physical Protection 50 82331B Emergency Plan - Facilities Equipment -B. cf g 7, Procedures 84330B Radioactive Waste Systems - Preop Liquid 30 and Solid Waste System 84331B i Radioactive Waste Systems - Preop Gaseous 20 l Waste System u 843328 i Radioactive Waste Systems - 80 QC and Capability Test 70304 Preoperational Procedure Review - ESF 90 70305 Preoperational Procedure Review - RPS 80 ..g.
- . Q. ' *
+ - Encl osure,5 ' 2 70306 Preoperational-Procedure Review - LOP ' 0 70311-Preoperational Procedure Verification 80 70315 Witness ESF-40 ~ 70316 Witness LOP 0 70317-Witness RPS .0 '70320 Evaluation of Test Results 10 -70322 Evaluation of Test Results - ESF 0 70325 Evaluation of Test Results - RPS 0 70326 E<aluation of Test Results - LOP 0 70329 Verification Tests Evaluation by Licensee O MC 2514 70308B Procedure Review--Integrated Hot 0 Functional Test.. 72500B . Initial Fuel Loading Procedure Review 0 72502B Approach to Critical Procedures Review 0 72504B Heat-Up Phase Procedure Review 0 '~ 725068 Power, Ascension Procedure Review (HPCI or 0 CRD System) 1 72509B Power Ascension Procedure Review - 0 CRD(GroupB)- 725108 Power Ascenston Procedure Review - 0 (RV or MSIV) 725128 Power Ascension Procedure Review 0 RCIC or RECIRC Inst. - RECIRC Pump Trip 72514B Power Ascension Procedure Review - 0 (Turbine Trip or Generator Trip) 72516B Power Ascension Procedure Review - 0 (Shutdown Outside Control Room-Loss of Off-Site Power) 1 _______-____.-__---_-_-.__-_._.__-_-_.--_-.__-__--_------------.__----Q l4: _ i;d
- p g'.;..f, '
l ' :'1 .i.~*^ r w -Enclosure 5 . 3.i r i-7 1 -725178-Power Ascension Procedore' Review - LOP 0 (Group: B)' s' 3
- 3.-
f.- 725188-' Power.- Ascension Procedure Review- . 0~ ~ (Core Performance)- T/I' 2514/01. -
- NT0L Inspection Re'quirements.
20 p .Rev. 2.iEncl. 1-4 4 e d 4 W i O t I .___._-___m_ m.------.-- -" -- - - - - ^ - - '